HomeMy WebLinkAboutDrainage Reports - 09/26/2016STORMWATER & EROSION CONTROL REPORT FOR City of Fort Collins Approved Plans Approved by: Date: q-2(o- /(o KIND CARE 6617 SOUTH COLLEGE AVENUE FORT COLLINS, COLORADO 80525 Project Number 2360-15 'October 10, 2015 , Revised April 10, 2016 Revised June 10, 2016 Prepared for: 6617 South College LLC 6617 South College Avenue Fort Collins, CO 80525 Prepared by: Forbes Engineering 2908 Cherly Street Fort Collins, CO 80524 Phone: (970) 295-4874 TABLE OF CONTENTS PAGE CERTIFICATION 1 I. GENERAL LOCATION AND DESCRIPTION A. Site Location 2 B. Description of Property 2 C. Flood Hazards 2 II. DRAINAGE BASINS AND SUB -BASINS A. Major Basin Description 3 B. Sub -basin Description 3 III. DRAINAGE ANALYSIS CRITERIA A. Regulations 3 B. Hydrological Criteria 4 IV. DRAINAGE FACILITY & DESIGN A. General Proposed Concept 4 B. Specific Drainage Design Details 4 V. SWMP CONCLUSION 5 VI. EROSION & SEDIMENT CONTROL A. Analysis of Site & Proposed -Construction 6-8 B. Stormwater Management Controls 9 C. Dry land vegetation 10 D. Detailed sequence of construction activities 11 E. Erosion Control Security Calculations 12 VII. EROSION CONTROL CONCLUSION 12 VIII. REFERENCES 12 VIII. APPENDICES 13 CERTIFICATION: I hereby certify that this preliminary stormwater plan & report for the Kind Care site development located at 6617 South College Avenue was prepared by me and meets or exceeds the criteria in the City of Fort Collins Stormwater Management Manual. Kevin Forbes Registered Professional Engines State of Colorado No. 35265 1 t I. GENERAL LOCATION AND DESCRIPTION A. Site Location The Kind Care Site Development is located in the Northeast quarter of ' Section 14, Township 6 North, Range 69 West of the 6 h Principal Meridian, County of Larimer, State of Colorado. The property lies on the west side of US Highway 287 (South College Avenue) approximately 100 feet south of West Trilby Road. See Vicinity Map in the Appendix. B. Description of Property ' Currently, the property area is approximately 141,957 square feet (3.26 acres). Of this 6175 square feet will to be dedicated to US Highway 287, leaving 135,782 square feet (3.12 acres) as the site development area. The ' lot is currently developed for commercial use with two businesses on site. The west portion contains a gravel yard, an open shed and a 9200 square ' foot building used as an office/warehouse. The east portion contains the Kind Care business which is made up of three buildings, a gravel parking area, an asphalt drive and various concrete walks and pads. Landscaping ' borders the project site on all sides. ' Other than a very small portion of landscaping located at the northwest corner of the property, the site has a very slight slope towards the east (approximately 1%). Currently there isn't any detention on the site although ' it appears that because of the shallow grade there has been an uncertain amount of surface run-off that pools along the landscaping area along the east side of the property. The soil classification for the Site is a Fort Collins loam (3-5% slopes). Fort ' Collins loams belong to the hydrologic soil group B, as assigned by the Natural Resources Conservation Service. Run-off is moderate and the hazards of wind and water erosion are slight to moderate. Depth to seasonal ' high water table is greater than 6 feet. ' C. Flood Hazards The Site does not lie within any floodplain. No known drainage studies ' exist for this Site and there are no wetlands associated with the Site. 2 H. DRAINAGE BASIN AND SUB -BASINS A. Major Drainage Basin The property is located southwest of and drains into the Stone Creek Basin which is part of the Fossil Creek Drainage Basin. The property drains into the west street gutter system of South College Ave which enters the stormwater system and the intersection of Trilby & College. From there stormwater run-off is transported to Stone Creek. No adverse effects to the Stone Creek Basin are anticipated with this development. B. Sub -Basins Both the existing & proposed drainage for the site is broken up into 3 sub - basins (see historic & developed drainage sub -basin maps in the appendix). Sub -basin A contains the majority of the site and is located in the southern portion of the property. It is fairly flat with an average slope of 1 % towards the east. The outfall is at the landscaping area along the west side of College Ave. Sub -basin B lies in the northwest portion of the property and also slopes east at a 1% slope. The outfall for Sub -basin B is into an existing pipe system that spills into Sub -basin A. Sub -basin C is located in the northeast portion of the property, it slopes east at an approximate grade of 2% with a non -concentrated sheet flow release into the west gutter system of South College Ave. The difference between the historic and developed sub -basins concerns the areas of the sub -basins only with a larger portion directed towards and into Sub -basin A as a result of the new building roof lines. III. DRAINAGE ANALYSIS CRITERIA A. Regulations The analysis of the storm drainage system for this project was prepared in accordance with the criteria set forth in the City of Fort Collins Stormwater Criteria Manual and the Urban Drainage and Flood Control District's Urban Storm Drainage Criteria Manual (USDCM. 3 ' B. Hydrological Criteria 1. Design Rainfall Intensity -Duration -Frequency ' Table for City of Fort Collins 2. Runoff Method Rational 3. Design Storms a. Minor 2-year b. Major 100-year IV. DRAINAGE FACILITY & DESIGN A. General Proposed Concept As expressed in the sub -basin descriptions, the change between the historic and developed drainage patterns is minimal. Existing drainage patterns will be maintained and utilized as well as a portion of the existing pipe system. Surface stormwater run-off will be detained and released at the two year historic flow rate into the west gutter system of South College Avenue. Additional volume in the detention pond has been added to account for the water quality capture volume. The WQCV has been calculated at 1846 cubic feet. ' B. Specific Drainage Design Details ' As described above, the existing drainage patterns will be maintained and erosion control measures will be installed (see Erosion & Sediment Control ' section in report). The Low Impact Development design method chosen for this project is in the form of a 1507 square foot rain garden. The location of ' the LID will be on the north side of the detention pond and will receive stormwater from approximately 72% of the site area. ' The detention pond outlet orifice has been design for a release rate of 2.44 cubic feet per second. The water quality capture volume has been calculated ' at 1846 cubic feet and the required 24 hour drawdown water quality orifice has been designed using six (6)'/4" diameter holes. 4 V. SWMP CONCLUSIONS Stormwater Management Conclusion ' A high water (no build) line has been added to the drainage map that ' delineates the 100 year watershed elevation with a 1/2 foot freeboard. The closest building is approximately 45 feet away & 2.32 feet above this line and will not be affected by the 100 year storm water detention or run-off. ' The analysis of the storm drainage system for this project was completed in accordance with the criteria set forth in the City of Fort Collins Stormwater Criteria Manual and the USDCM. No adverse effects to surrounding properties are anticipated from the proposed improvement of this site. 5 VI. EROSION & SEDIMENT CONTROL A. Analysis of Site & Proposed Construction Current Developed Condition The total site area (excluding the ROW dedication to US Hwy 287) is approximately 135,782 square feet (3.12 acres). The entire lot is currently developed for commercial use with two existing businesses on site. The western portion contains a gravel yard, an open shed and a 9200 square foot building used as an office/warehouse. The eastern portion contains the Kind Care business which is made up of three buildings, a gravel parking area, an asphalt drive and various concrete walks and pads. Landscaping borders the project site on all sides and the existing percent of vegetation has been estimated at approximately 35%. Nature & Purpose of Construction The proposed development is a split of the current single lot into 3 separate lots with site improvements to lots one and three. Lot one will contain the ' Kind Care business and the site improvements for the lot include; an increase in area of the asphalt parking and drive aisle, a sidewalk connection to the sidewalk along College Avenue, a 6 foot wide sidewalk along the south side of the drive aisle, demolition and reconstruction of the western warehouse and the construction of an office addition between the two existing buildings. The site improvements to lot three will include the removal of the existing gravel parking lot and the construction of a detention pond to serve the entire site. ' The site improvements will disturb approximately 44,540 square feet (1.02 acres) on -site and approximately 4077 square feet off -site. Some of the Site will be graded with topsoil & gravel stripped and stockpiled. The total quantity of cut from the detention pond has been estimated to be 540 cubic yards. It is possible that the estimated amount of cut will exceed the required amount of fill, so some of the existing soil could be exported off of the Site. ' The property is located southwest of and drains into the Stone Creek Basin P 1 which is part of the Fossil Creek Drainage Basin. The property drains into the west street gutter system of South College Avenue, travels north and ' crosses the west side of the Trilby & College intersection. From there the 6 ' stormwater run-off continues north and enters an area inlet approximately 200' north of the Trilby & College intersection. From this point the stormwater run-off enters the existing stormwater pipe system and is transported to Stone Creek. No adverse effects to the Stone Creek Basin are anticipated with this development. 1 Rainfall Erodibility and Erosion Sediment Control Measures 1 Temporary and permanent erosion control measures for the site are shown on the Erosion Control Plans (see sheets C4.0 & C4.1 in insert). The ' construction entrance will be at the existing curb cut along College Avenue. A vehicle tracking mat and concrete washout area will be provided for at the west end of Lot Three. Any and all stock piles for excess cut shall also be located at the west end of Lot Three and will be maintained with a silt fence along the lower end of its base. The location of these areas insures that any erosion sediments will be required to pass through the detention pond area and through the sediment trap located at the outlet box. Other graded areas ' will be left in rough surface condition until covered with planting and wood or stone mulch. The north east portion of the site has a grass surface and releases un-detained via sheet flow towards and into the west gutter system ' of South College Ave. This area will maintain the grass surface as best as possible while the foundation of the new addition is excavated and will have ' a perimeter silt fence constructed on the east end to catch any sediments prior to entering into the gutter system. It is the intention of the erosion control plans that the existing drainage paths will be maintained and left in original conditions & locations. This insures ' that the majority of the site (all but for the northeast portion of the site) will drain towards the detention pond area which will trap erosion sediments prior to exiting from the site. Silt fencing will be installed at the perimeter of the site and at the top of detention area as appropriate to intercept and detain sediment from runoff leaving the site. Other measures utilized in order to control sediment during construction include rock sock bags at curb cuts, curb inlets and at the detention pond outlet structure, as well as permanent seeding in the detention area. Rip rap will be installed as needed at the northern pipe inlet as well as a rock filter installed at the detention pond outlet structure in order to reduce/prevent erosion. 7 Timing & Sequence of BMP Installation Timing sequence of BMP installation is as follows: • Installation of silt fence perimeter barriers at northeast corner and along south and east end of the detention pond area • Construct vehicle tracking pad at the west end of Lot 3 and the detention pond area • Provide downstream inlet protection (rock socks) at existing area inlet located approximately 200' north of Trilby & College intersection • Rough grading with contour furrows for detention pond along with construction of outlet structure and outlet protection (rock filter) • Construct sediment trap at detention pond outlet box • Site Grading, subgrade preparation and foundation excavation • Install base course and rough surface all exposed soil areas • Utility construction — install storm water pipe system. • Footing & foundation installation • Paving and landscaping • Removal of Erosion Control Measures • Permanent seeding in detention areas • Sod Installation as needed g B. Stormwater Management Controls Description of Stormwater Management Controls Stormwater will sheet flow from the building areas toward the ponds. Ponds will be constructed early in the development process, including the bioretention/rain garden feature, outlet structures with water quality plates, rock socks and permanent seeding. The pond will also provide post - development stormwater quality control, as will grass -lined swales and permanent landscaping. All areas that will not be intercepted at ponds will ' be protected with silt fence during construction. ' Stormwater Management Plan Administrator 1 The owner of the property, 6617 South College LLC, shall act as the stormwater management plan administrator. ' Potential Pollutant Sources Disturbed and stored soils. Sediment generation due to disturbed areas (grading & clearing) is anticipated and will be controlled using the lower portion of the detention pond as a sediment trap. The sediment trap will be cleaned out as required. Stored soils are not anticipated but if so then the upper portion of the detention pond (west end of lot 3) will be used to stock pile soil and or rock. The stock piles will be limited to 10' maximum in height and will be required to have downstream toe protection using silt barriers. Vehicle tracking of sediment. A VTC will be installed at the west end of lot ' 3 and connected to the asphalt drive aisle. ' Management of contaminated soils. In the case of a release of fuel or other chemicals, absorbent booms or earthen berms will be immediately constructed to contain the spill and prevent runoff to adjacent surface waters. ' The contractor will be responsible for the cleanup of the released materials and for the removal of any contaminated soils. Loading & unloading operations. These operations will be executed in the area designated for the VTC or the upper detention pond. 9 1 Out -door storage. No out -door chemical storage is anticipated for this project, out -door storage will be limited to building materials and stored near the construction site. Equipment maintenance and fueling. During construction, no on -site equipment fueling or equipment maintenance is anticipated. Significant particulate generating. Due to the sandy loam nature of the site soil, it is not anticipated to have a significant particulate generation, but if so the construction manager is to bring in a water truck to abate the dust generation. Routine maintenance activities & on -site waste management. Good site ' house -keeping procedures including routine cleanup of construction debris and trash removal will be regularly maintained. ' Concrete washing. A dedicated concrete washout area, as shown on the enclosed Erosion Control and Detail sheets (see insert), will be constructed ' prior to placement of any concrete. ' Dedicated asphalt or concrete batch plants. Neither of these construction activities is anticipated for this site. ' Non -industrial waste sources. Both an individual worker trash roll -off as well as portable toilets are anticipated to be installed on this site. The portable toilets shall be anchored and located away from the drainage swales. The location of the roll -off will be up to the contractor, probably set up near the construction trailer or the building site or an area where it can be ' easily emptied or removed. ' C. Dry Land Vegetation The percentage of vegetative ground cover prior to construction is estimated to be approximately 32 percent. Vegetation includes sparse native and non- native grasses. ' The soil classification for the Site is a Fort Collins loam (3-5% slopes). Fort Collins loams belong to the hydrologic soil group B, as assigned by the Natural Resources Conservation Service. Run-off is moderate and the 10 hazards of wind and water erosion are slight to moderate. Depth to seasonal high water table is greater than 6 feet. The seed mix shall be a dryland seed mix and shall conform to the City of Fort Collins standards and specifications. D. Detailed Sequence of Construction Activities Final Stabilization Final stabilization at this site includes: • Building and paved areas • An on -site detention pond with a water quality structure, rip rap overflow, culvert and outlet protection • Storm drain pipes with inlet & outlet protection • Re -vegetation of disturbed areas with dryland seed mix Maintenance The General Contractor (GC) will perform a stormwater inspection of the site at least once per week during construction activities as well as within 24 hours of a storm event. The inspection will be documented on an inspection form appropriate for the Site. As stormwater maintenance issues are identified, the SWMP administrator will direct GC and sub -contractor personnel to execute the appropriate maintenance in a timely fashion. Documentation of the following events will be generated as they occur: • Records of spills, leaks, or overflows, including time and date, weather conditions, etc. • Implementation of specific items in the SWMP • Contacts with regulatory agencies and personnel Along with inspections; silt fence, rock socks and curb inlet protection will be cleaned of excessive sediment when necessary. Rock socks will be checked for undermining or bypass and repaired or expanded as needed. Mulching of bare soils will be checked regularly and areas where it was lost or damage will be re -mulched within seven working days when needed. 11 E. Erosion Control Security Calculations ' Security calculations ' The estimated cost of the erosion control measures is $5,122.50. A detailed spreadsheet is attached to this report. VH. CONCLUSIONS Erosion Control Conclusion The Erosion and Sediment Control Plan will be placed in the City of Fort ' Collins file for this project. The plan fulfills the City of Fort Collins criteria for erosion control. It is understood that additional erosion control measures may be needed if unforeseen erosion problems occur or if the submitted plan does not function as intended. The requirements of this plan shall run with the land and be the obligation of the land owner until such time as the plan is ' properly completed, modified or voided. Details for the erosion control measures can be found on sheets C4.0 and C4.1 of the construction plans. ' VIII. REFERENCES 1. Urban Storm Drainage Criteria Manual Volumes 1 and 2, Urban Drainage and Flood Control District, June 2001, and Volume 3, ' September 1999. ' 2. City of Fort Collins Stormwater Criteria Manual, City of Fort Collins Stormwater Department, 2009. 3. Soil Survey of Larimer County Area, Colorado, U.S. Department of ' Agriculture, Soil Conservation Service and Forest Service, December, 1980. 12 IX. APPENDICES 1. Vicinity Map ' Existing Impervious Area Exhibit Existing Drainage Sub -basins ' 2. Proposed Site Development Layout Proposed Impervious Area Exhibit Developed Drainage Sub -basins 3. Existing Stormwater Run-off Calculations Proposed Stormwater Run-off Calculations 4. Low Impact Development Calculations Rain Garden Spreadsheet Rain Garden Exhibit — Site Capture Percentage 5. Detention Pond Volume Calculations Mass Balance Spreadsheet Detention Pond Volume Calc. Extended Detention Volume Calc. ' Pond Outlet Orifice Plate Sizing Calculations Water Quality Orifice Sizing Calculations 6. Pipe Capacity Calculations ' 7. Tables & Figures 8. Erosion & Sediment Control Escrow Calculations 9. Developed Drainage Plan (insert) ' 10. Erosion Control Plans (insert) 13 VICINITY MAP 8c EXISTING SITE CONDITIONS 3AH AVW31 LU w Z jr. M �✓ Q � Q m Z.w' C�2 �. 3Ad 3031100 OS ON CO) O NOl ON1��jn8 ' S0131HSIs I M � U o O co ON IIIH 1JVI OS 0 Q N II Nou"mO mou co � U RC jl 1 ----- I I �R G J I I �I V) O W > m j —= 0U0 ZW N - Z U) w O WQz �+ Z W 0 w w 0 W U) W U $ g 0 0 O Z o F UW 0 Ow am � p U LLI O Z Q U O g g LS It O a Z CZ_'! N<Oce if if 0 Q m U a m V) z �- Q W N m O N m J LiIW— cn > Q U Q w _Z F=- Y Q � (if w W m � Q � Q zcU) U U) z_ X O Y W z 0 F Z t3 C so 000 old A C4 A m A H A 8 (n (ip PROPOSED SITE DEVELOPMENT LAYOUT 8c DRAINAGE � SUB —BASINS 0 IT in L� U- U- L� L� V1 V1 V1 V1 fn ID � 0 , N Of (n �' N , IM 0 CZ W o U) — � Zp zao w a -(-)I 8cr0o A N N M 0 F 1— co z LLJ N O -j LEI Ed � � Q Lj 0 LLJ t Y } LLJ m Q U 10 Z 9R V J O \ \ /N r1^5 Of W D (,7 7 CL �m >o cn oZ o �a 0 o o0 o f a_ rn 0 = � LLJ X In L6'I ~ V O U (/f � Z m O U m m O p Y w C O W E z oN C ` a o ° o OfO:f Q 0 W U O V) 3 K J z a € O� 'tN Z O F W F cW—i 0 O 0 La W U O K Z Q U Z U. O O z o _c fn % I C Q m U 0 a �U � m z U) F— to a z � m N � I m O N j I— W Q �l w Vif C) z LLJ LL- LLI Q ~ Y 52 W w m ED U Q O U) U a O 0 O _Z a- z Y (iD EXISTING 11 • PROPOSED STORMWATER � RUN-OFF � CALCULATIONS FORBES ENGINEERING STORM WATER RUNOFF CALCULATIONS KIND CARE SITE DEVELOPMENT FORT COLLINS, COLORADO Table RO-11 Rational Method Runoff Coefficients for Composite Analysis Steep, >7% 0.35 Job # 2460 Client: HIND CARE Date: 2/20/16 By: KEF Composite Runoff Coefficient Using Formula RO-8 Where: C = 21 Ci Ai / At 0 C = Composite Runoff Coefficient C 1= Runoff Coefficient for Specific Area (Ai) A i = Area of Surface with Runoff Coefficient of Ci, (acres or feet2) n = Number of different surfaces to be considered At= Total Area over which C is applicable, (acres or feet2) NOTE: Landscaping considered as Lawns, Heavy Soil, Flat, <2% C = 0.20 Existing Conditions for Basin A Watershed Note: Historic stormwater run—off for this area sheet flows for approximately 204 feet from the west property line to the paved area, then enters a shallow concrete pan and travels approximately 67' to enter into a pipe system approximately 212 feet long that discharges at the east end on the property. From there the stormwater enters the west curb & gutter system of US 287. Basin A Areas 1 AL(Landscape) Sq Ft 21.271 Ac(Conc) AR(Roofe) Sq Ft Sq Ft 632 7696 Using the Infrequent Storm Adjustment Factor (Table RO-12) Storm Return Period (years) Frequency Factor Cf 2 to 10 1.00 11 to 25 1.10 26 to 50 1.20 51 to 100 1.25 AG(Gravel) Ap(Pavement) At (Total) Sq Ft Sq Ft Sq Ft 52,007 18,226 99,832 C = 0.50 (2.29 AC) Adjusted Composite Runoff Coefficients C 2 C 100 0.50 0.63 Page 1 Storm Water Runoff Calculations Continued Calculated Using Rational Method Notes: 1. Runoff Coefficients (C) are from the City of Fort Collins Stormwater Criteria Manual, Table RO-11 and the Composite Runoff Coefficients are from the previous calculations 2. Rainfall Intensity (I) is from the Developed Intensity —Duration —Frequency Curve for the Fort Collins area Basin A Existing Conditions Cz Cloo Area (A) = 99,832 'SF = 2.29 Acres 0.50 0.63 Time of Concentration TC = T1 + TT — Initial Flow Time TI = [(1.87)(1.1—CxCf )(D)1/$]/(S)1/3 C5= 0.50, D = 204 ft, Drop = 3.5 ft, S = 1.72% T1= 13.4 Min & 10.5 Min — Overland Travel Time (paved & shallow gutter) L=67ft, Drop =1.7ft, S=2.5% From Fig. RO-1 V = 1.5 fps TT = 45 sec = .75 min. — Travel Time in pipes L=212ft, S=0.9% V=5.26fps TT = 40 sec = .67 mina Total Time of Concentration 2yr, T c = 14.8 Minutes 100yr, T c = 11.2 Minutes Rational Equation (Q=CIA) (AA) = 2.29 Acres C2 = .50 I2 = 1.9 Q2 = (C2)(I2)(A) = 2.18 CFS C1oo = .63 I1oo = 7.2 Q1oo = (C1oo )(I1oo )(A) = 10.39 CFS Page 2 Storm Water Runoff Calculations Continued Basin B Existing Conditions Watershed Note: Historic stormwater run—off for Sub —basin B sheet flows for approximately 336 feet from the west property line to the east along the north side of the existing building, from there it enters a shallow grass swale for approximately 1 78 feet. It then enters an 8"0 pipe approximately 42 feet long that then discharges into Sub —basin A. Basin B Areas ' A (landscape) Ac(Conc) As(Roofs) AG(Gravel) Ap(Pavement) At (Total) L Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft 13,846 0 5307 243 0 19,396 (0.45 AC) C = 0.41 ' Adjusted Composite C2 C loo Runoff Coefficients 0.41 0.51 Area (B) = 0.45 Acres Time of Concentration TC = T1 + TT — Initial Flow Time Tl = [(1.87)(1.1—CsCf )(D)1/2]/(S)'" C2= 0.41 & C100= 0.51, D = 336 ft, Drop = 3.2 ft, S = 0.95% Tl= 24.0 Min & 20.2 Min — Overland Travel Time (Shallow grass Swale) L = 78 ft. Drop = 1.5 ft, S = 1.9 % ' From Fig. RO-1 V = 0.9 fps TT = 87 sec = 1.44 min. ' — Travel Time in pipes L=42ft, S=2.4% V=8.6fps TT = 5 sec = 0 min. Total Time of Concentration 2yr, Tc = 25.4 Minutes 100yr, Tc = 21.7 Minutes Rational Equation (Q=CIA) C2 = .41 I2 = 1.4 C100 = .51 I100 = 5.4 (AB) = 0.45 Acres Q2 = (C2)(I2)(A) = 0.26 CFS Qloo = (Cloo )(Iloo )(A) = 1.24 CFS Page 3 Storm Water Runoff Calculations Continued Basin C Existing Conditions Watershed Note: There is not a concentration point for this area, stormwater sheet flows east & enters the west gutter system of South College Avenue Basin C Areas AL(Landscape) Ac(Conc) Sq Ft Sq Ft 11,585 827 C = 0.42 AR(Roofs) Sq Ft 1213 AG(Gravel) Sq Ft 255 Adjusted Composite Runoff Coefficients Ap(Pavement) Sq Ft 2694 Cs 0.42 Area (A) = 0.38 Acres Time of Concentration TC = T1 + TT — Initial Flow Time Tl = [(1.87)(1.1—CxCf )(D)1/2]/(S)1/s C2= 0.42 & C100= 0.53, D = 207 ft, Drop = 4 ft, T1= 14.69 Min & 12.31 Min Overland Travel Time TT = 0 Total Time of Concentration 2yr, Tc = 14.7 Minutes 100yr, Tc = 12.3 Minutes Rational Equation (Q=CIA) (AC) = 0.38 Acres At(Total) Sq Ft 16,554 (0.38 AC) C 100 0.53 S = 1.93% C2 = .42 I2 = 1.9 Q2 = (C2)(12)(A) = 0.30 CFS C1oo = •53 Iioo = 6.6 Qloo = (Cloo )(I1oo )(A) = 1.33 CFS Page 4 Storm Water Runoff Calculations Continued EXISTING SUB —BASINS PERCENT IMPERVIOUS VALUES BASED ON THE FOLLOWING Basin A Areas Character of Surface Streets Paved Gravel Walks Roofs Lawns Percent Impervious 100 40 90 90 0 A (Landscape) Ac(Conc) AR(Roofs) AG(Gravel) AG(Pavement) At(Total) Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft 21,271 632 7896 52,007 18,226 99,832 Percent Impervious 46.6% Basin B Areas AL(Landscape) Ac(Conc) Aa(Roofs) AG(Gravel) AG(Pavement) At(Total) Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft 13,846 0 5307 243 0 19,396 Percent Impervious 25.1% Basin C Areas A (Landscape) Ac(Conc) AH(Roofs) AG(Gravel) AG(Pavement) At (Total) Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft 11,585 827 1213 255 2694 16,574 Percent Impervious 27.9% Page 5 Storm Water Runoff Calculations Continued Basin A Proposed Conditions Watershed Note: Proposed stormwater run-off for Sub -basin A conforms to the historic as it will sheet flow. for approximately 204 feet from the west property line to the paved portion, then travels east within a shallow grass swale for approximately 157 feet and into the detention pond located in the southeast portion of the property. This sub -basin will contain the detention pond which will release into the west gutter system of South College Avenue. Basin A Areas A (landscape) Ac(Conc) As(Roofs) As(Gravel) Ap(Pavement) At (Total) Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft 39,197 3743 9314 29,840 17,583 99,677 (2.29 AC) C = 0.52 Adjusted Composite C2 C loo Runoff Coefficients 0.52 0.65 Area (A) = 2.29 Acres ' Time of Concentration To = Tl + TT ' - Initial Flow Time Tl = [(1.87)(1.1-CsCf )(D)1/2]/(S)l/3 C2= 0.52 & C1oo= 0.65, D = 268 ft, Drop = 3.7 ft, S = 1.38% Tl = 15.9 Min & 12.4 Min I- Overland Travel Time (Shallow grass swale) L = 157 ft, Drop = 2.5 ft, S = 1.6 % From Fig. RO-1 V = 2.6 fps TT = 60.4 sec = 1.0 min. Total Time of Concentration 2yr, T c = 15.9 Minutes 100yr, Tc = 13.4 Minutes Rational Equation (Q=CIA) (AA) = 2.29 Acres C2 = .52 I2 = 1.8 Q2 = (C002)(A) = 2.14 CFS Cloo = .65 1100 = 6.8 Qloo = (Cloo )(1100 )(A) = 10.12 CFS Page 6 Storm Water Runoff Calculations Continued Basin B Provosed Conditions Watershed Note: Proposed stormwater run-off for Sub -basin B conforms to the historic as it will sheet flow for approximately 336 feet from the west property line to the east and into a grass swale for approximately 78 feet. From there the run-off enters a pipe system which discharges into sub -basin A. Basin B Areas A (Landscape) Sq Ft 12,563 C = 0.45 Ac(Conc) Sq Ft 652 As(Roofs) Sq Pt 5145 Adjusted Composite Runoff Coefficients AG(Gravel) Ap(Pavement) At (Total) Sq Ft Sq Ft Sq Ft 570 620 19,550 (0.45 AC) C2 C100 0.45 0.57 Area (B) = 0.45 Acres Time of Concentration TC = T1 + TT - Initial Flow Time Tl = [(1.87)(1.1-CxCf )(D)'/E]/(S)'" C2= 0.45 & C100= 0.57, D = 336 ft, Drop = 3.2 ft, S = 0.95% T1= 22.6 Min & 18.5 Min - Overland Travel Time (Shallow grass swale) L=32ft, Drop =0.6ft, S= 1.8% From Fig. RO-1 V 0.9 fps TT = 35 sec = 0.6 min. - Travel Time in pipes L=42ft, S=2.4T V=8.6fps TT = 5 sec = 0 min. Total Time of Concentration 2yr, T c = 23.2 Minutes 100yr, Tc = 19.1 Minutes Rational Equation (Q=CIA) C2 = .45 I2 = 1.5 C1oo = .57 I100 = 5.7 (AB) = 0.45 Acres Q2 = (C2)(I2)(A) = 0.30 CFS Qloo = (Cloo )(I1oo )(A) = 1.46 CFS Page 7 Storm Water Runoff Calculations Continued Basin C Proposed Conditions Watershed Note: There is not a concentration point for this area, stormwater sheet flows east & enters the west gutter system of South College Avenue Basin C Areas AL(LandeCape) AC(Conc) As(Roofe) AG(Gravel) Ap(Pavement) At(Total) Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft Sq Ft 9206 2565 2829 0 1955 16,555 (0.38 AC) C = 0.53 Adjusted Composite Runoff Coefficients CZ C1oo 0.53 0.67 Area (A) = 0.38 Acres Time of Concentration Tc = T1 + TT — Initial now Time Tl = ((1.87)(1.1—CsCf )(D) 1/2 ]I(S) 1/3 C2= 0.53 & C100= 0.67, D = 207 ft, Drop = 4 ft, S = 1.93% Ti = 12.31 Min & 9.29 Min Overland Travel Time TT = 0 Total Time of Concentration 2yr, Tc = 12.3 Minutes 100yr, Tc = 9.3 Minutes Rational Equation (Q=CIA) (AC) = 0.38 Acres C2 = .53 I2 = 2.0 Q2 = (C2)(12)(A) _ 0.40 CFS C1oo = .67 I100 = 7.9 Qioo = (Cloo )(Iloo )(A) = 2.01 CFS Page 8 Storm Water Runoff Calculations Continued PROPOSED SUB -BASINS PERCENT IMPERVIOUS VALUES BASED ON THE FOLLOWING Basin A Areas A (landscape) Ac(Conc) As(Roofs) Sq Ft Sq Ft Sq Ft 39,197 3743 9314 Percent Impervious 41.4% Basin B Areas A (Landscape) Ac(Conc) As(Roofs) Sq Ft Sq Ft Sq Ft 12,563 652 5145 Percent Impervious 31.0% Basin C Areas AL(Landscape) Ac(Conc) As(Roofs) Sq Ft Sq Ft Sq Ft 9206 2565 2629 Percent Impervious 41.1% Character of Surface Streets Paved Gravel Walks Roofs Lawns Percent Impervious 100 40 90 90 0 As(Gravel) Ap(Pavement) At (Total) Sq Ft Sq Ft Sq Ft 29,840 17,583 99,677 AG(Gravel) Ap(Pavement) At (Total) Sq Ft Sq Ft Sq Ft 570 620 19,550 AG(Gravel) Ap(Pavement) At (Total) Sq Ft Sq Ft Sq Ft 0 1955 16,555 Page 9 o CO r 0) E N N w M N M O O r `- O r r CY U 00 c0 O r N M N N O O O O nr O Uf U Q0) 07 00 (N 't M W N O O af Q V) N c0 't M O U') 00 M U) Q W O O CO X 0) r r Q Z Q Q m U m O O N r d- N N 0 r M Q z O U N 00 v W M � `- O LLJ O o CL E U N ILO r� r O O O N O r r O U - O O N N O O Cr O O (00 Lo � O O O U Qam 07 oo N O O �Q Of Q LL- I� O LO i- U) LO (D LO Lr) Q w rn rn co of r r Q Z_ M Q m U m 0) M M r N r M N 00 L M r Page 10 � LOW IMPACT DEVELOPMENT � SPREADSHEET & EXHIBIT Designer: Company: ' Date: Project; Location: May 20, 2016 Kind Care Design Procedure Form: Rain Garden (RG) Sheet t of 2 1. Basin Storage Volume A) Effective Imperviousness of Tributary Area, I, I, = 40.0 % (100% it all paved and roofed areas upstream of rain garden) B) Tributary Area's Imperviousness Ratio (i = I,/100) 1= 0.400 C) Water Quality Capture Volume (WQCV) for a 12-hour Drain Time WQCV - O.14 watershed Inches (WOCV= 0.8 - (0.91- i'- 1.19 - iE. 0.78' i) D) Contributing Watershed Area (including rain garden area) Area - 119,227 sq ft E) Water Quality Capture Volume(WOCV) Design Volume Vwacv= 1,429 cuff Vol = (WQCV / 12) ' Area F) For Watersheds Outside of the Denver Region, Depth of ds= In Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region, Vwacv or ER = cu ft Water Quality Capture Volume (WQCV) Design Volume H) User Input of Water Quality Capture Volume (WQCV) Design Volume Vwacv USER = cu If (Only 0 a d'dferem WQCV Design Volume is desired) 2. Basin Geometry A) WQCV Depth (12-inch maximum) Dwocv = In B) Rain Garden Side Slopes (Z = 4 min., honz. dial per unit vertical) Z = 1t / It (Use'0'd rain garden has vertical walls) C) Minimum Flat Surface Area Aµ„ = sq ft D) Actual Flat Surface Area AawE = sq It E) Area at Design Depth (Top Surface Area) ATM = $q It F) Rain Garden Total Volume VT= cu If (VT= ((AT, . Aft, ) / 2) ' Depth) 3. Growing Media Choose One 18" Rain Garden Growing Media Q Other (Explain): City of Fort Collins Standard 4. Underdrain System A) Are underdrains provided? Choose One ® Np B) Underdrain system orifice diameter for 12 hour drain time — i) Distance From Lowest Elevation of the Storage y= N/A ft Volume to the Center of the Orifice if) Volume to Drain in 12 Hours Voi.,z = WA cu If III) Orifice Diameter, 3/8' Minimum Do = WA in UD-BMP_y3.03.xlsm, RG 5120/2016, 1:50 PM Design Procedure Form: Rain Garden (RG) Sheet 2 of 2 Designer: Company: Date: May 20, 2016 Project: Kind Care Location: 5. Impermeable Geomembrane Liner and Geotextile Separator Fabric rChooso Ona — 0 YES A) Is an impermeable liner provided due to proxlm0y 0 No of structures or groundwater comammation? 6. Inlet / Outlet Control r Choose One Sheet Flow- No Energy Dissipation Required A) Inlet Control I 0 Concentrated Flow- Energy Dissipation Provided Chnnw One 7. Vegetation Seed (Plan for frequent weed control) �@) 0 Plantings 0 Sand Grown or Other High Infiltration Sod 8. Irrigation r Choose One 0 YES A) Will the rain garden be irrigated? 0 NO Notes'. UD-BMP_v3.03.xlsm, RG 5/20/2016, 1 50 PM w Q w w a- Q V) /</� V �L/- V NNw (If 00 z "q- w WQ 1 I- L i to Q rn CD J Q II II z 0 Q I--- Of LU Q F— LU �z mu _ of x w w a- Z w Of Q << N 0 z '- Q� � tY cn z O 0 Ch F- Li- N zr�- v II w a_ F— co z w o N 0 w � w 0 0 w LL. F- LLI LLJ m U 0 0. I 1 1 DETENTION POND VOLUME CALCULATIONS Detention Volume - Mass Balance Method-100-yr (Major Storm) Input Runoff Coefficient, C.= 0.60 Frequency Factor, Cf'= 4 1.25 2-yr Release, 2.44 cfs Area = 3.12 acres Results Time (min) intensity (in hr) Q,,, (cfs) -Volume;, (ft3) 5 9.96 23.31 6991.92 2.44 10 7.74 18.11 10866.96 2.44 15 6.52 15.26 13731.12 2.44 20 5.61 13.13 15752.88 2.44 25 4.97 11.63 17437.68 2.44 30 4.52 10.58 19038.24 2.44 35 4.08 9.55 20049.12 2.44 40 3.74 8.74 20975.76 2.44 45 3.45 8.08 21818.16 2.44 50 3.23 7.55 22660.56 2.44 55 3.03 7.10 23418.72 2.44 60 2.86 6.69 24092.64 2.44 65 2.71 6.35 24766.56 2.44 70 2.59 6.06 25440.48 2.44 75 2.48 5.80 26114.40 2.44 80 2.38 5.56 26704.08 2.44 85 2.29 5.35 27293.76 2.44 90 2.21 5.16 27883.44 2.44 95 2.13 4.98 28388.88 2.44 100 2.06 4.83 28978.56 2.44 105 2.00 4.68 29484.00 2.44 110 1 1.94 4.54 29989.44 2.44 115 1.88 4.41 1 30410.64 1 2.44 120 1.835 4.29 1 30916.08 1 2.44 Volume,,,t W Volume detained (acre-feet) -.� 732.00 0.144 1464.00 0.216 2196.00 0.265 2928.00 0.294 3660.00 0.316 4392.00 0.336 5124.00 0.343 5856.00 0.347 6588.00 0.350 7320.00 0.352 8052.00 0.353 8784.00 0.351 9516.00 0.350 10248.00 0.349 10980.00 0.347 11712.00 0.344 12444.00 0.341 13176.00 0.338 13908.00 0.332 14640.00 0.329 15372.00 0.324 16104.00 0.319 16836.00 0.312 17568.00 0.306 FORBES ENGINEERING STORM WATER RUNOFF CALCULATIONS KIND CARE SITE DEVELOPMENT FORT COLLINS, COLORADO DETENTION POND VOLUME CALCULATIONS PROPERTY I� LINE i i —zo 3-7 DETENTION POND PARAMETERS INVERT OUT = 5036.67 HIGH WATER ELEVATION = 5038.6 WATER DEPTH = 1.93 FEET RAIN GARDEN AREA = 1507 SF JOB # 2360 CLIENT: KIND CARE DATE: 2/20/16 BY: KEF REQUIRED DETENTION VOL = 0.353 AC -FT (FROM MASS BALANCE SPREAD SHEET) VOL = 15,377 CF WATER QUALITY CAPTURE VOLUME 1,846 CF TOTAL REQUIRED VOLUME 17,223 CF DETENTION POND VOLUME RAIN GARDEN AREA VOLUME CONTOUR SF CF OUTLET 0 36.67 0 543 5037 3293 7,857 5038 12,420 9,874 5038.E 20,493 — OUTLET _ STRUCTURE & PIPE TOTAL 18,274 CF 0.42 AC -FT PROVIDED VOLUME (0 5038.6) U.S. HIGHWAY 287 18,274 CF (SOUTH COLLEGE AVENUE) FORBES ENGINEERING STORM WATER RUNOFF CALCULATIONS HIND CARE SITE DEVELOPMENT FORT COLLINS, COLORADO EXTENDED DETENTION VOLUME TOTAL SITE IMPERVIOUSNESS EXISTING = 40.0% PROPOSED = 40.9% JOB # 2360 CLIENT: KIND CARE DATE: 10/3/15 BY: KEF WQCV = Water Quality Capture Volume (watershed inches) WQCV =a[(0.9)I3— (1.19)I2+(0.78)I] a = coefficient corresponding to WQCV drain time (table 3-2) Use, a = 0.9 for 24 hour drain time I = imperviousness (in %/100) I = 40.9 / 100 = 0.409 WQCV = 0.9 [ (0.9)(0.409) s — (1.19)(0.409)2+ (0.78)(0.409) ] WQCV = 0.163 REQUIRED STORAGE VOLUME (AC —FT) V = ( WQCV 1 A 12 V = ( 0.163 )(3.12) 12 A = 3.12 ACRES V = 0.042 AC —FT V = 1846 CUBIC FEET FORBES ENGINEERING KIND CARE SITE DEVELOPMENT FORT COLLINS, COLORADO STORMIMATER CALCULATIONS Job J 2460 Client. KIND CARE Date: 2120116 8y: KEF Subject: Detention Pond Outlet Orifice Plate Detention Pond release point 12"0 storm pipe connected to existing west curb & gutter system for South College Avenue Maximum Release Rate out of pond, Qout 2.44 cfs, historic 2 year run—off value On —site Pond size 4 to 1 side slope, 1.93 foot depth at outlet Approximately 18,274 cubic feet = 743 cubic yards Detention Pond Outlet Restrictor Plate Q = AV, A = Q/V, V = (.6) 2 32.2 1.9 ) V = (.6)( (2 (32.2)(1.9 ) V = 6.64 fps A = 2.44/6.64 fps A = 0.367 ft 2 = 52.92 in Use 8Y4" diameter hole Or 7Y4"x7X" Square Orifice GRATE 12"0 STORM I I DRAIN (BEYOND) I WATER QUAL; ' PLATE ' /1.5'H x 1.5'W x 1/4" STEEL PLATE — W/ ORIFICE AS INDICATED — BOLT TO CONCRETE W/(4) 3/8"0 STAINLESS STEEL BOLTS AND ANCHORS 12"0 STORM DRAIN SPILL WAY INV OUT 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 FORBES ENGINEERING KIND CARE SITE DEVELOPMENT FORT COLLINS, COLORADO STORMWATER CALCULATIONS Job # 2460 Client. KIND CARE Dote: 4114116 By: KEF Subject: Water Quality Orifice Sizing Calculations Using Average Hydraulic Head and Average Discharge Water Quality Volume (WQv) = .04 ac—ft = 1,846 ft3 Wet Pond, Extended Detention Volume (EDv) = .75 (WQv) = 1,385 ft3 Drawdown Time, td = 24 hr. EDv depth, d = 12" Hydraulic Head (Havg) = 12"/2 = 6" Average release rate to discarge water quality volume over a 24—hour time period. Qavg = 0.75 x (WQv) = 0.75 x 1,846 t d (24hr)(3600)s/hr Qavg = 0.016 cfs WQv Orifice Sizing Calculations Q=ca( 2g H ) a= Q c ( (2 (g) CHT) _ 0.016 cfs a (0.6) (2)((32.2)(0.5) ) a = 0.0047 ft 2 = 0.68 in 2 Using %" min. diameter holes d=0.375in a = 0.11 in2 1/4' (MIN.) THICK Wp STEEL FLOW CONTROL (Wo+61 PLATE F-1 WATER HOLE (TYP.). SE (WO) �� o o �� TABLE BOTTOM ROW OF HOLES TO BE AT INVERT OF PLATE A # of holes = 0.68 / 0.11 = 6.18 3• (TYP.) STAINLESS STEEL ANCHOR BOLT (TYP.) FLOW CONTROL PLATE Use (6) %" diameter holes spaced ® 4" o.c. ' PIPE CAPACITY � CALCULATIONS FORBES ENGINEERING KIND CARE SITE DEVELOPMENT FORT COLLINS, COLORADO STORMWATER CALCULATIONS PIPE CAPACITY CALCULATIONS 43' DETEN M POND INV our �1ooY HGL APPROXIMATEOURET BOX EXISnNG GRADE 12"0 OUTLET PIPE NOT TO SCALE APPROXIMATE EXISMG GRADE 8"0 NORTH DRAINAGE PIPE NOT TO SCALE APPROX 43 LF OF 12'0 PVC PIPE SLOPED O 0.5R Job if 2460 Client: KIND CARE Dote: 2120116 By: KEF qRm PIPE CAPACITY CALCULATIONS 12*0 PVC PIPE n - 0.011 A = .785 SO FT SLOPED ® 0.5% S = 0.005 P = 31.27' = 2.61 FT R=A/P=0.30 Q - (1.486/n)(A)(RP(sy/2 Q =(1.486/0.011)(0.785)(0.30)2/3(0.005)1/' Q=3.36CFS L TOP OF 100Y NGL EXISTING 8'0 ASPHALT (2' DEPTH) C DRAINAGE PIPE APPROX 42 LF OF 8'0 PVC PIPE SLOPED O 0.5X 55i PIPE CAPACITY CALCULATIONS 8'0 PVC PIPE n = 0.011 A = 0.349 SO FT SLOPED ® 0.5% S = 0.005 P = 20.85' = 1.738 FT � Q (1.486/n)(A)(R) (S)'2 R-A/P-0.20 Q =(1.486/0.011)(0.349)(0.20)nO.005)1/2 Q = 1.14 CFS ' TABLES � AND FIGURES i EROSION CONTROL WORKSHEETS Erosion and Sediment Control Escrow/Security Calculation for The City of Fort Collins Project:, Wnd Care I Disturbed Acres:g0.55 EROSION CONTROL BMPs Silt Fence (SF) Inlet Protection (IP) Concrete Washout (CW) Vehicle Tracking Control (VI - R6rk .gnPkc bMP Amount.. Estimated Unit Total Units Quantity Price Price Ea. Ea Sub -Total: $3,415.00 1.5 x Sub -Total: $5,122.50 Amount of security: $5,122.50 Reseeding Amount Total Acres x Price/acre: $550.00 Unit Price of Seeding per acre: $1,000.00 Sub -Total: $550.00 1.5 x Sub -Total: $825.00 Amount to Re -seed: $825.00 Miniumum�EscroW Amount '> Minimum escrow amount: $1,500.00 Erosion Control Escrow: $5,122.50 1 Fields in yellow should be amended for this project. "The amount ojthe sewrhy mast be based on one and one-half dater the asdmate of the cost to install the approved measures, or one and one halfntnea the cost to re -vegetate the disturbed land to dry land grasses based upon unit cost determined 4 the Chy s Annual Revegetadon and S'tabUkadon Rid, whichever is greater. In no instance, will the amount ofsecur4 be kss than one thousand five hundred dollars (S],500) for raidendal development or three thousand dollars ($3,000) for commercial development" 6/10/2016 2:27 ?M CiCLIENTMWoddag FlIea12M KNdCaMWAV1nd Set 6816Z-1616 K6d Cam Ee jft U J J LLJ CD ¢o W N ¢ O oo U uj O XIX Z U ¢a 0J U 00 0Q Lo Z~ 00 3 YN 2R `YCj•' � � O ow 10-3-15 S'"b AS NOTED KEF ulna KEF -UmnS Sim 24'x360 ornke Nome -- PROPOSED DRAINAGE PUN ping Xa. D1.0 It L'I t l ) ) 11 1 1 � 1 I I EROSION CONTROL CONSTRUCTION SEQUENCE 1. INSTALL PERIMETER EROSION CONTROL MEASURES. 2. STRIP AND ROUGH GRADE SITE AND FILL AREAS. 3. PROVIDE EROSION CONTROL PROTECTION. (I.E. SILT FENCE) AND TEMPORARY SEEDING, WHERE REQUIRED. 4. GENERAL SITE STRIPPING AND TOPSOIL STOCK PILE. 5. FINAL GRADING OF FIRE ACCESS ROAD. 6. REMOVE ACCUMULATED SEDIMENT AND CONSTRUCT PERMANENT EROSION/DRAINAGE CONTROL STRUCTURES (IF REQUIRED). LEGEND SITE BOUNDARY/PROPERTY LINE EXISTING BUILDING PROPOSED BUILDING EXISTING EOC PROPOSED EOC EXISTING CURB & GUTTER -- PROPOSED CURB & GUTTER EXISTING EDGE OF GRAVEL --- PROPOSED EDGE OF GRAVEL EXISTING FENCE 1 EXISTING CONTOUR --------5042----- PROPOSED CONTOUR RR)PROanE MP-XIP GRAVEL YARD EROSION CONTROL SYMBOLS /VTy\�\Cyr' VEHICLE i KING MAT , M \/ i PERMANENT SEEDING I SF ! SILT FENCE * X OP ROOK W PROIEGIXIN RLTFR I W WMia rt WAvwuT enFA ROCK SOCK INLET PKGTECIION I limilimmil CURB ROCK SOCKS I p p a- I RR)RP-W PROIECW)N i UGW CONCRETE ASPHALT ma EROSION & SEDIMENT CONTROL NOTES 1. THE CITY STORMWATER DEPARTMENT EROSION CONTROL INSPECTOR MUST BE NOTIFIED AT LEAST 24 HOURS PRIOR TO ANY CONSTRUCTION ON THIS SITE. 2. ALL REQUIRED BMPB SHALL BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITY (STOCKPILING. STRIPPING,' GRADINO,JTC). ALL OF THEIR REQUIRED EROSION CONTROL MEASURES SHALL BE INSTALLED AT THE APPROPRIATE TIME IN THE CONSTRUCTION SEQUENCE AS INDICATED IN THE APPROVED PROJECT SCHEDULE, CONSTRUCTIONS PLANS AND EROSION CONTROL REPORT. 3. PRE-DISTRUBANCE VEGETATION SHALL BE PROTECTED AND RETAINED WHEREVER POSSIBLE. REMOVAL OR DISTURBANCE OF EXISTING VEGETATION SHALL BE LIMITED TO THE AREA REQUIRED FOR IMMEDIATE CONSTRUCTION OPERATIONS, AND FOR THE SHORTEST PRACTICAL PERIOD OF TIME. 4. ALL $OILS EXPOSED DURING LAND DISTURBING ACTIVITY (STRIPPING. GRADING, UTILITY INSTALLATIONS, STOCKPILING, FIWNG. ETC.) SHALL BE KEPT IN A ROUGHENED CONDITION BY RIPPING OR DISKING ALONG LAND CONTOURS UNTIL MULCH, VEGETATION, OR OTHER PERMANENT EROSION CONTROL IS INSTALLED. NO SOILS IN AREAS OUTSIDE PROJECT STREET RIGHT OF WAYS SHALL REMAIN EXPOSED BY LAND DISTURBING ACTIVITY FOR MORE THAN THIRTY (30) DAYS BEFORE REWIRED TEMPORARY OR PERMANENT EROSION CONTROL (E.G. SEFD/MULCH, LANDSCAPING, ETC.) IS INSTALLED, UNLESS OTHERWISE APPROVED BY THE STORMWATER DEPARTMENT. PS 5. THE PROPERTY MUST BE WATERED AND MAINTAINED AT ALL TIMES DURING CONSTRUCTION ACTIVITIES SO AS TO PREVENT WIND -CAUSED EROSION. ALL LAND DISTURBING ACTIVITIES SHALL BE IMMEDIATELY DISCONTINUED WHEN FUGITIVE DUST IMPACTS ADJACENT PROPERTIES, AS DETERMINED BY THE CITY ENGINEERING DEPARTMENT. 6. ALL TEMPORARY (STRUCTURAL) EROSION CONTROL MEASURES MUST BE INSPECTED AND REPAIRED OR RECONSTRUCTED AS NECESSARY AFTER EACH RUNOFF EVENT AND EVERY 14 DAYS IN ORDER TO ASSURE CONTINUED PERFORMANCE OF THEIR INTENDED FUNCTION. ALL RETAINED SEDIMENTS, PARTICULARLY THOSE ON PAVED ROADWAY SURFACES, SHALL BE REMOVED AND DISPOSED OF IN A MANNER AND LOCATION SO AS NOT TO CAUSE THEIR RELEASE INTO ANY DRAINAGE WAY. 7. NO SOIL STOCKPILE SHALL EXCEED TEN (10) FEET IN HEIGHT. ALL SOIL STOCKPILES SHALL BE PROTECTED FROM SEDIMENT TRANSPORT BY SURFACE ROUGHING, WATERING, AND PERIMETER SILT FENCING. ANY SOIL STOCKPILE REMAINING AFTER 30 DAYS SHALL BE SEEDED AND MULCHED. B. CITY ORDINANCE PROHIBITS THE TRACKING. DROPPING, OR DEPOSITING OF SOILS OR ANY OTHER MATERIAL ONTO CITY STREETS BY OR FROM ANY VEHICLE. ANY INADVERTENT DEPOSITED MATERIAL SHALL BE CLEANED IMMEDIATELY BY THE CONTRACTOR. TEMP. SEE N -C SF IP-1 & IP-2 NOTE: PROVIDE ROCK SOCK INLET PROTECTION & CURB ROCK SOCKS AT EXISTING CURB INLET LOCATED AT WEST FLOWLINE SPLATTER ISLAND, APPROXIMATELY 250' NORTH OF TRILBY & SOUTH COLLEGE INTERSECTION C TEMPORARY VTC NOTE NOTES: 1. CONTRACTOR SHALL PROVIDE A TEMPORARY VIC AT AN EXIT LOCATION BEST SUITED FOR THE CONSTRUCTION PHASES OF THE SPLATTER ISLAND (SEE SHEET C4.1 FOR SIZE & DEPTH SPECIFICATIONS). 2. CONTRACTOR SHALL REMOVE ANY EXISTING ASPHALT IN THE AREA FOR THE TEMPORARY VTC PRIOR TO INSTALLATION. 3. ANY & ALL SEDIMENT DEPOSITED ON HIGHWAY 287 BECAUSE OF CONSTRUCTION ACTIVITIES SHALL BE ADDRESSED & CLEANED WITHIN A 24 HOUR TIME PERIOD. EROSION CONTROL PLAN SCALE 1" = 30' 30 0 w 0 GRAPHIC SCALE - FEET i of Fort Collins, Colorado UTILITY PLAN APPROVAL City Engineer Dote BY: Water & Wartewater UOlity Dale BY: Stormwabr utility Dole BY: Porky k Recreo0on Dlrte BY: Traffic Engineer Dote BY: Emironmenlal Planner Dote LLJ CD a o W � ¢ J J Z w� UO W > UN O w� Fz V) ¢a Um r NO ZH �¢ cO 'w2 LD YV1 U VF FS LLJ $+oaa 5g5 LLJ o b Z .z zu z "zl rcn wF� �Ua m Z N O D M 9-3-15 —° AS NOTED eroin KEF 'Mitl KEF ar°'"°m' 24'K36' 5 M XOM EROSION CONTROL PLAN PwYq Kn C4.0 A CURB INLET ROCK -- Z_ SEE ROCK SOCK DESIGN SYM SOCK S DETAIL FOR JOINTING R SOCKS 16" CINDER OCKS 16" CINDER BLOCKS _ BLOCKS FLOW - 2"%4" WOODCURB STUD ; X�-- _ 1' MIN i CURB INLET 2"%4" WOOD STUD SECTION A IP-1 BLOCK AND ROCK SOCK SUMP OR ON GRADE INLET PROTECTION RI nrK AND CURB SOCK INLET PROTECTION INSTALLATION NOTES 1. SEE ROCK SOCK DESIGN DETAIL FOR INSTALLATION REQUIREMENTS 2. CONCRETE "CINDER" BLOCKS SHALL BE LAID ON THEIR SIDES AROUND THE INLET IN A SINGLE ROW, ABUTTING ONE ANOTHER WITH THE OPEN END FACING AWAY FROM THE CURB 3. GRAVEL BAGS SHALL BE PLACED AROUND CONCRETE BLOCKS, CLOSELY ABUTTING ONE ANOTHER AND JOINTED TOGETHER IN ACCORDANCE WITH ROCK SOCK DESIGN DETAIL MINIMUM OF APPROX BLOCK AND ROCK SOCK INLET TWO CURB 30 DEG PROTECTION (SEE DETAIL IP-1) SOCKS L _- _._.._.,SYM W t_ 5' MIN 3L-5L TYP IP-2, CURB ROCK SOCKS UPSTREAM OF INLET PROTECTION CURB SOCK INLET SOCK INLET PROTECTION INSTALLATION NOTESINST�LATION NOTES 1. SEE ROCK SOCK DESIGN DETAIL FOR INSTALLATION REQUIREMENTS 2. PLACEMENT OF THE SOCK SHALL BE APPROXIMATELY 30 DEGREES FROM PERPENDICULAR IN THE OPPOSITE DIRECTION OF FLOW. 3. SOCKS ARE TO BE FLUSH WITH THE CURB AND SPACED A MINUMUM OF 5 FEET APART. 4. AT LEAST TWO CURB SOCKS IN SERIES ARE REQUIRED UPSTREAM OF ON —GRADE INLETS. ^^'r'"o" ELEVAIION MIRAFI MODEL 10100 SILT FENCE FENCE / DETAIL L1 1/2" SQUARE x 48' LONG, DRIED ATTACH SILT FENCE BETWEEN LATHE & POSTS W/1 1/4" ROOFING NAILS COMPACTED BACKFILL 6" % 6" EXCAVATED TRENCH RUNOFF FLOW NATIVE SOIL KILN POSTS SECTION /L INSPECT AND REPAIR FENCE AFTER I EACH STORM EVENT. REMOVE SEDIMENT WHEN 6" OF THE HEIGHT ^ OF THE FENCE HAS BEEN FILLED. SEDIMENT CONTROL FENCE REMOVED SEDIMENT SHALL BE l l P LD PLACED IN TOPSOIL PILE. NOT TO SCALE 0 �v PLAN 3' - 6' RUCK 1. VEONHIDIE KING LONIRCL PID SIWL BE LO 1 AT 11 ACCESS POINT TO THE SLRUC N SITE. 2. A SIGN S L BE PIACEO HFM TO 1XE YEHICIE TRACKING CONTROL PRO TO DESIGNATE TIE LOCATION AS THE COXSTRIIRION EMNHCE/IXR. 3. WHICLE KING CONTROL DRUG SHALL CONSIST OF HARD, DENSE. DURABLE STORE, NCUVR SHME AND RESISTANT TO WEATHERING ROUNDED STONE (I... RIVER MEN O COBB`ES) SHALL NOT BE USED. THE STONES SENATE BE A MINIMUM OP 3- AND A MAXIMUM OF 6L DWAETER. THE STONES SHNL LANE A SPELFIC OPANIY OF AT LEA B 6I CONTROL OF QROM10N WILL BE BY NSWL INSPECTION. C CBALNED 04 WMAGED CURB AND CUTTER AND MERGER SHALL BE REPLACED BY COnIFACTgR. S. ALT UCHINOT NORMALLY USED THE CITY RESERNES THE RIGHT TO REQUIRE WHOLE { TRACKING CONTROL WITH A TEMPORARY CATTLE CWRO AND/OR WHEEL WASH FACILITIES AT SITES ����,,,,yyyyHEERE TRACKINGONTOFARM AREAS BECOMES A SIGNIFICANT PROBLEM AS D ERMNp THE 6, i VEHFLE TRACERS CONTROL WITH WHEEL WASH FALIIIDES ARE REQUIRED, ALL WHEELS EVERY VEHICLE LEAVING THE SITE SHNL BE CLEANED OF MUD DOING A - PRESSVREjWASHER. THE CONTRACTOR SHAL BE RESPONSIBLE FOR OBWNING A WATER SOURCE AND CONSTRUCTING A WASHWATER SEDIMENT TRAP. $0'MIX. MAINTFINANCF I. NOTES CONTRACTOR SHALL INSPECT VEHICLE TRACKING CONTROL PAD ONLY ROCK SURFACE SHALL BE CLEAN AND LOOSE ENOUGH TO PUT SLIGHTLY UNDER WHEEL LEADS AND CAUSE LOUSE ROCK TO DISLODGE MUD FROM THE WREN ROCK BECOMES COMPACTED OR FILLED WITH SEDIMENT SO THATTHE EETECRNENESS OF ME PAD G CONTRACTOR SHAH RIP. TURN MR, OR OTHERWISE LOOSEN BEEN. -- - PLACE ADDITIONAL NEW ROCK. OR REPLACE WITH NEW ROCK AS NECESSARY M RESIORE EFFECTRINESS. 2. SEDIMENT AND OTHER MATERIAL SPILLED. DROPPED OR TRUCKED ONTO PAWD SURFACES SHALL BE IMMEDIATELY OR BY THE END OF EACH WORKING DAY. s. XEEMMDOLED VEHICLE TRACKING .0 PAD SHALL BE REMOVED AT THE END OF CONSTRUMION. THE ARIA SHOULD BE TOPSOILED, SEEDED. CRIMPED, AND NUDGED) OR GTHERMSE SPAIMED 4. IF VEHICLE WHEEL WASH RACEMES ME REQUIRED. WNTRACTOfl SKILL INSPECT VEHICLE TfMgNG CONTROL AND WHEEL WASH FACRRIES WIRY. ACCUMVUIED SEDIMENTS SHNL BE REMOVED FROM THE PAD SURFACE. 3. ACCUMULATED SFDIMLM IN T{ WASMW.AIfR/SEOINEM TRAP SEAL BE REMOVED WHEN ME;SEpMEM REACHES AN AVERAGE DEPTH OF 1$-INCHES. Y MIN. 6' MIN. PAVED SURFACE L pPg12Z-e'IWN. �_r-6'MCI NO wTERWS INCUumw ROCS. IRP6, DIRT, - GMYEL OR MPHI SIWL BE PLACED IN CUTER TO FACILITw1E MOLMRNO CURER FEMME. CURB BE CUT DEAN TO A HEIGHT OF 2' OR HIGHER FOR OWNER SECTION A ACCESS AND REPIACED AT PROTECT COMPLERCN. OTHER ACCESS OENCES WY BE USED AS ACCEPTED BY THE CRY. I I/T AGOIEGTE PLED TO TOP OF =TOME 1 ro I WAGE LME- FLOW CONCRETE WASHOUT NOTES 1. CONCRETE WASHOUT AREA S BE RESEALED PReOH TO MY CONCISTE PVCEMFNT ON STF. 2. VEHICLE TRACKING CONTROL IS REWIRED IF ACCEss TO CONCRETE WAS MG 5 OFF DARTMEM 3 SIGNS SINGLE BE FVCD) AT THE CONSTRUCTION ENIIt4RCE AT T WMHWF AHEAD AND R]SEWHERE AS NECESSARY ro CLEMLY INDICATE THE LOCATOR OF THE CONCRETE WASHOUT MG TO CPERMORS OF CONCRETE TRUCKS AND PUMP WERE a, THE CONCRETE WASHOUT MCA SIWL BE REPARM MD ENLARGED OR CLEWED GORE M NECESSARY TO MOUNTAIN GPMRRY FOR WASTED CONCRETE 5, AT TIE ETD OF CONSTRUCTION. ALL CONCRETE SRWL OE RE FRO! THE SRE ND DISPOSED OF AT M ACCEPTED NOTICE DOE 6. WHEN THE CONCRETE YUSEVT MCA 6 READABLE). THE MOURBFD MIA SWL BE SEEDED AND MULCHED OR OTHERWISE STMU2ED IN A BANNER ACCEPTED WE THE BEEF T. EQUATION OF CONCRETE WAWDIIr .UffA OR SHEET IS CONCEPIINL BILE.. FINAL LOCA,EM TO BE DETERMINED IN TIE REED AT LCNRRA;TORS D5GEEM BLOW COMRICL PLATE DEe OU11Fr PIPE ROCK OUTLET PROTECTION FILTER NOT TO SCALE OP '71 SON W roIGTE THE UOMIGN OF THE CONCRETE W0.9MR AREA E—GROUND MR. SURFACE I T z-0- NOR u I I 4WACIm FYflAL10E21r MATERIAL TN. ]I11V CN FLATTER! IWE MIN. SIDE STAPES OR M (DOMINIONREWPH MASSIVE COHCIONCR EIE CONCRETE WASHOUT AREA / IAfn\ NOT TO SCALE CONTROL TRACKING PAD PL AN S L N VIEW HIS ICRAWL FILTER NOTES 1. SEDIMENT SHALL SE REMOVED WHEN ME HALF BE THE BASIN DESIGN DEPTH HAS BEEN MICRO. $. REMOVED SEDIMENT SIWL BE DEFROSTED IN I MI MCA TRI&TA% TO A SEDIMENT BASIN. City of Fort Collins, Colorodo UTILITY PLAN APPROVAL C'M Engineer Date BY: Water h Waetawaler Utility Oats CHECKED BY: SlHermWoler Utility Dote CHECKED BY: Pvb h Recreogon DRAW CHECKED BY: Traffic Engineer Dote BY: Environmental Planner Date U J Ld ¢o Lu N G J W 00 O 10 U > 0,6 O OfOf Z U� 00 Z Of CIDCIO CIO Y t/I a i? Z W 11UW� 6 WUW 6m G R CD r Z a A $+ W R8 2Zo6 Z<�0 2U FIG K=0 DEW Lj Nos Zod 2 s� v c'n gZu Ld a M(y 15 ii z O a�a LLRE IF Date 2-22-16 stli AS NOTED AA KEF Mere KEF ARAWF We" 240K36" AeW mew - EROSION CONTROL DETAILS D,ewq w C4.1