HomeMy WebLinkAboutDrainage Reports - 07/13/2017City of Fort Collins Pa by: Date: ' r� Drainage Report For Merit Midpoint 1590, LLC formerly Hess Land, LLC 2590 Midpoint Drive Fort Collins, CO 80525 Prepared by: Mike Beach, P.E. Date: February 27, 2017 Revised May 10, 2017 RiDGIVd.�P ENGINEERING & CONSULTING 5255 Ronald Reagan Blvd, Suite 210 Johnstown; CO 80534 (303) 322-6480 EMAIL: mbeach@ridgetopeng.com i. Plans - sa Page 1. Project Engineer's Certification........................................................................................ 3 2. Project Location & Overview..:......................................................................................... 4 3. Drainage Design Criteria.................................................................................................... 4 4. Hydraulic Calculations........................................................ :.............................................. 5 5. Facility Design.................................................................................................................... 6 6. Conclusion.........................................................................................................................8 7. References.........................................................................................................................9 Appendix A — Site Vicinity Map Appendix B — Flood Insurance Rate Map Appendix C — NRCS Soils Map Appendix D — Hydrologic Criteria Fort Collins Rainfall Intensity Curve Fort Collins Rainfall Intensity Table Table RO-3 — Recommended Percentage Imperviousness Values Appendix E — Hydraulic Calculations Runoff Coefficients & Imperviousness Time of Concentration - SF-2 Rational Method Runoff Flows — SF-3 (2-Year Event) Rational Method Runoff Flows — SF-3 (100-Year Event) Detention Volume by Modified FAA Method (Subbasins 1 & 2) Orifice Calculations Detention Basin Stage -Discharge Table (Subbasins 1 & 2) Rain Garden Calculations (Subbasins 1 & 2) Historic Runoff Flow Calculations (Coefficients, TOC, 2-Yr event) LID Table Spillway Calculations (Ponds 1 & 2) Drain Times (Ponds 1 & 2) Appendix F — Maps Subbasin Map Project # 16-015-002 Page 2 Section 1: PROJECT ENGINEER'S CERTIFICATION I hereby attest that this Final Drainage Report for the design of stormwater management facilities for Lot 18 (2590 Midpoint Drive) was prepared by me, or under my direct supervision, in accordance with the provisions of the City of Fort Collins Storm Drainage Design Criteria and Construction Standards for the responsible parties thereof. t. E� 45088 =e �� 0 �� /v-Zvi?,04' 4 ass/ NAI Ejr, Mike Beach, P.E. Registered Professional Engineer State of Colorado No. 45088 Project # 16-015-002 Section 2: Project Location & Overview Location The sites address is 2590 Midpoint Drive, Fort Collins, CO; which is in the SE 1/4, of the NW 1/4, of Section 20, TWP 7 N, R 68 W of the 6th PM in Larimer County, CO. W' Located along the north side of Midpoint Drive and east of South Timberline Road, the site is described as Lot 18 of the Prospect Industrial Park and contains 0.86 acres of undeveloped vacant land. (See Appendix A — Site Vicinity Map) Existing Condition The existing site is covered by native vegetation and slopes predominately towardsfMidpoint Drive at approximately 0.5% slope. Stormwater runoff collected nto,Midpoint Drive is ;P_ .� .. conveyed via gutter towards Sharp Point Drive where it is depositedinto ah-inlet that conveys the water to Poudre River. Proposed Condition The intent of the development is to construct a new single story pre-engineered metal building, approximately 9,047 SF, asphalt concrete parking, crushed asphalt overflow parking, landscaping and a stormwater detention and conveyance system. Floodplain FEMA Floodplain mapping in this neighborhood is located on map -panel 08069C0992G, revised May 2, 2012, which indicates the subject property is located in Zone X, which is outside the 100-year floodplain. (Appendix B — Flood Insurance Rate Map) Existing Soils The Natural Resource Conservation Service mapped the historic soils on the site as part of the Caruso clay loam. The Hydrologic Class is Type 'D' Soils. (Appendix C — NRCS Soils Map) Section 3: Drainage Design Criteria Reference Manuals Storm drainage design criteria is defined in the City of Fort Collins "Storm Drainage Design Criteria and Construction Standards Manual (FCSDCM) and Amendments, which references to the "Urban Drainage and Flood Control District" (UDFCD) and the "Urban Storm Drainage Criteria Manual" (USDCM), Volumes 1, 2, and 3, dated 2008 with revisions (the Manual), are used and referenced in this report. Four Step Process The City of Fort Collins has adopted the "Four Step Process" that is recommended in Volume 3 of the USDCM for selecting BMP's in urban redevelopment areas. The goal of this process is to minimize adverse impacts on receiving waters. The following describe how each step of the process are incorporated in the proposed development: Project # 16-015-002 Page 4 Step 1 — Employ Runoff Reduction Practices By selecting a site that is undeveloped that currently does not have detention or water quality treatment, the impacts of the proposed development will be less due to the addition of the detention pond with the water quality capture volume included. The project proposes to install rain gardens with underdrains and dry wells to aid in conveyance and infiltration opportunities and reduce the effects of the added impervious areas. Step 2 — Water Quality Capture Volume (WQCV) In order to reduce the sediment load and other pollutants leaving the site, it is important to provide WQCV to minimize the downstream impacts. This project proposes to provide rain garden/detention ponds located on the site. These ponds are sized to capture the WQCV and allow infiltration & release to the proposed drywells. Step 3 — Stabilize Drainageways Since this site is in close proximity to Poudre River it is important to take this Step into consideration. By providing stormwater detention and water quality and lowering the historic runoff and providing a metered outflow the project impacts to the drainageway are essentially reduced. The majority of the drainageway leaving the site is already stabilized. Step 4 — Implement Site Specific and Other Source Control BMP's The proposed project will contain the following BMP's: Rain Garden/Dry Wells: All runoff from the site will be directed into and through the proposed BMP facilities prior to leaving the site. As in the adjacent site (2600 Midpoint Dr., lot 19), we are proposing to install Dry Wells as necessary to connect the Rain Garden Underdrains and aid in infiltration into the existing soil stratum. Maintenance: In order for BMP's to remain effective proper maintenance needs are required. Scheduled visual inspections and routine repair after larger storm events are critical in the maintenance and effectiveness of the installed BMP's. The sites owner will be advised of these practices during installation in order to maximize the efficiency of the installed BMP's. Maintenance Standard Operating Procedures are also included in the Development Agreement with the City. Section 4: Hydraulic Calculations Criteria Runoff criteria for the proposed sites was analyzed for the 2-YR and 100-YR storm events. The Rational Method is being used for the design of the proposed improvements. Rainfall Intensities used in the proposed design were determined as a function of the Time of Concertation for each subbasin. The values used were determined by the City of Fort Collins Rainfall Intensity/Duration/Frequency curve (Figure 3-1 and Table 3-1a (see Appendix D). Project # 16-015-002 Page 5 Imperviousness Values from Table RO-3 (USDCM) were used in determining the sites imperviousness. The overall proposed site improvements and landscaping equate to a total onsite proposed Imperviousness of 58%. Level 1 Watershed -Level Volume Reduction Method is applied to the extent possible on the site. Grass areas are strategically located in order to provide surface flow where allowed, prior to the stormwater leaving the site. Time of Concentration & Runoff Coefficient The onsite area was separated into two (2) subbasins with slopes varying between 0.5% to 4%. The calculated Time of Concentration (Tc) for each basin are listed in Appendix E. See Basin Map in Appendix F for more information. W CV The UD-BMP_v3.03 (UDFCD) spreadsheet was used to calculate the required Rain Garden water quality capture volume for each of the two subbasins. See Appendix E for design information. Detention A "Modified FAA" Detention Spreadsheet for each of the subbasins was used to analyze the 100-year storm event with the allowable predeveloped 2-year release. See Appendix E for design information. Section 5: Facility Design The proposed improvements will increase the amount of impervious area; however, measures have been included in the design to minimize the amount of stormwater release from the site. Detention is sized for the 100-year rainfall event for each of the proposed ponds. The outlet structures are designed to release at the historic predeveloped 2-year event at a release of 0.142 cfs per for Subbasin 1.0 and 0.201 cfs per for Subbasin 2.0, see Appendix E for Historic calcs). The runoff will sheet flow until a concentrated point and then be conveyed via trickle channel or gutters and then deposited into the respective pond. The site was broken into three developed subbasins; Subbasin 1.0 (0.331 acres), Subbasin 2.0 (0.470 acres), and Subbasin 3.0 (0.053 acres). See Appendix E for breakdown of the different area types for each subbasin and Appendix F for the Subbasin Map. Subbasin 1.0 contains the proposed building and minor areas adjacent to the building. The runoff will be conveyed to the back of the building and outlet into proposed drainage pan behind the building, which will convey the water to the new pond located between the new building and Midpoint Drive. Project # 16-015-002 Page 6 The Emergency Overflow Spillway for this Subbasin is designed with a length of 4-ft and will provide a designed flow rate capacity of 5.940 cfs, whereas the required 100-year developed flow rate is 2.98 cfs, therefore the designed spillway is sufficient. See Appendix for calculations. Subbasin 2.0 is primarily the parking and paved areas which drains to the west to a swale (with a trickle channel), then deposited into anew detention/water quality pond located in the western corner of the site. See Appendix F for Subbasin location. The required Water Quality Control Volume (of 0.008 ac-ft) for this Subbasin will be treated via Rain Garden (RG). Orifice calculations are included in the appendix of this report. The Water Quality depth as designed is 1.0-ft in depth. A new detention outlet structure with a steel orifice plate will be constructed onsite. The orifice plate as detailed in the construction drawings will require one orifice with a 2-1/2" diameter orifice for detention. See Appendix E for calculations. The outlet structure will convey the detained water to Midpoint Drive. Provided Detention Volume for this Subbasin after construction of Lot 18 will include approximately 0.109 ac-ft. The Emergency Overflow Spillway for this pond is designed with a length is 4' and will provide a designed flow rate of 5.940 cfs, whereas the required 100-yr event required flow rate for the contributing basin is 3.07 cfs. Subbasin 3.0 contains a small portion of the access driveway, sidewalk, and landscape area that due to the existing grades on the site being substantially higher than the adjacent roadway cannot be directed to one of the detention ponds. The contributing area for this Subbasin is approximately 0.053 acres. This runoff would sheet flow to Midpoint Drive and continue along the curb and gutter to the next available catch basin. For Water Quality, the project proposes to include the WQCV as Rain Gardens (as described above) below the Detention Pond with Underdrains tied directly to Drywells to aid in the infiltration and natural discharge of the runoff. Both of the ponds include sized Rain Gardens for the appropriate events in accordance with the City of Fort Collins criteria. The Drywells shall be excavated untila depth where the sand and gravel material is encountered, but shall not be less than 6ft below the Proposed Finish Grade. A boring log shows the existing sand and gravel material was encountered near 7.5-ft below Existing Grade. See boring log within the appendix of this report for reference. Project # 16-015-002 Page 7 Below is a summary of each of subbasins design with supporting calculations within the Appendix of this report. Dev. 2- Year Flow (cfs) Dev. 100- Year Flow (cfs) WQCV Req'd (ac-ft) 100- Year Vol. Req'd (ac-ft) Tot. Volume Req'd (ac-ft) Tot. Volume Provided (ac-ft) 2-Yr Hist. Release Rate (cfs) Orifice (in) Sub 1.0 0.60 2.98 0.005 0.076 0.081 0.101 0.142 1-13/16" Sub 2.0 0.62 3.07 0.008 0.087 0.095 0.119 0.201 2-1/2- Sub 3.0 0.12 0.54 N/A N/A N/A N/A N/A N/A Section 6: Conclusions All computations that have been reviewed or completed within this report are in compliance with the City of Fort Collins Storm Drainage Design Criteria and Construction Standards manual and the Urban Drainage and Flood Control District Urban Storm Drainage Criteria Manual Volumes 1 & 2. The proposed drainage concepts presented in this report and on the construction plans adequately provide for stormwater detention and water quality treatment of impervious areas by releasing the 100-Year storm event at the Predeveloped 2-Year runoff rates. The Water Quality design will benefit the site by reducing the initial discharge from the site and removal of any sediments or other pollutants generated by the developed site. Section 7: References • The Natural Resource Conservation Service Soil Survey for Larimer County and the WSS website. • FEMA FIRM map -panel 08069C0992G Effective 05/02/2012. • "City of Fort Collins Stormwater Criteria Manual" dated December 2011 • Urban Drainage and Flood Control District Urban Storm Drainage Criteria Manual (UDFCD), Volumes 1, 2, and 3, dated 2008 with revisions (the.Manual). Project # 16-015-002 Page 8 Appendix A Site Vicinity Map E. PROSPECT RD.. \ E. PROSPECT RD. SITE LOCATION Cp �`ell 112, 9y o9 f P E. DRAKE RD. VICINITY MAP Appendix B Flood Insurance Rate Map m U ru c re mE y ao'm� d�m5o m u m n n wN �pu outLL W 4 O c c O Nvv W{gZy� w^ Oac gli ggagg� naYTGni q0Sm� ��ppo �Wp TtNmao ap �2m"nm`cc 2vo_` yim ZPZ id dOP: W z E LL WCoHII W '2 . $ CDa ELL o€vQaW Z LL Z Yo mm LU C J V d C Z N Z Z p 2 Of .(!�� a n O m n Y c 8 n� V O F'.6 a p A Z gs18' �$ b ,ar-& Ci V d a yti rn Nm�g=�09 e CUE n Y E x m C U N � m 0 m n � ui m n m u o 7$ W Z W OJWCwdOW W j V Op C Q'OPO N ZOGooa�O Q wZZptp�nLLOwz y y C QP N v v 6dau,<?WaywaQ�Z� wO dEZmpa co cc0wNWpQ A 4 QC` r i��sz \�G w z� °2w _ aw r� vyaQZOWW V �N 4 cO - Op a003:a wow rl a: 0 n�xgoo CM 1 W 4, O z�jwWO000aw� C N HlowU<lua0 0 e x x U v a \ v0V¢ � a L) -J u 0 x cn w K LL w W l- W \_ ` a Q N C) w N o �d� m° 00 -A F N pm Oj U X =2 LU .Wj J_ Q LO N �\aQ o � ov o L) ri M O R 0 a No Text 40° 33 W N 40' 33'3 N 3 Soil Map—Larimer County Area, Colorado 3 (Lot 18 - Midpoint Dr) 0 497390 497410 497430 497450 497470 3 Map Sole: 1:944 fi printed on A poroait (8.5" x 11") sheer. Meters N G 10 20 40 60 Feet 045 90 180 270 Map projection: Web Mercator Comer coordinates: WGS84 Edge tics: lfiM 7.nne 13N WCS84 usDA Natural Resources Web Soil Survey Conservation Service National Cooperative Soil Survey 497490 497510 I n 40° 33' 38" N 497530 3 0 2/29/2016 Page 1 of 3 in d d � o pj 01 om v O U N` w y� O (.1 N d d tl N l0 Of N N n O 0 6 A L D A d d N C of In « d A N N- w U O N o E 6 Q Ld MO E A roL ZN C Mn ,0 Z UH` . E H t 'o�cEE N a m CJa o yD wDj ¢ 6 q ti Fov y .a d E U N W m C. 12 0 0" ❑ R N o L 3 id D �p ' Y m O q L d N N OI n O a Sca L d nj c u) Q n y`N N a N C d d o Q D E 3 ro ttJJ Ld. ii t co `m Y v m o m '� a w n Dmy o mn� ZaaaF'id Eo C) m t y�En om� N v Kta JNiiom �m do m a Oav� vDo0 m 3 NZ oo.`o Dy EE `m> D aEIE -E. m n�aa N y o v a38 v m J w U E n'^O m> a Z ❑� n a U ro d y N d O N O a Eo'E m LL"' v dnmrom a v" rn m ;° d m E o'rn YDic _ yy O C F J O C m Z y- A A O s N A a Q❑ w m O a= 0 n ton c m dN rE J Mtn a; a m L c n A m EWdm dd o.A oody� o c rnC E� wa AND Niic N nd to aTi Ern N o Qd� m O N m .O d d O d O ro O N n L d O J O A m O L p A E 3 wEnN aE w3U �a'oao r5 mm m`o ❑N rdEo 6 IL U t m Q n O O J m Y m Q m O O L m Co m C � m � 3 r m m 0 m a m �l a O O O m t7 a N N N G m U U f7 a d �y2)cgx OX': 0 K®® > + X OANk a N m m Soil Map—Ladmer County Area, Colorado Map Unit Legend Lot 18 - Midpoint Dr Larimer County Area, Colorado (CO644) Map Unit Symbol Map Unit Name Acres in AOI Percent of AO1 122 Caruso Gay loam. 0 to 1 percent 1.9 100.0 slope Totals for Area of Interest 1.9 USDA Natural Resources Web Soil Survey 2/29/2016 Conservation Service National Cooperative Soil Survey Page 3 of 3 Appendix D Hydrologic Criteria 10.00 9.00 8.00 i 7.00 'm m L c 6.00 2 5.00 W f Z 4.00 J J Q LL = 3.00 9 2.00 1.00 0.00 H 0.00 RAINFALL INTENSITY -DURATION -FREQUENCY CURVE 10.00 20.00 30.00 40.00 50.00 60.00 STORM DURATION (minutes) -2-Year Storm - - - 10-Year Storm -100-Year StOnn Figure RA-16 City of Fort Collins Rainfall Intensity -Duration -Frequency Curves 4.0 Intensity -Duration -Frequency Curves for Rational Method: The one -hour rainfall Intensity -Duration -Frequency tables for use the Rational Method of runoff analysis are provided in Table RA-7 and in Table RA-8. Table RA-7 -- City of Fort Collins Rainfall Intensity -Duration -Frequency Table for Use with the Rational Method (5 minutes to 30 minutes) Duration (min) 5 2-Year Intensity (in/hr) 2.85 10-Year Intensity (in/hr) 4.87 100-Year Intensity (in/hr) 9.95 6 2.67 4.56 9.31 7 2.52 4.31 8.8 8 2.4 4.1 8.38 9 2.3 3.93 8.03 10 2.21 3.78 7.72 11 2.13 3.63 7.42 12 2.05 3.5 7.16 13 1.98 3.39 6.92 14 1.92 3.29 6.71 15 1.87 3.19 6.52 16 1.81 3.08 6.3 17 1.75 2.99 6.1 18 1.7 . 2.9 5.92 19 1.65 2.82 5.75 20 1.61 2.74 5.6 21 1.56 2.67 5.46 ' 22 1.53 2.61 5.32 ' 23 1.49 2.55 5.2 24 1.46 2.49 5.09 25 1.43 2.44 4.98 26 1.4 2.39 4.87 27 1.37 2.34 4.78 28 1.34 2.29 4.69 29 1.32 2.25 4.6 30 1.3 2.21 4.52 DRAINAGE CRITERIA MANUAL (V. 1) RUNOFF Table RO-3—Recommended Percentage Imperviousness Values Land Use or Surface Characteristics Percentage Imperviousness Business: Commercial areas 95 Neighborhood areas 85 Residential: Single-family Multi -unit (detached) 60 Multi -unit (attached) 75 Half -acre lot or larger Apartments 80 Industrial: Light areas 80 Heavy areas 90 Parks, cemeteries 5 Playgrounds 10 Schools 50 Railroad yard areas 15 Undeveloped Areas: Historic flow analysis 2 Greenbelts, agricultural 2 Off -site flow analysis (when land use not defined) 45 Streets: Paved 100 Gravel (packed) 40 Drive and walks 90 Roofs 90 Lawns, sandy soil 0 Lawns, clayey soil 0 * See Figures RO-3 through RO-5 for percentage imperviousness. CA = KA + (1.31i'—1.44i2 + 1.135i — 0.12) for CA >! 0, otherwise CA = 0 (RO-6) CCD = KCD + (0.858i' — 0.786i 2 + 0.774i + 0.04) _ (RO-7) CB = (CA + CCD )12 2007-01 RO-9 Urban Drainage and Flood Control District THUNDERPUP CONSTRUCTION FORT COLLINS, COLORADO PROJECT NO: 1142088A LOG OF BORING B-2 SHEET i OF 1 DATE: DECEMBER 2014 RIG TYPE: CME55 WATER DEPTH FOREMAN: DG START DATE 1211012014 WHILE DRILLING 1W AUGER TYPE: 4" CFA FINISH DATE - 1211012014 AFTER DRILLING NIA SPT HAMMER: AUTOMATIC SURFACE ELEV NIA 24 HOUR NIA SOIL DESCRIPTION D N pU MC DU A-LIMRS 400 SWELL LL PI PRESSURE %® 500 PSF TYPE (FEET) (BLOWSIFT) (PSF) (%) (PCF) (%) TOPSOIL & VEGETATION CLAYEY SAND (SC) mottled / brown / red 2 medium dense mottled 3 4 CS 5 19 9000i 6.3 119.3 27 14 45.1 2000 psf 2.1% 6 _7_ 8 - SAND 8 GRAVEL (SP/GP) brown / grey / red dense 9 E 10 48 4.3 with cobbles _ _ 11 12 13 14 cave in, auger cuttings SS 15 16 17 18 19 cave in, auger cuttings FSS 20 21 22 23 24 CLAYSTONE grey — — wet cave in, auger cuttings [SS 25 BOTTOM OF BORING DEPTH 25.5' Earth Engineenng consultants, LLc Appendix E Hydraulic Calculations e O E � m 0 T q 4 0 0 0 `0 'o U N O� T N M �O t0 41 N o O G O o o O O Q co CO m E n u a c m m E TU N N a u e a A O m a J C _ 0 C 0 N J U � n 66 m m a a Hf N C E E m U n a n o 0 E o= C y o N 0 fV o N a N � U m a q N <O CI O a m O O N r J Q Y � q N y 0 0 0 0 a 0 u1 m » g 0 0 0 O Q C O N p m a a O O O O C og a o 0 0 K m Q a O O N N H Q u o N m g q t'I P O O O O O r C O C d N q N'C A X XA m m% W W W q o � < = a m mm � u u u Q � � < m ♦ A A D on 'o d m O O m J J ( Oc m d n 0 J r O J y m N m n c � d w w 0 3 A u 0 (D 0 ■ 0 ■ 0 m u � n D n c m m O N < m < O A - N O Z _1 3 C/) m D O Z T O O A Z O j, c) m0 Z A DI T D O N -i Z m Location: Lot 18 RATIONAL METHOD PEAK RUNOOF Calculated By: RSB Event: 2-Year Date: 4/2712017 Historic Flow Rate Cf = 1.00 SUB -BASIN DATA Direct Runoff Q = Cf•C•i•A Q = Peak Discharge (cfs) C = Runoff Coefficient Cf = Frequency Adjustment Factor I = Rainfall Intensity (in/hr) from COFC IDF Curve (1 = 24.221 / (10+tc)A0.7968 A = Drainage Area (ac) ' t CO m U K o T 0 O E o m N U 3 O O P 1n N O �0 0 m r0 O C T a? O) N M r0 t0 Qr N O O � � U d a ECL c a U m U m 0 c rn: a m E o a c_ U a mca O = O , u� a o '�E _ aS p .a a u o. o o U U f co c LL d O U O E O O 0 N U > Z a' a j o a m a 0 C E E 0 U E U 0 O w c y N rc0m O N cp m o 0 0 0 0 � U n� m � m io m p � d Q t0p Q N m a J s C 2 a wa a d m c+ a m v O F m m m `p J M Q O O 0 0 0 0 H c o c N m u �ci ri m m a O o H N N V W Z F NO Qo N K F 0 Z Uw O Z of O o Q U 0 W z0 Q W H Z O cc N_ m O m } Dm N � W 5 J U 111111111 i I M In cn � p o. � w q C � N A OI m C C U t IUi W U � y o 00 O d N I� 11 II O II II II p W - � a on E IIIIIIIIIIIIIIIIIIIIIIIIII IIIIIIIIIIIIIIIIIIIIIIIIIN IIIIIIIIIIIIIIIIIIIIIIIIIE IIIIIIIIIIIIIIIIIIIIIIIIIN IIIIIIIIIIIIIIIIIIIIIIIIIN IIIIIIIIIIIIIIIIIIIIIIIIIE IIIIIIIIIIIIIIIIIIIIIIIIIN liiiiiiiiiiiiiiiiiiiiillin ■ 1� A N V N O V m m Location: Lot 18 RATIONAL METHOD PEAK RUNOOF Calculated By: RSB Event: 2-Year Date: 4/27/2017 Cf = 1.00 SUB -BASIN DATA DirectRunoff Q = Cf C`i`A Q = Peak Discharge (cfs) C = Runoff Coefficient Cf = Frequency Adjustment Factor = Rainfall Intensity (in/hr) from COFC IDF Curve (1•= 24.221 / (10+tc)^0.7968 A = Drainage Area (ac) Location: Lot 18 RATIONAL METHOD PEAK RUNOOF Calculated By: RSB Event: 100-Year Date: 4/27/2017 Cf = 1.25 SUB -BASIN DATA Direct Runoff Q = Cf C*i*A Q = Peak Discharge (cfs) C = Runoff Coefficient Cf = Frequency Adjustment Factor i = Rainfall Intensity (in/hr) from COFC IDF Curve (i = 84.682 / (10+tc)^0.7975 A = Drainage Area (ac) rI Equations: LOCATION: CALCULATED BY: PROJECT NUMBER: DATE: BASIN: Qo = CiA Vi = T*CiA = T*Qo V. =m'Qro*(60*T) S=V; -Va DETENTION VOLUME CALCULATIONS RATIONAL VOLUMETRIC (FAA) METHOD Lot 18 - Midpoint Dr MRB 16-015-002 7/26/2016 1.0 Rainfall intensity from Larimer County Area 1 IDF Curve A trib. To pond = 0.331 acre C100 = 0.90 (C*Cf) Developed C*A = 0.30 acre Qpo = 0.142 cfs tc = 5 min Storm Duration, T (min) Rainfall Intensity, i (in/hr) Qo (cfs) Vol. In V; (ft) Outflow Adjustment Factor, m Vol. Out Vo (ft) Storage S (ft) Storage S (ac-ft) 5 9.95 3.0 889 1.00 43 847 0.019 10 7.72 2.3 1380 0.75 64 1316 0.030 20 5.60 1.7 2002 0.63 107 1895 0.044 30 4.52 1.3 2424 0.58 149 2275 0.052 40 3.74 1.1 2674 0.56 192 2482 0.057 50 3.23 1.0 2887 0.55 234 2652 0.061 60 2.86 0.9 3067 0.54 277 2790 0.064 70 2.62 0.8 3278 0.54 320 2959 0.068 80 2.38 0.7 3403 0.53 -362 3041 0.070 90 2.22 0.7 3571 0.53 405 3167 0.073 100 2.05 0.6 3664 0.53 447 3217 0.074 110 1.93 0.6 3795 0.52 490 3305 0.076 120 1.80 0.5 3861 0.52 533 3328 0.076 130 1.60 0.5 3718 0.52 575 3143 0.072 140 1.40 0.4 3503 0.52 618 2886 0.066 150 1.20 0.4 3217 0.52 660 2557 0.059 160 1.15 0.3 3289 0.52 703 2586 0.059 170 1.10 0.3 3342 0.51 746 2597 0.060 180 1.05 0.3 3378 0.51 788 2590 0.059 Required Storage Volume: 3328 ft3 0.076 acre-ft Equations: DETENTION VOLUME CALCULATIONS RATIONAL VOLUMETRIC (FAA) METHOD LOCATION: CALCULATED BY: PROJECT NUMBER: DATE: BASIN: QD = CiA V; = T*CiA = T*QD V. =m*Qeo*(60*T) S=V; -Vo Lot 18 - Midpoint Dr MRB 16-015-002 4/27/2017 2.0 Rainfall intensity from Larimer County Area I IDF Curve A trib. To pond = 0.470 acre C100 = 0.75 (C*Cf) Developed C*A = 0.35 acre QPo = 0.201 cfs tc = 7.6 min Storm Duration, T (min) Rainfall Intensity, i (in/hr) QD (cfs) Vol. In V; W) Outflow Adjustment Factor, m Vol. Out V. (0 Storage S (ft3) Storage S (ac-ft) 5 9.95 3.5 1052 1.00 60 992 0.023 10 7.72 2.7 1633 0.88 106 1527 0.035 20 1 5.60 2.0 2369 0.69 166 2202 0.051 30 4.52 1.6 2868 0.63 227 2641 0.061 40 3.74 1.3 3164 0.60 287 2877 0.066 50 3.23 1.1 3416 0.58 347 3068 0.070 60 2.86 1.0 3629 0.56 408 3222 0.074 70 2.62 0.9 3879 0.55 468 3411 0.078 80 2.38 0.8 4027 0.55 528 3499 0.080 90 2.22 0.8 4226 0.54 589 3637 0.083 100 2.05 0.7 4336 0.54 649 3687 0.085 110 1.93 0.7 4490 0.53 709 3781 0.087 120 1.80 0.6 4568 0.53 769 3799 0.087 130 1.60 0.6 4399 0.53 830 3569 0.082 140 1.40 0.5 4145 0.53 890 3255 0.075 150 1.20 0.4 3807 0.53 950 2857 0.066 160 1.15 0.4 3892 0.52 1011 2881 0.066 170 1.10 0.4 3955 0.52 1071 2884 0.066 180 1.05 0.4 3997 0.52 1131 2866 0.066 Required Storage Volume: 3799 ft3 0.087 acre-ft j Detention Orifice Calculations Project: Lot 18 - Midpoint Dr Date: 4/27/2017 A = Area of Orifice (ftA2) Q = orifice flow rate (cfs) H = effective head on each orifice opening (ft) C = Discharge Coefficient (0.60 for square edges) g = Gravitational acceleration constant (32.2 ft/secA2) Q=CA(2gH)A0.5 Eq 12-19 UDFCD A = Q/(C(2gH)A0.5 Subbasin 1.0 Q (cfs) = 0.142 H (ft) = 2.5 Total Area (sq-in) Diameter(in) Standard Size Dia. (in) A = 0.013/(0.6((2*32.2*1.0)A0.5)). 2.69 1.85 1-13/16" Orifice Diam. = 2*(A/3.14)A0.5 Subbasin 2.0 Q (cfs) = 0.201 H (ft) = 1.6 Total Area (sq-in) Diameter (in) Standard Size Dia.,(in)o A = 0.028/(0.6((2*32.2*1.0)A0.5)) 4.69 2.45 2-1/2" Orifice Diam. = 2*(A/3.14)A0.5 Spillway Emergency Spillways for both Subbasins are set at the same elevation as the 100-Year WSEL, which is the same elevation of the top of the outlet structure. Any event above the 100-Year event will fill the ponds and overtop the structure/spillway and be released into the adjacent roadway. See Overflow Spillway Weir Calculations in this report. N PROPOSED DETENTION POND - STAGE/STORAGE Pond: 1.0 Location: Lot 18 Calculated By: MRS Date: 7/28/2016 V = 1/3 d (A + B + sgrt(A*B)) V = Volume between Contours, ftA2 d = Depth between Contours, ft A = Surface Area of Contour, ftA2 WQCV = 100-Year WSEL = Stage (ft) Surface Area (ftA2) Incremental Storage (ac-ft) Total Storage (ac-ft) Detention Storage(ac ft) 96 0 96.5 245 0.00 0.00 97 525 0.00 0.01 97.5 835 0.01 0.01 0.00 98 1125 0.01 0.02 0.01 99 1665 0.03 0.06 0.04 100 2228 0.04 0.10 0.09 Required Detention Volume = Provided Detention = Required WQCV = Provided WQCV = Total Required Volume = Total Volume Provided = 0.076 See "Detention Volume Calculations" 0.090 0.005 See "WQCV" RG Calc Sheet 0.010 0.081 0.100 Location: Calculated By: Date: WQCV = 100-year WSEL = PROPOSED DETENTION POND - STAGEISTORAGE Pond: 2.0 Lot 18 MRB 4/27/2017 V = 1/3 d (A+ B + sgrt(A-B)) V = Volume between Contours, ft^2 d = Depth between Contours, ft A = Surface Area of Contour, ft^2 Stage ft Surface Area ft^2 Incremental Storage (ac-ft) Total Storage (ac-ft) Detention Storage (ac ft) 96.5 0 96.66 244 0.0003 0.0003 97 370 0.0024 0.0027 97.66 655 0.008 0.010 98 1 1305 1 0.008 1 0.018 0.008 99.3 6075 0.101 0.119 0.109 Required Detention Volume = Provided Detention = Required WQCV = Provided WQCV = Total Required Volume = Total Volume Provided = 0.087 See "Detention Volume Calculations" 0.109 0.008 See "WQCV" RG Calc Sheet 0,010 0.095 0.119 Design Procedure Form: Rain Garden (RG) 11 Sheet 1 of 2 Designer: MRB Company: Ridgetop En( Dafa: May 24, 2016 Project: Lot 18 - Micip Location: Basin 1 1. Basin Storage Volume A) Effective Imperviousness of Tr bulary Area, I, 1, = 62.0 % (100% d all paved and roofed areas upstream M rain garden) B) Tributary Area's Imperviousness Ratio (I - I f100) I = 0.92a' C) Water Duality Capture Volume (WQCV) for a 12-hour Drain Tans WQCV= 0.19 vmlershed inches (WQCV= 0.8 , (0.91, i3- 1.19' 2. 0.78 *1) Of Contributing Watershed Area (including rain garden area) Area = 14,418 sq It E) Water Quality Capture Volume (WDCV) Design Volume Vwvcv = cu It Vol - (WQCV / 12) - Area F) For Watersheds Outside of the Denver Region, Depth of ds = 0.43 In Average Runoff Producing Stem G) For Watersheds Outside of the Denver Region, Vwocvomee - 233.6. cut 9 Water Quality Capture Volume (WOCV) Design Volume H) User Input of Water Ouallty, Capture Volume(WQCV) Design Volume Vwvcv usse= cuff (Only it a different WQCV Design Volume Is desired) 2. Basin Geometry A)WQCV Depth (12-inch maumum) Dwocv- 12 In B) Rea Garden Side Slopes (Z - 4 min., hone. list per unit vertical) Z - 4.00 6 / fl (Use "0' 8 rain garden has vertical wells) C) Mlmlmum Flat Surface Area A.e, - 199 sq a D) Actual Flat Surface Area A, = 245 sq it E) Area at Design Depth (Top Surface Area) A, = 835 sq it F) Rain Garden Total Volume V, 540 cu g (Vr ((AT.. A,,.) / 2)' Depth) 3. Graying Media chnsa one 018" pout Gad. GFwag MMIa Q other (6lmletiq 4. Underdrain System A)Ara undartlralns provided? Chou One O YES NO B) Underdeen system orifice diameter for 12 hour drain time i) Distance From Lowest Elevation of the Storage y= WA ff Volume to the Center of the Critics 1) Volume to Drain in 12 Hours Vcl,z= WA cut it III) Orifice Diameter. 318" Minimum D. = N/A in UD-BMP v3.03 Basin i, RG 512412016, 4.39 PM Design Procedure Form: Rain Garden (RG) Sheet a el z Designer: MRB Company: Rldgetop Engineering Date: May 24, 2016 Project: Lot 18-Midpoint Drive Location: Basin 1 5. Impermeable Geomembrana Liner and Geomidde Separator Fabric aooecOns, 0YES AI Is an Impermeable Ilner provided due to proximity QND of structures or groundwater contamination? 6. Inlet / Oullet Control Choose one Q Sheet FPow- No Energy Dissipation Rlctured A) Inlet Control O Concentrated Flmv- Energy Dissipated Provided Choose One 7. Vegetation QSeed(Plen for frequent waedcontrol) Q Plantings Q Send Grown or Other High Infiltration Sod B. Irrigation Choose one YES NO SPRINKLER HEADS ON FLAT SURFACE A) Will the rain garden be Irrigated? ONO Notes: • • C • • • • • • • UD-BMP_v3.03_Basin 1, RG • 5/24/2016, 4:39 PM II Design Procedure Form: Rain Garden (RG) 11 Designer: MRB Company: Rldgetop Engineering Data: April 27, 2017 Project: Lot 18-Midpoint Or Location: Basin 2 I. Bash Storage Volume A) Effective Imperviousness of Tributary Area. I, I, = 53.0 % (100% if all paved and roofed areas upstream of min garden) B) Tributary Area's Imparviousriess Ratio (I =101100) = 0.530 C) Water Duality Capture Volume(WDCV) for a 124%nur Drain Time WDCV= 0.17 walershed inches (WDCV=0.8"(0.91. 1'- 1.19-1'-0.78.1) D) Centrtbuflrg Watershed Area (including min garden area) Area = 23,029 sq it E) Water Duality Capture Volume(WOCV) Design Volume Vwocv' cuff Vol = ( WDCV 112)' Area F) For Watersheds Outside of the Denver Region, Depth of it. = 0.43 In Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region. Vwewoiesn - 32025i cu fl Water Duality Capture Volume (WDCV) Design Volume H) User Input of Water Ouellry Capture Volume (WDCV) Design Volume Vwacvussn = cu a (Only it a different WDCV Design Volume Is desired) 2. Basin Geometry A) WDCV Depth (12-inch maximum) Dwaw = 12 In B) Rain Garden Side Slopes (Z = 4 min., hodz. disl per unit vertical) Z - 4.00 hill (Use "0" N rain garden has vertical walla) C) Montreal Fiat Surface Area Aw„ = 220 sq It D) Actual Flat Surface Area A.a,w - 501 sq 8 E) Area at Design Depth (Tap Surface Area) A,. = sq It F) Rain Garden Total Volume Vr= cu tt IV,- ((Arun - A„e,)12) • Depth) 3. Griming Media aoo'a 0ae Q 18' Pain Garden 6rowhq Made Q Other (Explain): 4. Underdreio System A) Are underdrains provided? moose one O YEg Q NO B) Underdrein system orlgce diameter for 12 hour drain lime I) Distance From Lpwest Elevation of the Storage Y. WA If Volume to the Center of the Orifice Iq Volume to Drain In 12 Hours vul, = NIA cu a i10 Orifice Diameter, 318" Minimum U.-, = NIA in LID-BMP v3.03 Basin 2. RG 4 27 2C17 2 19 PM r-1 • Design Procedure Form: Rain Garden (RG) 51,02of2 Designer: MRB Company: Ridgetop Engineering Date: April 27, 2017 Project: Lot 18-Midpoint Dr Location: Basin 2 S. Impermeable Geomembrane Liner and Gemextile Separator Fabric rChoose ones I Q YFS A) Is an impermeable liner provided due to proximity I Q NO of structures or groundwater contamination? 8. Inlet I Dullet Control Ors, I Q Sheet Flow- No Energy Dlssipa0oo Required A) Inlet Control I Q Concentrata0 Flow. Energy Dissipation Pmvked CTIWH DIK' 7. Vegetation QSee0(PWn for frequent weed cunlsel) Q Plantings 0 Sand Grew or Other High Is txdon Sad B. Irrigation Choose One 1p' 1 ® YES NO SPRINKLER HEADS ON FLAT SURFACE A) WIII the min garden he irrigated? I ONO Notes: 41Z72017, 2:19 PM LID Table 75% On -Site Treatment by LID Requried mpervious Area 15.691 sq. ft. red Minimum Impervious Area to be Treated 11768 sq. ft. tributary to Rain Gardens 13,751 sq. ft. )n Area N/A sq. ft. vious Area Treated by Rain Gardens 13751 sq. ft. Actual % On -Site Treated by LID 88% Overflow Weir Calculations PROJECT: Lot 18 - Midpoint Dr Basin/Pond: Basin 1 Date: 1/8/2017 Per UDFCD Chapter 12, Section 5.14.2 Q = flow (cfs) CBCW = Broad Crested Weir Coefficient L = Broad -Crested Weir Length (ft) H = Head above Weir Crest (ft) Z = Side Slope (horizontal : vertical Equation 12-20 Q = (CBcw)(L)(HA1.5) CBcw = 3 L= 4 H = 0.5 Equation 12-21 Q = (2/5)(CBcw)(Z)(HA2.5) CBcw = 3 Z= 4 H = 0.5 Q = 4.243 cfs Q = 0.849 cfs Total Flow Over Weir Q = (Eq. 12-20) + (2)(Eq. 12-21) = 5.940 cfs Design Ono at Basin = 2.98 cfs Total allowable flow over weir exceeds the Design Q m C Overflow Weir Calculations PROJECT: Lot 18 - Midpoint Dr Basin/Pond: Subbasin 2 Date: 4/27/2017 Per UDFCD Chapter 12, Section 5.14.2 Q = flow (cfs) CBcw= Broad Crested Weir Coefficient L = Broad -Crested Weir Length (ft) H = Head above Weir Crest (ft) Z = Side Slope (horizontal : vertical Equation 12-20 Q = (CBcw)(L)(HA1.5) CBcw = 3 L= 4 H = 0.5 Q = 4.243 cfs Equation 12-21 Q = (2/5)(CBcw)(Z)(HA2.5) CBCw = 3 Z= 4 H = 0.5 Q = 0.849 cfs Total Flow Over Weir Q = (Eq. 12-20) + (2)(Eq. 12-21) = 5.940 cfs Design Qioo at Basin = 3.07 cfs Total allowable flow over weir exceeds the Design Q Stormwater Detention and Infiltration Design Data Sheet Lot 18 - Pond 1 Stormwater Facility Name: Facility Location & Jurisdiction: 2590 Midpoint Dr, Fort Collins User (input) Watershed Charauterisl Watershed Slope = Watershed Length -to -Width Ratio= Watershed Area = Watershed Imperviousness= Percentage Hydrologic Soil Group A = Percentage Hydrologic Soil Group B = Percentage Hydrologic Soil Groups C/D = 0.005 2.00 0.50 50.0% 0.0% 0.0% 100.0% L: W User Input: Detention Basin Characteristics WQCV Design Drain Time = 12.00 hours After completing and printing this worksheet to a pelf, go to: https://mauerture. digita Idataservices. com/gvh/7viewer=cswdlf. create a new stormwater facility, and attach the pdf of this worksheet to that record. Design Storm Return Period - Two -Hour Rainfall Depth = Calculated Runoff Volume = OPTIONAL Override Runoff Volume = Inflow Hydrograph Volume = Time to Drain 97%of Inflow Volume Time to Drain 99%of Inflow Volume = Maximum Forcing Depth - Maximum Ponded Area - Maximum Volume Stored - • • Drain times Pond 1, Design Data User Defined Stage [III User Defined Area IftA2] User Defined Stage ]it] User Defined Discharge Ids] 0.00 1 0.00 0.00 0.50 245 0,50 0.00 1.00 601 1.00 0.14 1.50 835 1.50 0.14 2.00 1,085 2.00 0.14 3.00 1,665 3.00 0.14 3.50 1,921 3.50 0.14 4.00 2,228 4.00 0.14 4.50 2,600 4.50 2.98 Rm,tpd Hvdrnarnnh Rp<i lta WQCV 2Year 5Year 10 Year 25 Year 50 Year 100 Year 0.53 0.98 1.36 1.71 2.31 2.91 3.67 0.007 0.019 0.033 0,047 0,072 0.095 0.127 0.007 0.019 0.033 0,047 0.071 0.094 0.127 9 7 6 5 7 8 11 10 9 10 10 11 12 12 0.72 1.16 1.71 2.19 2.88 3.4U 4.02 0,009 0.015 0.022 0.027 0.037 O.U43 0.051 0,003 0.009 0.019 0,030 O.OS2 0.073 0.102 in acre-ft acre-ft acre-ft hours hours It acres acre ft 11/23/2016, 7:11 AM L- Stormwater Detention and Infiltration Design Data Sheet 3 F RIN R OUT IN 2.5 - OUT 2 � 1.5 0 1 0.5 0 0.1 4.5 —100YR 4 3.5 3 r p 2.5 0 z z e 2 1.5 1 0.5 0 D.1 t Drain times Pond 1, Design Data 1 TIME [hr) 1 10 DRAIN TIME (hr] Stormwater Detention and Infiltration Design Data Sheet Lot 18 - Pond 2 Stormwater Facility Name: Facility Location &Jurisdiction: 2590 Midpoint Dr, Fort Collins User (Input( Watershed Characteristics Watershed Slope= Watershed Length -to -Width Ratio = Watershed Area = Watershed Imperviousness= Percentage Hydrologic Soil Group A= Percentage Hydrologic Soil Group B = Percentage Hydrologic Soil Groups C/D= ft/ft L:W acres percent percent percent percent 0.005 2.00 0.47 53.0% 0.0% 0.0% 100.0% User Input: Detention Basin Characteristics WQCV Design Drain Time = 12.00 hours After completing and printing this worksheet to a pdf, go to: httos://ma oerture.dieitaldata servlces.com/evh/?viewer=cswdif. create a new stormwater facility, and attach the pdf of this worksheet to that record. Design Storm Return Period Two -Hour Rainfall Depth Calculated Runoff Volume OPTIONAL Override Runoff Volume Inflow Hydrograph Volume = Time to Drain 97% of Inflow Volume Time to Drain 99% of Inflow Volume Maximum Ponding Depth Maximum Ponded Area = Maximum Volume Stored r rr 0 r rr r rr Routed Hvdmcraoh Result, WQCV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 0.53 0.98 1.36 1.71 2.31 2.91 3.67 0.007 0.019 0.033 0.045 0.069 0.091 0.121 0.006 0.019 0.032 0.045 0.068 0.090 0.121 9 9 a 8 7 7 8 10 10 10 10 11 11 13 0.59 1.D4 1.41 1.69 2.02 2.25 2.52 0.009 0.014 0.026 0.046 0.074 0.093 0.116 0.004 0.009 0.016 0.026 0.045 0,065 1 0.093 in acre-ft acre-ft acre-ft tours tours t ¢res ¢re-ft �. Drain times Pond 2, Design Data 4/28/2017, 1:11 PM Stormwater Detention and Infiltration Design Data Sheet zs —100YR IN — — 100YR OUT 2 1.5 - t 3 0 1 0.5 0 .......................... 01 TIME [hri 3 —100YR —50YR 25 2 s_ x 0 z 1.5 e z 0 0 1 0.5 a Drain times Pond 2, Design Data 0 0.1 1 10 DRAIN TIME [hr] 4/28/2017, 1:11 PM Appendix F Maps Project # 16-015-002 Page 14 sun• sia+ n � +NXr¢N vAl.t s.vlNG :/ •: Et:µ-r-•t �'>A[:S"-I � I 1 " . me / QrNC+[) fAMAAM INt[41A1. CwftlllltL t0 C➢w .41 CAIWIIWMIP2 m cow .COT BEDDING REOUIRMENTS Cttyof „FOFIin58,VVVV B PIPE TRENCH AND BEDDING DETAIL NTS U 40 MITT ^MG O ,D N40 W.tl Ilo.1 suX. 0 W TRAFFIC RATED CLEANOUT cm, CoL ns 5+ 11'�!,'1 I'i a N'MC N - 1ik 1tHl �VI l L�rVIUi i VVW-15 CLEANOUT DETAIL NTS SUBBASIN 1.0 POND BOTTOM. M96.M WOCV EL 4897.50 DEEVIRM DMRQ DIM 1-13/16- DE7ENTIm OIFBCE IF 4B17 •BD OD -AR WSEL 490000 TOP OF POND EL: 49DO.50 TOTAL POND DE➢M: 3.5' 5LIBBASN 2.0 POND BOTTOP. 4896.65 WON EL 1697.65 DETENTON ORFifF DINT.: 2-1/2' DETENTION ORIFICE E: 4897.66 100-1W WYL 4899.30 TOP OF POND EL 4899.80 TOTAL POND OPTI: 2.64' TOP OF POND ELEV. r • , 4 POND TOP ELEV. STAINLESS STEEL PLATE 100-YR ELEV. 100 YR ELEV. I STAINLESS STEEL PLATE I I < - ORIFICE OIAM. WOCV (ORIFICE IE) o 4 POND BOTTOM .—I � -� - � �1 . �n.n n.+T.n,, r r„ - - . • . - 30' DIM ADS DRAIN BASIN OR EOUIVA.ENT - SOLID UO FLUSH WITH BOTTOM OF POND - SIDE PERFORATORS - - RAIN GARDEN L �I EDT � ER 4' PERFORATE PIPE PER DRAINAGE PLAY -- 90' DOWNTURNED EIROW W ai TELL DRAIN BASIN MtH WASHED 12 ROCK - PERFORATED BOTTOM WTH I' DIM, NOES ` VNGlsturbeG Soll� DRY WELL DETAIL NTS I' T CONCRETE VALLEY CUTTER PAVEMENT MINIMUM 5' BAY COURSE NOTES. 1. 30PE SMALL PROMOTE F09TWE DRAINAGE TO ORAINACE STRUCTURES. SLOPE TOWARDS OR AWAY RON CURB AS REOUIRED. 2. EXPANSION JOINT PLACE AT ENDS OF Al RADA, 5' ON EACH SIDE OF DRAINAGE STRUCTURES, AND AT 0 MAX. INTERVALS IN STRAIGHT CJRB AND GUTTER. PROVIDE 16 118' LONG SMOOTH SUL DONEE BARS MT 1'r GREASE CAP THROUGH EXPANSION JONTS. (1/2- THICK BITUMINWR FILLER MATERIAL) 3, CONTRACTION JOINT: PROVIDE Y DEEP , 1/4- WOE CONTRACTOR JOINTS AT 15'INTERVALS. 4. 2'-6' LONG DE BAR ON 2'-6' CENTERS SNARL BE PROVIDED WHEN MRS IS ADJACENT TO PC C. PAVEMENT. 5. PROVIDE 2 06 A 2-6' LONC TE BARS TO CONNECTEXISTING AND NEW CURB AND OJTIER. 6. REMOVE FORMS AS EARLY AS POSSIBLE BRUSH TOP AND FACE OF CURBS TO REMOVE ALL IMPERFECTIONS. TYPICAL OF ALL FORM WORT(. 7. UGHT BROOM FNSH ON All EXTEMOR CONCRETE DRAIN PAN NTS WO AND OUTLET STRUCTURE N TS A, .c etNSPbrslM s�MwW5 xnEN ts• oE a seenm nNNWiM$IpN _ 7 J tTM., ITN MAn �� L I G¢AVNI£ON NAnmu — x-scAAIv SECTION A -A wAn IB B� ' nfurswe. WIOIwYR x' cu. s•Eei wwn T I`.2'rN'Ghv. NWGI[ w.nN.W nYr1 SC! OlT1LL I ` CA Ing W.W( vION I_. g c WR 10lW NNY SECTION B-8 Cvb - tC 1)'p IYW A` (-GA V. EWIM REn l-S Pe J'3' STE$I.ATE 1{-MASS SCIRW IWWITMbMIINMO e..p. T [SfEO RYSN WE ZM r4W PLAN O.C. l401T r.rNx• rX "eW"A ( OC WG4 ANGII ,W .OTT O.0 SECTION C-C DETAIL 1 !:ETAL SIDEWALK CULVERT FOR 'VERT. CURB & GJTTER AND DETACHED SIDEWALK - OUTFALL TO CURB TOSTORMWATER ZE C oor uPs, _ DETAILAoc�t wns CNSiRUCT10N DETAILS N D-1r B .NI uvl-nm GN4NN !++' p. 4CGEN METAL SIDEWALK CULVERT - DETACHED SIDEWALK (CONCRETE OUTFALL) NTS CITY OF FORT COLLINS. COLORADO UTIIJTY PLAN APPROVAL APPROVED: CITY ENGINEER DATE CHECKED By: --- WATER A: WASTEWATER UDUTY DATE CHECKED BY: STORMWATER UTILITY DATE CHECKED BY: PARKS AND RECREARON DATE CHECKED BY: TRAFFIC ENGINEER DATE RIDGETIOP � ENGINEER]NA: & A'IINN II L'l INI: rv+N a.nr Nw. SEx PROJECT TIRE LOT 18, PROSPECT INDUSTRIAL PARK 2590 MIDPOINT DR FORT COLLINS CO PREPAREOFOR R4 ARCHITECTS 226 REMINGTON, UNIT 3 FORT COLLINS. CO BUBM TIAL FINAL DEVELOPMENT PLAN uunwN ev uc.n CHF 1", I, EY MITI, PROJECT NG 1601'i110) ommuON6 . : _-mm CITYCOMMENTS 09fOs01• CRYCOMMENTS OL2il2bl; CONSTRUCTION CHANOES Pit ...0, OATS 7/27/2016 BHEEFTTTLE. STORM & SEWER DETAIL SHEET SHEETINFORMMIDN C-4.2 SUBBASIN 3.0 AREA = 0.053 AC Ud z Z 0 a 0 ad LOT 19, HOLSINGER DRYWALL RAN � Will MOD, See Menin MHAR ]PIN Man evil WATER QUALITY TREATMENT LEGEND SUBBI 1 (RAN Gai PoNMNG AEA) Si 2 (RAN GNDA POIgNG ASu BA9N BOUNDARY see 1G0-m Mss - � AM AAAAAAM nrMl lO • P222 e e ® e e e DEMdI RYFI AND Wo � r 41, -- SUBBASIN 2.0 — AREA = 0.470 AC I tOD-1F/II MRR 9JiAS �—_ BEWTIBM-IewdO BUILDING 9,047 SF SUBBASIN 1.0 �FE = 4901 AREA = 0.331 AC 75 % On -Site Treatment b) Gervious Area d Minimum Impervious Area to be Treated )utary to Rain Gardens Area Treated by Rain Gardens Actual % OnStte Treated by LID 181 11768 Eq. ft. 13,751 sq. ft. N/A sq. ft. 13751 sq. ft. 86% ,arkin Builtll�l later SUAd[e ENGINEERINGi CONSML G IDf watlPyNfd. T M3224500 IIIw aminion m• Mesw,06N Qe/L 12' Ponding Depth Inimum 12' mICN (Ayer _ OF eloreter Lion Sand Media CONNEQ ONOERDRAIN (see Blonuentlon Sand TO DRY WELL Media SpeCficatIGn below) J • ove and Sel=M _� COOT No. 4 Aggregate &M/K PVC Pipe (Optional Depending on Underlying Soil Conditions) BIORETENTION CROSSSECTION NOTE' ONTFACTOR TO ETON TO THE ER09O1 OGNTRO PUNS FOR TEMPORARY MEMIRIES WRING ODMORTAROI TO UNIT THE AMOUNT O )MRBANCE 00 HEAVY EWINENT EITTIN THE RAN GARDEN FORD AYAi ALBO EN9R3£ PROPER BMPIS AND EEOUENONG 5 FOLLOWED TO PREVENT LOA9NG OF THE CNAINAO WITTY end aDMENT DURING WISTRUCTOI, CITY OF FORT CONLINE [RNDON 3AND UMA NEOFIC AT PART I GENERAL An N SW I N HOOD Nre r .NPnN ter, .tea Dee d N,I ma >a M .N«,N x Nea,e,m. w+rPNe�eYriw�Mw mai.NnPM,an�.`M:n.m°Yu anN+oMN+ e Pwc,a. C. EUB/rtdMB®1tivr W,w.,w w�,rwrvlNYlo,NmMtlela,n4awnNw' P.YeLvalo EH3D ends 3. MryNµignxo,sLl�Me a -a a,sP lm bxwl�ire LLreaPn euanen w Glr, FYv p OEpeAY ICECI Peam,A�lPtin IYAy. i� ?�IbWePM✓�IUIIINwvwrcN��bPq.�.eNW Wnnndv wQtlYE. p ,iio as m. a"vl w: Irenae,�o�. �mm,.r wwrn mwam°�n,ewe.ERAam, a me o.Nr. vAm z. wL wTERMLs A sea PSM swmrld Wlov.LwpM,ne,nslM AVIM C.u. a sN.em PePw rrl NLE mwv a 3.,Dx a1..aYa PePw >,.wn.. FAW]LgrgevbbfYIMM.SPasNnenMCs^L,Ya z11W DVCV. a. sN.ne rPM NeRRP,waYr.w rw.,nr N,weaw am.wNr r MPw V N Mm „YM,MPaA aw w Pwvn, rA,,,N,-a. c. OMAN eaA3 Yvr e.ru a }I oti McMe a.a.,.. 2 waNYrtloYYenEM/Nn. M,YsuLLPbmpw llsOAlanvY4WPY wnensNaw„eMYL .. PW.,vEYmYYtlYlMbusl�kµl Tmn.y.Y MYA r PMMn,.e m m.E aewrDM e s r,.0 atl a Y �iNwY�NM,T wu�ge.nrr�euetl ReseEE nen,. w..e.belp„Kn, Ni w 0. TG maJ� 4W nwu5Nse WrrMslbw. MLan bn%. 0. WC pY esM N+m+l a I oa3x w a,nom, m wwre.. a wnPn P�oMPm�l aevww.m�„I`n ni een,:e:�°Nd�:Ke� muJtl mdko ae11N O peeY vttrt aremF'antr. YpEE9nNMBMDY A AT I Wmadated. aw a Haw DNA m OXMI&I ma� 0A wPIHN ves SHIP 10oMn Sea Of Device Aw',I oTue pnN� NM I end, Ad Whine NnAl de, handean 35 and SO PH Pent mN.. * yNand Irene, Me, Ed plum mabM1y d.,er emaseN M wanenwp N emmna,wrsPnn ASHISCH aw,M mAca,o, ugavu,u v. W,uew Pai e+weuM a¢AGmenlaWMreN W,b 4 p can dr+INIM aae n. %JIWe Me awnbnl Na M an Inner Her Idea We Po• ^ein he as MNIMI . %agorae ombM dra M m ghdi Xun did earn, Per Mlkn L vY lfvnl vlulMxuMOE pm pr,ribn x. cM,Nw P.na�.,,Y. ,nLM w .ww us EPA cw A N.aw. AD cm $W.,3. ieNn I E 3YsiY I. PwNPA.mrlPe.re us EPA CYMn NNa.a.w aRSM.3MArr PAn3-EMEO. M A l+vwY PMNbpggqRkhWx�b..snAnrvW.emenb. R .4M.Y L«ba ieaA1 naval ew r vw wNN m DPMNw YywA s TINJPY.atlb,nNNYI�M.Mnew••w na Nree E.,w.. } iwmM+an nrb NnM NRMNe. aoRE,ENngI SAND MEDIA SPECIFECATIAN E Ott OF FORT GOWNS, COLOtADO HUTT PUN APPROVAL j APPROVED: 1 Ott ENGINEER DATE CHECKED BY: WATER a WASTEWATER URUW DATE 17Ea(ED BY: STORMWATER UTIUTY DATE I OIEOED BY: _ PARKS AND RECREATION DATE I CHECKED BY: ' TRAFFIC ENGINEER DATE PROJEnTTRLE LOT 18, PROSPECT INDUSTRIAL PARK 2590 MIDPOINT DR FORT COLLINS, CO PREPARED FOR R4 ARCHITECTS 220 REMINGTON, UNIT 3 FORT COLLINS, CO SUBMITTED FINAL DEVELOPMENT PLAN DMNW BY BSA CHECKED By MRS PROJECT NO: I60150S1 RENSIONS RITE CIT"COMMENTS DAhDgPa CITYCOMMENTS GiO272%7 COAST1`UL710N GVNGES M M017 wIPee 7/27/2016 SHEETma DRAINAGE PLAN sHFFr IFFORMATM C-2.1 IDIWw whals below. I mPa - eD R. Call before you 7 Or 11