September 1, 2000
Mr. Dave Carlson
Cottier Construction, Inc.
P.O. Box 1051
Fort Collins, CO 80522
RE: Car Wash foundation inspection
Schrader Oil Country Store
4711 South Timberline Road
Fort Collins, CO 1�
WGA Project #2574-99 V�
Dear Dave,
On August 31, 2000 I performed -&-foundation inspection of the rebar in thespread foe�ing for the car wash and
determined that it met with the intent of the construction documents.
On September 1, 2000 I performed a foundation inspection of the-rebar in the stem wall for the car wash and
determined that it met with the intent of the construction documents.
Sincerely,
Donald Shields Jr.
Project Manager
� ���11t;3EAART ��J++,,.
l�tilC -T yON
no. 30
`u U
PLAZA
ENGINEER'S FIELD REPORT
Report Date: September 415, 2000-
Report No.: 1
Project: Schrader Country Store
Location: Timberline Road and Timberwood Drive, Fort Collins, Colorado
Engineer: Plaza Engineermg Consultants, Inc., Loveland, Colorado
Contactor: Cottier Construction, Inc., Fort Collins, Colorado
Subject: Concrete Wall Footings i
Date: September 12, 2000 (12:00 pm) 4Weather: Seasonal
OBSERVATIONS
In general, the concrete forms were properly set and free of debris. The reinforcing steel required
for the wall footings and integral pads was correctly placed, and the size of the footings and pads
were consistent with the requirements of the foundation plan prepared by this office. Vertical
dowels consisting_ of No. 4 Grade 60 reinforcing_ steel was also ready for placement.
FIELD INSTRUCTIONS GIVEN
None.
cc:
F Plaz�..
art
PLAZA ENGINEERING CONSULTANTS, INC.
P.O. Box 1002 Loveland, CO 80539-1002 (970)-663-6353
LAWRENCE A. WICKHAM
+M ROBERT J. GUSTAFSON
LUQ--S
DONALD G. SHIELDS
ON COREY S. STINAR
.A R C T C T S
1449 RIVERSIDE AVENUE (970) 493-2025
FORT COLLINS, COLORADO 80524 FAX (970) 493-2026
October 5, 2000
Mr. Dave Carlson
Cottier Construction, Inc.
P.O. Box 1051
Fort Collins, CO 80522
RE: Canopy Footing Inspection
Schrader Oil Country Store
4721 South Timberline Road
Fort Collins, CO
WGA Project #2574-99
Dear Dave,
On September 7, 2000 I performed -a - foundation -inspection of the rebar for the fuel island canopy footings and
determined that it met with the intent of the canopy footing design drawings prepared by Arning Industries.
Footing -holes were 3' V diameter x 8-'-6' deep. - Footing rebar cages -were 307 diameter x 8' 0" long with (10)
#6 bars vertical with 6" hooks, (3) #3 ties at 2 '/2" o.c. at the top and (8) #3 ties at 12" o.c. to bottom of cage.
Sincerely,
Donald Shields Jr.
Project Manager
LAWRENCE A. WICKHAM
WICKHAM ROBERT J. GUSTAFSON
DONALD G. SHIELDS
GUSTAFSON COREY S. STINAR
A R C H I T E C T S
1449 RIVERSIDE AVENUE (970) 493-2025
FORT COLLINS, COLORADO 80524 FAX (970) 493-2026
October 5, 2000
Mr. Dave Carlson
Cottier Construction, Inc.
P.O. Box 1051
Fort Collins, CO 80522
RE: Car Wash Masonry Inspections
Schrader Oil Country Store
4721 South Timberline Road
Fort Collins, CO
WGA Project #2574-99
Dear Dave,
On September 28' 2000 I performed an inspection of the first 48' (vertical) of structural masonry block for the
car wash and determined that the block, rebar and grout installations met with the intent of the Construction
Documents.
On September 29, 20001 performed -an inspection of the second-48" (vertical) of structural masonry block for
the car wash and determined that the block, rebar and grout installations met with the intent of the Construction
Documents.
On October 5, 2000 I performed an inspection of the structuraFinasomy block for-the-qar wash from 8'-0" a.f f.
to the top of the bond beam and determined that the block, rebar and grout installations met with the intent of the
Construction Documents.
Sincerely,
Donald Shields Jr.
Project Manager