February 25, 2008
EARTH ENGINEERING
COMPANY, INC.
HighCraft Builders
429 South Howes Street
Fort Collins, Colorado 80521
Attn: Mr. Scott Fetters
Re: Foundation Bearing Observation
3317 Moore Lane — Building Addition
Fort Collins, Colorado
EEC Project No. 08-01-016
Mr. Fetters:
As requested, Earth Engineering Company, Inc. (EEC) personnel have completed an
observation of the foundation bearing materials for footing foundations for the building
addition to the single-family residence. The results of those observations are included
with this report.
On February 19, 2008, EEC personnel observed foundation bearing materials for the
foundation footings for the referenced building addition to the residence located at the
referenced address. The above -grade portions of the current residence had been
demolished prior to our site visit; however, the foundation and floor slab remained in
place. We understand the building addition will be a lightly loaded wood frame addition
constructed on a garden level/walkout basement with an attached garage. At the time of
our field observations, the building area had been excavated to approximate foundation -
bearing elevation. The materials observed in the excavation area consisted predominantly
of brown to dark brown sandy lean clay. Two small areas of light brown/olive highly
weathered sandy claystone bedrock were also observed. Hand probe resistance tests
indicated that the in -situ lean clay and highly weathered bedrock materials were
stiff/moderately hard in consistency.
Swell/consolidation tests were performed on representative samples of the foundation
bearing materials in the basement and crawlspace foundation bearing levels to determine
swell potential with variation in moisture content. The dark brown sandy clay soils
showed low potential for swelling at present moisture and density conditions while the
P.O'. Box; 271428
P.O. Box 49322
FORT COLLINS', COLORADO 80527- 1 428 COLORADO'SPRINGS,. COLORADO 80949-9322
(970) 2.24-1522 (FAX) 663-0282 (.719) 442-6.813 (FAX) 447-9635
z6f ?__
Earth Engineering Company, Inc.
EEC Project No. 08-01-016
February 25, 2008
Page 2
light brown/olive highly weathered sandy claystone bedrock exhibited low to moderate
potential for swelling at present moisture/density conditions.
Based on the results of the outlined field testing and observation, it is our opinion the in -
situ materials could be used for support of the footing foundations using a design
maximum net allowable total load soil bearing pressure of 1,500 psf. It should be noted
that the potential for differential movement between the addition and the existing
residence should be addressed in the foundation design. While the site soils observed
exhibited relatively low swell potential at current moisture/density conditions, some
swelling was observed in the highly weathered bedrock materials. Slight movement of
lightly loaded elements supported over the highly weathered bedrock could occur and
should be expected. Moisture conditioning and reworking of the subgrade soils could be
considered to reduce the potential for post -construction movement; however, that risk
cannot be eliminated.
The conclusions presented in this report are based on the limited observations completed
as outlined above. A current and intrusive geotechnical subsurface exploration would be
necessary to more thoroughly evaluate the subsurface soils. Evaluation of the materials
beneath what was observable in the excavation is beyond the scope of this report.
We appreciate the opportunity to be of service to you on this project. If you have any
questions regarding this report, or if we can be of further service to you in any way,
please do not hesitate to contact us.
Very truly yours,
Earth Engineering Company, Inc.
Michael J. Coley, P.E.
Principal Engineer
EARTH ENGINEERING
COMPANY, INC.
February 26, 2008 d 8'/0
O
HighCraft Builders
429 South Howes Street
Fort Collins, Colorado 80521
Attn: Mr. Scott Fetters
Re: Foundation Footing Observation
3317 Moore Lane — Building Addition
Fort Collins, Colorado
EEC Project No. 08-01-016
Mr. Fetters:
Earth Engineering Company, Inc. (EEC) personnel have completed the i construction
observation services you requested for the referenced project. Those services included an
observation of the foundation footing dimensions for the referenced address. Two site
visits were required to complete the observations. The results of the site observations
completed by EEC personnel are included with this report.
On February 19 and 20, 2007, EEC personnel observed footing foundation widths for the
foundation footings for the above referenced single-family residence. The garage footings
were approximately 12 and 16 inches wide by 8 inches thick. The garden level basement
footings were approximately 12, 16, 20 and 26 inches wide by 8 inches thick at various
locations.
At the time of our final site observations, it appeared that the foundation footing widths
had been placed in general accordance with the construction plans prepared by Advanced
Engineering, LLC (Project No. 1011-31-01B).
P.O, BOX 271428 PO. Box 49322
FORT COLLINS', COLORADO 60527- 1 428. COLORADO SPRINGS,COLORADO 80949-9322
(976) 224-1'522 (FAX) 663-0282 (719) 442-6813: (FAX). 447-9635
gCTZ
EEC Project No. 08-01-016
February 26, 2008
Page 2
Earth Engineering Company, Inc.
.3 0to-O LR3
We appreciate the opportunity to be of service to you on this project. If you have any
questions regarding this report, or if we can be of further service to you in any way,
please do not hesitate to contact us.
Very truly yours,
Earth Engineering Company, Inc.
REG
0 �s
Qp9 ...:... T
' 57 •
A
Michael J. Coley, P.E.
Principal Engineer
ADVANCED
ENGINEERING, LLC
STRUCTURAL DRAINAGE DRAFTING
March 3, 2008
Mr. Scott Fetters
HighCraft Builders "Z� �' �� Q 1/1' 7-3
429 S. Howes Street
Ft. Collins, CO 80521
RE: 3317 Moore Lane, Fort Collins, Colorado
Advanced Engineering, LLC Project Number 1011-31-01C
Dear Mr. Fetters:
RECEIVED MAR 13 2009
On February 28, 2008 we visually observed the foundation wall reinforcement placed in the forms
for the addition being constructed at the above referenced site. It is our opinion the reinforcement
was in general conformance with our Foundation Plan, Project Number 1011-31-01B. We did not
observe the reinforcement for the interior or exterior footing pads at column locations.
The conclusions presented in this letter are not intended to cover structural items other than those
listed, site grading/elevations, setbacks, subsurface soil conditions, or architectural features of the
building. Thank you for the opportunity to serve you, feel free to call if you have any questions.
Sincerely,
Advanced Engineering,
Jason E. Baker, P.E.
Q.P� c' REG�ST
O .pN E• Bq� (gyp
33739
FSS/ONA����
146 Barberry Place, Loveland, Colorado 80537 Telephone 970-278-1909 Fax 970-278-1910
ADVANCED
ENGINEERING, LLC
STRUCTURAL DRAINAGE DRAFTING
April 16, 2008
Mr. Scott Fetters
HighCraft Builders
429 S. Howes Street
Ft. Collins, CO 80521
RE: 3317 Moore Lane, Fort Collins, Colorado
Advanced Engineering, LLC Project Number 1011-31-OIE
Dear Mr. Fetters:
On March 18, 2008 we visually observed the forms and reinforcement for the interior footing pads
at the residence being renovated at the above referenced site. It is our opinion the footing widths and
reinforcement were in general conformance with our Foundation Plan, Project Number 1011-31-
01B, and our recommendations for field modifications as required by site conditions.
On April 4, 2008 we visually observed the excavations and reinforcing for the deck piers at the
residence being renovated at the above referenced site. It is our opinion the reinforcement was in
general confonnance with our Foundation Plan, Project Number 1011-31-0113, and our
recommendations for field modifications as required by site conditions.
The conclusions presented in this letter are not intended to cover structural items other than those
listed, site grading/elevations, setbacks, subsurface soil conditions, or architectural features of the
building. Thank you for the opportunity to serve you, feel free to call if you have any questions.