September 4, 1987
Aller/Lingle Architects
151 South College
Fort Collins, Colorado 80524
Attention: Mr. Dave Lingle
1981
� / J
Cr
Q
LL
John A. Malin, P.E.
J,imes R. E?rly. P.E.
Subject: City Park Nine �Llll 5 g2 v
Dear Dave:
The modifications and structural repairs to the Clubhouse roof trusses
and roof framing indicated on the contract drawings for this project will
allow the roof to support the full 30 PSF snow load required by the City
of Fort Collins.
We trust that this meets your needs, however, if you should have any
further questions or if we can be of assistance, please call on us.
Very truly yours,
MARTIN 0.& EARLY
James R. Earlfz e
Partner
JRE/me
AFFILIATE OFFICES IN
CALIFORNIA ■'
- CALIFORNIA ■ "
P COLORAOo • """ ' ""' HAWAII -
%" +"' " NEVADAn' '
""""- CALIFORNIA e
CALIFORNIA, "''
%"" CALIFORNIA■ "` -^ ARIZONA
4
A Commitment To Progress
DEPARTMENT
November 17, 1987
Mr. David Lingle
Aller-Lingle Architects
151 South College Avenue
Fort Collins, CO 80524
BOARD OF HEALTH
Glenn W. Wellman, O.D., MPH, Estes Park
President
Betty Moseley, M A., Fort Collins
Vice President
William M. Basow, M.D., Fort Collins
Susan Ferguson, Loveland
Eldon Savage, Ph. D., MPH. Fort Collins
363 Jefferson Street, Fort Collins, Colorado 60524
General Health 221-7460 Environmental Health 221-7496
� 1-
��CEiVED Nov t 9 196'i
Dear Mr. Lingle:
The plans_ and -specifications submitted for City Park Nine Clubhouse
renovation,--4'11 S. Bryan_Avenue Fort Collins, Colorado have been reviewed and
approved by this department, however, please be aware of the following:
1. All food service equipment must be NSF (National Sanitation Foundation)
approved or its equivalent. Custom made equipment and used equipment cannot be
approved until it is visually inspected. Submit a complete equipment list,
accompanied by the make and model number and specification sheets, -,.to include
,the 3-compartment sink and the wall -mounted drainboard.
Also, a menu is a required submittal so, as to properly evaluate the equipment
proposed.
2; The refrigeration in the concession is limited to one refrigertaor (dimensions
unkown at this time). Sufficient conveniently located refrigeration facilities
".. must be provided to assure the maintenance of potentially hazardous food at the
required temperatures during storage and preparation. Upon review of the
specification sheets on this unit and the menu (both to be submitted, refer to
Item #1), this setup will be evaluated for sufficiency.
3. Be advised that no appurtenances, such as; syrup lines, carbonators, drop -in
cold plates, drain lines or bottle holders are permitted in potable ice bins or
ice machines or any unit used to store potable ice. Submit information as to
the soda dispensing system ,to be installed (refer to Item #1).
4. This operation is not approved for any type of grease cooking or any other type
cooking or heating of foods which would produce heat or steam as an approved
ventilation system will not be provided.
5. Submit the size dimensions of the 3-compartment sink basins including the
width, length and depth. Once this information is received, the hot water
BOARD OF COUNTY COMMISSIONERS
Courtlyn W. Hotchkiss C. Howard Zollner Daryle W. Klassen
District I District II District III
Mr. David Lingle
November 17, 1987
Page 2
demand can then be calculated. It appears that the proposed water heater,
state model #SB F30-150E with a recovery rate of 112 gph at 5000 ft altitude
will be adequate. However, final approval cannot be given until the final
calculations are made.
6. Provide mop hangers or hooks around the mop sink to hang and air dry mops.
7. Floor sinks and floor drains must not be installed under equipment or
cabinetry. All floor sinks and floor drains must be installed so that they are
flush with the finished floor. The location of the drain under the soda
cabinet is not acceptable if enclosed.
The floor drain for the ice machine should be located closer to the unit for
proper drainage. Drainline must be directed to the drain but cannot run along
the floor., Recommend locating drain under the unit. Unit must be on 6 inches
legs.
B. All drain lines, water lines and electrical conduit which run along the wall
must have sufficient space between lines and wall to facilitate proper cleaning
or lines can be boxed in to facilitate easy cleaning. Exposed pipes, lines, or
conduit running along the floor is not approved.
--- Please be advised, the use of shelving below the drainlines of the handsink and
food prep sink for food or paper product storage is not acceptable unless lines
are boxed in.
9. All outer openings including doors and windows must be kept closed, or
permanent screens must be installed on outer openings that will be left open
periodically.
10. 30 foot candles of light on all working surfaces in the kitchen and 20
--- foot-candles of light in the restrooms.
-Lighting as indicated in the plans appears to be adequate. Compliance with the
;above requirement will be evaluated during on site construction inspections.
?Fi.'n.^Rf445e�y t�a'y �d. i
11. Finishes:
a.. Submit a sample of the kitchen vinyl sheet flooring for color and texture
approval prior to installation.
b. Submit sample of the formica to be used on kitchen counters for color and
texture approval.
12. All equipment, cabinets, and counters that are not easily moveable must be: a)
spaced so that floors, walls, and exterior surfaces of equipment can be easily
cleaned; or b) be sealed to adjoining walls, equipment; cabinets, or counters.
Hard to clean areas, spaces or gaps are not approved.
13. Please be advised that the following items are required in
the time of the opening inspection and thereafter:
a) stab food thermometer (0' to 2207 )
b) food grade plastic gloves
c) approved sanitizer
d) test strips for your sanitizer
the establishment.at
,Mr David Lingle
November 17, 1987
Page 3
The above items (#1, 2, 3, 5, 7, and 11) can be submitted either in written
form (except the samples requested) or as an addendum to the plans submitted. The
written plans submitted are approved at this time. Be advised approval of plans,
including the above modifications, does not constitute acceptance of the completed
structure. An inspection of the premises must be conducted by this department
prior to approval for operation and licensure of the establishment. Failure to
follow the recommended changes may prevent or delay the licensure of this
establishment. Any approval of the plans will be null and void if construction is
not commenced within 120 days.
Please notify the department at least 48 hours prior to your opening date so
that a final acceptance inspection can be performed.
A state ,food service license and this department's written approval is
necessary prior to opening.
Please feel free to contact this department if questions arise, -or if I can be
of further service at 221-7496..
DS/hy
cc: Ms Leslie Beckmann, City of Fort Collins
Fort Collins Building Department
Sincerely,
Debbie Schulz