TO: Bruce Dalton, OZ Architecture
FROM: Patty Swigart, Celestica Colorado
COPY: Kevin Oliver, Celestica Colorado
Gerry Albanese, DPR Construction
SUBJECT: Certificate of Occupancy
April21, 1998
The purpose of this memo is to provide a description of the anticipated move -in activity at the
new Celestica Colorado facility located at 4721 Technology Parkway. This information is to be
used for consideration for the Certificate of Occupancy.
Dates The anticipated building construction completion date is mid -February 1999, Celestica
would like to begin placing equipment inside the building as early as possible before this date.
Scoot and Imuence: The three major functional areas within the building ate manufacturing,
warehouse/shipping/rccciving and office. Once the majority of the utilities and inside finishes are
completed and there is no risk of interference with the remaining construction schedule,
equipment would be placed in their planned locations awaiting final building systems test and fit.
up. It is anticipated that the sequence for equipment placement would be manufacturing first.
then the warehouse and lastly office. The most likely scenario is to place one manufacturing cell
in the manufacturing area and begin to level and align the equipment. In parallel, the racks in the
warehouse area would be installed. Celestica personnel would formally begin to occupy the
building once the Certificate of Occupancy is issued and all of the building systems have been
successfully tested.
We appreciate your assistance in defining the earliest possible date for equipment move -in and
the conditions and requirements for the Certificate of Occupancy. For any required additional
information, please contact me at 970-207-5067.