HomeMy WebLinkAboutDrainage Reports - 03/02/1994STEWART&ASSOCIATES Consulting Engineers and Surveyors February 25, 1994 Mr. Basil Hamdan Storm Water Utility City of Fort Collins P.U. Box 580 Fort Collins, Colorado 80522 Dear Mr. Hamdan: The following is the erosion control report for Trail West P.U.D. which is located at the intersection of South Overland Trail and West Stuart Street. Trail West P.U.D. is an 18.45 acre multi —family planned unit development that was approved in September 1979. The P.U.D. has been partially completed. There are seven multi —family buildings completed, and all of the water and sewer mains have been installed. All of Overland Trail has been improved, and approximately 800 feet of West Stuart has been improved. Approximately 400 feet of Neil Drive has the curb, gutter and walk installed, but no pavement has been laid in Neil Drive. The remaining buildings to be built will be divided into five phases. Likewise, it is proposed to phase the erosion control according to the five phases. The public improvements that remain to be constructed are nine sewer services and twenty—three water services; and the curb, gutter, walk and asphalt on the easterly 600 feet of West Stuart Street remains to be constructed. The undeveloped portion of the P.U.D. has moderate ground cover of weeds and grasses. The existing building sites for Phases 1, 2 and 3 will not require a great amount of overlot grading. Phases 4 and 5 will require more overlot grading. The ground cover will be disturbed for each phase separately. It is projected that the five phases will be completed in two years. The west half of Neil Drive will be constructed with Phase 1, and the east half will be constructed with Phase 3. The remainder of West Stuart Street will be constructed with Phase 3. The original P.U.D. had a proposed detention pond in the northeast corner of Phase 4. It was requested and approved in March of 1987 to delete the detention pond.' The existing development and Phases 1, 2 and 3 will drain to an existing Brown Farm Detention Pond via West Stuart Street. Phases 4 and 5 will drain to the Brown Farm Detention Pond through the existing Willow Lane large drainage Swale. James H. Stewart and Associates, Inc. 103 S. Meldrum Street P.O. Box 429 Ft. Collins, CO 80522 303/482-9331 Fax 303/482-9382 Erosion Control Report — Trail West P.U.D. Page 2 The erosion control methods that will be used are as follows: (a) do not disturb any areas not necessary for construction, (b) build silt fence along north line of each phase, (c) place straw bale barriers at outfall points, and (d) plant temporary crop with mulch in some areas. To the best of my knowledge, the erosion control report and plan are in compliance with the current Storm Drainage Design Criteria and Construction Standards of the City of fort Collins. The cost estimate of the erosion control methods is enclosed as a part of this report. If you have any questions regarding this site, please call. Sincerely, Richard A. Rutherford, P.E. & L.S. President jrr enclosures CONSTRUCTION SEQUENCE PROJECT: i )2 A IL WEs r P U. D- { NASB Z STANDARD FORM C SEQUENCE. FOR 19 94- ONLY:. COMPLETED BY: R A. E., DATE: JAu zo, i9 9 ¢ Indicate by use of a bar -line or symbols when erosion control measures will be installed. Major modifications to an approved schedule may require submitting a new schedule for approval by the City Engineer. YEAR MONTH j J I I I I RAINFALL EROSION CONTROL STRUCTURAL: Sediment Trap/Basin . Inlet Filters Straw Barriers Silt Fence Barriers Sand Bags Bare Soil Preparation Contour Furrows Terracing Asphalt/Concrete Paving) Other Fov v DA 7 /D,VS VEGETATIVE: Permanent Seed Planting Mulching/Sealant Temporary Seed Planting Sod Installation Nettings/Mats/Blankets Other I STRUCTURES: INSTALLED BY- VEGETATION/MULCHING CONTRACTOR DATE SUBMITTED HDI/SF-C:1989 s o -v D MAINTAINED BY APPROVED BY CITY OF FORT COLLINS ON JANUAI'i 1991 8-20 DESIGN CRITERIA. RAINFALL PERFORMANCE STANDARD EVALUATION --------------------------------------------------------------------- PROJECT: 1 '.AIL WEST P.U, C> STANDARD FORM A COMPLETED BY: R , A. [. DATE: JAu. zo,lgvd ---------------------------------------------------------------------I DEVELOPED ERODIBILITY Asb Lsb Ssb Lb Sb I PS SUBBASIN ZONE (ac) (ft) M . (feet) M I (o) --------- PHASE L ----------- 7Vl6,q - -- 17(,At. ------- ¢SOFT. ------- bfZ"/0 ------- ------- I — ----- — PHgsEIL H (oN 3SAa 4-(IoFr. 1 d0 �'p 77.G%I I PHAJ6IL fi16,H S,SZAt (pZOF7. 137/, 17 I n slip PHAs6 MT i416 H 2,44 A,. S80 Fr, 2,93'lp I PHArF,M: 1.5 3 At, 4-61 o F7. I 7G, 4 I--------------------------------------------------------------------- IIOI/SF-A:1939 EFFECTIVENESS CALCULATIONS I---------------------------------------------------------------------- PROJECT: T R-AIL_ W EST P. U, D. STANDARD FORM B IICOMPLETED BY: e -A. e. DATE: JA ,. zo,/9f� I Erosion Control C-Factor P-Factor Method Value Value Comment --------------------------------7------------------------- B v It- D i AN L 0,61 /. 0 ASPHALT tCoAvc, 0,01 1 0 BAP-e G,eOL)Njz�, 1.0 11a S-rz,Aw E'ALe'SAeeiac /, O 0.g TEMP CAD. IMVLC'M 6.06 1,0 S'L.T ;=E.1/C6, /. 0 Q$ -------------------- MAJORI -------------------------------------------------- PS. I SUB I AREA I BASINI (o) IBASINI (Ac) I CALCULATIONS ----- I ------ 79.Og1 I ----- = I :----- I /,7GAc.l -------------------------------------------- I I ^rPAt4 = 0,&0 Ac. P3 L t� cp = 0- zy 4e., aACC; 6,eo'J=0.87Aa. -. WTDC=CO,a0x.0r)+Co.29x0.00+(0,Vx 1.0) --T—I /. a = 0. s0 �ll7p P = 0-so X 0.8 = 0.¢0 CFF = — �0.S0x0.40)x/00= 80.00/0 OK ? 79.0% As pA•/f = 0-374c. B L-fl6 = 0. 18 Ac. $ AP-G 6 B0v.v0 0.65- 40. TEMP (rROP/,�I�tcH=O.tSq� = 0. 0 z- (V T D P = 0• SO x 0. Quo C FF = -(0.1D x0.49L)x100 = $1.3 0 k 7 -77, -------------------- 7------- DI/SF-B:1989 e '"� EFFECTIVENESS CALCULATIONS I------------------------ ---------------------------------------------- I PROJECT: -riz AIL— k%EJ'r P. v.v. STANDARD FORM B (COMPLETED BY: e:Ar- DATE: JAb.Lv,Ai4¢ Erosion Control C-Factor P-Factor Method Value Value Comment ---------------------o SvILD/u4 ----------------------------------- , 01 /• D I AcP;+ALTrc (0,Vc. 0.0) / o BARE Cosovup /, 0 /, O .ST,eAw BAL6BARpicse, /♦ 0 0.$ TEMrr Ce0P /M✓Lc.v O.Ob /, 0 SIL % F&"Ce /. p EXuT Coe0VA,?P Covee_ ---------------------------------------------------------------------I o o � MAJORI PS._ I SUB AREA BASIN I (;) (BASIN` (Ac) CALCULATIONS ----- ------ 179')%I I ----- 1 � I ------ I 5.5L -------------------------------------------- ASPHALT Z•S3AL• I bull n/uc 0•07- Ac. I 8 A R E 6 R.ovn/ b I. 93 4c E%/ST•6e0vjJDeav« C,44-Ae. W rD' C = (z'S3n 0.0/) L(0.4ZX o•0> t (I.93X 5•SZ = O.3to STD P = OSO x 0,80 = 0,4-0 t: Fr- = — ( 0. 4 o X 0, 3(,) X / oU - g s, C/o OL- } 7 9. 1 Yo ----------------------------------------------------------------------� DI/SF-B:1989 ---EFFECTIVENESS-CALCULATIONS-------- PROJECT: rP-Alc. LUC-sr P.O.P. STANDARD FORM B COMPLETED BY: A e DATE: .,1Au.u,/99¢ Erosion Control C-Factor P-Factor . Method Value Value Comment ---------------------------------- S3v11-p/.u0 0,01 o ---------------------- /. At pHiAL,7 £ CO)vC. 0.01 /• 0 BA 2 6 Cji EJ v u p /• 0 /, O Sr IC1 W a ae.ICg /• 0 0• 0 TBM P. GRop/MVLem /. O FE,vC s E1clj-r G cvv�vC Covert ---- O.Og MAJORI -----------------------------------------------------------------�, PS. I SUB I AREA BASINI (;) IBASINI (Ac) CALCULATIONS ----- ------ 8l•9 %! ----- .L I ------ 12 99A� -------------------o-.---3sa-�-------------------- ]�v1t.D/nay . I As PH AC,— ECovC, p. SG Ate. I 0S4c, I Ex„ ,. 6/ZOVND Cove, O•Z3gc, I I I TEMP, CROP/A v[CH O, Z5 AO• -41. 4- % I _-r_ /• S 3Ac, I UJro C (0.35x Oa/) }(o•S6x0•oi) F(/•OS)r/•o�� (017.3x0102 1(DZSxb•06 -G•44 0• ¢ S W7o P = O,SU x0.80 = o•�o E F = I - (v.4sxo•¢v) x /00 = 8t.o0/0 0k i 81,q % a V,L D/n)Cn = 0• Za AC. ASPHALT NC - 0• ¢3 A c. 6Aes G2o,vvp= o.8¢A,, W7-D C= (0•Lcx0.o) t(0,g3x0.01) f0,60".e) 1 S = 5S. ¢ W ro r = o.s'o x0.bo - O,40 �r-F = /- (o•ssax 0•¢0)n /rro = ?7.8 ok -,,, 76.4- -------------------------------------------------------------------- DI/SF-B:1989 STEWART&6SOCIATES Consulting Engineers and Surveyors January 21, 1994 Mr. Glen Schlueter Storm Water Utility City of Fort Collins P.O. Box 580 Fort Collins, Colorado 80522 Dear Mr. Schlueter: The following are the cost estimates for erosion control for Trail West P.U.D. by phases: Phase I 1. Silt Fence - 250 L.F. @ 1.50/ft $ 375.00 2. Straw Bale Barrier - 3 @ 50.00 150.00 3. Reseeding total area of 1.76 acres @ 649/Ac 1142.00 Phase II 1. Silt Fence - 150 L.F. @ 1.50/ft. $ 225.00 2. Straw Bale Barrier. - 3 @ 50.00 150.00 3. Temporary reseeding with mulch - 0,15 acres @ 1300/Ac 195.00 4. Reseeding total area of 1.35 acres @ 649/Ac 876.00 Phase III 1. Silt Fence - 880 L.F. @ 1.50/ft $1320.00 2. Straw Bale Barrier - 2 @ 50.00 100.00 3. Reseeding total area of 5.52 acres @ 649/Ac 3582.00 Phase IV 1. Silt Fence - 820 L.F. @ 1.50/ft $1230.00 2. Straw Bale Barrier - 2 @ 50.00 100.00 3. Temporary reseeding with mulch - 0.25 acres @ 1300/Ac 325.00 4. Reseeding total area of 2.44 acres @ 649/Ac 1584.00 Phase V 1. Silt Fence - 440 L.F. @ 1.50/ft $ 660.00 2. Straw Bale Barrier - 1 @ 50,00 50.00 3. Reseeding total area of 1.53 acres @ 649/Ac 993.00 In each phase except Phase IV, the total reseeding cost is the greatest, so the amount to be escrowed with the City of Fort Collins is 150% of the reseeding cost. In Phase IV, it is 150% of the first three costs. If you have any questions regarding this cost estimate, please call. Si�ncer_eIy, Richard A. Rutherford, P.E. & L.S. ��.`,�,@�•.•••••., -•, President `�•��� t�`�tsrt TF`..o - 502 Jrr :yrt• 3 ' James H. Stewart and Associates, Inc. '+,`P�,'• f & L. 4, 103 S. Meldrum Street +�i'�F •••••••' O ��` P.O. Box 429 Ft. Collins. CO 80522 303/482-9331 Fax 303/482-9382