HomeMy WebLinkAboutDrainage Reports - 06/13/2025Hoffman Mill Drainage Memo.docx 1/3 To: Bill Welborn, City of Fort Collins CC: File AECOM 7595 Technology Way Denver, CO 80237 T: +1 (303) 694 2770 F: +1 (303) 694 3946 aecom.com Project name: Hoffman Mill Minor Amendment Weigh Station Paving From: David Seyboldt Date: January 21st, 2022 Technical Memo Subject: Drainage Calculations 1.Purpose and Objectives This memo presents the results of the drainage analysis of the Hoffman Mill Weigh Station site and assesses the compatibility of the Weigh Station site improvements with the existing drainage infrastructure located on the Fueling Site. The existing infrastructure includes a detention pond, outlet pipe, and overflow spillway and is located immediately downstream of the Weigh Station site. The constructed Weight Station site improvements include a paved driveway and weigh scales. Proposed improvements include a shallow swale graded into the parking lot to direct runoff toward the detention pond instead of into the Fueling Site building. A Final Storm Drainage Letter was prepared by Interwest Consulting Group (Interwest) for the building adjacent to the Fueling Site in October 2018. The hydrologic assumptions and calculations made in that letter are maintained here where possible, as discussed further below. 2.Calculations The Weigh Station site improvements consist of a 30-foot-wide paved driveway extending from Hoffman Mill Road north to an existing building, a distance of approximately 415 feet. Adjacent to the driveway is a truck scale. These improvements have already been constructed. There was no grading performed on the site with these improvements, so the existing drainage patterns have not changed. The drainage basins delineated with the Interwest Drainage Letter remain applicable to this analysis. There were two primary objectives for the drainage calculations. First, to calculate the additional runoff generated on the site due to the added pavement. Second, to determine if the existing pond is adequate to capture and attenuate this flow. The pre-development condition was assumed to include the entire area tributary to the location of the Fueling Site pond prior to the construction of Fueling Site improvements. This was used to determine the allowable release rate from the pond. The drainage basins OS1 and H1 were combined into a single basin named EX1. For the post-development condition, the additional Weigh Station pavement area was added, the Fueling Site improvements were accounted for, and the basin was named PR1. The runoff coefficient C values for individual land uses and the times of concentration for the tributary areas were taken from the Interwest letter. The weighted C value for basin PR1 was updated to account for the new impervious area of the driveway. To obtain the total time for the new basins, the City of Fort Collins Approved Plans Approved by: Date: Wes Lamarque 06/13/2025 Technical Memo AECOM Hoffman Mill Drainage Memo.docx 2/3 time of concentration for basin OS1 was added to the travel time from basin H1 for pre-development conditions and D1 for post-development conditions. Finally, the 100-yr peak flow rates were computed. It was assumed that the new driveway did not significantly change the time of concentration for the basin. To analyze the existing pond capacity a storage routing table was developed to determine the maximum storage required, and then compared to the existing storage volume indicated on the Interwest letter. The maximum inflow to the pond is the 100-yr peak flow rate for the post-development condition. The maximum outflow is the 100-yr peak flow rate for the pre-developed condition. The maximum required storage was calculated to be 0.066 ac-ft; the existing pond volume is 0.073 ac-ft. A stage storage table for the existing pond was created using the pond contours from the Fueling Site construction plans. A storage volume of 0.066 ac-ft corresponds to a water surface elevation of 4947.24. Next, a calculation was performed to analyze the existing restrictor plate on the 18” pond outlet pipe. The calculation shows that the pipe can pass the pre-developed peak flow rate at a water surface elevation of 4947.40, which is below the spillway elevation of 4947.70. Since the outlet pipe will not convey its maximum flow until a certain headwater is reached, it is likely the pond will fill to the 4947.40 elevation and discharge at a constant rate until the water surface drops. But the storage routing calculation indicates that the volume at this elevation is greater than necessary to attenuate the peak inflow. 3. Drainage Improvements The users of the Fueling Site have indicated that during rainfall events the runoff flows across the site from west to east and instead of discharging to the existing ditch and detention pond a substantial amount flows down the driveway into the building adjacent to the Fueling Site and causes flooding. To mitigate this, the site will be graded to create a minor swale which runs from north to south. The swale will intercept runoff flowing from west to east and direct the runoff into the riprap rundown which leads into the ditch and detention pond. Since the entire site is utilized for truck operations, the swale is designed to have no impact to truck movements. It will have 2% side slopes and be approximately 4 inches deep; the longitudinal slope will be between 2.8% and 4%. The Bentley Flowmaster calculations show that the swale has capacity to convey the 100-yr event runoff from the site. In the area of the proposed swale, the site is currently compacted dirt / gravel; no changes are proposed to the surface materials. A new prefabricated 10’x12’ building will be installed on an existing concrete pad in front of the Weigh Station building. Since the concrete pad is existing it was included in the original impervious area calculations and will not affect these drainage calculations. 4. Conclusion The calculations performed for this site maintain the calculations included with the approved Interwest Drainage Letter with regards to land use coefficients and times of concentration. The weighted runoff coefficient of the drainage basin was recalculated for this memo based on the new paved driveway and weigh station. All the calculations referenced above are attached to this memo. The results indicate that the existing pond on the Fueling Site has the capacity to attenuate the increased runoff due to the pavement constructed on the Weigh Station Site. No changes to the existing pond, spillway, or outlet pipe are required due to the Weigh Station Site improvements. Technical Memo ECOM Hoffman Mill Drainage Memo.docx 3/3 Attachments: Rational Calculations Pond Routing Calculations Orifice Calculation Flowmaster Report Fueling Site Calculations Basin Map Runoff Coefficients Project: Hoffman Mill Calculated by DS Date: 9/28/2021 AECOM Project Number.: 60667912 Checked by RM Date: 10/1/2021 C2 C100 C Area (acres)C Area (acres) EX1 3.65 0.35 0.44 0.95 0.55 0.25 3.10 Pre Development Tributary Area entire site PR2 3.65 0.44 0.56 0.95 1.01 0.25 2.63 Post Development Tributary Area entire site Basin ID  Hardscape: Asphalt,Concrete, Rooftops Lawns, Sandy Soil >7% or Heavy Soil <2%Composite C Total Area  (ac) Fort Collins Rational Calc.xlsx Page 1 Standard Form SF-1 . Time of Concentration Basin ID C2, C5 C100 Area (ac) From  Interwest  Calcs EX1 0.35 0.44 0.35 21.72 Tc from basin OS1 plus travel time in basin H1 PR2 0.44 0.56 0.44 21.22 Tc from basin OS1 plus travel time in basin D1 Fort Collins Rational Calc.xlsx Page 1 Standard Form SF-2 . Storm Drainage System Design (Rational Method Procedure) Project: Hoffman Mill Computed: DS Date: 9/28/2021 Checked: RM Date: 10/1/2021 Design Storm: 100-yr IN L E T RE C E I V I N G FL O W AR E A DE S I G N (n a m e ) AR E A ( A C ) RU N O F F C O E F F tc (M I N ) C. A . (A C ) I* IN / H R Q (C F S ) tc (M I N ) SU M ( C * A ) (A C ) I* IN / H R Q (C F S ) (1) (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) EX1 3.65 0.44 21.72 1.62 5.36 8.67 Pre Development Tributary Area entire site PR2 3.65 0.56 21.22 2.03 5.43 11.00 Post Development Tributary Area entire site PROJECT STREET DE S I G N P O I N T DIRECT RUNOFF TOTAL RUNOFF Existing Offsite Flows REMARKS Fort Collins Rational Calc.xlsx Page 1 EXISTING DET POND 100 YR C(100)0.56 Tc (min) = 21.22 Area =3.65 acres Qout =8.67 cfs = Historic Release Rate Available Pond Vol=0.073 ac-ft Time Intensity Area Qin Cum. Vin Qout pipe Cum. Vout Storage Qout Overflow Vout Overflow (min) (in/hr) (AC) (cfs) (ac-ft) (cfs)(ac-ft)(2)(ac-ft)(1)(cfs) (cfs) 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5 9.95 0.86 4.75 0.03 4.75 0.03 0.00 0.00 0.00 6 9.31 1.03 5.33 0.04 5.33 0.04 0.00 0.00 0.00 7 8.80 1.20 5.88 0.06 5.88 0.06 0.00 0.00 0.00 8 8.38 1.38 6.40 0.07 6.40 0.07 0.00 0.00 0.00 9 8.03 1.55 6.90 0.09 6.90 0.09 0.00 0.00 0.00 10 7.72 1.72 7.37 0.10 7.37 0.10 0.00 0.00 0.00 11 7.42 1.89 7.79 0.12 7.79 0.12 0.00 0.00 0.00 12 7.16 2.06 8.20 0.14 8.20 0.14 0.00 0.00 0.00 13 6.92 2.23 8.59 0.15 8.59 0.15 0.00 0.00 0.00 14 6.71 2.41 8.97 0.17 8.67 0.17 0.01 0.00 0.00 15 6.52 2.58 9.34 0.19 8.67 0.18 0.01 0.00 0.00 16 6.30 2.75 9.62 0.21 8.67 0.19 0.02 0.00 0.00 17 6.10 2.92 9.90 0.23 8.67 0.20 0.03 0.00 0.00 18 5.92 3.09 10.17 0.25 8.67 0.21 0.04 0.00 0.00 19 5.75 3.27 10.43 0.27 8.67 0.23 0.05 0.00 0.00 20 5.60 3.44 10.69 0.29 8.67 0.24 0.06 0.00 0.00 21 5.46 3.61 10.95 0.32 8.67 0.25 0.066 0.00 0.00 22 5.32 3.65 10.78 0.33 8.67 0.26 0.06 0.00 0.00 23 5.20 3.65 10.53 0.33 8.67 0.27 0.06 0.00 0.00 24 5.09 3.65 10.31 0.34 8.67 0.29 0.05 0.00 0.00 25 4.98 3.65 10.09 0.35 8.67 0.30 0.05 0.00 0.00 26 4.87 3.65 9.87 0.35 8.67 0.31 0.04 0.00 0.00 27 4.78 3.65 9.68 0.36 8.67 0.32 0.04 0.00 0.00 28 4.69 3.65 9.50 0.37 8.67 0.33 0.03 0.00 0.00 29 4.60 3.65 9.32 0.37 8.67 0.35 0.03 0.00 0.00 30 4.52 3.65 9.16 0.38 8.67 0.36 0.02 0.00 0.00 31 4.42 3.65 8.95 0.38 8.67 0.37 0.01 0.00 0.00 32 4.33 3.65 8.77 0.39 8.67 0.38 0.00 0.00 0.00 33 4.24 3.65 8.59 0.39 8.67 0.39 0.00 0.00 0.00 Project: Basin ID: X 1 #1 Vertical #2 Vertical Sizing the Restrictor Plate for Circular Vertical Orifices or Pipes (Input)Orifice Orifice Water Surface Elevation at Design Depth Elev: WS = 4,947.40 feet Pipe/Vertical Orifice Entrance Invert Elevation Elev: Invert = 4,944.56 feet Required Peak Flow through Orifice at Design Depth Q = 8.67 cfs Pipe/Vertical Orifice Diameter (inches) Dia = 14.4 inches Orifice Coefficient Co =0.65 Full-flow Capacity (Calculated) Full-flow area Af = 1.13 sq ft Half Central Angle in Radians Theta = 3.14 rad Full-flow capacity Qf = 8.8 cfs Percent of Design Flow = 102% Calculation of Orifice Flow Condition Half Central Angle (0<Theta<3.1416) Theta = 2.64 rad Flow area Ao =1.10 sq ft Top width of Orifice (inches)To =6.97 inches Height from Invert of Orifice to Bottom of Plate (feet)Yo =1.12 feet Elevation of Bottom of Plate Elev Plate Bottom Edge = 4,945.68 feet Resultant Peak Flow Through Orifice at Design Depth Qo =8.7 cfs Width of Equivalent Rectangular Vertical Orifice Equivalent Width = 0.98 feet Existing Orifice Plate with new design flow RESTRICTOR PLATE SIZING FOR CIRCULAR VERTICAL ORIFICES Hoffman Orifice Plate.xls, Restrictor Plate 10/13/2021, 11:53 AM This is the WSEL required to pass the peak flow through the existing orifice This calculation shows that the existing orifice can pass the historic flow of 8.67 cfs before the WSEL exceeds the spillway invert of 4947.70 Parking Lot Swale Grading Project Description Manning FormulaFriction Method DischargeSolve For Input Data 0.022Roughness Coefficient ft/ft0.028Channel Slope in4.0Normal Depth H:V50.000Left Side Slope H:V50.000Right Side Slope Results cfs19.01Discharge ft²5.6Flow Area ft33.3Wetted Perimeter in2.0Hydraulic Radius ft33.33Top Width in4.7Critical Depth ft/ft0.012Critical Slope ft/s3.42Velocity ft0.18Velocity Head ft0.52Specific Energy 1.478Froude Number SupercriticalFlow Type GVF Input Data in0.0Downstream Depth ft0.0Length 0Number Of Steps GVF Output Data in0.0Upstream Depth N/AProfile Description ft0.00Profile Headloss ft/sInfinityDownstream Velocity ft/sInfinityUpstream Velocity in4.0Normal Depth in4.7Critical Depth ft/ft0.028Channel Slope ft/ft0.012Critical Slope Messages Page 1 of 227 Siemon Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 10/11/2021 FlowMaster [10.02.00.01] Bentley Systems, Inc. Haestad Methods Solution CenterHoffman.fm8 Parking Lot Swale Grading Messages This calculation shows the capacity of the swale which will be graded into the existing parking lot. Side slopes are 2% and the minimum longitudinal slope is 2.8%. Notes Page 2 of 227 Siemon Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 10/11/2021 FlowMaster [10.02.00.01] Bentley Systems, Inc. Haestad Methods Solution CenterHoffman.fm8 Design Engineer: Design Firm: Project Number: Date: % Impervious Runoff Coefficient C Return Period Frequency Adjustment Factor (Cf) 100% 0.95 2-year to 10-year 1.00 90% 0.95 100-year 1.25 90% 0.95 40% 0.50 0% 0.25 C2 to C10 C100 OS1 133,035 3.054 0 8,330 9,935 0 114,770 12.4% 0.35 0.43 H1 25,833 0.593 0 2,480 3,038 0 20,315 19.2% 0.40 0.50 Apavers (sq feet) Alawn (sq feet) Weighted % Impervious COMPOSITE Hoffman Mill Fuel Site EXISTING IMPERVIOUS AREA CALCULATION Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) DESIGN CRITERIA: BASINS: % Impervious values from Table RO-3 in the Urban Storm Drainage Criteria Manual Sub-basin Designation Atotal (sq feet) Atotal (acres) Apaved (sq feet) Aroof (sq feet) Awalk/RAP (sq feet) Lawns (Heavy, 2-7% Slope) J.Claeys Interwest Consulting Group 1344-095-00 June 6, 2018 Runoff Coefficients and Frequency Adjustment Factors for City of Fort Collins - Storm Water Criteria Manual Land Use Paved Roof Walks/RAP Gravel/Pavers 1344-095-00 Rational Calcs (FC).xlsx Page 1 of 4 Interwest Consulting Group The following pages are an excerpt from the Hoffman Mill Fueling Site Final Drainage Letter prepared by Interwest Consulting Group, October 31, 2018. Values highlighted in yellow were used unchanged for these hydrology and hydraulics calculations to analyze the existing pond and its capacity to attenuate the Weigh Station Site runoff. Design Engineer: Design Firm: Project Number: Date: EQUATIONS: -Equation 6-2 -Equation 6-4 -Urbanized Check Equation 6-5 - CoFC Overland Flow CONSTRAINTS: 300 ft - Overland flow shall not exceed for developed condition 500 ft - Overland flow shall not exceed for undeveloped condition Final t c = minimum of t i + t t and urbanized basin check recommended minimum t c = 5 min for urbanized basins Time of Concentration (100-yr) Type of Travel Surface Cv OS1 OS1 12.4% 0.43 3.054 300 0.0157 18.61 234 0.0120 Paved Areas 20 2.19 1.78 20.39 0.0141 21.16 20.39 H1 H1 19.2% 0.50 0.593 88 0.0291 7.40 154 0.0093 Paved Areas 20 1.93 1.33 8.73 0.0165 17.01 8.73 June 6, 2018 Hoffman Mill Fuel Site HISTORIC TIME OF CONCENTRATION J.Claeys Interwest Consulting Group 1344-095-00 LENGTH (ft) DESIGN CRITERIA: Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) Overland Flow Equations for City of Fort Collins - Storm Water Criteria Manual SUB-BASIN DATA INITIAL/OVERLAND TIME (ti)TRAVEL TIME (tt) tc=ti+tt (min) Urban Check Final tc (min)DESIGN POINT Sub-basin % Impervious C100 AREA (acres) tt (min) OVERALL SLOPE (ft/ft) tc (min) SLOPE (ft/ft) ti (min) LENGTH (ft) SLOPE (ft/ft) Table RO-2 VELOCITY (ft/s) ticttt+=5.0 wvSCV= V Ltt60 = =18 − 15 + 60 24+12  = 1.87(1.1 − )  1344-095-00 Rational Calcs (FC).xlsx Page 3 of 4 Interwest Consulting Group Design Engineer: Design Firm: Project Number: Date: % Impervious Runoff Coefficient C Return Period Frequency Adjustment Factor (Cf) 100% 0.95 2-year to 10-year 1.00 90% 0.95 100-year 1.25 90% 0.95 40% 0.50 0% 0.25 C2 to C10 C100 D1 25,836 0.59 0 2,481 10,384 0 12,971 44.8% 0.60 0.75 Hoffman Mill Fuel Site DEVELOPED IMPERVIOUS AREA CALCULATION DESIGN CRITERIA: Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) BASINS: % Impervious values from Table RO-3 in the Urban Storm Drainage Criteria Manual J.Claeys Interwest Consulting Group 1344-095-00 June 6, 2018 Land Use Paved Roof Walks Runoff Coefficients and Frequency Adjustment Factors for City of Fort Collins - Storm Water Criteria Manual Gravel/Pavers Lawns (Heavy, 2-7% Slope) Sub-basin Designation Atotal (sq feet) Atotal (acres) Weighted % Impervious COMPOSITEApaved (sq feet) Aroof (sq feet) Awalk (sq feet) Agravel/pavers (sq feet) Alawn (sq feet) 1344-095-00 Rational Calcs (FC).xlsx Page 1 of 4 Interwest Consulting Group Design Engineer: Design Firm: Project Number: Date: EQUATIONS: -Equation 6-2 -Equation 6-4 -Urbanized Check Equation 6-5 - CoFC Overland Flow CONSTRAINTS: 300 ft - Overland flow shall not exceed for developed condition 500 ft - Overland flow shall not exceed for undeveloped condition Final t c = minimum of t i + t t and urbanized basin check recommended minimum t c = 5 min for urbanized basins Time of Concentration (2-yr to 10-yr) Type of Travel Surface Cv D1 D1 44.8% 0.60 0.593 156 0.0072 13.08 150 0.0229 Paved Areas 20 3.03 0.83 13.90 0.0149 13.11 13.11 June 6, 2018 Hoffman Mill Fuel Site DEVELOPED TIME OF CONCENTRATION J.Claeys Interwest Consulting Group 1344-095-00 LENGTH (ft) DESIGN CRITERIA: Urban Storm Drainage Criteria Manual by Urban Drainage and Flood Control District, June 2001 (Revised January 2016) Overland Flow Equations for City of Fort Collins - Storm Water Criteria Manual SUB-BASIN DATA INITIAL/OVERLAND TIME (ti)TRAVEL TIME (tt) tc=ti+tt (min) Urban Check Final tc (min)DESIGN POINT Sub-basin % Impervious C2-10 AREA (acres) tt (min) OVERALL SLOPE (ft/ft) tc (min) SLOPE (ft/ft) ti (min) LENGTH (ft) SLOPE (ft/ft) Table RO-2 VELOCITY (ft/s) ticttt+=5.0 wvSCV= V Ltt60 = =18 − 15 + 60 24+12  = 1.87(1.1 − )  1344-095-00 Rational Calcs (FC).xlsx Page 2 of 4 Interwest Consulting Group Hoffman Mill Fueling Site Critical Pond Elevations Design Engineer: Design Firm: Project Number: Date: DESIGN CRITERIA Urban Storm Drainage Criteria Manual, Urban Drainage and Flood Control District, June 2001 (Revised April 2008) Volume obtained utilizing 2018 AutoCAD Civil3D Storage Summary 4947.00 ft 283 cu-ft 290 cu-ft 4947.70 ft 2,788 cu-ft 3,071 cu-ft 4944.56 ft 3,164 cu-ft 4946.90 ft Require 100-yr Detention Volume Total Detention Volume Provided 100-yr WSE J.Claeys Interwest Consulting Group 1344-095-00 September 25, 2018 Pond Invert Elevation Sand Filter Invert Elevation Required Water Qualtiy Capture Volume (WQCV) WQCV Provided WQCV Water Surface Elevation (WSE) Combined Required 100-yr Detention & WQCV 1344-095-00 PondCalcs.xls - Pond Stage Storage Page 1 of 3 Interwest Consulting Group HOFFMAN MILL ROAD 12 1 8 W . A s h , S u i t e A Wi n d s o r , C o l o r a d o 8 0 5 5 0 Ph o n e : ( 9 7 0 ) 6 7 4 - 3 3 0 0 Fa x : ( 9 7 0 ) 6 7 4 - 3 3 0 3 C O N S U L T I N G G R O U P I N T E R W E S T PR E P A R E D F O R PROJ. NO. DA T E : SC A L E ( H ) : SC A L E ( V ) : CH E C K E D B Y : DE S I G N E D B Y : PR O J E C T N A M E HO F F M A N M I L L F U E L I N G S I T E HI S T O R I C D R A I N A G E B A S I N S 06 / 0 6 / 1 8 1" = 6 0 ' N/ A JT C JT C 1344-095-00 1 of 1 BASIN COEFFICIENT (100-YR) BASIN DESIGNATION BASIN AREA DESIGN POINT DRAINAGE FLOW ARROW DRAINAGE BASIN BOUNDARY DRAINAGE BASIN FLOW PATH LEGEND SCALE 1" = 0 60' 6030