HomeMy WebLinkAboutSite Certifications - 01/06/2015NORTHERN ENGINEERING Mr. Wes Lamarque City of Fort Collins Stormwater Utility 700 Wood St. Fort Collins, CO December 7, 2015 RE: Drainage Certification for River District Block One Mixed Use Dear Mr. Lamarque, This drainage certification letter is provided to verify as -constructed conditions for River District Block One Mixed Use. Northern Engineering completed survey work November of 2015 to verify general compliance with the Final Utility Plans for River District Block One Mixed Use, dated 8/5/13 by Northern Engineering. Included in this drainage certification submittal are the following: Attachment 1 - City of Fort Collins Drainage Certification Form. Attachment 2 - As -constructed pond volume calculations. Attachment 3 - As -constructed record drawings for Grading and Storm Drain Plan and Profile Sheets. Based on the calculations shown in Attachment 2, the as -built water quality pond provides the required design volume of 0.012 acre-feet of storage at an elevation of 4952.45. The original pond design achieved the required volume at elevation = 4952.30. The as -built pond was constructed to provide the required water quality volume per the Final Drainage and Erosion Control Report for River District Block One Mixed Use prepared by Northern Engineering dated August 5, 2013. We have concluded, based on the attached information and personal site inspection, that the drainage features for the project site have been constructed in substantial compliance with the above referenced Final Utility Plans. Please feel free to contact me with any questions you may have. Thank you, NORTHERN ENGINEERING Frederick S. Wegert, PE Project Engineer 301 N. Howes Street, Suite 100, Fort Collins, CO 80521 1 970.221.4158 1 www.northernengineering.com Attachment 1 IN Fo` rt Collins COMMERCIAL, MULTI -FAMILY AND SUBDIVISION CERTIFICATION FORM & CHECKLIST (Overall Site Drainage) River District Block One Mixed Use (Project Name) 12 2 2015 (Date) (For Commercial or Multi -family, please list any applicable building permit numbers) Please fill in all applicable items in this Certification Form for Commercial, Multi -Family and Overall Single Family sites. A copy of the approved grading plan must be submitted with the as -built grading plan. (It is preferred to have the as -built elevations written in red next to the approved elevations) Use "OK" for items checked or actual numbers for items verified/surveyed in the field. Use "N/A" for items that are not applicable to the site that is being certified. Please provide an As -Built Redlined or Mylar drawing showing the following: A. Detention, Drainage Facilities, and Common Open Spaces 1. Pond Certification Provide Topographic Records (grading certification with as —built spot elevations) and Volume Verification Calculations. Show both the proposed and as -built elevations on the same plan sheet — Ok. (See attached computations.) Provide Pond Cross -Sections and Spot Elevations (especially @ Pond Embankment and Pond Flow Line) — Ok. — Positive Fall to Pan (if applicable) —Ok. — General Pond Grading including all Side -Slopes — Ok. — Invert Elevation —Ok. — Forebay Construction and Elevation —Ok. Spillway Weir (Location, Elevation; Height, Opening Width) - N/A. (Concrete weirs not part of design; all pond weirs graded into pond embankments.) Placement and size of riprap or alternative permanent erosion control measures — Ok. (To the extent we were able to visually verify.) Orifice Plate and/or Water Quality Outlet Structure Installation —Ok. (See attached water quality outlet structure detail markup.) 12/12/2014 Revision — Page 1 of 6 Fort Collins Water Quality Capture Volume (Volume Required, Volume Provided and Water Surface Elevation) — Ok. (See attached computations.) Berm and Embankment Compaction Level —Unable to verify. — Subsurface Media for Water Quality Ponds and Swales —Unable to verify. 2. Swales — Location (are they within easement?) — N/A. — Dimension and Cross -Section Verification — N/A. — Longitudinal Slopes and Side -Slopes —N/A. — Spot Elevations— N/A. — Permanent Erosion Control Measures (drop structures, riprap, lining) —N/A. — Tie-in to Storm Lines, Pans, Curbs, or other appurtenances— N/A. — Required Minimum Freeboard, Provided Freeboard —N/A. — Landscaping Infringement on Flow Line?— N/A. 3. Piaes — See attached Storm Sewer Plan and Profile Sheets. — SizeandType—Ok. — Slopes (As -Built and comparison to 0.4% Minimum) — Ok. Pipe Capacity Calculations (if slopes are significantly altered from design) — Ok. — Invert Elevations —Ok. Installation and Backfill — Unable to verify. — Cover — Ok. — Encasement and Clearance from other nearby utility lines —Unable to verify. — Joints Type and construction —Unable to verify. 4. Concrete Pan Channels — Size — N/A. 12/12/2014 Revision — Page 2 of 6 — Slope — N/A. — Cross Section — N/A. — Thickness — N/A. — Elevations —_N/A. 5. Inlets — Size and Type—Ok. — Size of Opening (or name of Standard Detail used) —Ok. — Grate Elevation — Ok. — Invert Elevation —Ok. — Box Size — Ok. 6. Street Cross -Pans — Size — Ok. — Type — Ok. — Grade—Ok. — Elevations—Ok. — Cross -Sectional Depth — Unable to verify. — Tie-in to Curb and Gutter —Ok. 0 7. Culverts — Size — N/A. — Type — N/A. — Invert Elevations —N/A. — Headwalls or Wing Walls — N/A. 8. Sub -Drains Fort Collins 12/12/2014 Revision — Page 3 of 6 Fort Collins — Size — N/A. — Type (Perforated/Solid)—N/A. — Cover — N/A. — Backfill — N/A. — Geo-Textile Liners— N/A. — Clean -Outs —N/A. 9. Curb Cuts — Size — N/A. — Tie-in to Swale, Pipe or other appurtenances — N/A. 10. Common Open Spaces — Overall grading contours of open spaces-Ok. — Spot elevations adjacent to private lots (property corners) — N/A. B. Low Impact Development (LID) Certification 1. LID Technique Specific Checklists (see attached) Permeable Interlocking Concrete Pavers (complete if technique utilized on site) — N/A. Not part of project. — Bioretention Cells (complete if technique utilized on site) —See attached. C. Grading Certification 1. Certification of Grade Elevations —Unable to verify with the current overlot grading. — Minimum Opening Elevations —Unable to verify with the current overlot grading. — Top of Foundation Elevations — Unable to verify with the current overlot grading. — Comparison to 100-year Water Service Elevations —Unable to verify with the current overlot grading. — Comparison to Freeboard Elevations and Base Floodplain Elevations — BFE —Unable to verify with the current overlot grading. 2. Verification of Site Grading 12/12/2014 Revision — Page 4 of 6 r Of Fort Collins — Engineer to evaluate site grading compliance with the approved grading plan. -See attached record drawing grading sheets. As -built elevations are to be redlined onto the approved grading plan sheet showing the as -built spot elevations next to the design spot elevations so compliance can be verified and documented. - See attached record drawings grading sheets. D. Post -Construction Site Cleanup 1. Permanent BMP Measures — Construction Debris Clean -Up (In particular debris affecting the drainage) - Ok. — Smoothing of Ruts in all Construction Areas - Ok. Reseeding of all Areas Affected by Construction Activities (Usually enforced by the City's Erosion Control Inspector but the engineer certifying the site needs to notify the contractor if areas are not seeded) - Contractor notified of areas not seeded. E. Statement of Compliance This certification is signed and stamped and by signing this form the Engineer(s) attests that they have inspected the site and to the best of their knowledge the as -built conditions of the drainage facilities are as described in the above form and in the As -Built plans enclosed. Failure to properly disclose all known information could result in the rejection of this certification and prevent the release of any and all Stormwater Utility permit holds on Building Permits and/or Certificates of Occupancy within this development. F. Signature and Stamp by a Colorado Registered Professional Engineer Engineer's contact information: Fee de,-:ck k/Ggeet N0r-141C'et En9 -%,nc.0 Z2L (Name) (Company Name) fredC na�i�►crnCn�:�►eU:.�,�Gwy 3U1 (�. HowcS Sk:+cloo (Email address) (Company Address) (9?e) 5-6E- Co IL®szl (Telephone number) 0 L /CF �C scorr�N�^ : LL 45018 � : �aSS/ONAL IPE STAMP 12/12/2014 Revision - Page 5 of 6 Fort Collins } 12/12/2014 Revision — Page 6 of 6 Fo` rt ColUns Construction Inspection Checklist for Permeable Interlocking Concrete Pavers Itern/Activity Yes I No I N/A I Documentation/Submittal Requirements Excavation Post -excavation infiltration rates are consistent with design infiltration capacity (for "full or partial infiltration" designs) N/A Impermeable Liner Impermeable liner meets designspecifications N/A Impermeable liner attached to concrete perimeter wall N/A Impermeable liner is not exposed N/A Any Penetrations of the impermeable liner have been sealed and checked for water -tightness. N/A Concrete Cut -Off Wall Meets Specifications for: N/A - Dimensions N/A - Reinforcement N/A - Footings N/A Underdrain System Underdrain pipe is per design specifications N/A At least one cleanout is provided per underdrain lateral N/A Cleanout pipe is not perforated N/A Cleanouts covers are installed and watertight N/A Underdrain is NOT wrapped in geotextile fabric N/A Underdrain orifice plate installed at outlet structure N/A Underdrain integrity tested after backfilling using TV and/or water test N/A Aggregate Base coarse (e.g. #2/4) has 90% fractured faces N/A Bedding coarse. e. . #89 is thoroughly washed N/A Subbase materials are installed and compacted according to manufacturerspecifications N/A Protection During Construction 12/12/2014 Revision — Page 1 of 2 PICP area is protected from construction site sediment, N/A including runoff from the upstream catchment and construction eauinment traffic. Close Out Upstream catchment is stabilized prior to diverting runoff N/A into PICP system Fo` rt Collins 12/12/2014 Revision — Page 2 of 2 Fort Collins } Construction Inspection Checklist for Bioretention Cells Item/Activity Yes I No I N/A I Documentation/Submittal Requirements Excavation Heavy equipment did not travel over bioretention cell during excavation N/A Unable to verify. Did not observe construction activities. Bottom of cell was "ripped" after excavation N/A Unable to verify. Did not observe construction activities. Bottom of cell is flat and level N/A Unable to verify. Did not observe construction activities. Excavated area is protected/surrounded by sediment/runoff control BMPs during construction N/A Unable to verify. Did not observe construction activities. Inlet Inlet invert elevation is at least 3 inches above. containment wall/berm N/A I Unable to verify. Did not observe construction activities. -Upstream catchment drains to inlet Yes Foreba Forebay is installed according to design s ecifications N/A No forebay included within design. Forebay has flat, concrete bottom N/A No forebay included within design. Outlet Structure/Overflow Outlet structure/overflow elevation is confirmed Yes I 1 1 1.44' from pond bottom to overflow. Impermeable Liner Impermeable liner meets design specifications N/A Unable to verify. Did not.observe construction activities. Impermeable liner attached to concrete perimeter wall N/A Unable to verify. Did not observe construction activities. Impermeable liner is not exposed N/A Unable to verify. Did not observe construction activities. Underdrain System Underdrain pipe is per design specifications N/A Unable to verify. Did not observe construction activities. - At least one cleanout is provided per underdrain lateral N/A Unable to verify. Did not observe construction activities. 12/12/2014 Revision — Page I of 2 Fort Collins Cleanout pipe is not perforated N/A Unable to verify. Did not observe construction activities. Cleanouts covers are installed and watertight N/A Unable to verify. Did not observe construction activities. Underdrain is NOT wrapped in geotextile fabric N/A Unable to verify. Did not observe construction activities. Underdrain orifice plate installed at outlet structure N/A Unable to verify. Did not observe construction activities. Underdrain integrity tested after backfilling using TV N/A Unable to verify. Did not observe construction and/or water test activities. Filter Media Filter media composition is per design specifications N/A Unable to verify. Did not observe construction activities. Filter media was "machine mixed" by supplier prior to N/A Unable to verify. Did not observe construction activities. -delivery Filter media installed flat and level N/A Unable to verify. Did not observe construction activities. Other Structural Com onents Containment wall/berm is continuous and level N/A Unable to verify. Did not observe construction activities. Landscaping Final landscaping does NOT include sod N/A Unable to verify. Did not observe construction activities. Final landscaping (wood/rock mulch) is flat and level N/A Unable to verify. Did not observe construction activities. Vegetation is planted according to landscape design N/A Unable to verify. Did not observe construction activities. -specifications Verify that weed barrier is not installed N/A Unable to verify. Did not observe construction activities. Temporary irrigation installed N/A Unable to verify. Did not observe construction activities. Close Out 12/12/2014 Revision — Page 2 of 2 F- rt ColUns Upstream catchment stabilized prior to diverting runoff N/A Unable to verify. Did not observe construction into bioretention cell activities. 12/12/2014 Revision — Page 3 of 2 Attachment 2 No Text NORTHERN ENGINEERING Detention Pond Stage Storage Curve Project Number: Project Location: Calculations By: Pond No.: 685-002 Fort Collins, Colorado F. Wegert Detenion Pond Project: Block One Date: 12/2/2015 Pond Outlet and Volume Data Outlet Elevation: Grate Elevation: Crest of Pond Elev.: 4951.20 4952.22 4952.82 Design Volume: Elev at Design Volume: Elev at Spillway: 0.012 acre ft 4952.45 4952.67 E isting Pond Stage Storage Curve Contour Contour Surface Area ft' Depth Incremental Volume Cummalitive Volume Maximum Elevation Minimum Elevation sq. ft. acre ft sq. ft. acre ft 4950.8 N/A 0.0 0 0.0 0.000 0.0 0.000 4951.0 4950.8 15.4 0.2 1.5 0.000 1.5 0.000 4951.2 4951.0 41.1 0.2 5.6 0.000 7.2 0.000 4951.4 4951.2 74.0 0.2 11.5 0.000 18.7 0.000 4951.6 4951.4 131.9 0.2 20.6 0.000 39.3 0.001 4951.8 4951.E 311.0 0.2 44.3 0.001 83.6 0.002 4952.0 4951.8 532.31 0.21 84.31 0.002 167.9 0.004 4952.2 4952.0 741.21 0.21 127.31 0.003 295.2 0.007 4952.4 4952.2 944.E 0.2 168.E 0.004 463.8 0.011 4952.6 4952.4 1,200.1 0.2 214.5 0.005 678.3 0.01E D: I Projects 1685-0021 Drainagel Detention 1 12/2/2015 3:17 PM 685-002 AB Pond Stage Storage.xlsxIPond Attachment 3