HomeMy WebLinkAboutLot Certifications - 04/14/2016 (7)/15 Page 1
CERTIFICATION OF LOT GRADING
Pursuant to City Code § 26-544 & City Land Use Code § 3.3.2 (e)
Date:
Address:
Lot: Block:
Subdivision:
Permit Application #:
Larimer County Parcel #:
Larimer County Reception #:
(on development agreement)
I, (print) , a Colorado registered professional engineer, verify that construction
of all stormwater facilities and grading is complete and hereby submit this certification.
Please answer the following questions by initialing the appropriate response. For each question initialed “No,” attach an
explanation detailing how this will affect stormwater drainage for this lot and any adjacent lots.
1. Certification includes attached Stormwater-approved grading plan. (NOTE: City’s
Building Department does not approve grading plans).
2. Certification includes attached as-built survey dated (must be within 60
days of date of certification) accurately and truthfully depicting elevations for:
z Top of foundation/finished floor
z Finished grade on each side of the structure
z Quarter points along each lot line (not more than 50 feet apart)
z Break points/high points
z Swales
z Berms
z Retaining walls
z Air conditioning pads
z Window wells
z Any other appurtenance(s) within an easement
3. All elevations are within a 0.2 foot tolerance of the approved grading plan.
4. The top of foundation is at least 6 inches above the highest grade surrounding the
structure.
5. There is a minimum grade of 5% away from the structure within the first 5 to 10 feet
adjacent to the residence.
6. All slopes meet or exceed the minimum requirement of 2% (1% is acceptable on single
family lots when the swale is draining the runoff from only two adjoining properties)
and are not steeper than 25% (4:1).
7. All flow lines of stormwater drainage swales are a minimum of 6 inches below the
elevation of ground adjacent to the structure and will direct drainage as shown on the
Stormwater-approved grading plan.
8. All downspout locations and discharge directions are shown on the as-built survey.
Runoff is not directed toward neighboring properties.
No Yes
No Yes
No Yes
No Yes
No Yes
No Yes
No Yes
No Yes
SMS
SMS
SMS
SMS
SMS
SMS
SMS
SMS
runoff to be directed toward the designed side yard swales located on the property lines.
unprotected neighboring properties. It is acceptable for
/15 Page 2
9. A smooth transition (no grade break) is provided to all adjacent properties.
10. The grading of this lot does not adversely affect neighboring properties or City
infrastructure.
11. Landscaping has been completed prior to survey. If not, please indicate who will be
responsible for completing landscaping:
12. Final site cleanup has been completed.
13. I personally visited the site as part of the certification process, and in my professional
opinion, the as-built survey is an accurate representation of the site conditions.
.
No Yes
No Yes
No Yes
No Yes
No Yes
14. Based on this information, I certify that (check one):
Ƒ The elevations and drainage patterns of the lot/site are in substantial conformance with the City
approved drainage and grading plan for the property (information attached).
Ƒ The elevations and drainage patterns of the lot/site as measured are in general conformance with the
City approved drainage plan with exceptions (information attached). In my professional judgment the
elevations and grading of the lot/site as constructed are functionally adequate and equivalent to the
specifically approved drainage plan, and will affect stormwater drainage on and off the lot/site in a
manner consistent with the approved drainage plan.
Name:
Email:
Phone:
Company:
Address:
NOTE: A complete certification must be submitted at least two weeks prior to a request for a Certificate of Occupancy
for the lot/site, including, but not limited to, drawings of the lot/site showing the approved design and as-built surveyed
elevations of all structures, drainage and grading features, written information/explanation of discrepancies, and other
information necessary to confirm the above certification to:
Email (preferred)
WaterUtilitiesEng@fcgov.com
Mailing Address
Fort Collins Utilities
ATTN: Water Utilities Engineering
281 North College Avenue
Fort Collins, CO 80521
Questions?
970-221-6700
PE Stamp
Sign and date
SMS
SMS
SMS
SMS
SMS
4-14-2016
Metco, the builder's landscaping contractor
Steven M. Strickling
sstrickling@civas-eng.com
(720) 240-5882
CIVAS Engineering, LLC
10056 Brisbane Lane
Littleton, CO 80130
✔
&
TOF=4944.19
#5727
10056 Brisbane Lane Littleton Colorado 80130
tel 720-240-5882 fax 720-223-6092 www.civas-eng.com
April 14, 2016
FORT COLLINS UTILITIES
700 Wood Street
Fort Collins, Colorado 80521
Re: Lot 2, Block 11, Kechter Crossing Planned Land Division
Certification of Lot Grading
The elevations for Lot 2, Block 11, Kechter Crossing Planned Land Division deviate from the
elevations shown on the City approved Final Grading Plan for Kechter Crossing Planned Land
Division. The top of foundation elevation is approximately 0.5 feet higher, the front property corner
elevations are approximately 0.3 feet to 0.4 feet lower, the southerly rear property corner elevation
is approximately 0.3 feet lower and the northerly rear property corner elevation is approximately
0.3 feet higher lower than those shown on the Final Grading. However, the elevations and slopes
for Lot 2, Block 11, Kechter Crossing Planned Land Division are in conformance with the City of
Fort Collins lot grading criteria and the drainage patterns are in general conformance with the City
approved Final Grading Plan for Kechter Crossing Planned Land Division. Therefore, it is our
professional opinion that these elevation deviations will still allow for stormwater drainage to
generally be consistent with the City approved Final Grading Plan.
The elevation of the rear yard swale high point elevation shown on the Final Grading Plan is
approximately 0.7 feet higher than the rear property line elevations shown on the Final Grading
Plan. In order to maintain the Type A lot drainage, as shown on the Final Grading Plan, a berm is
required in a portion of the rear yard to provide adequate slope from the rear yard to the rear yard
swale. This is not indicated on the Final Grading Plan. However, it was required to be constructed.
It is our professional opinion that this is not significant and will still allow for stormwater drainage
to generally be consistent with the City approved Final Grading Plan.
Sincerely,
CIVAS Engineering, LLC.
4−14−2016
Steven M. Strickling, P.E.
April 14, 2016 Kechter Crossing Planned Land Subdivision
5727 Tilden Street
Fort Collins, CO 80528
B1502888
86082-18-002
2 11 20120065100
Steven M. Strickling
3-22-16