HomeMy WebLinkAboutDrainage Reports - 07/25/2011Cigr of Ft. ColBns ro Plans Approved By Date % 5-t/ FORBES ENGINEERING CIVIL & STRUCTURAL ENGINEERING ' February 28, 2011 Revised May 6, 2011 tSecond revision June 1, 2011 t Mr. Glen Schlueter Storm Water Utility City of Fort Collins ' P.O. Box 580 Fort Collins, Colo. 80222 Storm Water Run-off & Water Quality Calculations for the Spirit of Joy Church Mr. Schlueter: ' I have revised the stormwater run-off calculations to comply with the City of Fort Collins storm design criteria. The previous stormwater run-off calculations were determined using the Urban Storm Drainage Criteria Manual with respect to run-off coefficients; the revised calculations use the runoff coefficients per tables 3-1 and 3-3 of the Hydrology Standards. Also, the design of the water quality structure has been changed from a 24 drain time to a 40 hour drain time. As requested, I have provided an exhibit that shows existing and proposed impervious areas (see ' attachments). The amount of increased imperviousness due to the addition and added pavement is approximately 3.8%, (12% was used in the determination of the WQCV). ' I have reviewed and compared run-off calculations from the earlier report by Phil Robinson with Stewart & Associates (revised report dated April 19, 1991). Historic run-off decreases for the 2y and increases for the 100y, but remains relatively the same for the 10y storm (see calculations in ' attachments). The developed run-off calculations for the site were calculated using the previously calculated time of concentration and decrease very slightly (again, see calculations provided in the attachments). 1 As with the previous drainage plan and report prepared for the Spirit of Joy Church, we plan to allow the runoff from the site to be undetained. The stormwater run-off will be released into the outflow ditch so that it can be carried downstream before the major flows from the upstream development reaches the site. An extended detention basin for the captured water quality volume water (approximately 1444 cubic feet) and a quality structure have been designed to maintain water quality. The water quality structure has been designed to release at a 40 hour drain time (see attachment) and will be provided on the construction drawings. The drainage design and computations have been prepared in accordance with the provisions of the City of Fort Collins. Storm Drainage Design Criteria and Construction Standards and the site improvements for the Spirit of Joy Church are in compliance with the original report. With the completion of the designed water quality structure, the extended detention basin for the captured water quality volume and implementation of erosion control measures, this project will improve existing drainage conditions and will not adversely impact downstream properties. Please call if I can be of further assistance in this matter, or if you have any questions. I can be reached at (970) 232-6014. Sincerely, FORBES EF Kevin Forbes, Colo. %�24 PresidentEnc.'�Ut�ie� 01) ' FORBES ENGINEERING STORM WATER RUNOFF CALCULATIONS SPIRIT OF JOY CHURCH FORT COLLINS, COLORADO 1 1 1 ADDITIONAL ASPHALT LANDSCAPED ISLANDS ASPHALT J D(ISTING CHURCH ADDITIONAL ROOF AREA CONC WALK .._ .. SPIRIT OF JOY CHURCH NOT TO SCALE ' NOTE: SEE FULL DRAINAGE PLAN FOR DETAILED SITE ' AREA DESIGNATIONS JOB # 1300 CLIENT: STEWART & ASSOC DATE: 2124111 BY- KEF DEVELOPED SITE AREAS LOT AREA 185,326 SQ FT 4.25 AC ROOF AREA 12,306 SQ FT 0.283 AC ASPHALT 36,384 SQ FT 0.835 AC CONCRETE 11,972 SQ FT 0.275 AC LANDSCAPING 124,664 SQ FT 2.862 AC NEW IMPERVIOUS AREAS DUE TO ADDITION ROOF AREA 6190 SQ FT 0.142 AC ASPHALT 5104 SQ FT 0.117 AC CONCRETE 1541 SQ FT 0.035 AC Page 1 ' SPIRIT OF JOY CHURCH FORT COLLINS, COLORADO HISTORIC RUN-OFF CALCULATIONS CHECK OF PREVIOUS HISTORIC RUN—OFF (3/28/1991 REPORT BY STEWART & ASSOC) ' 12 = 1.25 Q2 = 1.0 CFS THIS WAS DEVELOPED W/ Tc = 39 MIN ' 11a= 2.2 Q10= 1.9 CFS (37 MIN FOR TC100 ), COMPOSITE C = .2 & I �Go = 3.65 Q100 = 3.9 CFS A 1.25 FACTOR FOR FOR THE 100 YEAR ' USING CURRENT FEQUENCY CURVE DATA, & RUNOFF COEFFICIENTS & Ta = 39 MIN RUN—OFF COEFFICIENTS FREQUENCY ADJUSTMENT FACTOR ' 2 YEAR 10 YEAR 100 YEAR 2 YEAR 10 YEAR 100 YEAR 0.20 0.20 0.20 1.00 1.00 1.25 ' USING RATIONAL EQUATION (Q=CIA) A = 4.25 ACRES C2 = .20 12 = 1.09 Q2 = (C2)(12)(A) = 0.927 CFS ' C10 = .20 110 = 1.85 Q10 = (C1o)(11o)(A) = 1.58 CFS C100 = .20 Itoo = 3.93 Q1oo = (C1oo)(C1)(I 1oo)(A) = 4.18 CFS * THE INCREASE IN THE 100Y RUN—OFF VALUES FROM THE ORIGINAL REPORT ARE DUE TO THE CHANGE IN THE FREQUENCY CURVE 1 Original Report Revised Report 1 Q 2 1.0 CFS > 0.93 CFS DECREASED BY 77. ' Q 1 Q 1.9 CFS > 1.6 CFS DECREASED BY 16% Q 100 3.9 CFS < 4.2 CFS INCREASED BY 8% 1 ' Page 2 ' SPIRIT OF JOY CHURCH ' FORT COLLINS, COLORADO DEVELOPED RUN-OFF CALCULATIONS CHECK OF PREVIOUS RUN—OFF CALC'S — FULLY DEVELOPED (3/28/1991 REPORT BY STEWART & ASSOC) ' 17 = 1.9 Q2 = 4.6 CFS THIS WAS DEVELOPED W/ TC = 18 MIN ' 1 t0= 3.3 Q10 = 8.0 CFS (14 MIN FOR TC100 ). COMPOSITE C = .57 1100 = 6.2 Q100 = 18.8 CFS & A 1.25 FACTOR FOR FOR THE 100 YEAR USING CURRENT FEQUENCY CURVE DATA, RUNOFF COEFFICIENTS & TC = 14 MIN ' COMPOSITE RUNOFF COEFFICIENT CALCULATIONS RUNOFF COEFFICIENTS PER TABLE 3-3 ' LAND USE RUN—OFF COEFFICIENT LAWNS, SANDY SOIL 0.10 LAWNS, HEAVY SOIL 0.20 ' CONCRETE 0.95 ROOFS 0.95 ASPHALT 0.95 PACKED GRAVEL 0.50 COMPOSITE RUNOFF COEFFICIENT WAS CALCULATED USING THE FOLLOWING FORMULA; n ' C= IE CI AI /At ' WHERE C = COMPOSITE RUNOFF COEFFICIENT C1= RUNOFF COEFFICIENT FOR SPECIFIC AREA Al A, = AREA OF SURFACE WITH RUNOFF COEFFICIENT OF C, ' n = NUMBER OF DIFFERENT SURFACES TO BE CONSIDERED At= TOTAL AREA OVER WHICH C IS APPLICABLE; THE SUM OF ALL A1's IS EQUAL TO At DEVELOPED SITE AREAS ' AL(LANDSCAPE) AC(CONC) AR(ROOFS) AG(GRAVEL) AG(PAVEMENT) At(TOTAL) SQ FT SQ FT SQ FT SQ FT SQ FT SQ FT 124,664 ' (2.862 AC) 11,972 12,306 0 (0.275 AC) (0.283 AC) 36,384 (0.835 AC) 185,326 (4.25 AC) ' COMPOSITE RUNOFF COEFFICIENT C = 0.45 Page 3 ' SPIRIT OF JOY CHURCH ' FORT COLLINS, COLORADO CALCULATED USING RATIONAL METHOD NOTES: 1. RUNOFF COEFFICIENTS (C) ARE FROM TABLE 3-3 & PREVIOUS CALCULATIONS 2. THE RAINFALL INTENSITY (I) IS FROM A DEVELOPED INTENSITY —DURATION — FREQUENCY CURVE FOR LARIMER COUNTY AREA I — FORT COLLINS AREA ' RUN—OFF COEFFICIENT FREQUENCY ADJUSTMENT FACTOR ' 2 YEAR 10 YEAR 100 YEAR 2 YEAR 10 YEAR 100 YEAR 0.45 0.45 0.45 1.00 1.00 1.25 CHECK ON TIME OF CONCENTRATION AREA (A) = 4.25 ACRES OVERLAND FLOW (GRASS) ' L = 270 FT, DROP = 2.6 FT, S = 0.96%, INITIAL FLOW TIME T11= [(1.8)(1.1—CCf)(L)'/Z1/(S)'/' ' FOR T2& T1o, T11= 27.0 MINUTES FOR T1oo. Tit= OVERLAND FLOW (PAVEMENT) L = 165 FT, DROP = 0.60 FT, S = 0.367, INITIAL FLOW 11ME Ti2= [(1.8)(1.1—CCf)(L)'/21/(S)'/' ' FOR T2 & T10 . T12= 4.87 MINUTES FOR T1oo , TRAVEL TIME IN SWALE WEST SWALE (SHORT GRASS SHALLOW SWALE) L = 180 FT, S = 1.07., V = 1.5 FPS, ' TT = 2.0 MINUTES 25.5 MINUTES T11= 3.25 MINUTES ' TIME OF CONCENTRATION To= Tl + T + TT FOR T2 & T10 , To = 33.9 MINUTES FOR T100 , To = 30.8 MINUTES ' (PER ORIGINAL CALCS) USE Tc = 18 MIN (14 MIN FOR 100y) ' USING RATIONAL EQUATION (Q=CIA) A = 4.25 C2 = .45 12 = 1.70 Q2 = (C2)(12)(A) = 3.25 CFS C10 = .45 110 = 2.90 Q10 = (C1o)(11o)(A) = 5.55 CFS C1oo = .45 1100 = 6.71 Q1oo = (C 1oo)(Cf )(I 1oo)(A) = 16.0 CFS Page 4 y ♦ s �f T u P- 'Fai N �fj{h a fi' - N r In• IE O O O O O O O O O O O O OOCIOOOMMOOOO 6 O 4 M CV O (aglui) Avsua;ul CD N u 11 Design Procedure Form: Extended Detention Basin (EDB) - Sedimentation Facility 11 11 [] Designer. Kevin Forbes 1 of 3 Company: Forbes Engineering Date: REVISED MAYS. 2011 Project: Spirit of Joy Church Location: Ft Collins, CO 1. Basin Storage Volume A) TriblgaryArea's Imperviousness Ratio (i = I,/ 1D0 ) B) Contributing Watershed Area (Area) C) Water Quality Capture Volume (WQCV) (WQCV =t0•(0.91 •0-1.19-P+0.78-D) D) Design Volume: Vol = (WQCV / 12) - Area' 1.2 2. Outlet Works A) Outlet Type (Check One) B) Depth at Outlet Above Lowest Perforation (H) C) Recommended Mapmum Outlet Area per Row, (AJ D) Perforation Dimensions: i) Cinwlar Perforation Diameter or ii) Width of 2" High Rectangular Perforations E) Number of Columns (nc, See Table 6a-1 For Ma)dmum) F) Actual Design Outlet Area per Row (Ao) G) Number of Rows (m) H) Total Outlet Area (A,) 3. Trash Rack A) Needed Open Area: Ah = 0.5 • (Figure 7 Value)' Ad B) Type of Outlet Opening (Check One) C) For 2", or Smaller, Round Opening (Ref.: Figure 6a): i) Width of Trash Rack and Concrete Opening (W.) from Table 6a-1 ii) Height of Trash Rack Screen (Hm) 1, = 12.00 % i=1 0.12 I Area = 4.250 acres WOCV = 0.08 watershed inches Vol = 0.0332 acre-feet X Orifice Plate Perforated Riser Pipe Other. H = 1.83 feet Q Ao=squam Inches D=r o�-jirhca, Of33 ke W =1 l inc hes nc=F --- l---1 number Ao= 0.1 square inches nr = number Aa = 0.6 square inches A, = square inches < 2" Diameter Round I --IT High Rectangular Other W. = inches Hm = 52 inches €t� El 04 b �3w - -- EI —MEN ... ................ .■.OMEN■■■■■■...�. ................ .................. . ..........- 9E'e'= 9E=MMMO .■MEM.EWEN1 ..MMMMI .■ENMM� ............ M '-. ....=BE... C....I.1 : . MEN... ZI O U W U) LO M N O rn rn rn rn� � o .- N ^ > Z W 3 O O i �O gl s o3g e 0 �oN ' _ w J a6 g cn 0 I a� f �g mg tw nay od s d m §0 9 I 1 STEWART&ASSOC[ATES Consulting Engineers and Surveyors October 30, 1991 Mr. Glen Schlueter Storm Water Utility City of Fort Collins P.O. Box 580 Fort Collins, Colorado 80522 ' Dear Glen: I have checked the grading and construction of drainage facilities at Lot 1 of the Spirit of Joy Lutheran Subdivision. The grades of the parking lot, building, and drainage swales, and the construction of the trickle pan and pipe culverts were all done in substantial compliance with the approved plan. Please call if you need any additional information about this project. Sincerely, G7 Phillip V. Robinson, P.E. & L.S. Vice President ' jrr J cc: Mr. Ron Young, Adolfson—Peterson, Inc. James H. Stewart and Associates, Inc. 214 N. Howes Street P.O. Box 429 Ft. Collins, CO80522 303/482-9331 I i 1 STORM DRAINAGE REPORT FOR LOT 1, SPIRIT OF JOY LUTHERAN SUBDIVISION PREPARED FOR SPIRIT OF.JOY LUTHERAN CHURCH C/O ROBB, BRENNER & BRELIG PREPARED BY STEWART & ASSOCIATES, INC. FEBRUARY 18, 1991 REV15E,n 31zef91 (3EVI5ED ¢l14``4I I ' SITE LOCATION AND EXISTING CONTITIONS ' The Spirit of Joy Lutheran Church site contains 4.25 acres, and is located at the northwest corner of Harmony Road and Lemay Avenue. The site is platted as the Spirit of Joy Lutheran Subdivision. The site is located ' in the McClellands Drainage Way. The site drains to the south into a previously constructed ditch, which, is the outfall ditch from the detention pond systems constructed in Whalers Cove. This ditch drains from west to east across the Spirit of Joy Lutheran Church site, then east under Lemay ' Avenue, then south under Harmony Road, to an outflow ditch which goes southeast across the Oak Ridge development. The prevously designed flow quantity under', Harmony Road and into the Oak Ridge development is 55 c.f.s., ' although our calculations show the pipe will carry 61 c.f.s. PROPOSED DEVELOPMENT ' We plan to allow the runoff from the Spirit of Joy Lutheran Church site to go undetained into the outflow ditch, so that it can be carried downstream before the major flows from the upstream development reach the ' site. Our calculations show that the 27" X 44" pipe under Harmony Road will carry the maximum outflow from the Whalers Cove detention pond, along with the 100 year developed runoff from the church site, the runoff from ' Lemay Avenue, and the runoff from Harmony Road. The existing site and developed site runoff quantities are calculated on sheets 2 and 3 of this report. The developed site takes into account the planned future expansion of the building and parking lot. The runoff from the proposed development shall be directed to the southeast across the site, so that no additional runoff is allowed into the Whalers Cove ' swale which lies just west of the site. The 100 year runoff from the developed site is 18 c.f.s. after 14 minutes. This quantity can be easily carried by the existing ditch and pipe system, and since it will peak before upstream flows reach the site, there will be no problem caused by the undetained runoff. ' The offsite flows consist of the outflow from the Whalers Cove detention pond which crosses the south edge of the property in an existing ditch, the Lemay Avenue runoff which is picked up by existing catch basins on each ' side of the street, and the Harmony Road runoff which drains to the existing ditch across the south edge of the property. There are no other offsite flows onto the property. Sheets 4 and 5 show the quantity calculation of these offsite flows. Sheets 6 and 7 of the calculations show the capacity of the 27" X 44" pipe under Lemay and Harmony, and the total runoff which will be directed ' to this pipe. Sheet 11 is a vicinity map showing flow directions, and sheet 12 is the site grading and drainage plan. ' Phillip I. Robinson, P.E. & L.S. 1 COMPUTATIONS Stewart & Associates, Inc. 214 N. Howes St.. Ft. Collins, CO 80521 (303) 482-9331 ' By: P) J�s Date 3)Ztr 91 Client: s i ri Ir o; rd Lvl-ko �h Sheet No. 2 of r - 11 Chkd By: Date Project: Si } e e A/y✓ GO . Le/no 4- j }O NOk Subject %7 %S40 HCr� s'i'%e 1'l/n09 COMPUTATIONS Stewart & Associates, Inc. 214 N. Howes St. Ft. Collins, CO 80521 (303) 482-9331 By: Date lajqi Client: -5vjrl� Sheet No. 3 of � I I I Chkd By: Date- Project: SLLe- 4 /V k/ CVf-- LAMP v 4 14e4rMa4t' Subject -514� rvr)o� 5),L") y II Ic sl 7o. '3 +�l -16V ill; ;1 j G'fUZ- i /'nl 5 '3. 3 2. B, C7 C45 100 cA= I(ItZi5 TF4 ES Old Y, vFi -ri P'E 8- A�S! IT F U 7u �z p-, P, r-- i) PL4 K! COMPUTATIONS ' Stewart & Associates, Inc. 214 N. Howes St. Ft. Collins, CO 80521 (303) 482-9331 By: PifE Date - 2d) 9 I Client: Sheet No. 4- of /Z ' Chkd By: ,,�� (�•(('' 7 Date Project: S/ ��` a� mt/ Go r LeMa � Subject �+S 1 e ;)a wJ �(p � tn/A a )er-s Cp V e I I I! I I E X I s 7-1 N G- �. T i� P 4 _ U(_= j Al, t�.Ej ; 10. - - - i I ; I ; 1ivv-85.3Nl= Gq�ctci�/ z$�I �Z�yIII o_.�I.- a o_ -1 - - J eG�� Frq U,-r4'i 1=�g.,l m'ir vs -I ur�r.1 I /-�e� ✓asr I of G• 2�H� �c.e �y� _ !.rz � x�fi � I I I I ' 1%clrav 1c s�oTC f _ = I- r — , i F r r'or� �r�� c-h�a,r ; s Ga Gtci'� �yvl ! I � I i�) /c) V :;- l% I I 1'�"li.2t'"E'IFIOf.CI NC61btl -,yr� -r t.�„�_ O '- -- -jf' j4e'!rS --- , I I I i i i I I i I i i j I I COMPUTATIONS ' Stewart & Associates, Inc. 214,1N.Howes St. Ft. Collins, C080521 (303)482-9331 By: PIR Date 3)215*)01/ Client: of Soy �C'Aer_aki Sheet No. of /Z Chkd By: Date- Project: Sfkf -V AJw r-or Ler�my 1-ar-riven Subject J �.✓e -1! 4, 114Vp_,k) TZ 0 x 93 -,3 7 % �O 0i� 'e 7-c GUD +L0 + T 3A 2_1 2 3 7 L E7 M A) 1%1)=�jUE 4;1! 1; L Area 9 20 k 40 3 ceo dCl 7! 0, 720, 7 ��OK 7 as ,-e' J 0. 1(9 �7 1z btu Q too, 5-1 360 �e 0 'Liis j<Y 'f oh� 0SI -'Z �360'4 cl� �ov 4 4 0, T, 13V 3V,�, U. -.1 ------- C iA 0., 0. _� J 2-3 1 V, 0O1'� 05) 0 COMPUTATIONS Stewart & Associates, Inc. 214 N. Howes St. Ft. Collins, C0 80521 (303) 482.9331 ' By: Dirt Date 3 z09 Client: S1 1!h o� To y ��'�7ero^ Sheet No.�_of / 2 J Chkd By: Date Project: 5 i 3 e 0.* N L/ car- Lento - ii rwi'Ntany Subject r_ r ci `'y 0 T- 4 ¢ if x 2-71i RCP ohel « J emo,v l uf(-sAo^,- J ' Are0. 0 = 0.0/5 I 1 ! ' 1 I f R° i I ! ilvV 82, ) MllnvS�.%��QdGi %}cam /os1 - o, 6 ' �yo�ra�Iic. S �Ope � !¢•Y30Q. _ �r01% I c/3 % �i •l L7���)� G GI.S� I �Q.7i� i o. 01¢ l06 G- S I I I ' GQ�atei r 6r i,)e eo., f-a� (71 I� a.: 6 is G4(4-Ix i 44 Ji x 77it 0v4JC.J1 .lei ;un 1 er: li��'' ytl� iCci.// /0WGOver'/ S�;GTS'1� 71 �' ��.� use' In' the p� r5i 1P1 po:,c:i� el_ G45�C 1nt di ��eie�ce i3 '� shall 5, er4 eel( + U a shov 170' ccic/Se i ctin a.civeirse, Olol.✓ns;lrecrm I I I ; ' i . [1 COMPUTATIONS ' Stewart & Associates, Inc. I 214 N. Howes LSt. Ft. Collins, CO 80521 (303) 482-9331 By: �i/_ Date3 2J 't Client:_ : 72! c4 o' i Sheet No.-7of Chkd By: /"c Date- SubjectProject: Sl�' N ✓ CGr L.?n�u�r- /�c�/rn.or�y __/Q7/ run0--r F 10 ¢9 " x 27 II Vi�C uo7niei P-ai'MOny rvn0 4 ru r✓oqr;� r 1inGTr9 run U1 �ra,r wl;otG'r� zcrive FranVll' de -o/v�r �l Vj-c�t she i ,7 -�1'OMt AA/ /-{ I Si--i� �MPy '✓Pn �j i e.PJ G?S G.¢ J f S- `1 rJ 6 /. 2 cJ COMPUTATIONS ' Stewart & Associates, Inc. 214 N. Howes St. Ft. Collins, CO 80521 (303) 482-9331 'BY: P1 R Date 3 2 Jll Client: SPLt,Aef-, n Sheet No. ofZ2 Chkd By: Date t Project: sloe 00L N v✓ cVf`. Lem oty 4- 14.fMf/NL Subject -G! Capa e j y 01 %fig f i 1 LOV FLOW G /area 0,75; I0.175- 3 2f 0:7s��._r-I Mau Q = /01). , i = CA-5 Pam wllt catfir` i = I�. s ', lOd Y,- fo i ccS/n APHCITy OF EX/57t%IG DizCr=! 01'.C)4 I�LCjX67 S. slpE / j 2. RYea _ ZO ;s, c, :SJ_ 0'. S� _ Pf J = Z= y o� 4. c���cv� :��=rs!;..� �� a : ,s��r�P �o:ndir i 0'1 CLe�ay) Fron Fi�Jre s-z the G61c1, bcs'irf. will ha✓e a co oci''� of / 1, CIS ner � .'off otDPrt nF G1- (l.'SICf�( 80 ¢,�FS %his Is :ICJ Vectr -FIO,.✓ )-6e E:+s and n/t'sf'. sr�Es hF L er­,oy �.. and- jS /80,� o� f� e 100 -F�uw. COMPUTATIONS Stewart & Associates, Inc. 214 N. Howes St. Ft. Collins, CO 80521 (303) 482-9331 ' By: p)Tt Date Client: -5bz �4 o--Joa Lo4ero,H Sheet No. of I Z ChkdBy: Date Project: Sti& k/ Cur - Subject i'ar(cit)< Lai` %-<unlJ4 ��ull�y de✓elaEer—l) PAFRPCIN G rJ 'RUNoFFI n/044 eu Ai-e_c%- = sf pa rr lo 4 C O. `13 G = 6 fu.ivr ullr d e✓elan ed :,4 p• L = 2 err' s lv/a e = J f Tc= /0 G/fa = (o,e x� S)� U.43 1.86.E r �w = G! /a o.8i ( �)( 0',").3. 3. ic�! I , Sou'u '1EGS� PG 0 e✓elope . /-)ream _ �,/G /1c c = 0.95 . L ./100 TG- 5 vim J 3,J �1a= G1i4 5'.6t(0•'161). O.S'e4I: �1Go= GFCI,A'= 41.7 GfS: I i ' v✓es% Pq r--I- o-� /a ( -Fulvr¢. 4.!/y �l e ✓ego e� L 35�0 s)o7 CIA 41'-4`)C,rj':IGTS Qwo = G G1/a (1l(3/� l ¢s�' Z: s I COMPUTATIONS Stewart & Associates, Inc. 214 N. Howes St. Ft. Collins, CO 80521 (303) 482-9331 By: �%� Date_ Client:`ni r o I oy i}� grog Sheet No. / U of j Z Chkd By: Date Proiect: S) Gi NL✓ nr / e_ J -. Subject �`� i ji I; Gs i a 21 I , • ' 1 I r� I o 7�ar�' hbTi�east! alGieve lope�. �artTi✓1� /af �/ 01# 3;3 G,Ff Qtuv� �cUrrh' I Area- ¢.I s !s%13e ;I )Yi! ! 11-7 030 z.7 BPS G1= /3 tr �¢ J}(i.�) ; %1, I t ''w ore f h'a� re�vlrc! I � I T1te swa�F ! ✓i!1); cc#rry� �hq JUO I SCA- 62 ?�/.!L i I i i I i I �A10 5CA)LE) ' OLVEF nr COVRr -------1- 3 ' N J J Q Z ExisT 4-' cr3 S. LEMA✓ /-iJE Exis r 4 cQ J �_ ! 3a OF,s-1 IN Pl7GH — GHVRCN 51TE II o FULLY' z cDEVElUPttCZd, u -- 8.0 cfs I a 18. EXIST z4Z' G g F \\ Q C�F?GLE o ILL !n PC SHEET / ( of )7. Public Improvements Opinion of Costs Spirit of Joy Church Manna nnte- Senarate costs are needed for nn.site and nff-site imorovemerKs Public Improvement Item Iynits Unit Cost Est. Item Cost .. _-- .- , ..,. .., . , , ...-s,. .... - , 20.2.1 Erosion Control Stockpile Topsoil CY $0.00 Straw Bales EA $10.00 5 $50.00 Inlet Protection EA $0.00 Silt Fence LF $1.50 563 $844.50 Sediment Trap EA $0.00 Vehicle Tracking Pad I EA $3,000.00 1 $3,000.00 Subtotal 20.2.1 Erosion Control $3,894.50 20.2.2 Street Improvements Clearing and Grubbing Lump Sum LS $0.00 Removal of Structures and Obstructions EA $0.00 Subgrade Preparation SY $0.00 Excavation CY $0.00 Borrow CY $0.00 Fill CY $0.00 Rock Excavation CY $0.00 Filter Material CY $0.00 Lime Treatment SY $0.00 Asphalt Patching TONS $0.00 Asphalt Pavement Sq Yd $0.00 Base Course TONS $0.00 Concrete Pavement SY-IN $0.00 Geotextile SY $0.00 Riprap CY $0.00 Survey Monuments EA $0.00 Adjust Manholes EA $0.00 Adjust Valves EA $0.00 Adjust Monuments I EA $0.00 Mobilization and Demobilization 1 $0.00 Subtotal 20.2.2 Street Improvements 20.2.3 Structures $u.uu Bridge Structure EA $0.00 Culverts EA $0.00 Guardrail LF $0.00 Railing (Pedestrian) LF I $0.00 Railing (Traffic) LF $0.00 20.2.4 Pedestrian and Bikeway Facilities 20.2.5 Sti Subtotal 20.2.3 Structures Sidewalk Grading SY $0.00 4-inch Thick Sidewalk SY $0.00 6-inch Thick Sidewalk SY $0.00 Directional Curb Ramp SY $0.00 Comer Curb Ramp SY $0.00 Mid Block Ramp SY $0.00 Concrete Bikeway SY $0.00 Sidewalk Chase EA $0.00 Curb and Gutter Grading LF $0.00 Curb and Gutter - Type II LF $0.00 Curb and Gutter- Type I LF $0.00 Glue -down Curb LF $0.00 Subtotal 20.2.4 Pedestrian and Bikeway Facilities ;.= 1r met Lighting Standard Pedestrian Light I EA I 1 $0.00 Standard Street Light I EA I 1 $0.00 Subtotal 20.2.5 Street Lighting $0.00 20.2.6 Traffic Signals. Signing and Striping Standard Street Signs EA $0.00 Standard Sign Posts EA $0.00 Standard Regulatory Signs EA $0.00 Standard Speed Limit Signs EA $0.00 Latex Paint (4 inches) LF $0.00 Latex Paint (8 inches) LF $0.00 Latex Paint (12 inches) LF $0.00 Latex Paint (18 inches) LF $0.00 Latex Paint (24 inches) LF $0.00 Epoxy Pavement Marking (4 inches) LF $0.00 Epoxy Pavement Marking (8 inches) LF $0.00 Epoxy Pavement Marking (12 inches) LF $0.00 Epoxy Pavement Marking (18 inches) LF $0.00 Epoxy Pavement Marking (24 inches) LF $0.00 Preformed Tape for Symbols & Crosswalks LF $0.00 Preformed Thermoplastic SF $0.00 Traffic Signals EA Subtotal 20.2.6 Traffic Signals, Signing and Striping $0.00 I i 1 1 20.2.7 Work Zone Traffic Control Traffic Control 20.2.8 Storm Drainage Facilities LS Subtotal 20.2.7 Work Zone Traffic Grading SY $0.00 Inlets EA $0.00 Manholes EA $0.00 Pipe (Material Type - Size) LF $0.00 Trickle Channel (width) LF $0.00 Outlet Structure (orifice plate) EA $0.00 Subtotal 20.2.8 Storm Drainage Facilities 20.2.9 Removals and Repair $0.00 Asphalt Patching SY $0.00 Concrete Sidewalk R & R SY $0.00 Concrete Curbwalk R & R LF $0.00 Milling SY $0.00 Asphalt Removal SY $0.00 Subtotal 20.2.9 Removals and Repair 20.2.10 Construction Surveying/Staking ILS Subtotal 20.2.10 Construction Surveying/Staking $0.00 20.2.11 Material Testing $0.00 Subtotal 20.2.11 Material Testing $0.00 20.2.12 Record Drawings Subtotal 20.2.12 Record Drawings $0.00 20.2.13 Construction Management I I I Inla Subtotal 20.2.13 Construction Management $0.00 Water Line Construction Water Mains I 1 1 $0.00 On -Site Water Supply Service LF $0.00 Fire Hydrants $0.00 Subtotal Water Line Construction $0.00 i 1 1 1 1 Sewer Line Construction Trunk Lines $0.00 Mains $0.00 Laterals or House Connections $0.00 On -Site Sewage Facilities Septic EA $0.00 Subtotal Sewer Line Construction $0.00 Other $0.00 Subtotal Other $0.00 SUBTOTAL OF PUBLIC IMPROVEMENTS: Additional 15% required by Section 12.6.2.C: GRAND TOTAL OF PUBLIC IMPROVEMENTS: Landscape Improvements: $3,894.50 $584.18 $4,478.68 Plant Materials - $0.00 Irrigation System $0.00 Paving / Surfacing $0.00 Structual Elements (Gazebo's, Benches, Fountains, etc.) $0.00 Mulch / Weed Barrier Materials SF $0.00 Edging / Tree Staking Materials $0.00 SUBTOTAL OF LANDSCAPE IMPROVEMENTS: $0.00 Additional 15% required by the Dev. Agreement $0.00 GRAND TOTAL OF LANDSCAPE IMPROVEMENTS: $0.00 BOARD OF COUNTY COMMISSIONER �0�. REG[o. LARIMER COUNTY I If project in GMA) Chairman DEVELOPER