January 9, 1995
Mr. Basil Hamdan
City of Fort Collins
Stormwater Utility
235 Mathews
Fort Collins, Colorado 80521
Re: Lot 159, Huntington Hills Filing 2
Dear Basil:
9?el� C•O.
Esc Qom - n
vucwt Q9 (Sg iJ ISM
As required by the hold placed on the certification of occupancy, we surveyed the elevations of the rear
lot comers. The northwest comer is 4967.1, the northeast corner is 4963.5 and the middle lot comer is
4965.9. Each of these elevations are within 0.3 foot of the planned elevation. The first floor elevation of
the house is 4968.4, which is 1.1 feet higher than planned.
The swale on the west side of the lot has been completed and should be adequate for conveying
drainage water to the street. The eastem swale between lots 159 and 158 is not complete for two
reasons: (1) the soils are frozen and cannot be moved without large earthwork equipment, and (2) the
eastem half of the swale was not built on the adjacent property. Another complicating factor is the
difference between the first floor elevations of the house which is approximately 4 feet.
The fine grading which is necessary for this swale cannot be completed until the ground thaws. We
suggest releasing the hold from the lot with an agreement by Mr. McCaliff and the future homeowner
that Mr. McCaliff will come back and construct the swale when the soil thaws.
If you have any questions or need additional information, please call.
Sincerely,
Ayres Associates, formerly
R rce Co u nts Engineers
Paul R. Barker, P.E.
Manager, Civil Engineering
PRB:sp
Enclosure
Owen Ayres & Associates, Inc.
Engineers/Scientists/Surveyors
3665 JFK Parkway, Building 2, Suite 300, P.O. Box 270460, Fort Collins, CO 80527
(303) 223-5556, Denver Metro (303) 572-1806, FAX (303) 223-5578
Printed on recycled paper
HAMD195.LTR
34-0233.00