Loading...
HomeMy WebLinkAboutCHANGE ORDER - RFP - 7220 WATER WW TREATMENT & SITE INFRASTRUCTURE DESIGN CONSTRUCTION CONTRACTOR (22)WTF CCB Phase 3 Contract Change Order December 2016 00950-1 SECTION 00950 CHANGE ORDER NO. 2 PROJECT TITLE: WTF Chlorine Contact Basin Phase 3 Construction CONTRACTOR: Hydro Construction Purchase Order and Business Unit Numbers: PO9162138 and BU 5020331000 DESCRIPTION: 1. Reason for change: additional site work items to complete the construction of CCB project 2. Description of Change: additional site work items include installation of new gate and fencing for north access road, reinforced concrete pipes, riprap, and gravel along north side of CCB to facilitate drainage for the access road for large vehicular traffic to and around CCB, haul in topsoil to facilitate landscaping and additional seeding, repair and replace existing tracking pads, and update of construction general conditions due to additional construction site work and extension of schedule. 3. Change in Contract Cost: $205,865.00, plus previous change order of $125,962, for a total change orders amount of $331,827.00, with these two change orders, the new total contract amounts to $7,184,266.00. 4. Change in Contract Time: With these new work items, the master schedule for the substantial completion of the CCB construction will be extended to September 30, 2017. ORIGINAL CONTRACT COST $ 6,852,437.00 TOTAL APPROVED CHANGE ORDERS $125,962.00 TOTAL PENDING CHANGE ORDERS $0.00 TOTAL THIS CHANGE ORDER $205,867.00 TOTAL % OF THIS CHANGE ORDER 3.0% TOTAL C.O.% OF ORIGINAL CONTRACT 4.8% ADJUSTED CONTRACT COST $ 7,184,266.00 (Assuming all change orders approved) ACCEPTED BY: DATE: Contractor's Representative ACCEPTED BY: DATE: Special Projects Manager REVIEWED BY: DATE: Chief Engineer APPROVED BY: DATE: Water Production Manager APPROVED BY: DATE: Water Resources and Treatment Operations Manager APPROVED BY: DATE: Purchasing Agent over $60,000 APPROVED BY: DATE: Gerry Paul, Director of Purchasing (over $60,000) DocuSign Envelope ID: E498F625-2912-4A31-BB91-6BADF2C28C74 5/12/2017 5/12/2017 5/15/2017 5/15/2017 5/15/2017 5/16/2017 5/18/2017 Standard Estimate Report Pag FCWTF CCB CO #2 5/10/2017 10:25 AM Item Description Takeoff Qty Labor Amount Material Amount Subcontract Amount Name Equipment Amount Other Amount Total Amount 01 Gen Cond 1000.000 GENERAL CONDITIONS 14 Project Manager 4.00 wk 3,976 - - 1,000 150 5,126 14 Project Engineer 4.00 wk 6,816 - - 1,000 150 7,966 14 Superintendent 4.00 wk 10,224 - - 1,000 321 11,545 12 Office Supplies 1.00 mo - - - 508 508 12 Copier 1.00 mo - - - 325 0 325 18 Telephone Charges 1.00 mo - - - 128 128 20 Temporary Toilets 1.00 mo - - - 224 224 10 Fuels - Gas 4.00 wk - - - 641 641 12 Fuels - Diesel 4.00 wk - - - 1,924 1,924 GENERAL CONDITIONS 21,016 3,325 4,046 28,387 480.00 Labor hours 480.00 Equipment hours 1900.000 OWNED EQUIPMENT 50 500 Gal. Fuel Tank 1.00 mo - - - 150 - 150 45 Connex Box 1.00 mo - - - 1,010 - 1,010 OWNED EQUIPMENT 1,160 1,160 01 Gen Cond 21,016 0 0 4,485 4,046 29,547 480.00 Labor hours 480.00 Equipment hours 04 Sitework 1900.000 OWNED EQUIPMENT 10 C832 Hypac Compactor 0.50 mo - - - 1,136 - 1,136 10 Skidsteer 1.00 mo - - - 2,412 - 2,412 10 938 Cat Loader 1.00 mo - - 3,531 - 3,531 10 944Cat Loader 1.00 mo - - 3,531 - 3,531 20 470Hitachi Trackhoe 1.00 mo - - - 11,000 - 11,000 10 Dump Truck 1.00 mo - - 1,670 - 1,670 10 Water Truck 1.00 mo - - 1,864 - 1,864 OWNED EQUIPMENT 25,144 25,144 4.00 Labor hours 2000.000 SITEWORK 19 RCP 24" 100.00 lf 1,373 5,400 0 583 - 7,356 19 Gravel Roadways 19,205.00 sf 5,164 61,456 0 367 - 66,987 19 Riprap @ RCP 14.00 cy 659 56 140 2 - 857 19 Topsoil 2,000.00 cy 3,294 0 20,000 267 - 23,562 19 Tracking Pad 28.00 cy 1,318 1,316 280 4 - 2,918 -sub Sub - Landscaping 1.00 ls - - 17,500 - - 17,500 -sub Sub - Fencing 150.00 lf - - 6,750 - - 6,750 SITEWORK 11,808 68,228 44,670 1,223 125,929 430.12 Labor hours 97.793 Equipment hours 04 Sitework 11,808 68,228 44,670 26,367 0 151,073 434.12 Labor hours 97.793 Equipment hours Estimate Totals Standard Estimate Report Page FCWTF CCB CO #2 5/10/2017 10:25 AM Description Amount Totals Hours Rate Cost Basis Percent of Total Labor 32,824 914.115 hrs 15.94% Material 68,228 33.14% Subcontract 44,670 21.70% Equipment 30,852 577.793 hrs 14.99% Other 4,046 1.97% Bond 4,014 B 1.95% 184,634 184,634 89.69 Profit & Overhead 21,233 11.500 % T 10.31% Total 205,867 1 DocuSign Envelope ID: E498F625-2912-4A31-BB91-6BADF2C28C74