HomeMy WebLinkAboutSite Certifications - 03/25/2021October 20, 2020
City of Fort Collins
Stormwater Utility
700 Wood Street
Fort Collins, Colorado 80521
RE: Final Drainage Report for
The Standard at Fort Collins
Dear Staff:
This drainage certification letter is provided to verify as-constructed conditions for The Standard at
Fort Collins. Northern Engineering completed survey work (10/09/2020) to verify general compliance
with the Final Utility Plans for The Standard at Fort Collins, dated 05.10.18.
Included in this drainage certification submittal are the following:
Appendix A - City of Fort Collins Overall Site and Drainage Certification Form and City of Fort Collins
During Construction Inspection Checklist
Appendix B - As-Builts
Appendix C – Contractor Pictures
Appendix D – Approved Contractor Submittals (Drain Basins, Aggregate, Storm Pipe, Geomembrane,
and Stormtech Chambers)
We have concluded, based on the attached information and personal site inspection, that the drainage
features for the project site have been constructed in substantial compliance with the above referenced
Final Utility Plans, with the following exceptions:
•Item III.A.2: The longitudinal slope of the storm pipes were designed at less than 0.40%. The
storm pipes were installed per the slopes in the approved drawings.
•Item V.A: Not all storm drains were installed. Specifically, Drain Basin A6-3.2 and Drain Basin
A21. Neither one of these storm drains were critical in the design because they did not serve as
inlets but rather connection points for the storm lines. Drain Basin A6-3.2 was swapped out for
a tee and Drain Basin A21 was removed because of the proximity of FES A23.
•Item V.A.4: Not all inverts are within the construction tolerance of 0.2’. However, most of the
inlets are prefabricated and thus the total depth of the inlet remained unchanged.
•Item XV.A: Even though this is marked yes there are still a lot of pictures missing. Northern
Engineering requested pictures be taken throughout the entire construction process on several
occasions and this did not occur. However, subgrade elevations were surveyed prior to
Stormtech installations.
Accepted by The City of Fort Collins
3/25/2021 Wes Lamarque
Although it is not a requirement of the Drainage Certification, it was brought to Northern
Engineering’s attention that groundwater is actively pumped into the internal sand filter system within
the parking garage at a rate of 70 gpm (0.16 cfs) as confirmed by Katerra on January 30th, 2019. The 70
gpm is routed through the 2-year storm chamber in the sand filter (see photos) and discharging to Lake
Street. The 2-year storm chamber has a max release rate of 2 cfs; therefore, the groundwater is utilizing
roughly 8% of the max capacity. From an engineering standpoint this is negligible, and during the 2-
year storm event, some of the detention will back up into the 100-year chamber and discharge into
Prospect Road. However, this flow generated by the groundwater will cause additional maintenance
issues within the sand filter as well as in Lake Street. Due to the lack of storm water infrastructure
within Lake Street, there is no viable option of rerouting the groundwater runoff at this time.
Please feel free to contact me with any questions you may have.
Northern Engineering Services, Inc.
Frederick S. Wegert, PE Blaine Mathisen, EI
Project Engineer Project Engineer
10/20/2020
8/16 Page 1
OVERALL SITE and DRAINAGE CERTIFICATION
Commercial, Multi-Family and Subdivision Certification Form and Checklist
Project Name:
Date:
Building Permit Numbers:
(Commercial or multi-family)
Per the requirement in Fort Collins Stormwater Criteria Manual (FCSCM) Volume 1, Section 6.11, please fill in
all applicable items in this Certification Form for Commercial, Multi-Family and Overall Single Family sites.
NOTE: several items must be verified during construction. A copy of the approved grading plan must be
submitted with the as-built grading plan. (As-built elevations must be written in red next to the approved
elevations.)
•Use “Yes” for items completed as described.
•Use “N/A” for items that are not applicable to the site being certified.
•If any blanks are “No,” attach an explanation referencing the item number below.
Attach an explanation or description of the as-built condition for any items listed or for anything not listed but
shown on the approved construction plans.
Provide an as-built redline or Mylar drawing with the following:
I.Water Quality and Quantity Detention Basin Certification - FCSCM Vol.2, Ch.10
For multiple detention basins on a site, provide the following for each basin separately:
A. Volume: As-built topographic verification is attached at 1-foot (or less) contour intervals and
volume verification calculations for the water quality capture volume and the 100-year detention storage
volume.
1. Detention basin topography was prepared by a professional land surveyor registered in the state
of Colorado.
2.Both proposed and as-built contours are shown on the same plan sheet (dashed lines for
proposed and solid lines for as-built).
3.All critical spot elevations as shown on the approved construction plans have been verified and
the as-built elevations are shown on the plan sheet.
4.Stage-storage-discharge tables are provided on a separate document.
5.Verification that designed drain time is in compliance with Colorado Revised Statute § 37-92-
602(8) is attached and has been uploaded to the Statewide Compliance Portal
(tinyurl.com/COCompliancePortal) for approval. Uploaded documents must include:
a.The cover sheet from the approved drainage report
b.The stamped certification page from the approved drainage report
c.As-built topographic survey
d.Stamped certification page from the Overall Site & Drainage Certification
e.PDF output from the Stormwater Detention and Infiltration Design Data Speadsheet
8/16 Page 2
B.Water Quality and Quantity Detention Basin Grading: Attached is as-built verification that there is
a minimum 2% positive fall into the concrete trickle pans or flow-line(s) from all areas in the bottom of
the detention pond. If there is a “soft pan” in the flow-line, all areas still must meet the minimum 2%
grade requirement.
1.Low Flow: Choose one of the following detention basin low flow options as applicable:
a. Turf swale for low flow path in detention basin.
There is a minimum 2% grade in the flow-line(s) of the detention basin. The flattest as-built grade
is .
b.Concrete pan for low flow in detention basin.
There is a concrete pan installed that meets the grades as shown on the approved construction
plans. (Show as-built spot elevations.)
c.Soft pan for low flow in detention basin.
•Verify and document the soft pan material gradation, trench width and depth - to be verified
during construction by engineer. Picture documentation is preferred or engineer’s statement of
visual inspection and compliance. (Choose one below.)
o There is a soft pan with an underdrain installed that meets the design on the approved
construction plans. (Show the underdrain grades, bedding material, geotextile, spot elevations,
bends, cleanouts, etc.)
o There is soft pan installed without an underdrain but there is a type A or B soil. The soil
type must be documented by supplying verification from a registered professional geotechnical
engineer.
NOTE: Spot elevations are to be within 0.2 ft. +/-.
2. Side Slopes: The as-built side slopes of the detention basin have been calculated and are shown.
Indicate the side slope with an arrow and a numerical value (e.g., 6.25:1). The maximum slope allowed
is 4:1. Small areas of 3:1 may be acceptable, but slopes steeper than 3:1 must be stabilized or re-
graded. Provide documentation if a variance was granted for steeper slopes during the design process.
3.Spillway Certification: The following items must be field verified:
a.The location of the spillway is indicated on the as-built plan.
b.The width of the spillway is indicated on the as-built plan.
c.The elevation(s) of the spillway is shown on the as-built plan.
d.A concrete ribbon defines the location and grade of the spillway.
e.There is downstream scour protection in the spillway as per the construction plans. Indicate
type: (riprap size “D50” gradation and bedding type, geotextile, buried
riprap with inches of bury, etc.).
f.There are no obstructions in the spillway, such as trees, bushes, sidewalks, landscape
features, rocks, etc.
8/16 Page 3
4.Outlet Structure Certification
a.The orifice plate for the approved release rate is installed with the correct size and location of
the orifice.
b.The orifice plate for the water quality outlet is installed with the correct hole size, number of
rows and columns of holes.
c.The bottom hole on both the water quality and quantity outlets are at the bottom of the plate
so no water ponds in front of the plate.
d.The well screen is the correct material and is installed as shown on the construction plans.
e.100-year overflow grate elevation is . (Elev. A on detail D-46)
f.The top elevation of the water quality capture volume is . (Elev. B on detail
D-46)
g.Overflow grate is made of the correct material, has the correct bar spacing, is hinged at the
top and bolted at the bottom.
h.The bottom of the outlet box has no obstructions or misalignments that will cause it to retain
runoff water and is sloped at 2% towards outlet.
II.Channels/Swales - FCSCM Vol.1, Ch.7, Sect.3&4
A. Capacity: The as-built capacity of all the major channels and swales has been verified. They meet
or exceed capacity requirements shown in the approved drainage study for this project.
1.All swales are located within the drainage easements as shown on the construction plans.
2.Longitudinal slopes and side-slopes (cross-sections) have been verified. Design criteria requires
longitudinal slopes of 2% min. (on vegetated swales) and side-slopes no steeper than 4:1. If these
criteria are not met, the certification engineer will write a justification and propose mitigation for each
instance or have the issues corrected. If variances to these criteria have previously been approved and
are shown on the construction plans, no justification is needed.
3.As-built spot elevations on channels/swales are shown that correspond to spot elevations
shown on the approved construction plans.
4.All permanent erosion control measures are installed as shown on the approved construction
plans (e.g., drop structures, riprap, TRMs, etc.). (Include pictures and verification of the materials used
as part of this verification.)
5.All pans, curbs, storm pipes or other appurtenances appropriately tie into each other in the
system. (Pictures at tie-in points suggested.)
6.The minimum freeboard is provided for all channels and swales as shown on the approved
construction plans or as identified in the approved drainage study. (Show the freeboard provided on
the cross-sections as on the construction plan set or attached as separate documentation.)
7.The low flow portion of all channels or swales is clear of obstructions. (No landscaping, trees,
shrubs, sod, etc. infringe on the low flow portion of channels or swales.)
8/16 Page 4
III.Storm Pipes (aka storm drains) - FCSCM Vol.1, Ch.6, Sec. 4
A. Storm Drain Pipe Capacity: The as-built capacity of all pipes installed on this project has been
verified and meets or exceeds the capacity requirements shown in the approved drainage study for this
project.
1.All storm drain pipe sizes and materials have been verified and are in conformance with the
approved construction plans. (Indicate on the plan and profile sheets that they have been verified.)
Material and size substitutions must be approved prior to installation. If a pipe size or material was
changed during construction, the certification engineer must attach the approval documents or supply
them with this certification. Approval documents must include a calculation documenting the capacity
equivalency (equal or greater) of the substituted size.
2.The longitudinal slope of the pipe is as shown on the approved construction plans. The
acceptable minimum slope is 0.4%. All slopes flatter than the designed slope on the construction plans
must be justified with capacity calculations on an attached sheet.
3.The as-built invert elevations have been verified and are shown on the plan and profile sheets of
the approved construction plans.
B.Storm Drain Pipe Installation Requirements: All pipes are installed in accordance with the
approved construction plans.
1.The minimum cover requirements for all pipes have been met as shown on the approved
construction plans. These will be called out in critical locations.
2.All encasements and clearances as specified on the approved construction plans have been met.
3.Any specific joint types or construction methods specified on the approved construction plans
have been met. (List on a separate sheet and attach to this certification.)
IV.Concrete Pans - FCSCM Vol.1, Ch.7, Sec.4.1.3.4
A. Construction/Installation: All concrete pans have been constructed in accordance with the
approved construction plans.
1.The concrete pans are the correct size/width as shown on the approved construction plans.
2.The longitudinal slopes of the pans are as shown on the approved construction plans. The
certification engineer must justify or mitigate longitudinal slopes less than the minimum of 0.4% unless
a flatter slope was approved and is shown on the approved construction plans. Provide mitigation or
justification by separate document.
3.The cross-section of the pan is as shown on the construction plans. (Specifically, the pan cross-
section is “V” shaped and meets the side slope shown on the detail.)
4.The concrete pans are a minimum of 6 inches thick without reinforcement and a minimum of 4
inches thick with a minimum of 6X6-W14xW14 reinforcement per detail D20B and D20C. (Provide
documentation of the reinforcement used if different than shown on the details or on the approved
construction plans.)
5.The spot elevations shown on the concrete pan(s) have been verified and are shown on the as-
built drawings.
8/16 Page 5
V. Storm Drain Inlets - FCSCM Vol.1, Ch.6, Sec. 3
A. Construction/Installation: All storm drain inlets have been constructed in accordance with the
approved construction plans.
1.The size and type of inlets are consistent with the inlets shown on the approved construction
plan. Indicate by writing “Verified” on each inlet on the plan sheet or list on a separate document the
inlet number(s), type and size (length). If the inlet installed is other than the one on the approved
construction plan detail sheet, provide the name and source of the detail with justification for equal or
better capacity.
2.The size of the inlet opening is consistent with the approved detail. (Check height and width.)
3.The elevation of the grate (if applicable) is at the elevation shown on the street profile or as
indicated by a spot elevation on the construction plans.
4.The as-built invert elevations of all pipes entering and leaving the inlet are shown on the plan
and profile sheets within construction tolerance of 0.2 feet. If substantially different, provide
justification and capacity calculations to show the capacity is not affected or propose mitigation.
5.The as-built size of the inlet box is as shown on the construction plans or an explanation or
justification is attached.
6.All Type C, R, 13 and 16 inlet covers are stenciled or stamped with the following (or an
equivalent) designation: NO DUMPING – DRAINS TO POUDRE RIVER.
VI.Culverts - FCSCM Vol.2, Ch.9
A. Construction/Installation: All culverts have been constructed and/or installed in accordance with
the approved construction plans.
1.All culvert sizes have been verified as indicated on the as-built construction plans as correct.
2.The culvert material type for all culverts installed is as on the approved construction plans and is
indicated on the as-built plans.
3.The as-built invert “in and out” elevations have been verified and are indicated on the as-built
construction plans.
4.The culvert headwalls or wing walls have been installed as shown on the approved construction
plans. Headwalls or wing walls may be needed in the as-built conditions onsite if the slopes adjacent to
the culvert are greater than 4:1. Please note areas needing stabilization in the certification narrative.
An alternative to consider is a turf reinforcement mat (TRM).
VII.Sub-Drains
A. Construction/Installation: All sub-drains shown on the construction plans have been installed in
accordance with those plans. Sub-drains installed with the sanitary sewer are to be verified on the
sanitary sewer plan and profile sheets of the construction plans. (NOTE: Indicate any sub-drains installed
after the plans were approved on the as-built plans.)
1.The size of the sub-drains are as approved on the construction plans and are indicated on the as-
built plans.
2.The type of sub-drain, in particular the perforated and non-perforated sections of the drain, are
as indicated on the approved construction plans.
8/16 Page 6
3.The cover requirements per the construction plans are provided.
4.The cleanouts have been installed at the locations shown on the construction plans and are
accessible for cleaning. (Cleanouts can be buried a maximum of 6 inches deep with their locations
marked.)
5.The backfill materials for sub-drains are as shown on the approved construction plans. (This
includes the type, depth and width.)
6.The geo-textile liner completely wraps the sub-drain and the permeable backfill material unless
shown otherwise on the approved construction plans. (Sub-drain pipe wrapped in a sock filter material
is accepted only if approved prior to installation.)
VIII.Curb Cuts
A. Construction: All curb cut openings are constructed in accordance with the approved construction
plans.
1.The size (width) of the curb cut opening is as shown on the approved construction plans.
2.The curb cut openings tie into a downstream swale, pipe, or other appurtenances with a smooth
transition and there no obstructions such as riprap or sod impeding the flow downstream of the curb
cut.
IX.Sidewalk Culverts & Chases
A. Construction/Installation: All sidewalk culverts have been installed at the locations shown on the
approved construction plans.
1.The size (width and length) of the culverts are as shown on the approved construction plans.
2.The cover plate is a minimum 5/8-inch galvanized plate bolted to a galvanized angle iron per the
detail shown on the approved construction plans or per the City’s detail.
3.The sidewalk culvert invert “in and out” elevations have been verified and are indicated on the
as-built plans.
4.The sidewalk culvert opening is as shown on the approved construction plans or per the City’s
detail.
5.There is a smooth transition both on the inlet and outlet ends of the sidewalk culvert with no
obstructions such as riprap or sod impeding the flow into or out of the sidewalk culvert.
X. Site Grading
A. Construction: All common open spaces have been graded in accordance with the approved
construction plans.
1.The grading on all common open spaces bordering private lots has been verified as correct and
the as-built rear lot corner elevations have been shown on the as-built plans.
8/16 Page 7
2.The as-built contours for “overlot grading” are shown on the as-built construction plans for all
common open spaces, tracts, outlots, etc. If not in compliance, please attach a narrative describing the
situation for noncompliance and when it may be corrected. An escrow for overlot grading may be
required. (NOTE: Residential Lot Grading Certification is a separate process from this Overall Site
Certification. It is understood that residential lots will be brought to final grade once the foundation is
backfilled so they may be lower than the plan shows at this Overall Site Certification stage.)
3.All turf reinforcement mats (TRMs) have been installed as shown on the approved construction
plans and the slopes are stabilized.
XI.Riprap - FCSCM Vol.1, Ch.7, Sec.4.4.4.3
A. Construction: All riprap has been installed in the locations and sizes indicated on the approved
construction plans.
XII.Permanent Erosion Control Fabric - FCSCM Vol.1, Ch.7
A. Construction: All fabric has been installed in the locations and sizes indicated on the approved
construction plans.
1.All fabric was installed per the details on the approved construction plans.
XIII.Post-Construction Site Cleanup - FCSCM Vol.3, Ch.7
A. Construction: All construction debris and obstructions of any kind have been removed from
drainage paths.
1.All construction debris has been removed except in staging area(s).
2.All ruts have been smoothed out in all construction areas.
3.All areas needing reseeding have been identified and future stabilization goals have been
coordinated with the Erosion Control Inspector and in accordance with FCSCM Vol.2 Chapter 12. Note
the area needing stabilization in the narrative.
XIV.Certification of Other Permanent BMPs - FCSCM Vol.2, Ch.8, Sec.2 & FCSCM Vol.2, Ch.12
A.The construction of channel drop structures is in accordance with the approved plan both in
location, horizontal dimensions and cross-section.
XV.Certification of LID and Water Quality Facilities - FCSCM Vol.3, Ch.4
A.Attached are the During Construction Inspection Checklist for Low Impact Development (LID) and
other items to be verified during construction, along with pictures and other required documentation.
1/19 Page 1 of 2
DURING CONSTRUCTION INSPECTION CHECKLIST
To be completed by Construction Superintendent
This checklist is to be completed during construction and included with the Overall Site and Drainage Certification.
· Use “Yes” for items completed as described.
· Use “N/A” for items that are not applicable to the site being certified.
· If any blanks are “No,” attach an explanation referencing the item number below.
Project Name: Date:
Building Permit Numbers:
I. Compaction
A. All berms and embankments meet the compaction requirements as specified in the project geotechnical report or comply with the
City’s standard, which is “soils should be compacted within a moisture content range of 2% below to 2% above optimum moisture content
and compacted to 95% of the Maximum Standard Proctor Density (ASTM D698).” Compaction requires verification during construction.
Provide testing log from contractor/engineer.
II. Storm Drain Pipe Installation Requirements
A. The pipe trenches have been compacted in accordance with Section 02225-3.07.A.1. of the Fort Collins Development Construction
Standards for Water, Wastewater, Stormwater (e.g., the trenches in the roadways are to be 95% of maximum density and all other areas
are to be at 90%, both in accordance with ASTM D698).
III. Energy Dissipation and Erosion Protection - FCSCM Chapter 9, Section 7.0
A. Riprap
1. The riprap bedding is a granular bedding of the gradation and thickness indicated on the approved construction plans.
2. A filter fabric was installed instead of granular bedding and is the material shown on the approved construction plans or was an
approved equal. Provide documentation for an approved equal.
3. The riprap is the gradation shown on the approved construction plans with a D50 of .
4. The riprap thickness is as shown on the approved construction plans and extends to the horizontal limits shown.
5. The riprap is buried to the depth indicated on the approved construction plans. (A minimum of 6 inches of soil is required.)
B. Permanent Erosion Control Fabric - FCSCM Vol.1, Ch.7
1. All fabric was installed per manufacturer’s specifications.
1/19 Page 2 of 2
IV. Other Permanent BMPs
A. All cut-off walls have been installed in accordance with the approved construction plans. (Cut-off walls are required for irrigation
ditch crossings of storm drain pipes.)
V. Extended Detention Basins
A. Installation of this facility was verified via inspection by a City-Stormwater Inspector at the point of installation of the water quality
control box(es). Provide date of inspection and name of inspector:
Included certification sheet(s):
Please check the appropriate box(es) for the Low Impact Development
(LID) facilities found on this site and complete the corresponding
certification sheets.
☐ Permeable Interlocking Concrete Pavers
☐ Bioretention Cells (Rain Gardens)
☐ Sand Filters
☐ Vegetated Buffers
☐ Underground Infiltration
☐ Other LID – For certification of Dry Wells, Tree Filters,
Constructed Wetland Channels & Ponds, etc., contact City Staff
to determine requirements to exhibit the LID facility has been
constructed and functions as intended per the approved
drainage report.
*Please provide photographic documentation of the installation of all
stages of all LID facilities.
**Please contact the City Stormwater Inspector at
stormwaterinspection@fcgov.com to discuss inspection requirements
for each LID facility and request inspections.
***All facilities being certified must be “clean” – free of sediment &
construction debris – prior to certification or acceptance of the facility.
Completed by:
Name:
Title:
Email:
Phone:
Company:
Address:
1/19 Page 1 of 2
Permeable Interlocking Concrete Pavers
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Stormwater Inspection
Pre-construction meeting was held with City-Stormwater
Inspector to discuss installation, inspection, checklist, and
protection from sedimentation
☐ ☐ ☐
Record date, inspector name, meeting
location (i.e. DCP, initial erosion control
inspection, etc.)
Sub-surface inspection(s): Installation of this facility was
verified via inspection by a City-Stormwater Inspector at the
point of installation of the outlet, underdrain, geomembrane
layer, and sub-base courses (per design in Final Plan
Documents)
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Surface inspection(s): Installation of this facility was verified via
inspection by a City-Stormwater Inspector at the point of
installation of the pavers and joint fill material
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Excavation
Heavy equipment did not encroach into the excavated area
(prevents over-compaction) ☐ ☐ ☐
Bottom of cell was “ripped” after excavation ☐ ☐ ☐ Provide photographs before and after
“ripping”
Bottom surface of cell is flat and level ☐ ☐ ☐ Provide photograph
Impermeable Liner
Impermeable liner meets design specifications ☐ ☐ ☐ Provide specifications of delivered
material
Impermeable liner is attached to concrete perimeter wall ☐ ☐ ☐ Provide photograph
Impermeable liner is buried with no exposure ☐ ☐ ☐
Any penetrations of the impermeable liner have been sealed
and checked for water-tightness ☐ ☐ ☐ Provide photograph (if necessary)
Edge Restraint and Concrete Cut-Off Wall
The required edge restraint meets design specifications ☐ ☐ ☐ Provide specification of installation
Concrete cut-off wall meets design specifications for: ☐ ☐ ☐ Provide specification of installation
- Dimensions ☐ ☐ ☐
- Reinforcement ☐ ☐ ☐
- Footings ☐ ☐ ☐
Underdrain System
Underdrain pipe meets design specifications ☐ ☐ ☐ Provide photograph
At least one cleanout is provided per underdrain lateral ☐ ☐ ☐ Provide photograph
1/19 Page 2 of 2
Cleanout pipe is solid (not perforated/slotted) ☐ ☐ ☐ Provide photograph
Cleanout covers are installed and watertight ☐ ☐ ☐ Provide photograph
Verify the underdrain is NOT wrapped in geotextile fabric ☐ ☐ ☐ Provide photograph
Verify there is no orifice plate on the underdrain outfall ☐ ☐ ☐ Provide photograph
Underdrain integrity tested after backfilling using TV and/or
water test ☐ ☐ ☐ Provide documentation of test results
Aggregate
Sub-base Course(e.g., #2/4):
- Has 90% fractured faces
- Is thoroughly washed (virtually free of fine sediment)
- Is installed to the required design depth
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Basecourse (e.g., #57):
- Has 90% fractured faces
- Is thoroughly washed (virtually free of fine sediment)
- Is installed to the required design depth
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Leveling Course / Joint Fill (e.g., crushed #89):
- Has 90% fractured faces
- Is thoroughly washed (virtually free of fine sediment)
- Is dry screened
- Is installed to the required design depth and to the top
of the paver joints
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Aggregate materials are installed and compacted according to
manufacturer’s and/or design specifications ☐ ☐ ☐ Provide photographs and documentation
of compaction
Protection During Construction
PICP area is protected from construction site sediment,
including runoff from the upstream catchment and
construction equipment traffic ☐ ☐ ☐
Specify how the area was covered and/or
otherwise protected to prevent
construction runoff from entering the
pavement
Close Out
Cracked/broken paver units have been removed and replaced ☐ ☐ ☐
Paver height offsets are no more than 1/4” between adjacent
units & surface contains no deformations
(depressions/settlement) exceeding 1/2"
☐ ☐ ☐
Upstream catchment is stabilized prior to diverting runoff into
PICP system ☐ ☐ ☐
1/19 Page 1 of 2
Underground Infiltration
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Stormwater Inspection
Manufacturer’s representative pre-construction meeting: A
pre-construction meeting was completed with the
manufacturer’s representative and installers
☐ ☐ ☐
Record date and who was present at the
meeting
Pre-construction meeting was held with City-Stormwater
Inspector to discuss installation, inspection, checklist, and
protection from sedimentation
☐ ☐ ☐
Record date, inspector name, meeting
location (i.e. DCP, initial erosion control
inspection, etc.)
Inspection(s): Installation of this facility was verified via
inspection by a City-Stormwater Inspector at the point at which
the chambers had been laid/prior to backfilling.
Correct fabric placement was confirmed.
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Excavation
Heavy equipment did not travel across underground cell area
during excavation (prevents over-compaction) ☐ ☐ ☐
Bottom of cell was “ripped” after excavation ☐ ☐ ☐ Provide photographs before and after
“ripping”
Bottom of cell is flat and level, or graded per approved grading
plans ☐ ☐ ☐ Provide photograph
Non-woven fabric is installed per manufacturer’s specifications
and was not damaged during construction (around system) ☐ ☐ ☐ Provide photograph
Woven fabric is installed per manufacturer’s specifications and
was not damaged during construction (beneath chambers) ☐ ☐ ☐ Provide photograph
Excavated area is protected/surrounded by sediment/runoff
control BMPs during construction ☐ ☐ ☐ Provide photograph
Impermeable Liner
Impermeable liner meets design specifications ☐ ☐ ☐ Provide specifications of delivered
material
Impermeable liner is not exposed ☐ ☐ ☐
Any penetrations of the impermeable liner have been sealed
and checked for water-tightness. ☐ ☐ ☐ Provide photograph (if necessary)
Aggregate
Foundation and embedment materials are installed and
compacted according to design and manufacturer’s
specifications
☐ ☐ ☐
Provide load ticket and photograph(s)
Underdrain System
1/19 Page 2 of 2
Underdrain pipe meets design specifications ☐ ☐ ☐ Provide photograph
At least one cleanout is provided per underdrain lateral ☐ ☐ ☐ Provide photograph
Cleanout pipe is solid (not perforated/slotted) ☐ ☐ ☐ Provide photograph
Cleanout covers are installed and watertight ☐ ☐ ☐ Provide photograph
Verify the underdrain is NOT wrapped in geotextile fabric ☐ ☐ ☐ Provide photograph
Verify there is no orifice plate on the underdrain outfall ☐ ☐ ☐ Provide photograph
Underdrain integrity tested after backfilling using TV and/or
water test ☐ ☐ ☐ Provide documentation of test results
Manifold system
Overflow weir elevation is set at/above water quality storm
elevation ☐ ☐ ☐ Record weir elevation on survey
Maintenance access is provided for each Isolator Row ☐ ☐ ☐
At least one inspection port has been provided for each Isolator
Row (located in middle third of each row) ☐ ☐ ☐
Upstream catchment drains to inlet/intake properly ☐ ☐ ☐
Underground Detention Chambers
All chambers were installed per approved Utility Plans and
manufacturer’s specifications ☐ ☐ ☐ Photograph
Close Out
Upstream catchment is stabilized prior to diverting runoff into
Underground Detention system ☐ ☐ ☐
All Isolator Rows, chambers, and pipes are cleaned and
sediment/debris has been removed ☐ ☐ ☐
E E E E E E E E E E E E E E E E
W
E
E
E
UD
UD
UD
UD
UD
UD
F
F
E E E E E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
E
FD
C
FD
C
W
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
UD
UD
UD
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
E
W W W W W W W W W W W W W W W W W W W W W W
X
X
XXXXXXXXXXX
G
E
E
E
WVWV
WV
WV
HYD
ELECTTVAULT
ELEC
MH
S
SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS
W
S
G
SS
SS
W
W
S S
SSSS
W
W
W
W
W
W
W
W
W
W
W
W
W
W
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
W
W W
W
SS
SS
SS
SS
HYD
C.O.
W
W W
W
W
CS
ST
ST
ST
ST
ST
ST
ST ST ST ST ST ST ST ST ST ST ST ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST ST ST ST ST ST ST ST ST ST ST ST
ST
ST
D
VAULT
ELEC
8" x 4" W/
4" x 3" REDUCER
3" G.V. AND T.B.
N:124314.51
E:190781.06
16" x 8" WET TAP
W/ 8" G.V. (S) AND T.B.
N:124360.75
E:190781.47
LAKE STREET
(60' PUBLIC ROW)
ST
A
D
I
U
M
A
P
A
R
T
M
E
N
T
S
BUILDING 1
8" x 6" SWIVEL TEE
W/ 6" G.V. (W) AND T.B.
N:124105.27
E:190779.20
PO
N
D
N
2
(W
I
T
H
S
A
N
D
F
I
L
T
E
R
)
31' EMERGENCY ACCESS,
VEHICULAR PUBLIC ACCESS,
DRAINAGE, AND UTILITY
EASEMENT
WQ
P
O
N
D
N
1
(S
C
-
1
6
0
C
H
A
M
B
E
R
S
)
9' UTILITY
EASEMENT
DRAINAGE EASEMENT
PER THE SLAB PROPERTY PLAT
30' EMERGENCY ACCESS,
NON-VEHICULAR PUBLIC ACCESS,
AND DRAINAGE EASEMENT
(PER THE SLAB PROPERTY PLAT)
DRAINAGE EASEMENT
(PER LAKE STREET APARTMENTS PLAT)
TIE TO EXISTING
ELECTRIC VAULT
3" METER
VAULT
3" WATER
SERVICE
SIDEWALK CHASE
PER THE SLAB
GAS
METERS (2)
EXISTING 16" WATER MAIN EXISTING 16" WATER MAIN
SSMH (4')
INV. IN=5012.41 (W)
EXISTING 18" WATER MAIN
PRIVATE
FIRE
HYDRANT
TRANSFORMER
TRENCH DRAIN
STORM LINE B1
(SEE SHEET C3.06)
STORM LINE B
(SEE SHEET C3.06)
STORM LINE A2
(SEE SHEET C3.05)
STORM LINE B9-1
(SEE SHEET C3.06)
EXISTING GAS LINE
2' CONCRETE PAN
STORM LINE B
(SEE SHEET C3.06)
1 1/2" METER
INTERNAL TO
BUILDING
1 1/2" WET TAP
N:124360.37
E:190867.76
FIRE DEPARTMENT
CONNECTION
SEE SHEET C4.05
SEE SHEET C4.05
SEE SHEET C3.03
SEE SHEET C3.03
18" SEPARATION
8" x 4" TEE
SEE SHEET C4.05
EXISTING 8" CLAY SERVICE TO
BE REMOVED AND REPLACED
WITH 10" PVC SERVICE
EXISTING SSMH (4')
(TO BE DRILLED)
INV. IN=5013.14 (W)
INV. IN=5013.41 (S)
INV. OUT=5013.11 (E)
51
.
2
0
L
F
1
0
"
P
V
C
@
4
.
0
0
%
SANITARY SERVICE 1
INV. OUT=5015.46 (N)
° BEND
° BEND
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
C3.01
UT
I
L
I
T
Y
P
L
A
N
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
----
MATCHLINE
SEE SHEET C3.02
GRAPHIC SCALE:
NORTH
LEGEND:
GENERAL NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE
FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.ALL WATER AND SANITARY SEWER CONSTRUCTION SHALL BE PER THE
CITY OF FORT COLLINS CONSTRUCTION STANDARDS, LATEST EDITION.
3.UTILITY SERVICES ARE SHOWN IN A SCHEMATIC FASHION ONLY. EXACT
LOCATIONS SHALL BE PER THE REQUIREMENTS OF THE RESPECTIVE
UTILITY PROVIDERS, AND ARE SUBJECT TO CHANGE IN THE FIELD.
4.ALL WATER FITTINGS, VALVES, AND OTHER UTILITY APPURTENANCES ARE
ONLY GRAPHICALLY REPRESENTED AND ARE NOT TO SCALE.
5.ALL EXISTING SANITARY SEWER SERVICES ARE APPROXIMATE AND SHALL
BE FIELD VERIFIED PRIOR TO CONSTRUCTION. ALL SEWER SERVICES TO
BE UNUSED SHALL BE ABANDONED AT THE MAIN AND COORDINATED WITH
FORT COLLINS UTILITIES (970-221-6700).
6.PRIOR TO ORDERING MATERIAL AND MOBILIZING, CONTRACTOR SHALL
FIELD LOCATE AND VERIFY ELEVATIONS OF ALL CONCRETE AND ASPHALT
TIE-INS, EXISTING SEWER MAINS, WATER MAINS, AND ALL OTHER UTILITIES
AT THE POINTS OF CONNECTION SHOWN ON THE PLANS. SPECIAL
ATTENTION SHALL BE PAID TO ALL PROPOSED UTILITY CROSSINGS. IT IS
RECOMMENDED THAT THE CONTRACTOR POTHOLE SAID CROSSINGS
PRIOR TO ORDERING MATERIAL. REFER TO GENERAL NOTE #9 ON SHEET
C0.01 IF A CONFLICT ARISES AND/OR A DESIGN MODIFICATION IS DESIRED.
7.LIMITS OF STREET CUT ARE APPROXIMATE. FINAL LIMITS ARE TO BE
DETERMINED IN THE FIELD BY THE CITY ENGINEERING INSPECTOR. ALL
REPAIRS TO BE IN ACCORDANCE WITH CITY STREET REPAIR STANDARDS.
KEYMAP: (NTS)
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
SEE SHEET C4.05
SEE SHEET C3.03SEE SHEET C4.05
SEXISTING SANITARY MH
GEXISTING GAS METER
EEXISTING ELECTRIC METER
VAULT
ELECEXISTING ELECTRIC VAULT
TEXISTING TELEPHONE PEDESTAL
HYDEXISTING FIRE HYDRANT
TRAFFIC
VAULTEXISTING TRAFFIC VAULT
EEXISTING BURIED ELECTRIC
GEXISTING BURIED GAS
WEXISTING WATER LINE
SSEXISTING SANITARY SEWER LINE
GPROPOSED GAS LINE
PROPOSED WATER SERVICE LINE
PROPOSED SANITARY SERVICE LINE
PROPOSED STORM SEWER
PROJECT BOUNDARY
FDC
EXISTING EXISTING R.O.W
PROPOSED EASEMENT LINE
PROPOSED CURB & GUTTER
PROPOSED FIRE DEPARTMENT CONNECTION
PROPOSED FIRE SERVICE LINE
PROPOSED ELECTRIC METER
EPROPOSED ELECTRIC LINE
UDPROPOSED PERFORATED STROM
PROPOSED GAS METER
( IN FEET )
0
1 INCH = 20 FEET
20 20 40 60
RECORD DRAWING
SS
SS
SS
UD
UD
UD
UD
UD
G
UD
UD
UD
VAULT
ELECVAULT
ELEC
UD
UD
UD
UD
UD
UD
F
E E E E E E E E E E E
E
E E E E E
FD
C
W
E
E
E
E
E
E
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
UD
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
E
E
E
E
E
X
X
X
X
X
X
X X X X X X
XX
X
X
X
X
X
X
X
X X
X
CT
V
T T T T T
W
W
T
S
WVWV
T WVAULT
TELE
HYD
SS SS SS SS SS SS SS SS SS SS SS
E E E E E E E E E E E E E
E E E E E
W W
W W W W W W W W W W W W W W W W W W W W W W W W W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W W
SS
SS
W
W W
C.O.
W
W W
W
CSW
CS
ST
ST
ST
ST ST ST ST ST ST ST ST ST ST ST ST ST ST ST ST ST ST
ST
ST
ST
ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
FES
D D
D
DD
D
D
ST
ST
ST ST ST ST ST ST ST ST ST ST ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
STST
ST
ST
ST
ST
ST
ST
ST ST ST
ST
ST ST ST
8" x 8" TEE
W/ 8 G.V. (N) AND T.B.
N:123802.76
E:190795.56PROSPECT ROAD
(60' PUBLIC ROW)
TH
E
S
L
A
B
BUILDING 2
CONNECT TO EXISTING
8" WATERLINE
N:123802.14
E:190828.81
POND S4
(SC-740 CHAMBERS)
POND S3
(SC-740 CHAMBERS)
POND S2
(SC-740 CHAMBERS)
PO
N
D
S
1
(S
C
-
1
6
0
C
H
A
M
B
E
R
S
)
20' EMERGENCY ACCESS, NON-VEHICULAR
PUBLIC ACCESS, AND DRAINAGE EASEMENT
26' EMERGENCY ACCESS, NON-
VEHICULAR PUBLIC ACCESS,
DRAINAGE AND UTILITY EASEMENT
POND S5
(SC-310 CHAMBERS)
15' UTILITY
EASEMENT
26' EMERGENCY ACCESS, ACCESS,
DRAINAGE & UTILITY EASEMENT
(PER LAKE STREET APARTMENTS PLAT)
5' UTILITY AND
DRAINAGE EASEMENT
(PER THE SLAB
PROPERTY PLAT)
DRAINAGE EASEMENT
(PER LAKE STREET APARTMENTS PLAT)
4" METER
VAULT
SEWER TO BE
ABANDONED
IN PLACE
RELOCATED VAULT
TRANSFORMER
TRANSFORMER
RELOCATED VAULT
EXISTING FIRE
HYDRANT
CONNECT TO EXISTING
GAS LINE
GAS METER
COORDINATE WITH
CABLE PROVIDER
SIDEWALK CHASE
CURB CHASE
EXISTING 4" WATER LINE
ELECTRIC METER
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
METER TO REMAIN
FOR IRRIGATION SERVICE
EXISTING 3
4" WATER
SERVICE TO BE CONNECTED
TO PROPOSED 8" MAIN
STORM
(SEE SHEET C4.05)STORM
(SEE SHEET C4.05)
STORM
(SEE SHEET C4.05)
STORM LINE A10
(SEE SHEET C3.04)
STORM LINE A (CONT.)
(SEE SHEET C3.04)
STORM LINE A
(SEE SHEET C3.04)
STORM LINE A2
(SEE SHEET C3.05)
STORM LINE A2-1
(SEE SHEET C3.05)
SEE SHEET C4.05
SEE SHEET C4.05
SEE SHEET C4.05
SEE SHEET C4.05
SEE SHEET C4.05
SEE SHEET C3.03
18" SEPERATION
18" SEPERATION
8" x 4" TEE
W/ 4" G.V. (W) AND T.B.
N:124015.16
E:190795.56
SEE SHEET C4.05
32'
22'
9'
4'
W W W W W W W
W
W
W
W
8" x 6" REDUCER
W/ 8" G.V. (E)
N:123813.28
E:190234.44
TIE INTO EXISTING
6" WATER MAIN
°
°
4'
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 20 FEET
20 20 40 60
NORTH
C3.02
UT
I
L
I
T
Y
P
L
A
N
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
----
MATCHLINE
SEE SHEET C3.01
MA
T
C
H
L
I
N
E
SE
E
T
H
I
S
S
H
E
E
T
MA
T
C
H
L
I
N
E
SE
E
T
H
I
S
S
H
E
E
T
LEGEND:
GENERAL NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE
FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.ALL WATER AND SANITARY SEWER CONSTRUCTION SHALL BE PER THE
CITY OF FORT COLLINS CONSTRUCTION STANDARDS, LATEST EDITION.
3.UTILITY SERVICES ARE SHOWN IN A SCHEMATIC FASHION ONLY. EXACT
LOCATIONS SHALL BE PER THE REQUIREMENTS OF THE RESPECTIVE
UTILITY PROVIDERS, AND ARE SUBJECT TO CHANGE IN THE FIELD.
4.ALL WATER FITTINGS, VALVES, AND OTHER UTILITY APPURTENANCES ARE
ONLY GRAPHICALLY REPRESENTED AND ARE NOT TO SCALE.
5.ALL EXISTING SANITARY SEWER SERVICES ARE APPROXIMATE AND SHALL
BE FIELD VERIFIED PRIOR TO CONSTRUCTION. ALL SEWER SERVICES TO
BE UNUSED SHALL BE ABANDONED AT THE MAIN AND COORDINATED WITH
FORT COLLINS UTILITIES (970-221-6700).
6.PRIOR TO ORDERING MATERIAL AND MOBILIZING, CONTRACTOR SHALL
FIELD LOCATE AND VERIFY ELEVATIONS OF ALL CONCRETE AND ASPHALT
TIE-INS, EXISTING SEWER MAINS, WATER MAINS, AND ALL OTHER UTILITIES
AT THE POINTS OF CONNECTION SHOWN ON THE PLANS. SPECIAL
ATTENTION SHALL BE PAID TO ALL PROPOSED UTILITY CROSSINGS. IT IS
RECOMMENDED THAT THE CONTRACTOR POTHOLE SAID CROSSINGS
PRIOR TO ORDERING MATERIAL. REFER TO GENERAL NOTE #9 ON SHEET
C0.01 IF A CONFLICT ARISES AND/OR A DESIGN MODIFICATION IS DESIRED.
7.LIMITS OF STREET CUT ARE APPROXIMATE. FINAL LIMITS ARE TO BE
DETERMINED IN THE FIELD BY THE CITY ENGINEERING INSPECTOR. ALL
REPAIRS TO BE IN ACCORDANCE WITH CITY STREET REPAIR STANDARDS.
KEYMAP: (NTS)
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
SEE SHEET C4.05
SEE SHEET C3.03SEE SHEET C4.05
SEXISTING SANITARY MH
GEXISTING GAS METER
EEXISTING ELECTRIC METER
VAULT
ELECEXISTING ELECTRIC VAULT
TEXISTING TELEPHONE PEDESTAL
HYDEXISTING FIRE HYDRANT
TRAFFIC
VAULTEXISTING TRAFFIC VAULT
EEXISTING BURIED ELECTRIC
GEXISTING BURIED GAS
WEXISTING WATER LINE
SSEXISTING SANITARY SEWER LINE
GPROPOSED GAS LINE
PROPOSED WATER SERVICE LINE
PROPOSED SANITARY SERVICE LINE
PROPOSED STORM SEWER
PROJECT BOUNDARY
FDC
EXISTING EXISTING R.O.W
PROPOSED EASEMENT LINE
PROPOSED CURB & GUTTER
PROPOSED FIRE DEPARTMENT CONNECTION
PROPOSED FIRE SERVICE LINE
PROPOSED ELECTRIC METER
EPROPOSED ELECTRIC LINE
UDPROPOSED PERFORATED STROM
PROPOSED GAS METER
RECORD DRAWING
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
W
W
W
W
W W W W W W W W W
WWWWW
HYD
SS
SS
SSC.O.
W
W
W
W
W W W W W W W W
W
W
W
W
W
W
ST
ST
ST
ST
ST ST ST ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
D
X
X
X
X
X
X
X
X
X
UD UD UD
UD
UD
F
F
E E E E E E E E E
E
E
E
E
E
E
EEEEEE
E
E
E
E
E
E
E
E
E
E
S
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
UD
UD
UD
UD
UD
UD
UD
UD
MONITORING WELL
TRAFFIC RATED
E
E
E
E
E
E
E
E
8" FIRE SERVICE LINE
FOR BUILDING A
8" TRANSFER
FIRE SERVICE LINE
FOR BUILDING B
TRANSFORMER
45° BEND
N:124046.14
E:190795.56
8" x 8" TEE
1 - 8" G.V. (W) & T.B.
1 - 8" G.V. (S)
1 - 8" G.V. (N)
N:124074.82
E:190778.93
45° BEND
N:124069.66
E:190796.82
45° BEND
N:124064.54
E:190778.84
8" FIRE SERVICE
FROM BUILDING A
STORM LINE B9
(SEE SHEET C3.06)
STORM LINE A2
(SEE SHEET C3.05)
BLAST WALL
(SEE LANDSCAPE PLANS)
45° BEND
N:124090.79
E:190817.99WQ POND N1
(SEE SHEET C4.05)
UNDERDRAIN
(SEE SHEET C3.02)
MAINTAIN 18
SEPARATION
45° BEND
N:124067.33
E:190730.83
45° BEND
N:124075.18
E:190738.79
8" x 6" SWIVEL TEE
1 - 6" G.V. (W) & T.B.
N:124105.27
E:190779.20PRIVATE FIRE
HYDRANT ASSEMBLY
10 L.F. OF MECHANICAL
RESTRAINTS PAST BEND
45° BEND
N:124070.16
E:190740.82
45° BEND
N:124065.22
E:190735.81
(MAINTAIN 18" SEPARATION)
TOP OF FIRE LINE=5022.32
TOP OF FIRE LINE=5022.32
TOP OF WATER LINE=5023.98
MAINTAIN 12" VERTICAL
SEPARATION
INVERT OF UNDERDRAIN=5025.03
TOP OF WATERLINE=5023.83
(MAINTAIN 18" SEPARATION)
TOP OF FIRE LINE=5023.98
MAINTAIN 18"
SEPARATION
MAINTAIN 18"
SEPARATION
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 5 FEET
5 5 10 15
NORTH
C3.03
DE
T
A
I
L
E
D
U
T
I
L
I
T
Y
P
L
A
N
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
----
LEGEND:
GENERAL NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE
FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.ALL WATER AND SANITARY SEWER CONSTRUCTION SHALL BE PER THE
CITY OF FORT COLLINS CONSTRUCTION STANDARDS, LATEST EDITION.
3.UTILITY SERVICES ARE SHOWN IN A SCHEMATIC FASHION ONLY. EXACT
LOCATIONS SHALL BE PER THE REQUIREMENTS OF THE RESPECTIVE
UTILITY PROVIDERS, AND ARE SUBJECT TO CHANGE IN THE FIELD.
4.ALL WATER FITTINGS, VALVES, AND OTHER UTILITY APPURTENANCES ARE
ONLY GRAPHICALLY REPRESENTED AND ARE NOT TO SCALE.
5.ALL EXISTING SANITARY SEWER SERVICES ARE APPROXIMATE AND SHALL
BE FIELD VERIFIED PRIOR TO CONSTRUCTION. ALL SEWER SERVICES TO
BE UNUSED SHALL BE ABANDONED AT THE MAIN AND COORDINATED WITH
FORT COLLINS UTILITIES (970-221-6700).
6.PRIOR TO ORDERING MATERIAL AND MOBILIZING, CONTRACTOR SHALL
FIELD LOCATE AND VERIFY ELEVATIONS OF ALL CONCRETE AND ASPHALT
TIE-INS, EXISTING SEWER MAINS, WATER MAINS, AND ALL OTHER UTILITIES
AT THE POINTS OF CONNECTION SHOWN ON THE PLANS. SPECIAL
ATTENTION SHALL BE PAID TO ALL PROPOSED UTILITY CROSSINGS. IT IS
RECOMMENDED THAT THE CONTRACTOR POTHOLE SAID CROSSINGS
PRIOR TO ORDERING MATERIAL. REFER TO GENERAL NOTE #9 ON SHEET
C0.01 IF A CONFLICT ARISES AND/OR A DESIGN MODIFICATION IS DESIRED.
7.LIMITS OF STREET CUT ARE APPROXIMATE. FINAL LIMITS ARE TO BE
DETERMINED IN THE FIELD BY THE CITY ENGINEERING INSPECTOR. ALL
REPAIRS TO BE IN ACCORDANCE WITH CITY STREET REPAIR STANDARDS.
KEYMAP: (NTS)
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
SEE SHEET C4.05
SEE SHEET C3.03SEE SHEET C4.05
SEXISTING SANITARY MH
GEXISTING GAS METER
EEXISTING ELECTRIC METER
VAULT
ELECEXISTING ELECTRIC VAULT
TEXISTING TELEPHONE PEDESTAL
HYDEXISTING FIRE HYDRANT
TRAFFIC
VAULTEXISTING TRAFFIC VAULT
EEXISTING BURIED ELECTRIC
GEXISTING BURIED GAS
WEXISTING WATER LINE
SSEXISTING SANITARY SEWER LINE
GPROPOSED GAS LINE
PROPOSED WATER SERVICE LINE
PROPOSED SANITARY SERVICE LINE
PROPOSED STORM SEWER
PROJECT BOUNDARY
FDC
EXISTING EXISTING R.O.W
PROPOSED EASEMENT LINE
PROPOSED CURB & GUTTER
PROPOSED FIRE DEPARTMENT CONNECTION
PROPOSED FIRE SERVICE LINE
PROPOSED ELECTRIC METER
EPROPOSED ELECTRIC LINE
UDPROPOSED PERFORATED STROM
PROPOSED GAS METER
RECORD DRAWING
EXISTING
GROUND
PROPOSED
GRADE
100-YR HGL
5020
5025
5030
5035
5040
5045
5020
5025
5030
5035
5040
5045
9+5010+0011+0012+0013+0014+0014+75
DR
Y
W
E
L
L
A
2
ST
A
1
0
+
0
0
.
0
0
RI
M
5
0
2
9
.
6
±
IN
V
.
I
N
5
0
2
7
.
4
1
(
N
)
IN
V
.
I
N
5
0
2
7
.
6
5
(
W
)
IN
V
.
O
U
T
5
0
2
7
.
6
5
(
S
)
29.05 LF
24" PVC
@ 0.20%
TR
E
N
C
H
D
R
A
I
N
A
3
ST
A
1
0
+
2
9
.
0
5
IN
V
.
5
0
2
7
.
7
9
(
S
W
)
IN
V
.
5
0
2
7
.
7
1
(
E
)
5.95 LF
12" PVC
@ 0.20%
45
°
E
L
B
O
W
A
4
ST
A
1
0
+
3
5
.
0
0
IN
V
.
5
0
2
7
.
8
0
76.52 LF
12" PVC
@ 0.20%
12
'
'
x
1
2
'
'
T
E
E
A
5
ST
A
1
1
+
1
1
.
5
2
IN
V
.
5
0
2
7
.
9
5
97.31 LF
12" PVC
@ 0.20%
12
'
'
x
1
2
'
'
T
E
E
A
6
ST
A
1
2
+
0
8
.
8
2
IN
V
.
5
0
2
8
.
1
5
97.18 LF
12" PVC
@ 0.20%
12
'
'
x
1
2
'
'
T
E
E
A
7
ST
A
1
3
+
0
6
.
0
0
IN
V
.
5
0
2
8
.
3
4
91.40 LF
12" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
A
8
(1
5
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
3
+
9
7
.
4
1
FL
.
E
L
5
0
3
3
.
0
±
IN
V
.
I
N
5
0
2
8
.
5
3
(
N
)
IN
V
.
O
U
T
5
0
2
8
.
5
3
(
E
)
25.59 LF
12" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
A
9
(2
4
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
4
+
2
3
.
0
0
FL
.
E
L
5
0
3
2
.
5
±
IN
V
.
I
N
5
0
2
9
.
0
8
(
W
)
IN
V
.
I
N
5
0
2
8
.
5
8
(
N
E
)
IN
V
.
I
N
5
0
2
8
.
5
8
(
E
)
IN
V
.
O
U
T
5
0
2
8
.
5
8
(
S
)
WATERLINE CROSSING
STA 10+24.55
INV. 5024.13
401 INSTALL WITH WATER TIGHT GASKETS
50
2
8
.
8
7
@ 0.21%
25.59 LF
12" PVC
@ 0.20%
24 LF
50
2
8
.
5
4
50
2
8
.
6
1
50
2
8
.
9
8
(
N
)
50
3
2
.
4
5
50
2
8
.
5
6
50
2
8
.
5
6
369.4 LF 12" PVC @ 0.18%
50
2
7
.
6
7
50
2
7
.
9
1
50
3
2
.
5
4
NE
E
D
R
I
M
UD
VAULT
ELECVAULT
ELEC
UD
UD
F
FD
C
W
S
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
X
X
X X
X
X
X
X
T T
S
WVWV
W
HYD
SS SS SS SS SS
W
W W W W W W W W W W W
PROSPECT ROAD
(60' PUBLIC ROW)
STORM A (CONT.)
(SEE THIS SHEET)
STORM LINE A10
(SEE THIS SHEET)
DRY WELL A2
STA 10+00.00
N: 123856.81
E: 190820.11
29.05 LF
TRENCH DRAIN
@ 0.20%
TRENCH DRAIN A3
STA 10+29.05
N: 123856.93
E: 190791.06
5.95 LF
12" PVC
@ 0.20%
45° ELBOW A4
STA 10+35.00
N: 123854.10
E: 190785.82
76.52 LF
12" PVC
@ 0.20%
12''x12'' TEE A5
STA 11+11.52
N: 123854.50
E: 190709.31
97.31 LF
12" PVC
@ 0.20%
12''x12'' TEE A6
STA 12+08.82
N: 123855.02
E: 190612.00
97.18 LF
12" PVC
@ 0.20%
12''x12'' TEE A7
STA 13+06.00
N: 123855.53
E: 190514.82
91.40 LF
12" PVC
@ 0.20%
DRAIN BASIN A8
STA 13+97.41
N: 123856.02
E: 190423.42
25.59 LF
12" PVC
@ 0.20%
DRAIN BASIN A9
STA 14+23.00
N: 123881.45
E: 190420.58
W
W
W
W
W
C.O.
W
CSW
CS
ST ST ST ST ST ST ST
ST
ST
ST
ST
ST
STST
FES
D D
D
DD
DD
ST ST ST ST
ST
ST ST ST
ST
ST
ST
ST
UD
VA
U
L
T
EL
E
C
W
W
W
W
W
W
W
DRAIN BASIN A10
STA 10+00.00
N: 123881.36
E: 190405.08
5.10 LF
12" PVC
@ 2.00%
45° ELBOW A10-1
STA 10+05.10
N: 123876.26
E: 190405.12
10.23 LF
12" PVC
@ 2.00%
5.31 LF
12" PVC
@ 2.00%
45° ELBOW A10-2
STA 10+15.33
N: 123869.07
E: 190412.39
AREA INLET A10-3
STA 10+20.64
N: 123863.76
E: 190412.42
ST
ST
ST
ST
ST D
D
ST
ST
100-YR HGL
5025
5030
5035
5040
5045
5050
5025
5030
5035
5040
5045
5050
9+50 10+00 10+75
AR
E
A
I
N
L
E
T
A
1
0
-
3
(1
2
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
2
0
.
6
4
FL
.
E
L
5
0
3
2
.
2
±
IN
V
.
O
U
T
5
0
2
9
.
5
2
(
N
)
5.31 LF
12" PVC
@ 2.00%
45
°
E
L
B
O
W
A
1
0
-
2
ST
A
1
0
+
1
5
.
3
3
IN
V
.
5
0
2
9
.
4
2
10.23 LF
12" PVC
@ 2.00%
45
°
E
L
B
O
W
A
1
0
-
1
ST
A
1
0
+
0
5
.
1
0
IN
V
.
5
0
2
9
.
2
1
5.10 LF
12" PVC
@ 2.00%
DR
A
I
N
B
A
S
I
N
A
1
0
(2
4
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
0
0
.
0
0
RI
M
5
0
3
2
.
5
±
IN
V
.
I
N
5
0
2
9
.
1
1
(
N
)
IN
V
.
I
N
5
0
2
9
.
1
1
(
S
)
IN
V
.
O
U
T
5
0
2
9
.
1
1
(
E
)
50
3
2
.
5
1
50
2
8
.
8
9
50
2
9
.
0
3
50
2
8
.
8
0
50
3
2
.
3
3
50
2
9
.
5
7
LENGTH
& SLOPE
UNKNOWN
100-YR HGL
5020
5025
5030
5035
5040
5045
5020
5025
5030
5035
5040
5045
9+50 10+00 11+00 12+00 13+00 13+75
DR
A
I
N
B
A
S
I
N
A
1
1
(2
4
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
0
0
.
0
0
RI
M
5
0
3
3
.
0
±
IN
V
.
I
N
5
0
2
9
.
2
8
(
N
)
IN
V
.
I
N
5
0
2
9
.
2
8
(
E
)
IN
V
.
O
U
T
5
0
2
9
.
2
8
(
S
)
11.51 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
2
ST
A
1
0
+
1
1
.
5
1
IN
V
.
5
0
2
9
.
3
0
38.18 LF
8" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
A
1
3
(1
0
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
4
9
.
6
9
RI
M
5
0
3
3
.
2
±
IN
V
.
I
N
5
0
2
9
.
3
8
(
E
)
IN
V
.
O
U
T
5
0
2
9
.
3
8
(
S
)
32.15 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
4
ST
A
1
0
+
8
1
.
8
4
IN
V
.
5
0
2
9
.
4
4
22.50 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
5
ST
A
1
1
+
0
4
.
3
4
IN
V
.
5
0
2
9
.
4
9
31.19 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
6
ST
A
1
1
+
3
5
.
5
3
IN
V
.
5
0
2
9
.
5
5
31.48 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
7
ST
A
1
1
+
6
7
.
0
1
IN
V
.
5
0
2
9
.
6
1
44.02 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
8
ST
A
1
2
+
1
1
.
0
3
IN
V
.
5
0
2
9
.
7
0
28.81 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
1
9
ST
A
1
2
+
3
9
.
8
4
IN
V
.
5
0
2
9
.
7
6
31.50 LF
8" PVC
@ 0.20%
8'
'
x
4
'
'
T
E
E
A
2
0
ST
A
1
2
+
7
1
.
3
4
IN
V
.
5
0
2
9
.
8
2
18.00 LF
8" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
A
2
1
(1
0
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
2
+
8
9
.
3
4
RI
M
5
0
3
1
.
3
±
IN
V
.
I
N
5
0
2
9
.
8
6
(
S
)
IN
V
.
I
N
5
0
3
0
.
1
4
(
N
E
)
IN
V
.
O
U
T
5
0
2
9
.
8
6
(
W
)
5.25 LF 8" PVC @ 5.00%
FE
S
A
2
2
ST
A
1
2
+
9
4
.
5
9
FL
.
E
L
5
0
3
1
.
1
±
IN
V
.
O
U
T
5
0
3
0
.
4
0
(
S
W
)
296 INSTALL WITH WATER TIGHT GASKETS
50
3
0
.
3
2
50
2
9
.
4
2
50
2
9
.
4
2
50
2
9
.
1
1
44.6 LF 8" PVC
@ 0.29%
UNKNOWN
50
3
3
.
1
7
50
3
3
.
0
2
50
2
9
.
2
9
BASIN A21 - NOT INSTALLED
*NO ADVERSE IMPACTS*
UD
F
FD
C
W
FD
C
S
UD
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
X
X
X X X
SS
SS
SS
DRAIN BASIN A11
STA 10+00.00
N: 123966.85
E: 190404.64
8''x4'' TEE A12
STA 10+11.51
N: 123978.36
E: 190404.63
11.51 LF
8" PVC
@ 0.20%
38.18 LF
8" PVC
@ 0.20%
DRAIN BASIN A13
STA 10+49.69
N: 124016.54
E: 190404.63
32.15 LF
8" PVC
@ 0.20%
8''x4'' TEE A14
STA 10+81.84
N: 124016.54
E: 190436.77
22.50 LF
8" PVC
@ 0.20%
8''x4'' TEE A15
STA 11+04.34
N: 124016.54
E: 190459.27
31.19 LF
8" PVC
@ 0.20%
8''x4'' TEE A16
STA 11+35.53
N: 124016.54
E: 190490.46
31.48 LF
8" PVC
@ 0.20%
8''x4'' TEE A17
STA 11+67.01
N: 124016.54
E: 190521.94
44.02 LF
8" PVC
@ 0.20%
8''x4'' TEE A18
STA 12+11.03
N: 124016.54
E: 190565.96
28.81 LF
8" PVC
@ 0.20%
8''x4'' TEE A19
STA 12+39.84
N: 124016.54
E: 190594.77
31.50 LF
8" PVC
@ 0.20%
8''x4'' TEE A20
STA 12+71.34
N: 124016.54
E: 190626.27
18.00 LF
8" PVC
@ 0.20%
DRAIN BASIN A21
STA 12+89.34
N: 124016.54
E: 190644.27
5.25 LF 8" PVC @ 5.00%
FES A22
STA 12+94.59
N: 124020.78
E: 190647.37
W
W
W
W
W
W
W
W
SS
SS
SS
W
HYD
C.O.
W
ST ST ST ST ST ST ST
ST
ST
ST
STST
FES
D D
D
DD
D
D
D
ST ST ST ST
ST
ST
ST ST
ST
ST
ST
ST
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 50 FEET
50 50 100 150
NORTH
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
C3.04
PL
A
N
A
N
D
P
R
O
F
I
L
E
ST
O
R
M
L
I
N
E
A
,
A
1
0
,
&
A
(
C
O
N
T
.
)
----
NORTH NORTH
STORM LINE A STORM LINE A10 STORM LINE A (CONT.)
PROFILE SCALE:PROFILE SCALE:PROFILE SCALE:
LEGEND:
GENERAL NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE
FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND
INLET BOX STRUCTURES. SPECIFIED LENGTH OF PIPE INCLUDES THE
LAYING LENGTH OF PLACED END SECTIONS.
3.CONTRACTOR SHALL CONFIRM AND COORDINATE WITH STAMPED
PLUMBING DRAWINGS FOR ALL ROOF DRAINS AND COURTYARD DRAIN
SIZES AND LOCATIONS. NOTIFY OWNER, ARCHITECT, AND ENGINEER(S) OF
ANY DISCREPANCIES PRIOR TO MOBILIZATION.
4.ALL STORM SEWER TO BE INSTALLED WITH WATER TIGHT JOINTS AT EACH
CONNECTION.
5.ALL STORM SEWER IS TO BE MAINTAINED AND OWNED BY THE PROPERTY
OWNER. ALL LINES ARE PRIVATE.
6.CONTRACTOR SHALL PROVIDE MINIMUM COVER OVER STORM SEWER PIPE
DURING CONSTRUCTION IN ACCORDANCE WITH MANUFACTURES
RECOMMENDATIONS.
7.ALL ROOF DRAIN CONNECTION SHALL BE PER DETAIL 400 ON SHEET C6.04.
THE CONTRACTOR SHALL TERMINATE THE ROOF DRAIN LATERALS 5 FEET
OUTSIDE OF BUILDINGS. EXACT LOCATIONS OF THE ROOF DRAIN
CONNECTION AT THE PROPOSED BUILDING SHALL BE COORDINATED WITH
THE ARCHITECTURAL DRAWINGS.
SEXISTING SANITARY MH
GEXISTING GAS METER
EEXISTING ELECTRIC METER
VAULT
ELECEXISTING ELECTRIC VAULT
TEXISTING TELEPHONE PEDESTAL
HY DEXISTING FIRE HYDRANT
TRAFFIC
VAULTEXISTING TRAFFIC VAULT
EEXISTING BURIED ELECTRIC
GEXISTING BURIED GAS
WEXISTING WATER LINE
SSEXISTING SANITARY SEWER LINE
GPROPOSED GAS LINE
PROPOSED WATER SERVICE LINE
PROPOSED SANITARY SERVICE LINE
PROPOSED STORM SEWER
PROJECT BOUNDARY
FDC
EXISTING EXISTING R.O.W
PROPOSED EASEMENT LINE
PROPOSED CURB & GUTTER
PROPOSED FIRE DEPARTMENT CONNECTION
PROPOSED FIRE SERVICE LINE
PROPOSED ELECTRIC METER
EPROPOSED ELECTRIC LINE
UDPROPOSED PERFORATED STROM
PROPOSED GAS METER
"PRIVATE STORM LINE""PRIVATE STORM LINE""PRIVATE STORM LINE"
DateCity Engineer
Date
Date
Date
Date
Stormwater Utility
Parks & Recreation
Traffic Engineer
Date
Water & Wastewater Utility
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Environmental Planner
RECORD DRAWING
VA
U
L
T
EL
E
C
UD
UD UD
F
F
FDC
W
FDC
S
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
UD MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
X XX
X
X
T
T
S
WVWV
W
HYD
SS
SS
SS
SS
SS
SS
W
W
W
W
W
W
W
W
W
W
UP
D.
S
.
R.D
.
D.
S
.
D.S
.
PR
O
S
P
E
C
T
R
O
A
D
(6
0
'
P
U
B
L
I
C
R
O
W
)
STORM LINE A2
(SEE THIS SHEET)
STORM LINE B9-1
(SEE SHEET C3.06)
DRAIN BASIN A2-1
STA 10+69.71
N: 123884.08
E: 190820.29
16.23 LF 6" PVC @ 3.01%
32.28 LF 6" PERFORATED PVC @ 0.50%
MONITORING WELL A2-1.2
STA 10+48.51
N: 123916.36
E: 190804.06
69.10 LF 6" PERFORATED PVC @ 0.50%
MONITORING WELL A2-1.5
STA 11+33.11
N: 124000.96
E: 190804.06
47.19 LF 6" PVC @ 0.50%
UNDERDRAIN
(SEE SHEET C3.02)
DRAIN BASIN A2-1.6
STA 11+80.30
N: 124005.30
E: 190757.07
W W W
W W W W W
W
HYD
W
CSWCS
ST
ST
ST
ST
STST ST
ST
ST
ST
ST
STSTSTST
ST
FES
D
D
D
ST
ST
ST
ST
ST ST
MONITORING WELL A2-1.1
STA 10+16.23
N: 123884.08
E: 190804.06
5020
5025
5030
5035
5040
5045
5020
5025
5030
5035
5040
5045
9+5010+0011+0012+0013+0014+0015+0016+00
PROPOSED
GRADE
EXISTING
GROUND
100-YR HGL
10
0
-
Y
R
S
T
R
M
O
U
T
L
E
T
A
2
-
4
ST
A
1
5
+
2
2
.
3
8
IN
V
.
5
0
2
8
.
4
0
(
S
)
7.42 LF 12" PVC @ 0.65%
DR
A
I
N
B
A
S
I
N
A
2
-
3
(1
2
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
5
+
1
4
.
9
7
RI
M
5
0
3
1
.
2
±
IN
V
.
I
N
5
0
2
8
.
3
5
(
N
)
IN
V
.
O
U
T
5
0
2
8
.
3
5
(
W
)
239.91 LF 12" PVC @ 0.20%
DR
A
I
N
B
A
S
I
N
A
2
-
2
(1
2
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
2
+
7
5
.
0
5
RI
M
5
0
3
0
.
8
±
IN
V
.
I
N
5
0
2
7
.
8
7
(
E
)
IN
V
.
O
U
T
5
0
2
7
.
8
7
(
S
)
205.34 LF 12" PVC @ 0.20%
DR
A
I
N
B
A
S
I
N
A
2
-
1
(1
2
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
6
9
.
7
1
RI
M
5
0
3
0
.
6
±
IN
V
.
I
N
5
0
2
7
.
4
6
(
N
)
IN
V
.
I
N
5
0
2
7
.
4
6
(
W
)
IN
V
.
O
U
T
5
0
2
7
.
4
6
(
S
)
27.27 LF 12" PVC @ 0.20%
DR
Y
W
E
L
L
A
2
ST
A
1
0
+
4
2
.
4
4
RI
M
5
0
2
9
.
6
±
IN
V
.
I
N
5
0
2
7
.
4
1
(
N
)
IN
V
.
I
N
5
0
2
7
.
6
5
(
W
)
IN
V
.
O
U
T
5
0
2
7
.
6
5
(
S
)
7.17 LF 24" PVC @ 0.20%
HE
A
D
W
A
L
L
A
1
ST
A
1
0
+
3
5
.
2
7
IN
V
.
5
0
2
7
.
6
4
(
N
)
239 INSTALL WITH WATER TIGHT GASKETS
50
3
1
.
3
4
50
3
0
.
7
4
50
2
7
.
9
5
50
2
7
.
9
5
50
3
0
.
1
8
50
2
7
.
7
2
50
2
7
.
7
2
50
2
7
.
7
2
50
2
7
.
6
7
50
2
7
.
6
7
204.44 12" PVC @ 0.11%
25.4 12" PVC @ 0.20%
243.9 12" PVC @ 0.24%
50
2
8
.
5
4
50
2
8
.
5
4
EXISTING
GROUND
5020
5025
5030
5035
5040
5045
5020
5025
5030
5035
5040
5045
9+5010+0011+0012+0012+30
DR
A
I
N
B
A
S
I
N
A
2
-
1
(1
2
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
6
9
.
7
1
RI
M
5
0
3
0
.
6
±
IN
V
.
I
N
5
0
2
7
.
4
6
(
N
)
IN
V
.
I
N
5
0
2
7
.
4
6
(
W
)
IN
V
.
O
U
T
5
0
2
7
.
4
6
(
S
)
16.23 LF
6" PVC
@ 3.01%32.28 LF
6" PERFORATED PVC
@ 0.50%
MO
N
I
T
O
R
I
N
G
W
E
L
L
A
2
-
1
.
2
ST
A
1
0
+
4
8
.
5
1
RI
M
5
0
3
0
.
7
±
IN
V
.
I
N
5
0
2
8
.
1
1
(
N
)
IN
V
.
I
N
5
0
2
8
.
1
1
(
W
)
IN
V
.
O
U
T
5
0
2
8
.
1
1
(
S
)
69.10 LF
6" PERFORATED PVC
@ 0.50%
CO
U
P
L
I
N
G
A
2
-
1
.
3
ST
A
1
1
+
1
7
.
6
1
IN
V
.
5
0
2
8
.
4
6
8.00 LF 6" PVC @ 0.50%
CO
U
P
L
I
N
G
A
2
-
1
.
4
ST
A
1
1
+
2
5
.
6
1
IN
V
.
5
0
2
8
.
5
0
7.50 LF
6" PERFORATED PVC
@ 0.50%
MO
N
I
T
O
R
I
N
G
W
E
L
L
A
2
-
1
.
5
ST
A
1
1
+
3
3
.
1
1
RI
M
5
0
3
1
.
3
±
IN
V
.
I
N
5
0
2
8
.
5
3
(
W
)
IN
V
.
I
N
5
0
2
8
.
5
3
(
N
)
IN
V
.
O
U
T
5
0
2
8
.
5
3
(
S
)
47.19 LF 6" PVC @ 0.50%
DR
A
I
N
B
A
S
I
N
A
2
-
1
.
6
(2
4
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
1
+
8
0
.
3
0
RI
M
5
0
3
2
.
5
±
IN
V
.
I
N
5
0
2
9
.
2
7
(
N
)
IN
V
.
I
N
5
0
2
8
.
7
7
(
S
W
)
IN
V
.
O
U
T
5
0
2
8
.
7
7
(
E
)
MO
N
I
T
O
R
I
N
G
W
E
L
L
A
2
-
1
.
1
ST
A
1
0
+
1
6
.
2
3
RI
M
5
0
3
0
.
2
±
IN
V
.
I
N
5
0
2
7
.
9
5
(
N
)
IN
V
.
I
N
5
0
2
7
.
9
5
(
S
)
IN
V
.
O
U
T
5
0
2
7
.
9
5
(
E
)
PROPOSED
GRADE
WATERLINE
STA 11+41.65
INV. 5026.45
18" (min.)
50
3
2
.
4
4
50
2
9
.
4
1
50
2
8
.
7
7
50
2
8
.
7
3
50
3
1
.
2
4
50
2
8
.
2
8
50
2
8
.
2
5
50
2
8
.
2
3
43.3 6" PVC @ 1.04%
84.4 6" PVC @ 0.24%
50
3
0
.
6
0
50
2
8
.
0
3
50
2
8
.
0
3
50
2
8
.
0
3
50
3
0
.
1
4
50
2
7
.
8
3
50
2
7
.
8
3
50
2
7
.
8
3
31.2 6" PVC
@ 0.64%
50
3
0
.
1
8
50
2
7
.
7
2
50
2
7
.
7
2
50
2
7
.
7
2
15.3 6" PVC
@ 0.72%
W
UD UD
UD UD
F
F
FDC
W
FDC
S
FDC
S
W
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
UD MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
MONITORI
N
G
W
E
L
L
TRAFFIC R
A
T
E
D
S
W
W
W
W
W
W
W
X XX
X
X
X
X
T
T
WV
WVWV
W
WV
WV
HYD
MH
S
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
W
W
W
W
W
W
W
W
W
W
W
UP
D.
S
.
D.
S
.
R.D
.
D.S
.
D.
S
.
D.
S
.
D.
S
.
D.S
.D.
S
.
D.
S
.
R.D
.
D.
S
.
VA
U
L
T
EL
E
C
PR
O
S
P
E
C
T
R
O
A
D
(6
0
'
P
U
B
L
I
C
R
O
W
)
STORM LINE B1
(SEE SHEET C3.06)
STORM LINE B1
(SEE SHEET C3.06)
STORM LINE B9-1
(SEE SHEET C3.06)
HEADWALL A1
STA 10+35.27
N: 123849.64
E: 190820.11
7.17 LF 24" PVC @ 0.20%
DRY WELL A2
STA 10+42.44
N: 123856.81
E: 190820.11
27.27 LF 12" PVC @ 0.20%
DRAIN BASIN A2-1
STA 10+69.71
N: 123884.08
E: 190820.29
205.34 LF 12" PVC @ 0.20%
DRAIN BASIN A2-2
STA 12+75.05
N: 124089.42
E: 190821.66
23
9
.
9
1
L
F
1
2
"
P
V
C
@
0
.
2
0
%
DRAIN BASIN A2-3
STA 15+14.97
N: 124087.22
E: 191061.57
7.42 LF 12" PVC @ 0.65%
100-YR STRM OUTLET A2-4
STA 15+22.38
N: 124094.63
E: 191061.57
W
S
S
W W W W W
W W W W W
W
HYD
W
CSWCS
WCS
ST
STST
ST
ST
ST
ST
ST
STST
STSTST ST
ST
ST
ST
ST
ST
STSTSTST
ST
D
D
ST
ST ST
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
NORTH
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
C3.05
PL
A
N
A
N
D
P
R
O
F
I
L
E
ST
O
R
M
L
I
N
E
A
2
&
A
2
-
1
----
NORTH
PROFILE SCALE:PROFILE SCALE:
LEGEND:
GENERAL NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE
FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND
INLET BOX STRUCTURES. SPECIFIED LENGTH OF PIPE INCLUDES THE
LAYING LENGTH OF PLACED END SECTIONS.
3.CONTRACTOR SHALL CONFIRM AND COORDINATE WITH STAMPED
PLUMBING DRAWINGS FOR ALL ROOF DRAINS AND COURTYARD DRAIN
SIZES AND LOCATIONS. NOTIFY OWNER, ARCHITECT, AND ENGINEER(S) OF
ANY DISCREPANCIES PRIOR TO MOBILIZATION.
4.ALL STORM SEWER TO BE INSTALLED WITH WATER TIGHT JOINTS AT EACH
CONNECTION.
5.ALL STORM SEWER IS TO BE MAINTAINED AND OWNED BY THE PROPERTY
OWNER. ALL LINES ARE PRIVATE.
6.CONTRACTOR SHALL PROVIDE MINIMUM COVER OVER STORM SEWER PIPE
DURING CONSTRUCTION IN ACCORDANCE WITH MANUFACTURES
RECOMMENDATIONS.
7.ALL ROOF DRAIN CONNECTION SHALL BE PER DETAIL 400 ON SHEET C6.04.
THE CONTRACTOR SHALL TERMINATE THE ROOF DRAIN LATERALS 5 FEET
OUTSIDE OF BUILDINGS. EXACT LOCATIONS OF THE ROOF DRAIN
CONNECTION AT THE PROPOSED BUILDING SHALL BE COORDINATED WITH
THE ARCHITECTURAL DRAWINGS.
SEXISTING SANITARY MH
GEXISTING GAS METER
EEXISTING ELECTRIC METER
VAULT
ELECEXISTING ELECTRIC VAULT
TEXISTING TELEPHONE PEDESTAL
HYDEXISTING FIRE HYDRANT
TRAFFIC
VAULTEXISTING TRAFFIC VAULT
EEXISTING BURIED ELECTRIC
GEXISTING BURIED GAS
WEXISTING WATER LINE
SSEXISTING SANITARY SEWER LINE
GPROPOSED GAS LINE
PROPOSED WATER SERVICE LINE
PROPOSED SANITARY SERVICE LINE
PROPOSED STORM SEWER
PROJECT BOUNDARY
FDC
EXISTING EXISTING R.O.W
PROPOSED EASEMENT LINE
PROPOSED CURB & GUTTER
PROPOSED FIRE DEPARTMENT CONNECTION
PROPOSED FIRE SERVICE LINE
PROPOSED ELECTRIC METER
EPROPOSED ELECTRIC LINE
UDPROPOSED PERFORATED STROM
PROPOSED GAS METER
GRAPHIC SCALE:GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 50 FEET
50 50 100 150
STORM LINE A2 STORM LINE A2-1
"PRIVATE STORM LINE""PRIVATE STORM LINE"
DateCity Engineer
Date
Date
Date
Date
Stormwater Utility
Parks & Recreation
Traffic Engineer
Date
Water & Wastewater Utility
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Environmental Planner
RECORD DRAWING
W
FDC
FDC
S
W
S
W
W
W
W
W
W
WV
MH
S
SS
SS
SS
SS
SS
SS
S
VA
U
L
T
EL
E
C
WQ OUTLET B1-3
STA 11+44.67
N: 124189.65
E: 191073.76
7.66 LF 18" PVC @ 5.44%
DRAIN BASIN B1-2
STA 11+37.01
N: 124189.67
E: 191081.42
47.66 LF
18" PVC
@ 0.20%
DRAIN BASIN B1-1
STA 10+89.35
N: 124237.33
E: 191081.32
89.35 LF 18" PVC @ 0.20%
HEADWALL B1
STA 10+00.00
N: 124326.68
E: 191081.15
W
S
S
W W W
WCS
STST
ST
ST
ST
ST
ST
STST
5015
5020
5025
5030
5035
5040
5015
5020
5025
5030
5035
5040
9+50 10+00 11+00 12+00
HE
A
D
W
A
L
L
B
1
ST
A
1
0
+
0
0
.
0
0
RI
M
5
0
2
6
.
3
±
IN
V
.
I
N
5
0
2
3
.
7
5
(
S
)
89.35 LF
18" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
B
1
-
1
(1
8
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
0
+
8
9
.
3
5
RI
M
5
0
2
7
.
1
±
IN
V
.
I
N
5
0
2
3
.
9
3
(
S
)
IN
V
.
I
N
5
0
2
3
.
9
3
(
W
)
IN
V
.
O
U
T
5
0
2
3
.
9
3
(
N
)
47.66 LF
18" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
B
1
-
2
(1
8
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
1
+
3
7
.
0
1
RI
M
5
0
2
7
.
0
±
IN
V
.
I
N
5
0
2
4
.
0
3
(
W
)
IN
V
.
O
U
T
5
0
2
4
.
0
3
(
N
)
7.66 LF
18" PVC
@ 5.44%
WQ
O
U
T
L
E
T
B
1
-
3
ST
A
1
1
+
4
4
.
6
7
IN
V
.
5
0
2
4
.
4
4
(
E
)
EXISTING
GROUND
PROPOSED
GRADE
100-YR HGL
50
2
4
.
4
1
50
2
4
.
3
9
50
2
7
.
1
1
50
2
4
.
0
0
50
2
4
.
0
0
50
2
4
.
7
5
51.0 18" PVC
@ 0.76%
NE
E
D
R
I
M
50
2
3
.
7
8
85.8 18" PVC
@ 0.26%
50
2
7
.
3
2
5015
5020
5025
5030
5035
5040
5015
5020
5025
5030
5035
5040
9+5010+0011+0012+0013+0014+0015+0015+50
276.85 LF
18" PVC
@ 0.20%
DR
A
I
N
B
A
S
I
N
B
3
(1
8
"
D
R
A
I
N
B
A
S
I
N
)
ST
A
1
2
+
7
6
.
8
5
RI
M
5
0
2
6
.
6
±
IN
V
.
I
N
5
0
2
4
.
7
3
(
S
W
)
IN
V
.
O
U
T
5
0
2
4
.
2
3
(
E
)
13.96 LF
12" PVC
@ 0.20%
TR
E
N
C
H
D
R
A
I
N
(
4
5
°
E
L
B
O
W
)
B
4
ST
A
1
2
+
9
0
.
8
0
IN
V
.
5
0
2
4
.
7
6
TRENCH DRAIN
(SEE TRENCH DRAIN C DETAIL)
MI
D
.
C
O
N
N
E
C
T
I
O
N
B
5
ST
A
1
3
+
0
4
.
6
6
IN
V
.
5
0
2
4
.
7
9
15.75 LF
(3) 8" PVC
@ 0.20%
IN
L
E
T
B
6
ST
A
1
3
+
2
0
.
4
0
FL
.
E
L
5
0
2
6
.
3
±
IN
V
.
I
N
5
0
2
4
.
8
2
(
S
)
IN
V
.
I
N
5
0
2
4
.
8
2
(
S
W
)
IN
V
.
O
U
T
5
0
2
4
.
8
2
(
N
)
IN
L
E
T
B
8
ST
A
1
4
+
8
3
.
8
1
RI
M
5
0
2
8
.
7
±
IN
V
.
I
N
5
0
2
5
.
1
4
(
S
E
)
IN
V
.
I
N
5
0
2
5
.
1
4
(
S
)
IN
V
.
O
U
T
5
0
2
5
.
1
4
(
N
W
)
EXISTING
GROUND
PROPOSED
GRADE
100-YR HGL HE
A
D
W
A
L
L
B
2
ST
A
1
0
+
0
0
.
0
0
IN
V
.
5
0
2
3
.
6
7
(
W
)
161.60 LF
12" PVC
@ 0.20%
50
2
6
.
5
7
50
2
4
.
0
2
50
2
4
.
0
2
50
2
3
.
7
2
275.0 18" PVC
@ 0.11%
50
2
8
.
6
6
50
2
5
.
1
1
50
2
5
.
1
1
50
2
5
.
0
5
157.8
@ 0.13%
8" PVC
50
2
6
.
7
6
50
2
4
.
8
3
50
2
4
.
8
3
50
2
4
.
8
3
14.5
@ 3.52%
50
2
4
.
3
1
50
2
4
.
2
0
15.2
@ 1.18%
5020
5025
5030
5035
5040
5045
5020
5025
5030
5035
5040
5045
9+5010+0011+00
IN
L
E
T
B
9
-
1
ST
A
1
0
+
2
7
.
2
0
FL
.
E
L
5
0
2
9
.
9
±
IN
V
.
O
U
T
5
0
2
7
.
5
6
(
E
)
27.20 LF
12" PVC
@ 2.00%
EXISTING
GROUND
PROPOSED
GRADE
DR
A
I
N
B
A
S
I
N
B
9
ST
A
1
0
+
0
0
.
0
0
RI
M
5
0
2
9
.
8
±
IN
V
.
I
N
5
0
2
7
.
0
2
(
W
)
IN
V
.
O
U
T
5
0
2
5
.
4
2
(
N
)
50
2
9
.
7
9
50
2
8
.
3
4
50
2
9
.
9
3
50
2
6
.
9
5
50
2
5
.
4
7
24.1
@ 5.77%
W
UD
UD
F
F
FD
C
S
FD
C
S W
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
UD
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
S
W W W W W W W W W
X
XXXX
WVWV
WV
WV
HYD
MH
SSSSSSSSSSSSS SS SS SS S
VAULT
ELEC
276.85 LF 18" PVC @ 0.20%
DRAIN BASIN B3
STA 12+76.85
N: 124329.59
E: 190796.32
13.96 LF 12" PVC @ 0.20%
TRENCH DRAIN (45° ELBOW) B4
STA 12+90.80
N: 124321.65
E: 190784.83
MID. CONNECTION B5
STA 13+04.66
N: 124321.65
E: 190770.98
(3) 15.75 LF 8" PVC @ 0.20%
INLET B6
STA 13+20.40
N: 124305.91
E: 190770.98
INLET B8
STA 14+83.81
N: 124146.46
E: 190769.57
HEADWALL B2
STA 10+00.00
N: 124327.73
E: 191073.16
16
1
.
6
0
L
F
1
2
"
P
V
C
@
0
.
2
0
%
STORM LINE B1
(SEE THIS SHEET)
STORM LINE B9
(SEE THIS SHEET)
UNDERDRAIN
(SEE SHEET C3.01)
W
S S
W
W
W
W
W
W
W
HYD
W
W
CS
ST
ST
ST ST ST ST ST
ST
ST
ST
ST
ST
ST
ST
ST ST ST ST
ST
D
UD
UD
UD
F
F
W
FD
C
S
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
UD
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
X
X
X
DRAIN BASIN B9
STA 10+00.00
N: 124090.85
E: 190766.40
27.20 LF
12" PVC
@ 2.00%
INLET B9-1
STA 10+27.20
N: 124087.01
E: 190739.48
STORM LINE B
(SEE THIS SHEET)
W
W
W
W
W
W
W
W
HYD
W
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
D
D
D
ST
ST
ST
ST
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
DateCity Engineer
Date
Date
Date
Date
Stormwater Utility
Parks & Recreation
Traffic Engineer
Date
Water & Wastewater Utility
City of Fort Collins, Colorado
UTILITY PLAN APPROVAL
Environmental Planner
C3.06
PL
A
N
A
N
D
P
R
O
F
I
L
E
ST
O
R
M
L
I
N
E
B
1
,
B
,
&
B
9
----
GRAPHIC SCALE:GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 50 FEET
50 50 100 150
LEGEND:
GENERAL NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE
FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND
INLET BOX STRUCTURES. SPECIFIED LENGTH OF PIPE INCLUDES THE
LAYING LENGTH OF PLACED END SECTIONS.
3.CONTRACTOR SHALL CONFIRM AND COORDINATE WITH STAMPED
PLUMBING DRAWINGS FOR ALL ROOF DRAINS AND COURTYARD DRAIN
SIZES AND LOCATIONS. NOTIFY OWNER, ARCHITECT, AND ENGINEER(S) OF
ANY DISCREPANCIES PRIOR TO MOBILIZATION.
4.ALL STORM SEWER TO BE INSTALLED WITH WATER TIGHT JOINTS AT EACH
CONNECTION.
5.ALL STORM SEWER IS TO BE MAINTAINED AND OWNED BY THE PROPERTY
OWNER. ALL LINES ARE PRIVATE.
6.CONTRACTOR SHALL PROVIDE MINIMUM COVER OVER STORM SEWER PIPE
DURING CONSTRUCTION IN ACCORDANCE WITH MANUFACTURES
RECOMMENDATIONS.
7.ALL ROOF DRAIN CONNECTION SHALL BE PER DETAIL 400 ON SHEET C6.04.
THE CONTRACTOR SHALL TERMINATE THE ROOF DRAIN LATERALS 5 FEET
OUTSIDE OF BUILDINGS. EXACT LOCATIONS OF THE ROOF DRAIN
CONNECTION AT THE PROPOSED BUILDING SHALL BE COORDINATED WITH
THE ARCHITECTURAL DRAWINGS.
SEXISTING SANITARY MH
GEXISTING GAS METER
EEXISTING ELECTRIC METER
VAULT
ELECEXISTING ELECTRIC VAULT
TEXISTING TELEPHONE PEDESTAL
HY DEXISTING FIRE HYDRANT
TRAFFIC
VAULTEXISTING TRAFFIC VAULT
EEXISTING BURIED ELECTRIC
GEXISTING BURIED GAS
WEXISTING WATER LINE
SSEXISTING SANITARY SEWER LINE
GPROPOSED GAS LINE
PROPOSED WATER SERVICE LINE
PROPOSED SANITARY SERVICE LINE
PROPOSED STORM SEWER
PROJECT BOUNDARY
FDC
EXISTING EXISTING R.O.W
PROPOSED EASEMENT LINE
PROPOSED CURB & GUTTER
PROPOSED FIRE DEPARTMENT CONNECTION
PROPOSED FIRE SERVICE LINE
PROPOSED ELECTRIC METER
EPROPOSED ELECTRIC LINE
UDPROPOSED PERFORATED STROM
PROPOSED GAS METER
NORTH NORTH NORTH
STORM LINE B1 STORM LINE B STORM LINE B9
PROFILE SCALE:PROFILE SCALE:PROFILE SCALE:
"PRIVATE STORM LINE""PRIVATE STORM LINE""PRIVATE STORM LINE"
RECORD DRAWING
X
X
XXXXXXXXXXX
VAULT
ELEC
FD
C
FD
C
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
13
:
1
10:
1
4:
1
12:1
7:
1
22:149
:
1
18" VERTICAL
CURB AND GUTTER
18" VERTICAL
CURB AND GUTTER
AT EXISTING FLOW LINE
ELEVATIONS
2.1%
2.1%
4.
9
%
2.
0
%
2.
0
%
2.
0
%
ST
A
D
I
U
M
A
P
A
R
T
M
E
N
T
S
RAMP
RAMP
RAMP
18" VERTICAL
CURB AND GUTTER
RAMP
RAMP
RISERS
RAMP
BUILDING 1
INLET
EMERGENCY
ACCESS EASEMENT
9' UTILITY EASEMENT
RAMP
5' NON-VEHICULAR
PUBLIC ACCESS
EASEMENT
TRENCH DRAIN
6:
120
:
1
31' EMERGENCY ACCESS, VEHICULAR
PUBLIC ACCESS, DRAINAGE & UTILITY
EASEMENT
RISERS
RISERS
RISERS
2' CONCRETE
PAN
HEADWALL
2.1%
2.1%
2.7
%
THE SLAB
TH
E
S
L
A
B
RAMP
RISERS
LAKE STREET
(60' PUBLIC ROW)
DRAINAGE EASEMENT
PER THE SLAB PROPERTY PLAT
30' EMERGENCY ACCESS,
NON-VEHICULAR PUBLIC ACCESS,
AND DRAINAGE EASEMENT
(PER THE SLAB PROPERTY PLAT)
DRAINAGE EASEMENT
(PER LAKE STREET APARTMENTS PLAT)
SEE SHEET C2.00
FOR CLARIFICATION ON
WALL LOCATIONS AND TYPE
ALONG LAKE STREET
SEE SHEET C2.00 FOR CLARIFICATION ON
WALL LOCATIONS AND TYPE ADJACENT
TO THE EAST OF SLAB PROPERTY
LAKE ST. FRONTAGE
(SEE SHEET C4.03)
LAKE ST. FRONTAGE
(SEE SHEET C4.03)
EA
S
T
W
A
L
L
1
(S
E
E
S
H
E
E
T
C4
.
0
4
)
EA
S
T
W
A
L
L
1
(S
E
E
S
H
E
E
T
C4
.
0
4
)
SOUTH WALL 1
(SEE SHEET C4.04)
SOUTH WALL 1
(SEE SHEET C4.04)
SOUTH WALL 2
(SEE SHEET C4.04)
SOUTH WALL 1
(SEE SHEET C4.04)
EA
S
T
W
A
L
L
2
(S
E
E
S
H
E
E
T
C4
.
0
4
)
SEE SHEET C2.00 FOR CLARIFICATION ON
WALL LOCATIONS AND TYPE ADJACENT
TO THE NORTH OF SLAB PROPERTY
(23
.
2
4
)
28
.
2
2
28
.
6
3
28.
5
3
30.7
2
30
.
6
2
30.
7
2
29.67
30.
3
5
30
.
8
9
30.5
9
29.23
29.1
3
28.56
28.
1
2
24.63 24.53
25.5125.55
28.79
30.
3
7
30.00
30.6
2
(23
.
8
9
)
FFE=27.50
30.09
26.50
26
.
8
2
26.28
28.04
28
.
6
0
24.8
4
28.56
30.8
4
31.0531.00
30.42
24.90
(24.5
9
)
24.91
24
.
9
9
25
.
0
3
25.
1
0
(25.2
4
)
(25
.
1
6
)
(23.4
9
)
23.6
3
28.23
30.62
31.08
30.
4
5
30.
3
1
31.
3
8
34.00
30.58
29.30
30.5
1
31.4831.33
8' SIDEWALK
26.8
0
26.8
0
26.8
0
29.54
29.36
30.33
30.41
29.80
30.7
1
30.6
1
30.10
30.10
29.36
31.20
31.0
0
31.0
0
31.5
0
31.5
0
31.0
3
31.0
3
31.5
0
31.5
0
31
.
0
5
31.6
0
29.7
9
1.
9
%
2.3%
2.6
%
4.2
%
(23.8
7
)
(23.6
6
)
(23.4
1
)
SIDEWALK CHASE
PER DESIGN OF
STADIUM APARTMENTS
CONCRETE CHASE
PER DESIGN OF
STADIUM APARTMENTS
REMOVE LANDSCAPE
WALL PER STADIUM
APARTMENTS
30.18
26.91
27.08 27.18
27.18 27.26
27.36
27.42
27.52
27.59
27.
8
3
27.87
27.90
28.02
28.10
28.10
28.20
28.25
28.
3
4
28.39
28.54
28.55
27.28
27.34
27.44
27.50
27.74
27.79
27.89
27.93
27.98
28.07
28.11
28.16
28.25
28.30
28.42
28.48
28.54
2.1%
29.32
29.41
29.56
29.62
29.76
29.82
29.96
30.04
30.10
30.24
30.3
0
30
.
9
7
29.49
29.94
31
.
1
7
28.51
28.46
28.00
27.83
27.66
28.
5
7
29
.
0
0
30.1
0
29.59
29.9
3
30.9
7
30.7
2
30.6
1
30.7
1
29.75
29.56
29.51
29.4
3
29.1
9
29.2
5
28.57
28.36
27.88
29.5
6
29.59
29.7
3
29.75
29.8
7
30.39
28
.
6
5
27.54
28.00
2.0%
2.
0
%
1.2%
2.0%
0.4%
2.0%
2.0%
FFE = 27.50
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 20 FEET
20 20 40 60
NORTH
C4.01
GR
A
D
I
N
G
P
L
A
N
MATCHLINE
SEE SHEET C4.02
----
KEYMAP: (NTS)
EXISTING DECID. TREE
EXISTING CONIF. TREE
EXISTING LIGHT POLE
EXISTING STUMP
STEXISTING STORM SEWER LINE
EXISTING CURB/GUTTER FLOWLINE
EXISTING EDGE OF ASPHALT
4950
4:1BANK SLOPE
PROPOSED ASPHALT CROSS SLOPE
CONCENTRATED FLOW DIRECTION
PROPOSED SWALE FLOWLINE
PROPOSED OUTFALL CURB/GUTTER FLOWLINE
PROPOSED STORM DRAIN WITH INLET
PROPOSED CONTOUR
EXISTING CONTOUR
79.45PROPOSED FINISH GROUND ELEVATION
(79.45)
EXISTING GROUND ELEVATION
PROPOSED INFLOW CURB/GUTTER FLOWLINE
2.0%
BENCHMARK/BASIS OF BEARING
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE
RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM
ELEVATIONS REQUIRED FOR PROTECTION FROM THE 100-YEAR STORM.
3.EROSION CONTROL PRACTICES, SITE PROTECTION, AND REVEGETATION
METHODS SHALL FOLLOW CITY REGULATIONS.
4.REFER TO SITE PLAN, LANDSCAPE PLAN, AND PLAT FOR ADDITIONAL
INFORMATION.
5.THE CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING AND VERIFYING
ELEVATIONS OF ALL EXISTING SEWER MAINS, WATER MAINS, CURBS,
GUTTERS AND OTHER UTILITIES AT THE POINTS OF CONNECTION SHOWN ON
THE PLANS, AND AT ANY UTILITY CROSSINGS PRIOR TO INSTALLING ANY OF
THE NEW IMPROVEMENTS. IF A CONFLICT EXISTS AND/OR A DESIGN
MODIFICATION IS REQUIRED, THE CONTRACTOR SHALL COORDINATE WITH
THE ENGINEER TO MODIFY THE DESIGN.
6.REFER TO SHEETS C2.00 AND C2.01 FOR CLARIFICATION ON WALL TYPES AND
LOCATIONS.
PROJECT DATUM: NAVD 88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 29-92: APPROXIMATE 300 FEET SOUTH OF
WEST PROSPECT RD. AND SHIELDS ST., ON THE NORTH END OF THE WEST
BRIDGE PARAPET WALL.
ELEVATION: 5025.67
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 28-92: SOUTHWEST CORNER OF WEST
PROSPECT RD. AND CENTRE AVE., ON A WATER VALVE PIT.
ELEVATION: 5010.65
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM.
SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR
VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE
FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED = NAVD88 - 3.17.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE SOUTH LINE OF THE SOUTHWEST QUARTER OF
SECTION 14, TOWNSHIP 7 NORTH, RANGE 69 WEST OF THE 6TH P.M. AS BEARING
SOUTH 89°22'14" EAST
PROPOSED PERMEABLE PAVERS
LEGEND:
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
A1 A2 A3
SEE SHEET C4.03
LAKE ST. FRONTAGESEE SHEET C4.03
SOUTH WALL 2
EAST WALL 2
SOUTH WALL 1
SEE SHEET C4.04
EAST WALL 1
RECORD DRAWING
X
X
X
X
X
X
X X X X X X
XX
X
X
X
X
X
X
X
X X
X
SS
SS
SS
FD
C
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
PROSPECT ROAD
(60' PUBLIC ROW)
10' SIDEWALK
6:1
2.8%
13
:
1
10:
1
18" VERTICAL
CURB AND GUTTER
CONSTRUCT ± 16 L.F.
30" VERTICAL CURB
AND GUTTER
CONSTRUCT ± 14 L.F.
30" VERTICAL CURB
AND GUTTER
RISERS
RISERS
CONSTRUCT ± 31 L.F.
30" VERTICAL CURB
AND GUTTER
CONSTRUCT ± 10 L.F.
30" VERTICAL CURB
AND GUTTER
CONSTRUCT ± 20 L.F.
30" VERTICAL CURB
AND GUTTER
SIDEWALK CHASE
CONCRETE CHASE
TO HAVE METAL PLATE
ALL THE WAY TO
PROSPECT RD.
TH
E
S
L
A
B
RAMP
RISERS
RAMP
BUILDING 2
ROLL OVER CURB
AND GUTTER
HEADWALL
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
DRAINAGE
EASEMENT
26' EMERGENCY ACCESS, NON-VEHICULAR
PUBLIC ACCESS, DRAINAGE & UTILITY
EASEMENT
EMERGENCY
ACCESS EASEMENT
15' UTILITY EASEMENT
20' EMERGENCY ACCESS, NON-VEHICULAR
PUBLIC ACCESS & DRAINAGE EASEMENT
20' EMERGENCY ACCESS & NON-VEHICULAR
PUBLIC ACCESS EASEMENT
ROLL OVER CURB
AND GUTTER
2.
0
%
2.
0
%
2.
0
%
2.
5
%
2.
0
%
2.
3
%
RAMP
10' SIDEWALK
7' SIDEWALK
2.7
%
2.8%
2.7%
2.4%
2.3%
3.
2
%
2.8%
1.8%
2.2%
2.1%
2.8%
2.2%1.5%
6.
7
%
14
.
2
%
TRENCH DRAIN
STADIUM APARTMENTS
EXISTING CONCRETE
CHASE TO BE COVERED
WITH STANDARD SIDEWALK
CHASE LID.
26' EMERGENCY ACCESS, ACCESS,
DRAINAGE & UTILITY EASEMENT
(PER LAKE STREET APARTMENTS PLAT)
5' UTILITY AND
DRAINAGE EASEMENT
(PER THE SLAB
PROPERTY PLAT)
DRAINAGE EASEMENT
(PER LAKE STREET APARTMENTS PLAT)
SEE SHEET C2.01
FOR CLARIFICATION ON
WALL LOCATIONS AND TYPE
ALONG PROSPECT ROAD
SEE SHEET C2.01 FOR CLARIFICATION ON
WALL LOCATIONS AND TYPE ADJACENT
TO THE WEST OF SLAB PROPERTY
ROLL OVER CURB AND GUTTER
(PER STADIUM APARTMENTS)
COURTYARD A1
(SEE SHEET C4.03)
COURTYARD A2
(SEE SHEET C4.03)
COURTYARD A3
(SEE SHEET C4.03)
EA
S
T
W
A
L
L
2
(S
E
E
S
H
E
E
T
C4
.
0
4
)
EA
S
T
W
A
L
L
2
(S
E
E
S
H
E
E
T
C4
.
0
4
)
BLAST WALL
(SEE LANDSCAPE PLANS)
BLAST WALL
(SEE LANDSCAPE PLANS)
BLAST WALL
(SEE LANDSCAPE PLANS)
33.1
5
33.1
5 33.09 32.9
8
32.5
9
32.4
8 32.18 31.8
9
31.4
6
31.0
0
31.4
6
31.4
3
30.24
30.2
1
30.5
8
30.5
8
31.7
0
31.7
0
33.2
3
33.2
3
33.8
1
33.8
1
(2
8
.
3
3
)
30
.
6
2
31.7
7
(3
2
.
2
8
)
(31.90)
(32.9
9
)
(33.1
8
)
33.28
33.21
33.11
33.14
32.95
33.15
(32
.
8
0
)
(33
.
1
6
)
28.8
2
29.43
29.7
329.93
31.
4
8
31.
4
8
30.
3
5
30
.
8
9
30.5
9
30
.
3
7
30.6
2
31.
6
6
31.59
31.46
31.8
4
31.0
5
(31
.
8
2
)
(32.2
9
)
32
.
3
9
32.45
32.9
8
32.3
4
33.1
9
33.0
1
30.4
330.4
5
31.1031.20
31.42
31.38
32.57
32.59
32.75
32.80
33.03
33.0
7
33.27
33
.
2
7
FFE=34.00
(3
1
.
3
0
)
(3
1
.
0
4
)
(3
0
.
6
8
)
(3
1
.
4
3
)
(27
.
6
0
)
(27
.
5
1
)
30.09
33.33
33.12
31.17
(3
0
.
2
2
)
(2
9
.
9
7
)
(2
8
.
8
8
)
(2
9
.
1
2
)
(2
9
.
4
3
)
(2
9
.
5
5
)
31.67
33.
7
1
34.00
32.2
0
32.2
5
(32.1
7
)
(32
.
6
8
)
30.8
4
31.0531.00
30.42
30.6
3
30.62
31.08
30.
4
5
30.
3
1
33.1
2
33.3
3
31.
3
8
34.00
34.00
31.48
32.59
31.0132.50
30.58
31.98
31.3
6
30.15 29.08
28.8
9
32.08
31.54
30.4
6
29.71
31.3
7
31.2
8
31.36
31.
1
1
29.1
0
29.5
1
30.1
5
30.5
6
(28.0
8
)
31.7
1
31.
6
6
34.00
34.00
30.8
5
34.0
0
34.00
34.
0
0
34
.
0
0
31.
1
5
30.5
1
31.4831.33
32.38
31.81
33.3
3
33.09
33.3
2
33.18 33.28
30.6
1
32.79
32.61 33.11
32.95
31.24
30.34
30.05
31.34
31.20
31.5
0
31.5
0
31.0
3
31.0
3
31.5
0
31.5
0
31.
0
5
31.6
0
33.0
1
33.5
2
32.5
1
33.3
2
32.2
2
33.1
4
34.0
0
34.0
0
34.0
0
34.0
0
1.
9
%
2.3%
2.6
%
4.2
%
29.98
31.57
34.00 33
.
8
9
33.
7
5
12
:
1
12
:
1
20
:
1
17
:
1
30.3
9
33.3
2
33.3
3
33.0
0
30
.
9
7
31
.
1
7
31.99
31.57
33.14
33.14
30.6
1
2.
0
%
1.2%
2.0%
32.90
32.83
33.1
0
33.0
3
32.57
32.7
7
32.6
9
32.49
5.0%
5.0%1.4%
4.6%
5.1%
32.9
5
32.
8
0
32.64
FFE = 33.99
FFE = 31.50
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 20 FEET
20 20 40 60
NORTH
C4.02
GR
A
D
I
N
G
P
L
A
N
MATCHLINE
SEE SHEET C4.01
----
KEYMAP: (NTS)
EXISTING DECID. TREE
EXISTING CONIF. TREE
EXISTING LIGHT POLE
EXISTING STUMP
STEXISTING STORM SEWER LINE
EXISTING CURB/GUTTER FLOWLINE
EXISTING EDGE OF ASPHALT
4950
4:1BANK SLOPE
PROPOSED ASPHALT CROSS SLOPE
CONCENTRATED FLOW DIRECTION
PROPOSED SWALE FLOWLINE
PROPOSED OUTFALL CURB/GUTTER FLOWLINE
PROPOSED STORM DRAIN WITH INLET
PROPOSED CONTOUR
EXISTING CONTOUR
79.45PROPOSED FINISH GROUND ELEVATION
(79.45)
EXISTING GROUND ELEVATION
PROPOSED INFLOW CURB/GUTTER FLOWLINE
2.0%
BENCHMARK/BASIS OF BEARING
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE
RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM
ELEVATIONS REQUIRED FOR PROTECTION FROM THE 100-YEAR STORM.
3.EROSION CONTROL PRACTICES, SITE PROTECTION, AND REVEGETATION
METHODS SHALL FOLLOW CITY REGULATIONS.
4.REFER TO SITE PLAN, LANDSCAPE PLAN, AND PLAT FOR ADDITIONAL
INFORMATION.
5.THE CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING AND VERIFYING
ELEVATIONS OF ALL EXISTING SEWER MAINS, WATER MAINS, CURBS,
GUTTERS AND OTHER UTILITIES AT THE POINTS OF CONNECTION SHOWN ON
THE PLANS, AND AT ANY UTILITY CROSSINGS PRIOR TO INSTALLING ANY OF
THE NEW IMPROVEMENTS. IF A CONFLICT EXISTS AND/OR A DESIGN
MODIFICATION IS REQUIRED, THE CONTRACTOR SHALL COORDINATE WITH
THE ENGINEER TO MODIFY THE DESIGN.
6.REFER TO SHEETS C2.00 AND C2.01 FOR CLARIFICATION ON WALL TYPES AND
LOCATIONS.
PROJECT DATUM: NAVD 88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 29-92: APPROXIMATE 300 FEET SOUTH OF
WEST PROSPECT RD. AND SHIELDS ST., ON THE NORTH END OF THE WEST
BRIDGE PARAPET WALL.
ELEVATION: 5025.67
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 28-92: SOUTHWEST CORNER OF WEST
PROSPECT RD. AND CENTRE AVE., ON A WATER VALVE PIT.
ELEVATION: 5010.65
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM.
SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR
VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE
FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED = NAVD88 - 3.17.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE SOUTH LINE OF THE SOUTHWEST QUARTER OF
SECTION 14, TOWNSHIP 7 NORTH, RANGE 69 WEST OF THE 6TH P.M. AS BEARING
SOUTH 89°22'14" EAST
PROPOSED PERMEABLE PAVERS
LEGEND:
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
A1 A2 A3
SEE SHEET C4.03
LAKE ST. FRONTAGESEE SHEET C4.03
SOUTH WALL 2
EAST WALL 2
SOUTH WALL 1
SEE SHEET C4.04
EAST WALL 1
RECORD DRAWING
33.90
FFE=34.00
FFE=34.00
33.33
34.00
32.7
9
33.0
0
32.7
9
33.33
33.3
3
33.3
3
33.33
32.9
4
32.7
9
32.
9
8
32.84
32
.
3
0
32.13
32.07
33
.
1
3
32.
2
1
33.
4
9
33.3
3
32
.
5
8
33.7
2
33.9
1
33
.
5
7
33.5
6
33.3
1
33
.
2
1
33.1
3
33.2
2
33.1
932.8
6
33.1
2 33.
1
0
33.3
3
32.44
33.32
34.00
SEAT WALL
(BY OTHERS)
8" DOME GRATE
8" DOME GRATE
8" DOME GRATE
8" SOLID GRATE
33
.
3
3
33.33 33.3
3
33.33
33.33
33.33
33.27
33.33
33.33
34.
0
0
33.98
33.26
33.03
33.1633.16
33.14
33.33
33.33
33.3
3
8" DOME GRATE
8" STANDARD GRATE
33.2
2
33
.
4
6
33.2
4
33.3
3
33.4
0
33.2
4
33
.
6
7
33.98
32.9633.0333.0833.22
3.1%
4.1%
4.2%3.7%
8.3%
4.7
%
15.4%
17.4%
4.2%
5.9%
21.
2
%
16
.
0
%
8.0%
13.6%
3.1%
10
.
9
%
5.9%
2.4
%
33.5
6
33.6
2
33.7
9
MONITORING WELL
W/ SOLID GRATE
8" SOLID GRATE
8" SOLID GRATE
FFE = 33.99
FFE=34.00 FFE=34.00
33.3
3
33.3
3
33.3
3
32.9
4
32.0
5
32.94
32.05
31.7
7
32.05
32.93
32.
9
2
32.88
33.3
3
32.0
5
32.0
5
33.2
6
33.4
0
33
.
0
6
33
.
0
6
33.19
32.0
7
33.3
3
33.9
8
33.9
0
34.0
0
33.9
0
33.4
0
33.3
0
33.4
4
33.1
9
33.2
4
32.9532.9
0
32.8
5
33.0
3
32.
5
3
33.3
6
32.9
8
32.5
9
33.3
3
33.3
3
33.3
3
33.3
3
33.9
8
SEAT WALL
(BY OTHERS)
8" DOME GRATE
8" SOLID GRATE
8" DOME GRATE
12" PEDESTRIAN
GRATE
32.6
6
32.6
6
33.2
7
33.33
33.33
33.
3
3
33.33
33.3
3
33.3
3
33.3
3
SEAT WALL
(BY OTHERS)
33.2
3
34.0
0
32.8
1
2-RISERS
32.3
1
32.2
5
32.1
7
32.5
7
32.0
5
32.08
8" DOME GRATE
12.5%
5.9%
5.6%
5.
3
%
5.2%
2.
8
%
3.0%
2.3
%
33.1
2
33.2
3
1.8
%
2.0
%
1.9
%
7.6%
10.0%
MONITORING WELL
W/ SOLID GRATE
32.1
0
17.3%
5.5%
5.
2
%
5.5%
5.6%
FFE = 33.99
FFE=34.00
FFE=34.00
33.
3
3
33.2
7
33.2
6
33.
1
9
33.0
1
32.7
7
33.2
9
33.88
33.9
8
33.3
3
33.9
8
33.9
8
33.
8
8
33.98
34.00
33.3
1
33.1
1
33.1
1
33.5
2
33.34
32.6
4
33.
7
4
33.2
2
33.30
33.2
7
32.69
33.1
2
32.5
3
33.3
0
33.3
4
33.4133.1
7
33.1
7
33.9
8
33.4
5
33.17
33.16
31.8431.84
SEAT WALL
(BY OTHERS)
12" PEDESTRIAN GRATE
8" DOME GRATE
8" DOME GRATE
8" DOME GRATE
8" SOLID GRATE
33.4
8
33
.
4
8
33.4
8
33.
4
8
31.29
31.3
4
33.4
3
33.
9
9
33.98
33.4
3
34.00
33.1
1
34.2
9
33.8
8
32.
7
7
33.1
2
32
.
6
2
33.2
4
33.4
2
33.5
2
33.5
2
33.9
8
33.
8
8
33.0
2
33.
8
8
33.
8
8
13.3%
2.0%
12.8%
2.0%
4.4%
6.9%
5.0%
3.0%
6.2%
2.0%
0.
5
%
5.
0
%
4.8%
9.2%
20
.
7
%
MONITORING WELL
W/ SOLID GRATE
33.4
4
33.4
4
33.4
8
33.48
33.
4
5
33.4
4
2 RISERS
FFE = 33.99
(24
.
4
9
)
24.
9
8
27.2
4
25.0
1
27.2
4
27.3025.66
25.4
2
25.20 25.0
2
27.2
4
27.2
4
27
.
4
9
27.
4
9
27
.
5
0
27.
5
0
27.
4
2
27.4
8
27.5
0
27.50
27.34
26.05
27.
5
0
24.81
24.
7
5
26.9
9
27.3
2
24.
8
6
27.
2
8
24.8
5
24.8
3
24.6
6
27.50
27.
2
8
24.7
6
24.64
24.6
7
24.75
27.2
8
24.6
4
24.8
0
24.51
24.4
9
24.47
24.59 24.57
27.29
24.37 24.20
24.3
3
24.40
25.
8
2
26.
8
3
25.84
25.8
0
25.9
2
27.
1
9
27.2
7
27.2
3
24.22
27.36
24.16
24.1
3
24.1
6
24
.
1
0
24.1
6
27.37
27.
5
0
27.4
2
27.27
24.65
27.42 27.4
2
27.
4
2
27.42 26.69
26.92
25.
9
2
26.92
26.83
26.8
3
26.8
3
27.4227.4127.41
26.7
8
24.7
2
24.
6
9
24.6
9
24.7
8
24.7
5
27
.
4
2
27.
5
0
24.
0
9
27.37
25.26
24.1
4
LAKE STREET
(60' PUBLIC ROW)
RAMP
RAMP
4.4%
4.4%
RISERS
RISERS
BIKE RACK (TYP.)
RISERS
2.
0
%
2.
0
%
11.6
%
2.
0
%
1.
6
%
2.
0
%
2.
2
%
2.8
%
2.
0
%
4.9%
2.
1
%
2.
0
%
2.
0
%
2.
0
%
2.
0
%
2.
0
%
FFE=27.50FFE=27.50FFE=27.50 FFE=27.50 FFE=27.50
25.0
2
25.1
9
27.
5
0
27.
4
8
27
.
5
0
27
.
5
0
27
.
5
0
27.4
8
26.8
4
26.8
6
27.
3
2
24.63
27.
2
9
24.50
25.84
24.2825.80
27.5
0
27.5
027.
5
0
26.
9
2
27.
5
0
27.5
0
27.5
0
27
.
5
0
27
.
4
8
27
.
5
0
24.
9
8
27.4327.50
27.41
27.44
27.
4
9
RAILING (TYP.)
(SEE LANDSCAPE PLANS)
SANDSTONE BOULDER (TYP.)
(SEE LANDSCAPING PLANS)
4' PRIVATE WALK
8' SIDEWALK
8' SIDEWALK
30" VERTICAL
CURB AND GUTTER
RAMP
SANDSTONE BOULDERS (TYP.)
(SEE LANDSCAPE PLANS)
SEE SHEET C2.00 FOR
CLARIFICATION ON WALL
TYPE AND EXACT LOCATION
25.
1
1
24.
8
5
24.
8
0
24.
9
0
24.
8
4 25.8
9
24.3
0
27
.
5
0
27.5
0
26.8
3
26.8
3
27.4
1
27.4
9
27.4
9
27.5
0
27.5027.5
027.50
27
.
4
0
26.17
27.50
27.
4
6
27.
4
6
27.
4
4
27.42
27.
5
0
(2
3
.
6
6
)
(2
3
.
8
7
)
27.4
226.8
2
26.9
1
27.0
4
26.11
25.72
3-RISERS
4-RISERS
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
KEYMAP: (NTS)
EXISTING DECID. TREE
EXISTING CONIF. TREE
EXISTING LIGHT POLE
EXISTING STUMP
STEXISTING STORM SEWER LINE
EXISTING CURB/GUTTER FLOWLINE
EXISTING EDGE OF ASPHALT
4950
4:1BANK SLOPE
PROPOSED ASPHALT CROSS SLOPE
CONCENTRATED FLOW DIRECTION
PROPOSED SWALE FLOWLINE
PROPOSED OUTFALL CURB/GUTTER FLOWLINE
PROPOSED STORM DRAIN WITH INLET
PROPOSED CONTOUR
EXISTING CONTOUR
79.45PROPOSED FINISH GROUND ELEVATION
(79.45)
EXISTING GROUND ELEVATION
PROPOSED INFLOW CURB/GUTTER FLOWLINE
2.0%
BENCHMARK/BASIS OF BEARING
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE
RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM
ELEVATIONS REQUIRED FOR PROTECTION FROM THE 100-YEAR STORM.
3.EROSION CONTROL PRACTICES, SITE PROTECTION, AND REVEGETATION
METHODS SHALL FOLLOW CITY REGULATIONS.
4.REFER TO SITE PLAN, LANDSCAPE PLAN, AND PLAT FOR ADDITIONAL
INFORMATION.
5.THE CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING AND VERIFYING
ELEVATIONS OF ALL EXISTING SEWER MAINS, WATER MAINS, CURBS,
GUTTERS AND OTHER UTILITIES AT THE POINTS OF CONNECTION SHOWN ON
THE PLANS, AND AT ANY UTILITY CROSSINGS PRIOR TO INSTALLING ANY OF
THE NEW IMPROVEMENTS. IF A CONFLICT EXISTS AND/OR A DESIGN
MODIFICATION IS REQUIRED, THE CONTRACTOR SHALL COORDINATE WITH
THE ENGINEER TO MODIFY THE DESIGN.
6.REFER TO SHEETS C2.00 AND C2.01 FOR CLARIFICATION ON WALL TYPES AND
LOCATIONS.
PROJECT DATUM: NAVD 88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 29-92: APPROXIMATE 300 FEET SOUTH OF
WEST PROSPECT RD. AND SHIELDS ST., ON THE NORTH END OF THE WEST
BRIDGE PARAPET WALL.
ELEVATION: 5025.67
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 28-92: SOUTHWEST CORNER OF WEST
PROSPECT RD. AND CENTRE AVE., ON A WATER VALVE PIT.
ELEVATION: 5010.65
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM.
SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR
VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE
FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED = NAVD88 - 3.17.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE SOUTH LINE OF THE SOUTHWEST QUARTER OF
SECTION 14, TOWNSHIP 7 NORTH, RANGE 69 WEST OF THE 6TH P.M. AS BEARING
SOUTH 89°22'14" EAST
PROPOSED PERMEABLE PAVERS
LEGEND:
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
A1 A2 A3
SEE SHEET C4.03
LAKE ST. FRONTAGESEE SHEET C4.03
SOUTH WALL 2
EAST WALL 2
SOUTH WALL 1
SEE SHEET C4.04
EAST WALL 1
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 20 FEET
20 20 40 60
NORTH
COURTYARD A1 COURTYARD A2 COURTYARD A3
C4.03
DE
T
A
I
L
G
R
A
D
I
N
G
P
L
A
N
LAKE ST. FRONTAGE
----
MA
T
C
H
L
I
N
E
S
E
E
E
A
S
T
W
A
L
L
1
RECORD DRAWING
X
X
X
X
26.1
6
26.0
9
30.3
4
25.9
1
30.1
3
28.8
0
31.9
9
TH
E
S
L
A
B
29.00
SEE SHEET C2.00 FOR
CLARIFICATION ON WALL
TYPE AND EXACT LOCATION
32.0
0
32.0
0
32.0
0
26.8
0
27.4
1
28.2
0
30.4
1
31.9
1
31.9
1
31.9
1
24.57
23
.
6
7
27.
5
0
27.50
VAULT
ELEC
25.9
3
25.6
8
24.48
24.4
8
(23
.
8
8
)
(23
.
8
9
)
27.0
7
27.5
0
27.5
0
27.50
27.3
4
27.50
27.50
27.5
0
27.5
0
27.4
1
???(24
.
0
8
)
(24
.
1
0
)
27.2
0
27.2
2 27.
2
0
24.3
2
25.
7
526.0
0
14
.
1
%
???
7.0
%
2.0%
2.0%
2.0%
???
7.
9
%
RISERS
RAMP
FFE=27.50
FFE=27.50
TH
E
S
L
A
B
26.
5
9
23.
6
9
23.91
26.
5
9
DRAIN BASIN
27.0
0
27.5
0
26.80
26.8
0
27.5
0
26.8
0
27.5
0
26.7
2
27.5
0
4'
RAILING (TYP.)
(SEE LANDSCAPE PLANS)
CONCRETE CHASE
CONCRETE
CHASE
27.4
2
25.6
1
27.3
9
26.9
8
24
.
5
6
24.53
24.30
27.14 24.3
327.22
27.3
3
2.0%
2.
0
%
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
MONITORING WELL
TRAFFIC RATED
X
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
(28
.
0
2
)
(27
.
9
3
)
(27
.
7
7
)
(27
.
5
9
)
(27
.
4
1
)
(27
.
1
0
)
(27
.
1
9
)
(27
.
6
9
)
(27
.
9
5
)
(27
.
7
0
)
(27
.
2
0
)
(27
.
6
1
)
(27
.
9
0
)
(28
.
0
0
)
(28.0
5
)
32.4
4
32.3
0
31.7
7
31.3
0
29.6
9
28.4
9
28.4
3
31.15
TH
E
S
L
A
B
SEE SHEET C2.01 FOR
CLARIFICATION ON WALL
TYPE AND EXACT LOCATION
30.5
8
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
30.61
28.02
28.11
28.
4
2
30
.
6
8
30.70
(28
.
3
0
)
28.3
2
(28
.
6
2
)
30.6
0
(28
.
4
5
)
(28
.
6
2
)
(28
.
0
2
)
30.7
7
30.8
7
31.0
0
30.8
8
31.0
0
30.68 30.68
31.16
31.15
RISERS
TH
E
S
L
A
B
29.6
0
26.4
5
30.7
0
31.00
30.5
4
30.6
2
30.7
0
31.2
0
31.2
3
31.4
3
31.4
5
31.6
5
31.6
7
31.8
7
31.8
9
30.9
6
30.6
8
30.68
30
.
7
2
31
.
0
0
31.00
31.0
0
30.6
2
30.6
2
30.6
2
30.5
8
30.4
6
31.5
5
31.3
3
31.1
1
30.88 30.69
2.0%2.0%
2.0%
2.0%
2.0%
2.0%
31.7
8
5:1
6:1
11:1
20:1
30.8
9
30.9
8
30.7
8
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
KEYMAP: (NTS)
EXISTING DECID. TREE
EXISTING CONIF. TREE
EXISTING LIGHT POLE
EXISTING STUMP
STEXISTING STORM SEWER LINE
EXISTING CURB/GUTTER FLOWLINE
EXISTING EDGE OF ASPHALT
4950
4:1BANK SLOPE
PROPOSED ASPHALT CROSS SLOPE
CONCENTRATED FLOW DIRECTION
PROPOSED SWALE FLOWLINE
PROPOSED OUTFALL CURB/GUTTER FLOWLINE
PROPOSED STORM DRAIN WITH INLET
PROPOSED CONTOUR
EXISTING CONTOUR
79.45PROPOSED FINISH GROUND ELEVATION
(79.45)
EXISTING GROUND ELEVATION
PROPOSED INFLOW CURB/GUTTER FLOWLINE
2.0%
BENCHMARK/BASIS OF BEARING
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE
RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM
ELEVATIONS REQUIRED FOR PROTECTION FROM THE 100-YEAR STORM.
3.EROSION CONTROL PRACTICES, SITE PROTECTION, AND REVEGETATION
METHODS SHALL FOLLOW CITY REGULATIONS.
4.REFER TO SITE PLAN, LANDSCAPE PLAN, AND PLAT FOR ADDITIONAL
INFORMATION.
5.THE CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING AND VERIFYING
ELEVATIONS OF ALL EXISTING SEWER MAINS, WATER MAINS, CURBS,
GUTTERS AND OTHER UTILITIES AT THE POINTS OF CONNECTION SHOWN ON
THE PLANS, AND AT ANY UTILITY CROSSINGS PRIOR TO INSTALLING ANY OF
THE NEW IMPROVEMENTS. IF A CONFLICT EXISTS AND/OR A DESIGN
MODIFICATION IS REQUIRED, THE CONTRACTOR SHALL COORDINATE WITH
THE ENGINEER TO MODIFY THE DESIGN.
6.REFER TO SHEETS C2.00 AND C2.01 FOR CLARIFICATION ON WALL TYPES AND
LOCATIONS.
PROJECT DATUM: NAVD 88
BENCHMARK #1:
CITY OF FORT COLLINS BENCHMARK 29-92: APPROXIMATE 300 FEET SOUTH OF
WEST PROSPECT RD. AND SHIELDS ST., ON THE NORTH END OF THE WEST
BRIDGE PARAPET WALL.
ELEVATION: 5025.67
BENCHMARK #2:
CITY OF FORT COLLINS BENCHMARK 28-92: SOUTHWEST CORNER OF WEST
PROSPECT RD. AND CENTRE AVE., ON A WATER VALVE PIT.
ELEVATION: 5010.65
PLEASE NOTE: THIS PLAN SET IS USING NAVD88 FOR A VERTICAL DATUM.
SURROUNDING DEVELOPMENTS HAVE USED NGVD29 UNADJUSTED FOR THEIR
VERTICAL DATUMS.
IF NGVD29 UNADJUSTED DATUM IS REQUIRED FOR ANY PURPOSE, THE
FOLLOWING EQUATION SHOULD BE USED: NGVD29 UNADJUSTED = NAVD88 - 3.17.
BASIS OF BEARINGS
THE BASIS OF BEARINGS IS THE SOUTH LINE OF THE SOUTHWEST QUARTER OF
SECTION 14, TOWNSHIP 7 NORTH, RANGE 69 WEST OF THE 6TH P.M. AS BEARING
SOUTH 89°22'14" EAST
PROPOSED PERMEABLE PAVERS
LEGEND:
UP
D.S.D.S.
R.D.
D.S.
D.S.D.S.
D.S.
D.S.
D.S.R.D.
D.S.
X
A1 A2 A3
SEE SHEET C4.03
LAKE ST. FRONTAGESEE SHEET C4.03
SOUTH WALL 2
EAST WALL 2
SOUTH WALL 1
SEE SHEET C4.04
EAST WALL 1
GRAPHIC SCALE:
( IN FEET )
0
1 INCH = 20 FEET
20 20 40 60
C4.04
DE
T
A
I
L
G
R
A
D
I
N
G
P
L
A
N
NORTH
NORTH
----
SOUTH WALL 2
SOUTH WALL 1
MATCHLINE SEE SOUTH WALL 2
MATCHLINE SEE SOUTH WALL 1
MA
T
C
H
L
I
N
E
S
E
E
E
A
S
T
W
A
L
L
2
MATCHLINE SEE SOUTH WALL 2
NORTHNORTH
EAST WALL 1 EAST WALL 2
MA
T
C
H
L
I
N
E
S
E
E
LA
K
E
S
T
R
E
E
T
F
R
O
N
T
A
G
E
RECORD DRAWING
W
W
W
W
W
W
W
W
W
W
W W W
WW
HYD
W W W W
W
W
ST
ST
ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
D
UD
E E E
E
E
E
E
E
E
E
E
E
FD
C
UD
UD
UD
UD
UD
UD
UD
MONITORING WELL
TRAFFIC RATED
E
E
E
0.5
%
SG
0.5
%
SG
0.5
%
SG
28.6
0
FG
28.6
3FG
29.9
4
FG29.93FG
25
.
5
5
SG
25.5
4
SG
25.1
4
SG
25.1
3
SG
78
.
1
6
L
F
6
"
P
E
R
F
O
R
A
T
E
D
P
V
C
@
0
.
5
0
%
STORM LINE B9
(SEE SHEET C3.06)
UNDERDAIN
(SEE SHEET C3.03)
INSPECTION
PORTS (2)
25.55
AB (SG)
25.
5
3
AB
(
S
G
)
25.15
AB (SG
)
25.14
AB (SG)
30
.
7
8
AB
(
F
G
)
30.72AB (F
G
)
28
.
6
9
AB
(
F
G
)
28
.
6
9
AB
(
F
G
)
MONITORING WELL B10
INV. IN=5028.13 (E)
INV. OUT=5025.54 (N)
FG=5030.32
DRAIN BASIN B9
INV. IN=5027.02 (W)
INV. OUT=5025.42 (N)
FG=5029.77
INLET B8
INV. IN=5025.14 (SE)
INV. IN=5025.14 (S)
INV. OUT=5025.14 (NW)
FG=5028.72
RIM = 5029.93
INV. = 5025.47 (N)
INV. = 5026.95 (W)
RIM = 5028.66
INV. = 5025.11 (N)
INV. = 5025.05 (S)
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
D D
D
DD
STST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
UD
UD
UD
UD
UD
UD
UD
UD
X
X
X
X
X
X
X
0.3%
SG
0.3%
SG
0.3%
SG6.25 LF 4" PVC @ 2.00%
32.9
8FG33.01
FG
32.5
4FG 32.6
7
FG
28.96
SG
29
.
0
0
SG
29.1
6
SG
29.1
2
SG
2.53 LF 4" PVC @ 2.00%
12.02 LF 4" PVC @ 2.00%
4.56 LF 4" PVC @ 2.00%
18
.
7
3
L
F
4
"
P
V
C
@
2
.
0
0
%
2.67 LF 4" PVC @ 2.00%
4.67 LF
4" PVC
@ 2.00%
29
.
4
6
L
F
4"
P
V
C
@
2
.
0
0
%
22
.
1
3
L
F
4
"
P
V
C
@
2
.
0
0
%
4.67 LF 4" PVC @ 2.00%
INSPECTION PORTS (2)
27.72
AB (SG)
27
.
6
2
AB
(
S
G
)
28.70
AB (SG)
28.28
AB (SG
)
33
.
0
5
AB
(
F
G
)
33
.
0
0
AB
(
F
G
)
32.
5
5AB
(
F
G
)
32.
5
8AB
(
F
G
)
DRAIN BASIN A10
INV. IN=5029.11 (N)
INV. IN=5029.11 (S)
INV. OUT=5029.11 (E)
FG=5032.49
DRAIN BASIN A9
INV. IN=5029.08 (W)
INV. IN=5028.58 (NE)
INV. IN=5028.58 (E)
INV. OUT=5028.58 (S)
FG=5032.54
DRAIN BASIN A11
INV. IN=5029.28 (N)
INV. IN=5029.28 (E)
INV. OUT=5029.28 (S)
FG=5032.99
WQ STRUCTURE A11-1
INV. IN=5029.20 (E)
INV. OUT=5029.20 (W)
FG=5032.94
90° ELBOW A11-2
INV.=5029.33
FG=5033.14
ROOF LEADER A9-5
INV. OUT=5028.96 (W)
FG=5033.07
90° ELBOW A9-4
INV.=5028.91
FG=5032.86
4''x4'' TEE A9-1
INV.=5028.67
FG=5032.87
90° ELBOW A9-2
INV.=5029.04
FG=5032.89
ROOF LEADER A9-3
INV. OUT=5029.10 (W)
FG=5033.28
ROOF DRAIN A11-3.1
INV. OUT=5029.86 (W)
FG=5033.32
4''x4'' TEE A11-3
INV.=5029.77
FG=5033.08
90° ELBOW A11-4
INV.=5030.36
FG=5032.92
ROOF LEADER A11-5
INV. OUT=5030.45 (W)
FG=5033.30
INV. = 5028.92 (W)
INV. = 5029.23 (E)
INV. = 5029.08 (S)
RIM = 5033.02
INV. = 5029.29 (N)
INV. = 5029.28 (E)
INV. = 5029.11 (S)
INV. = 5028.89 (N)
INV. = 5029.03 (S)
INV. = 5028.80 (E)
RIM = 5032.58
INV. = 5028.87 (N)
INV. = 5028.54 (NE)
INV. = 5028.61 (E)
INV. = 5028.61 (S)
ST ST ST ST ST ST ST
ST
ST ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
UD
UD
UD
0.3%
SG
0.3%
SG
10.90 LF
4" PVC
@ 2.00%
29
.
9
3
L
F
6
"
P
E
R
F
O
R
A
T
E
D
P
V
C
@
0
.
2
0
%
12
.
1
9
L
F
8"
P
V
C
@
2
.
0
0
%
13.51 LF 8" PVC @ 2.00%
20
.
2
4
L
F
8
"
P
V
C
@
2
.
0
0
%
10.92 LF
8" PVC
@ 2.00%
9.97 LF
8" PVC
@ 2.00%
33.4
5FG 33.87
FG
32.85
FG
33.2
4FG
28.4
2
SG
28.5
2
SG
28.48
SG
18.03 L
F
4
"
P
V
C
@
2
.
0
0
%
21.95 LF
4
"
P
V
C
@
2
.
0
0
%
5.83 LF 4" PVC @ 2.00%
21.14 LF 4" PVC @ 2.00%
2.51 LF 4" PVC @ 2.00%
2.51 LF 4" PVC @ 2.00%
30
.
7
5
L
F
4
"
P
V
C
@
2
.
0
0
%
2.67 LF 4" PVC @ 2.00%
7.28 LF 4" PVC @ 2.00%
4.53 LF 4" PVC @ 2.00%
23
.
4
7
L
F
4
"
P
V
C
@
2
.
0
0
%
2.53 LF 4" PVC @ 2.00%
14
.
3
8
L
F
1
2
"
P
V
C
@
0
.
5
0
%
INSPECTION
PORT
28.4
6
SG
28.41
AB (SG)
28.4
1AB (
S
G
)
28.27AB (S
G
)
33
.
5
1
AB
(
F
G
)
33.6
6
AB (
F
G
)
33.50
AB (F
G
)
33
.
5
2
AB
(
F
G
)
Outlet Structure A7-1
INV. IN=5028.92 (W)
INV. IN=5028.42 (NE)
INV. OUT=5028.42 (S)
FG=5033.13
WQ STRUCTURE A7-2
INV. IN=5028.94 (N)
INV. IN=5028.94 (W)
INV. OUT=5028.94 (E)
FG=5032.86
DRAIN BASIN A7-4
INV. IN=5029.23 (E)
INV. IN=5029.23 (N)
INV. OUT=5029.23 (W)
FG=5033.62
STRUCTURE A7-3
INV. IN=5029.03 (W)
INV. IN=5029.03 (E)
INV. OUT=5029.03 (S)
FG=5032.58
ROOF LEADER A7-3.1
INV. OUT=5029.25 (E)
FG=5033.33
UD 45° BEND A7
INV. IN=5028.42 (N)
INV. OUT=5028.42 (SW)
FG=5033.24
MONITORING WELL A7
INV. OUT=5028.48 (S)
FG=5033.79
DRAIN BASIN A7-5
INV. IN=5029.48 (N)
INV. IN=5029.48 (E)
INV. OUT=5029.48 (S)
FG=5032.13
DRAIN BASIN A7-5.1
INV. OUT=5029.75 (W)
FG=5032.79
DRAIN BASIN A7-6
INV. IN=5029.88 (E)
INV. IN=5029.88 (W)
INV. OUT=5029.88 (S)
FG=5032.79
DRAIN BASIN A7-4.1
INV. IN=5029.45 (S)
INV. IN=5029.45 (E)
INV. OUT=5029.45 (W)
FG=5033.56
ROOF LEADER A7-6.1
INV. OUT=5030.24 (W)
FG=5033.31
ROOF LEADER A7-7
INV. OUT=5030.32 (E)
FG=5033.29
ROOF LEADER A7-4.1.1
INV. OUT=5029.57 (W)
FG=5033.33
4''x4'' TEE A7-4.2
INV.=5029.87
FG=5033.73
ROOF LEADER A7-4.2.1
INV. OUT=5029.92 (W)
FG=5033.78
ROOF LEADER A7-4.4
INV. OUT=5030.54 (W)
FG=5033.33
90° ELBOW A7-4.3
INV.=5030.49
FG=5033.24
ROOF LEADER A7-2.3
INV. OUT=5029.23 (E)
FG=5033.31
90° ELBOW A7-2.2
INV.=5029.18
FG=5033.20
4''x4'' TEE A7-2.1
INV.=5029.03
FG=5033.13
90° ELBOW A7-2.4
INV.=5029.50
FG=5033.29
ROOF LEADER A7-2.5
INV. OUT=5029.55 (E)
FG=5033.31
12''x12'' TEE A7
INV.=5028.34
FG=5033.04
RIM = 5032.95
INV. = 5029.85 (E)
INV. = 5029.85 (W)
INV. = 5029.85 (S)
RIM = 5032.92
INV. = 5029.47 (N)
INV. = 5029.47 (E)
INV. = 5029.47 (S)
RIM = 5032.85
INV. = 5029.85 (W)
RIM = 5033.58
INV. = 5029.23 (E)
INV. = 5029.23 (W)
INV. = 5029.23 (N)
RIM = 5033.59
INV. = 5029.49 (E)
INV. = 5029.49 (W)
INV. = 5029.49 (S)
RIM = 5032.61
INV. = 5029.01 (E)
INV. = 5029.01 (W)
INV. = 5029.01 (S)
RIM = 5033.51
INV. = 5028.41 (NE)
INV. = 5029.01 (W)
INV. = 5028.41 (S)
28.40
AB (SG)
RIM = 5032.87
INV. = 5029.00 (E)
INV. = 5028.90 (W)
INV. = 5028.90 (N)
ST ST ST ST ST ST ST
ST
STSTST
ST
ST
ST ST ST
ST
ST
ST
ST
ST
ST
ST
ST
ST
G
UD
UD
UD
0.3%
SG
0.3%
SG
11.12 LF
4" PVC
@ 5.00%
29
.
9
3
L
F
6
"
P
E
R
F
O
R
A
T
E
D
P
V
C
@
0
.
2
0
%
19
.
8
6
L
F
8
"
P
V
C
@
2
.
0
0
%
34.0
1FG
34.0
1FG 34.0
1
FG
34.0
1
FG
28.23
SG
28.31
SG28.3
5
SG
28.2
7
SG
5.57 LF 4" PVC @ 5.00%
21.01 LF 4" PVC @ 2.00%
2.51 LF 4" PVC @ 5.00%
30.72 LF 4" PVC @ 2.00%
2.51 LF 4" PVC @ 2.00%
2.51 LF 4" PVC @ 2.00%
5.04 LF 4" PVC @ 2.00%
6.76 LF 4" PVC @ 2.00%
23.99 LF 4" PVC @ 2.00%
2.51 LF 4" PVC @ 2.00%
9.
5
8
L
F
4"
P
V
C
@
2
.
0
0
%
19.11 LF 4" PVC @ 2.00%19.56 LF 4" PVC @ 2.00%
14
.
3
8
L
F
1
2
"
P
V
C
@
0
.
5
0
%
INSPECTION
PORT
28.3
7AB (
S
G
)
28.
3
3AB
(
S
G
)
28
.
2
6
AB
(
S
G
)
28.2
4AB (
S
G
)
33.03
AB (F
G
)
33.47
AB (F
G
)
32
.
7
7
AB
(
F
G
)
32.91
AB (F
G
)
DRAIN BASIN A6-3.2
INV. IN=5029.26 (E)
INV. IN=5029.26 (S)
INV. OUT=5029.26 (W)
FG=5032.81
STRUCTURE A6-3
INV. IN=5028.84 (W)
INV. IN=5028.84 (E)
INV. IN=5028.84 (N)
INV. OUT=5028.84 (S)
FG=5032.88
WQ STRUCTURE A6-2
INV. IN=5028.75 (N)
INV. IN=5028.75 (W)
INV. OUT=5028.75 (E)
FG=5032.53
ROOF LEADER A6-3.1
INV. OUT=5029.40 (E)
FG=5033.33
UD 45° BEND A6
INV. IN=5028.23 (N)
INV. OUT=5028.23 (SW)
FG=5032.98
Monitoring Well A6
INV. OUT=5028.29 (S)
FG=5033.59
DOME GRATE A6-4
INV. IN=5029.24 (N)
INV. OUT=5029.24 (S)
FG=5031.77
ROOF LEADER A6-3.2.1
INV. OUT=5029.54 (W)
FG=5033.33
4''x4'' TEE A6-3.3
INV.=5029.68
FG=5033.43
ROOF LEADER A6-3.3.1
INV. OUT=5028.80 (W)
FG=5033.74
90° ELBOW A6-3.4
INV.=5030.29
FG=5033.16
ROOF LEADER A6-3.5
INV. OUT=5030.34 (W)
FG=5033.30ROOF LEADER A6-2.3
INV. OUT=5029.04 (E)
FG=5033.28
90° ELBOW A6-2.2
INV.=5028.99
FG=5033.01
4''x4'' TEE A6-2.1
INV.=5028.85
FG=5033.03
90° ELBOW A6-2.4
INV.=5029.33
FG=5033.22
ROOF LEADER A6-2.5
INV. OUT=5029.38 (E)
FG=5033.31
4''x4'' TEE A6-5
INV.=5029.43
FG=5032.03
ROOF LEADER A6-5.1
INV. OUT=5029.82 (W)
FG=5033.28
ROOF LEADER A6-6
INV. OUT=5029.81 (E)
FG=5033.31
12''x12'' TEE A6
INV.=5028.15
FG=5032.49
RIM = 5032.40
INV. = 5028.56 (N)
INV. = 5028.68 (W)
INV. = 5028.68 (E)
RIM = 5033.01
INV. = 5028.91 (E)
INV. = 5028.91 (N)
INV. = 5028.91 (S)
RIM = 5032.56
INV. = 5028.68 (W)
INV. = 5028.04 (NE)
INV. = 5028.04 (S)
OUTLET STRUCTURE A6-1
INV. IN=5028.72 (W)
INV. IN=5028.22 (NE)
INV. OUT=5028.22 (S)
FG=5032.98
RIM = 5031.78
INV. = 5030.21 (N)
INV. = 5030.21 (S)
REPLACED WITH TEE
ST ST ST ST ST ST ST
ST
ST
ST
ST
ST
ST ST
ST
ST
ST
ST
STST
ST
ST
STST
ST
ST
ST
UD
UD
UD
0.3%
SG
0.3%
SG
20.08 LF 4" PVC @ 2.00%
29
.
9
3
L
F
6
"
P
E
R
F
O
R
A
T
E
D
P
V
C
@
0
.
2
0
%
7.7
3
L
F
8"
P
V
C
@ 2
.
0
0
%
15
.
5
0
L
F
8"
P
V
C
@ 2
.
0
0
%
34.01
FG
34.01
FG
34.0
1
FG
34.0
0FG
28.11
SG28.1
5
SG
28.0
7
SG
28.0
3
SG
22.49 L
F
4
"
P
V
C
@
2
.
0
0
%
9.14 LF
4" PVC
@ 2.00%
10.53 LF
4" PVC
@ 2.00%
3.04 LF 4" PVC @ 2.00%
2.48 LF 4" PVC @ 2.00%
5.29 LF 4" PVC @ 2.00%
7.01 LF 4" PVC @ 2.00%
25
.
4
6
L
F
4
"
P
V
C
@
2
.
0
0
%
2.51 LF 4" PVC @ 2.00%
7.31 LF 4" PVC @ 2.00%
4.24 LF 4" PVC @ 2.00%
2.54 LF 4" PVC @ 2.00%
30.21 LF 4" PVC @ 2.00%
2.57 LF 4" PVC @ 2.00%
21
.
5
8
L
F
4
"
P
V
C
@
2
.
0
0
%
3.17 LF 4" PVC @ 2.00%
INSPECTION PORT
28.14
AB (S
G
)
28.
1
3AB
(
S
G
)
28.05
AB (S
G
)
28
.
0
4
AB
(
S
G
)
32
.
8
1
AB
(
F
G
)
33.2
3AB (F
G
)
33
.
9
1
AB
(
F
G
)
33.
3
2
AB
(
F
G
)
OUTLET STRUCTURE A5-1
INV. IN=5028.52 (W)
INV. IN=5028.02 (NE)
INV. OUT=5028.02 (S)
FG=5033.41
STRUCTURE A5-3
INV. IN=5028.64 (E)
INV. IN=5028.64 (N)
INV. OUT=5028.64 (S)
FG=5032.64
90° ELBOW A5-3.1
INV.=5029.04
FG=5033.92
UD 45° BEND A5
INV. IN=5028.03 (N)
INV. OUT=5028.03 (SW)
FG=5033.65
MONITORING WELLl A5
INV. OUT=5028.09 (S)
FG=5033.74
WQ STRUCTURE A5-2
INV. IN=5028.55 (N)
INV. IN=5028.55 (W)
INV. OUT=5028.55 (E)
FG=5032.53
DOME GRATE A5-3.4
INV. IN=5029.10 (E)
INV. IN=5029.10 (W)
INV. OUT=5029.10 (S)
FG=5032.77
DOME GRATE A5-3.3
INV. IN=5028.95 (N)
INV. IN=5028.95 (E)
INV. OUT=5028.95 (S)
FG=5033.01
Roof Drain A5-3.3.1
INV. OUT=5029.40 (W)
FG=5033.98
90° ELBOW A5-3.4.1
INV.=5029.29
FG=5033.31
ROOF LEADER A5-3.4.2
INV. OUT=5029.35 (S)
FG=5033.28
90° ELBOW A5-3.4.3
INV.=5029.31
FG=5033.23
ROOF LEADER A5-3.4.4
INV. OUT=5029.38 (S)
FG=5033.27
ROOF LEADER A5-2.3
INV. OUT=5028.85 (E)
FG=5033.40
90° ELBOW A5-2.1.2
INV.=5028.80
FG=5033.34
4''x4'' TEE A5-2.1
INV.=5028.69
FG=5033.21
4''x4'' TEE A5-2.4
INV. IN=5029.20 (N)
INV. IN=5029.20 (W)
INV. OUT=5029.20 (S)
FG=5033.24
ROOF LEADER A5-2.4.1
INV. OUT=5029.25 (E)
FG=5033.42
90° ELBOW A5-2.5
INV.=5029.35
FG=5033.25
ROOF LEADER A5-2.6
INV. OUT=5029.43 (E)
FG=5033.48
ROOF LEADER A5-3.4
INV. OUT=5030.13 (W)
FG=5033.95
90° ELBOW A5-3.3
INV.=5030.08
FG=5033.42
ROOF LEADER A5-3.2.1
INV. OUT=5029.52 (W)
FG=5033.96
4''x4'' TEE A5-3.2
INV.=5029.47
FG=5033.85
12''x12'' TEE A5
INV.=5027.95
FG=5031.56
UNDER WOOD
DECK (UNABLE
TO VERIFY
INVERTS/RIM)
RIM = 5032.98
INV. = 5029.38 (E)
INV. = 5029.38 (W)
INV. = 5029.38 (S)
RIM = 5033.03
INV. = 5028.49 (W)
INV. = 5027.91 (NE)
INV. = 5027.91 (S)
RIM = 5032.46
INV. = 5028.40 (N)
INV. = 5028.40 (W)
W W W W W
ST
ST
ST
D
D
ST ST ST ST ST ST
ST
ST
ST ST ST ST ST ST
UD UD UD
W
E
E
0.3%
SG
7.99 LF
6" PVC
@ 2.00%
36.90 LF 6" PERFORATED PVC @ 0.20%
33.91FG
33.8
6FG
33.0
8FG
33.0
8
FG
29.17
SG
29.1
5
SG29.2
3
SG
29.2
4
SG
2.70 LF 4" PVC @ 2.00%
62.08 LF 4" PVC @ 2.00%
10.41 LF
4" PVC
@ 2.00%
8.76 LF
4" PVC
@ 2.00%
2.66 LF 4" PVC @ 2.00%
48.31 LF 4" PVC @ 2.00%
2.62 LF
4" PVC
@ 2.00%
47.19 LF 6" PVC @
0
.
5
0
%
INSPECTION
PORT
28.80
AB (SG)28.90
AB (S
G
)
28
.
8
6
AB
(
S
G
)
28.7
7AB (
S
G
)
33
.
5
5
AB
(
F
G
)
33
.
6
7
AB
(
F
G
)
32
.
6
3
AB
(
F
G
)
32
.
5
3
AB
(
F
G
)
UD 45° BEND A2-1.6
INV. IN=5028.77 (W)
INV. OUT=5028.77 (NE)
FG=5032.58
DRAIN BASIN A2-1.6
INV. IN=5029.27 (N)
INV. IN=5028.77 (SW)
INV. OUT=5028.77 (E)
FG=5032.50
4''x4'' TEE A2-1.9
INV.=5029.89
FG=5033.81
WQ STRUCTURE A2-1.8
INV. IN=5029.73 (N)
INV. IN=5029.73 (S)
INV. OUT=5029.73 (E)
FG=5033.81
90° ELBOW A2-1.8.1
INV.=5029.94
FG=5033.81
MONITORING WELL A2-1.6
INV. OUT=5028.85 (E)
FG=5033.74
ROOF LEADER A2-1.8.3
INV. OUT=5031.24 (N)
FG=5031.90
90° ELBOW A2-1.8.2
INV.=5031.18
FG=5031.90
90° ELBOW A2-1.10
INV.=5030.07
FG=5033.98
ROOF LEADER A2-1.11
INV. OUT=5030.12 (S)
FG=5033.98
90° ELBOW A2-1.12
INV. IN=5030.86 (N)
INV. OUT=5030.86 (W)
FG=5032.30
ROOF LEADER A2-1.13
INV. OUT=5030.91 (S)
FG=5032.29
RIM = 5032.44
INV. = 5029.41 (N)
INV. = 5029.69 (W)
INV. = 5028.73 (E)
RIM = 5033.78
INV. = 5029.78 (N)
INV. = 5029.71 (S)
INV. = 5028.43 (E)
Sheet
of 31
ST
A
N
D
A
R
D
A
T
F
O
R
T
C
O
L
L
I
N
S
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
GRAPHIC SCALE:
( IN FEET )
010 10 20 30
1 INCH = 10 FEET
NORTH
PROPOSED SUBGRADE SPOT ELEVATION 33.43
PROPOSED SUBGRADE SLOPES
NOTES:
2.0%
EXISTING SPOT ELEVATION
PROPOSED UNDERDRAIN
PROPOSED HDPE STORM
UD
PROPOSED FINISHED GRADE SPOT ELEVATION 33.43
(33.43
)
SG
FG
SG
ISOLATOR ROW
THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES
ARE APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE
COMMENCING NEW CONSTRUCTION, THE CONTRACTOR SHALL BE
RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND SHALL BE
RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
CONTRACTOR SHALL BE RESPONSIBLE FOR ANY NECESSARY FIELD LOCATES
AND POTHOLING OF SUBSURFACE UTILITIES. ENGINEERING AND CITY SHALL
BE NOTIFIED OF ANY POTENTIAL CONFLICTS.
3.MAINTAIN 10' HORIZONTAL AND 18" VERTICAL MINIMUM SEPARATION
BETWEEN ALL SANITARY SEWER MAINS, WATER MAINS, AND SERVICES.
4.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND
INLET BOX STRUCTURES. SPECIFIED LENGTH OF PIPE INCLUDES THE LAYING
LENGTH OF FLARED END SECTIONS.
5.PRIVATE STORM SEWER MATERIAL MAY BE RCP, PVC OR HDPE. ALL RCP
SHALL BE CLASS III OR GREATER. PIPE MATERIAL, BEDDING, AND
INSTALLATION WITHIN PUBLIC RIGHTS-OF-WAY SHALL BE GOVERNED BY THE
CITY OF FORT COLLINS. HDPE MUST BE SMOOTH WALLED INTERIOR. HDPE
FITTINGS MAY BE USED FOR PVC INSTALLATIONS. ALL JOINTS SHALL BE
'WATERTIGHT' USING APPROPRIATE GASKETS OR JOINT WRAPS (PER ASTM
C443 FOR RCP AND PER ASTM F477 / D3212 FOR PLASTIC PIPE).
6.REFER TO SHEET C6.07 FOR WATER QUALITY STRUCTURE DETAILS.
7.CONTRACTOR SHALL NOTIFY THE DESIGN ENGINEER AND THE CITY OF FORT
COLLINS STORMWATER UTILITY A MINIMUM OF ONE WEEK IN ADVANCE SO AS
TO ALLOW FOR FIELD OBSERVATION AND DOCUMENTATION OF THE
FOLLOWING SYSTEM ITEMS IN THE PERMEABLE PAVER AREA:
-SUBGRADE
-INSTALLATION OF GEOTEXTILE FABRIC
-INSTALLATION OF UNDERDRAIN
-PLACEMENT AND COMPACTION OF FOUNDATION STONE
-PLACEMENT OF CHAMBERS AND EMBEDMENT STONE
8.SUBGRADE AREAS ARE TO BE FIELD SURVEYED BY A LICENSED
PROFESSIONAL. THE DESIGN ENGINEER MUST CONFIRM THE SUBGRADE
ELEVATIONS AND DIMENSIONS PRIOR TO PLACEMENT OF GEOTEXTILE
FABRIC, SUB-BASE, OR ANY OTHER MATERIAL.
9.THE CONTRACTOR SHALL, AT ALL TIMES DURING AND AFTER SYSTEM
INSTALLATION, PREVENT SEDIMENT, DEBRIS, AND DIRT FROM ANY SOURCE
FROM ENTERING THE CHAMBER SYSTEM.
10.GENERAL CONTRACTOR SHALL CONVENE A PRE-CONSTRUCTION MEETING
TO ENSURE THAT ALL SUBCONTRACTORS HAVE AN UNDERSTANDING OF
HOW THE VAULT SYSTEM IS INTENDED TO FUNCTION. CONTRACTOR SHOULD
DISCUSS THE PROPOSED SEQUENCE OF CONSTRUCTION AND IDENTIFY
ACTIVITIES THAT MAY REQUIRE PROTECTION OF THE SYSTEM.
11.THE CONTRACTOR SHOULD PROVIDE SLACK IN GEOTEXTILE FABRIC TO
ENSURE PROPER INSTALLATION AND AGGREGATE PLACEMENT WITHOUT
DAMAGE. PROVIDE SUFFICIENT SLACK SO THE FABRIC IS NOT TORN WHEN
ROCK IS PLACED. IF TEARS ARE SEEN OR DISCOVERED, REPAIR THEM AS
RECOMMENDED BY MANUFACTURER WITH NO LESS THAN 18 INCHES OF
OVERLAP ON ALL SIDES OF THE TEAR.
12.SEE SHEETS C6.02-C6.07 AND PLANS BY ADS FOR ADDITIONAL DESIGN
INFORMATION.
13.CONTRACTOR SHALL COORDINATE ANY NECESSARY TELEPHONE, CABLE
AND ELECTRIC LOWERINGS (OR RE-ROUTING) WITH THE RESPECTIVE UTILITY
PROVIDERS TO FACILITATE THE INSTALLATION OF THE PROPOSED STORM
DRAIN AND UTILITY SERVICES.
14.VAULT LAYOUT SHOWN IN THESE PLANS IS FOR REFERENCE ONLY. FINAL
VAULT LAYOUT AND DESIGN SHALL BE PER MANUFACTURER. CURRENT
DESIGN AND SPECIFICATIONS PROVIDED BY ADS.
15.CONTRACTOR TO COORDINATE ALL ROOF LEADERS WITH THE
ARCHITECTURAL AND PLUMBING PLANS PRIOR TO CONSTRUCTION OR
ORDERING OF MATERIAL. IF A CONFLICT EXISTS, CONTRACTOR TO CONTACT
THE ENGINEER.
LEGEND:
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what's below.
before you dig.Call
R
C4.05
SU
B
G
R
A
D
E
P
L
A
N
WQ POND N1
(21 SC-160 CHAMBERS)
POND S1
(77 SC-160 CHAMBERS)
POND S2
(20 SC-740 CHAMBERS)
POND S3
(18 SC-740 CHAMBERS)
POND S4
(18 SC-740 CHAMBERS)
POND S5
(10 SC-310 CHAMBERS)
----
1
RECORD DRAWING
UP
UP
UP
UP
UP
UP
UP UP
UPUP
1
AP5-01
AP4-102
10 11
A
E
F
9
9
C
B
D
STAIR 5
STAIR 6
EXIT AT 5030'
5026' - 6"
5027' - 6"
E2
ELEV.
LOBBY
5027' - 6"
10
'
-
3
"
1'
-
8
"
84
'
-
5
"
1'
-
8
"
21
'
-
4
"
DE
T
E
N
T
I
O
N
V
A
U
L
T
5025' - 0"
5025' - 0"
5030' - 0"
1' - 0"
RA
M
P
D
O
W
N
2.
7
0
%
CAST IN
PLACE
CONCRETE
24' - 1 1/2"
1' - 8"
12' - 2 1/2"
1' - 8"
3
AP-EX-01
4
AP-EX-01
1
AP5-01
AP4-102
10 11
A
E
F
C
B
D
3
AP-EX-01
STAIR 5
STAIR 6
5039' - 6"
E2
ELEV.
LOBBY
4' - 0" X 4' - 0" GRATE FOR
DETENTION VAULT
ACCESS
- LOCATE BETWEEN
PRECAST DOUBLE TEE'S
- REFER TO SHOP
DRAWINGS FOR DOUBLE
TEE ORIENTATION
24' - 0" 15' - 0"
4
AP-EX-01
BUILDING B -
LEVEL 1
5027' - 6"
BUILDING B -
LEVEL 2
5039' - 6"
BUILDING B -
LEVEL 3
5050' - 1 7/8"
BUILDING B -
BASEMENT LEVEL
5016' - 10"
10 11
4
AP-EX-01
VAULT
ACCESS
DETENTION
VAULT
5025' - 0"
BUILDING B -
LEVEL 1
5027' - 6"
BUILDING B -
LEVEL 2
5039' - 6"
BUILDING B -
LEVEL 3
5050' - 1 7/8"
1
AP5-01
BUILDING B -
BASEMENT LEVEL
5016' - 10"
AEFCBD
3
AP-EX-01
CL
E
A
R
H
E
I
G
H
T
12
'
-
3
"
DETENTION VAULT
VAULT ACCESS VAULT ACCESS
5025' - 0"
12
'
-
3
"
84' - 5"
5025' - 0"
C
d
w
e
l
l
d
e
s
i
g
n
s
t
u
d
i
o
-
A
L
L
R
I
G
H
T
S
R
E
S
E
R
V
E
D
DRAWN BY CHECKED BY
JOB NUMBER:
SHEET NAME:
THIS DRAWING AND ASSOCIATED DOCUMENTS ARE THE EXCLUSIVE
PROPERTY OF DWELL DESIGN STUDIO, AND ARE NOT TO BE
REPRODUCED OR COPIED IN WHOLE OR IN PART, EXCEPT AS
REQUIRED FOR THE STATED PROJECT. THEY ARE ONLY TO BE
USED FOR THIS PROJECT AND SITE SPECIFICALLY IDENTIFIED
HEREIN AND ARE NOT TO BE USED ON ANY OTHER PROJECT
WITHOUT WRITTEN CONSENT OF DWELL DESIGN STUDIO.
SCALES AS NOTED ON THIS DRAWING ARE VALID ON THE ORIGINAL
DRAWING ONLY, THE DIMENSIONS OF WHICH ARE 30 x 42 INCHES.
DISCLAIMER:
SEAL:
ISSUE
d
e
s
i
g
n
s
t
u
d
i
o
d
w
e
l
l
36
5
5
B
R
O
O
K
S
I
D
E
P
A
R
K
W
A
Y
,
S
U
I
T
E
1
5
0
.
A
L
P
H
A
R
E
T
T
A
,
G
A
.
3
0
0
2
2
PH
O
N
E
:
7
7
0
.
8
6
4
.
1
0
3
5
F
A
X
:
7
7
0
.
8
6
4
.
1
7
9
0
A DEVELOPMENT FOR:
REVISION
DATE DESCRIPTION
9/
1
/
2
0
1
7
2
:
1
5
:
4
0
P
M
D
:
\
R
e
v
i
t
L
o
c
a
l
\
1
6
5
8
0
2
-
L
a
n
d
m
a
r
k
-
C
en
t
r
a
l
_
2
0
1
6
_
g
v
e
n
a
b
l
e
.
r
v
t
AP-EX-01
Author Checker
165802
PARKING DECK
- DETENTION
VAULT -
EXHIBIT
TH
E
S
T
A
N
D
A
R
D
A
T
F
O
R
T
CO
L
L
I
N
S
FT
.
C
O
L
L
I
N
S
,
C
O
L
O
R
A
D
O
11/01/2016 SCHEMATIC DESIGN SET
08/04/2017 SCHEMATIC REDESIGN SET
DATE DESCRIPTION
1/8" = 1'-0"
1
PARKING DECK - AT DETENTION VAULT - BUILDING B - LEVEL 1
- 5027'-6" 1/8" = 1'-0"
2
PARKING DECK - AT DETENTION VAULT - BUILDING B - LEVEL 2
- 5039'-6"
1/8" = 1'-0"
3 PARKING DECK - AT DETENTION VAULT - CROSS SECTION
1/8" = 1'-0"
4
PARKING DECK - AT DETENTION VAULT - LONGITUDNAL
SECTION
5 WORKING - 3D - PARKING DECK Copy 1
100-YEAR OUTLET PIPE
RELEASE TO PROSPECT ROAD
WQCV & 2-YEAR OUTLET PIPE
RELEASE TO LAKE STREETAA
DETENTION STRUCTURE WITHIN GARAGE
CONCRETE FLOOR
1.5' WATER QUALITY VOLUME 1.5' WATER
QUALITY VOLUME
100-YEAR STORM (VOL = 2774 cu. ft.)
0.5% MIN.
0.5% MIN.
TOP OF
CONCRETE
EL: 5025.0'
18" SAND FILTER (MIN.)SAND FILTER100-YEAR
OUTLET PIPE
RELEASE TO
PROSPECT ROAD
INVERT EL: 5028.4
WQ EL: 4928.0'
HWSE: 4931.1'
SPILLWAY VENTSSPILLWAY VENTS
TOP OF POND: 4932.1'
INVERTED S
I
P
H
O
N
WATER QUALITY
AND 2-YEAR
OUTLET PIPE
RELEASE TO
LAKE STREET
INVERT 5025.5
2-YEAR ORIFICE PLATE
RESTRICTED FLOW RATE 2.0 CFS
INVERT = 5024.4'
100-YEAR ORIFICE PLATE
RESTRICTED FLOW RATE 3.83 CFS
INVERT = 5028.7'
TOP OF
SAND MEDIA
EL: 5026.0'
TOP OF
SAND MEDIA
EL: 5026.5'
2-YEAR STORM
VOL. 575 cu. ft.
2-YEAR STORM
HWSE = 5028.5'
VOL. = 575 cu. ft.
6" PERF.
PVC PIPE
6" PERF. PIPE OUTLET
INV. 5024.5
5'
100-YEAR STORM (VOL = 2774 cu. ft.)2-YEAR EL: 4928.4'
E N G I N E E R N GI
EHTRON R N FIGURE 1
Drainage Structure with Sand Filter
August 9, 2017 the standard @ ft.collins
( IN FEET )
0
1 INCH = 20 FEET
20 20
221413-2 - DETENTION POND LINER
NOT REVIEWED NOTE COMMENTS
& CORRECTIONS
REJECTED
BY:
SUBMITTAL#
DATE:
SPEC:
4
Ryan.Emery 6/18/2019
221413-2 221413
REVISE & RESUBMITREVIEWED
Review is for general conformance with contract documents only and does not relieve the
subcontractor/supplier of responsibility for compliance with applicable drawings, specifications, and
code.
Katerra Construction, LLC.
TYPICAL PROPERTY TEST METHOD UNITS 10-mil 20-mil 30-mil
Thickness ASTM D5199 mil 10.0 ± 5% 20.0 ± 5% 30.0 ± 5%
Width ASTM D751 inches 761⁄4 ± 1⁄4
Specific Gravity ASTM D792 1.20 min.
Tensile Properties
Breaking Strength
Elongation at
Break
100% Modulus
ASTM D882 lbf/in.
%
lbf/in.
24 min.
250 min.
10 min.
48 min.
360 min.
21 min.
73 min.
380 min.
32 min.
Tear Resistance ASTM D1004 lbf 2.5 min. 6.0 min. 8.0 min.
Low Temperature ASTM D1790 Pass at -23˚C Pass at -26˚C Pass at -29 ˚C
Dimensional Stability ASTM D1204 % 4 max. 4 max. 3 max.
Water Extraction ASTM D1239 % 0.15 max. 0.15 max. 0.15 max.
Volatile Loss ASTM D1203 % 1.5 max. 0.9 max. 0.7 max.
Resistance to Soil Burial
Breaking Strength
Elongation at Break
100% Modulus
ASTM G160
% Change
% Change
% Change
5 max.
20 max.
20 max.
Hydrostatic Resistance ASTM D751
Procedure A
psi 42 min. 68 min. 100 min.
Plastatech®IG
Industrial Grade Geomembrane
Plastatech Engineering, Ltd.
725 East Morley Drive, Saginaw, MI 48601
800-892-9358 • Fax: 989-754-1626
www.plastatech.com
“Plastatech” is a registered trademark
owned by Plastatech Engineering Ltd.
Plastatech IG Data Sheet_V1_5.6.15 – PL14-0020
!"#$%&'()#*+,+--%+,.#/0/# # # $1#2""3-.#45#6&+3&%7#859:#
;<
=/# >-(?@+#2+( 3'-"A#
9/# B@@C#'%&+"/#
8/# 1"(- &+-@3"#"?@%D#'%&+&,-#!!+,#"!-(& ?-"/#
4/# 0 -&+@3?"/#
E/# F&()G&?-%#H& H-"/#
I/# J%-+(#'%&+"/#
K/# L &"+,#D&?-%& "/#
;M
=/# %@'3(?#N&?&A##L@%#-&(#?7!-#@C#!%@'3(?#+'(&?-'/#
O;
< ;
=/# N%&+&,-#!!+,#"!-(& ?-"#"& #P-&%# &P- .#"?&D!.#@%#@?-%#D&%)+,"#@C#"!-(C-'#?-"?+,#
&,-+(7/#
;
=/# B@@C#'%&+"#"& #P-#&"#"(-'3 -'#@+#'%&G+,"/#
;
=/# N@G+"!@3?#='&!?@%"A#
9/# N-"(%!?@+A##1&+3C&(?3%-'.#,%&7Q%@+#(&"?+,.#C@%#&??&(+,#?@#@%R@+?& Q
@3? -?.#!&%&!-?#%@@C#'%&+#&+'#?@#-S?-%@%.#"--?#D-?& #'@G+"!@3?/#
8/# >R-A##2+ -?#"R-#?@#D&?(#!&%&!-?#'%&+#@3? -?/#
F/# N@G+"!@3?#F@@?"A#
9/# N-"(%!?@+A##1&+3C&(?3%-'.#=>J1#=#E:T=#E:1.#,%&7Q%@+#(&"?+,.#G?#"?%&!#
@%#-&%"#C@%#&??&(+,#?@#P3 '+,U#V>#E#@3? -?U#&+'#"@!Q&!! -'#P?3D+@3"#
(@&?+,/#
8/# >R-A##2+ -?#"R-#?@#D&?(#'@G+"!@3?#&+'#V>#E#@3? -?/#
0/# 0@+'3(?@%#V@RR -"A#
9/# N-"(%!?@+A##F%@+R-#P@'7#G?#?%-&'-'#+ -?#&+'#P%@+R-#G& #C &+,-#G?#
D@3+?+,#@ -"/#
8/# >R-A##>&D-#&"#(@++-(?-'#(@+'3(?@%/#
; W#>--#>-(?@+#88949X#Y#>&+?&%7#Z&"?-#!+,#>!-(& ?-"/#
M [\
\ W#>--#>-(?@+#88949X#Y#>&+?&%7#Z&"?-#!+,#>!-(& ?-"/#
]
=/# J%-+(#N%&+"#"& #P-#&"#"(-'3 -'#@+#?-#'%&G+,"/###
]
=/# 0@!!-%#>--?A##=>J1#F#9I8TF#9I81.#98#@R/T"^/#C?//#
Project Name:
Blaine Mathisen 1.14.2020
Engineer's review is for general conformance with the design concept and Contract Documents.
Markings or comments shall not be construed as relieving the Contractor from compliance with
the project plans and specifications, nor departures therefrom. The Contractor remains
responsible for details and accuracy, for confirming and correlating all quantities and
dimensions, for selecting fabrication processes, for techniques of assembly, for installation
procedures and public entity inspections, for performing this work in a safe manner, and for
obtaining all necessary approvals from the Owner, Architect, General Contractor, and
Jurisdiction Having Authority, as applicable.
Confirm
Rejected
No Exceptions Taken
See Comments
8
BY DATE
!"#$%&'()#*+,+--%+,.#/0/# # # $1#2""3-.#45#6&+3&%7#859:#
;/# <+(=0>&?-'#@?-- #@--?A##B@C1#B#DE4FB#DE41.#G?#5/85#!-%(-+?#(>!!-%#(>+?-+?#&+'#5/5H=
+(#I+I3I#?()+-""#3+ -""#>?-%G"-#+'(&?-'/##2+( 3'-#$J5#>?='!#,& K&+L-'.#I =
!>"!&?L-'#M+"#M>%#!&+?+,#M#+'(&?-'/#
0/# * &"?(#1-IN%&+-#@--?A##B@C1#O#H5D:.#M -PN -.#( >%+&?-'#!> 7-?7 -+-.#H5=I #I+I3I#
?()+-""/#
O/# Q&"?-+-%"A##1-?& #(>I!&?N -#G?#I&?-%& #&+'#"3N"?%&?-#N-+,#M&"?-+-'/#
*/# 1-?& #B((-"">%-"A##@--?#I-?& #"?%!".#( &I!".#&+(>%+,#'-K(-".#&+'#"I &%#&((-"">%7#3+?"#
%-R3%-'#M>%#+"?& &?>+S#I&?(+,#>%#(>I!&?N -#G?#I&?-%& #N-+,#+"?& -'/#
Q/# @> '-%A##B@C1#;#48.# -&'=M%--#& >7/#
T U
B/# 2+"?& #%>>M#'%&+"#&?# >G#!>+?"#>M#%>>M#&%-&"#&((>%'+,#?>#%>>M#I-IN%&+-#I&+3M&(?3%-%V"#G%??-+#
+"?& &?>+#+"?%3(?>+"/##W>>M+,#I&?-%& "#&%-#"!-(M-'#+#OK">+#5X#@-(?>+"/#
9/# 2+"?& #M &"+,#(> &%#>%#M &+,-#>M#%>>M#'%&+#?>#!%-K-+?# -&)&,-#N-?G--+#'%&+#
&+'#&'Y>++,#%>>M+,/##1&+?&+#+?-,%?7#>M#G&?-%!%>>M#I-IN%&+-"#G-%-#
!-+-?%&?-'/#
8/# 2+"?& #-P!&+">+#Y>+?".#M#+'(&?-'.#+#%>>M#'%&+#>3? -?"/#
4/# >"?>+#%>>M#'%&+"#M>%#-&"7#&((-""#&+'#I&+?-+&+(-/#
;/# 2+"?& #'>G+"!>3?#&'&!?-%"#>+#>3? -?#>M#N&()=>3? -?#!&%&!-?#%>>M#'%&+"#&+'#(>++-(?#?>#"--?#
I-?& #'>G+"!>3?"/#
0/# 2+"?& #'>G+"!>3?#N>>?"#&?#,%&'-#G?#?>!#98#+(-"#&N>K-#,%&'-/##@-(3%-#?>#N3 '+,#G& /#
O/# 2+"?& #(>+'3(?>%#+>LL -"#&?#-P!>"-'#N>??>I#>M#(>+'3(?>%"#G-%-#?-7#"! #>+?>#,%&'-/#
*/# 2+"?& #( -&+>3?"#+#&N>K-,%>3+'#!!+,#&+'#N3 '+,#'%&+#!!+,#&((>%'+,#?>#?-#M> >G+,#
+"?%3(?>+"#3+ -""#>?-%G"-#+'(&?-'A#
9/# Z"-#( -&+>3?"#?-#"&I-#"L-#&"#'%&+&,-#!!+,#3!#?>#[@#H/##Z"-#[@#H#M>%#
&%,-%#'%&+&,-#!!+,#3+ -""# &%,-%#( -&+>3?#"#+'(&?-'/#
8/# \>(&?-#( -&+>3?"#&?#-&(#(&+,-#+#'%-(?>+#>M#!!+,#,%-&?-%#?&+#HE#
'-,%--"/#
4/# \>(&?-#( -&+>3?"#&?#I+I3I#+?-%K& "#>M#E5#M--?#M>%#!!+,#[@#H#&+'#"I& -%#
&+'#955#M--?#M>%# &%,-%#!!+,/#
H/# \>(&?-#( -&+>3?"#&?#N&"-#>M#-&(#K-%?(& #"> #&+'#G&"?-#"?&()/#
Q/# Q>%#M >>%#( -&+>3?"#M>%#!!+,#N- >G#M >>%".#+"?& #( -&+>3?#'-()#! &?-"#G?#?>!#M 3"#G?#
M+"-'#M >>%/#
$/# Q>%#( -&+>3?"# >(&?-'#+#(>+(-& -'#!!+,.#+"?& #( -&+>3?#G& #&((-""#(>K-%".#>M#?7!-"#
+'(&?-'.#G?#M%&I-#&+'#(>K-%#M 3"#G?#M+"-'#G& /#
]/# 2+"?& #>%L>+?& #N&()G&?-%#K& K-"#+#M >>%#G?#(>K-%#M 3"#G?#M >>%/#
2/# 2+"?& #?-"?#?--"#+#K-%?(& #(>+'3(?>%"#&+'#+-&%#M >>%/#
6/# 2+"?& #G& #( -&+>3?"#+#K-%?(& #(>+'3(?>%"/##2+"?& #&((-""#'>>%#+#G& #M#+'(&?-'/#
^/# 2+"?& #?%-+(#'%&+"#&?# >G#!>+?"#>M#"3%M&(-#&%-&"#?>#N-#'%&+-'/##@-?#,%&?-"#>M#'%&+"#M 3"#G?#
M+"-'#"3%M&(-#3+ -""#>?-%G"-#+'(&?-'/#
\/# 2+"?& #" --K-#M &"+,#'-K(-#G?#-&(#(>+'3(?>%#!&""+,#?%>3,#M >>%"#G?#G&?-%!%>>M#
I-IN%&+-/#
!"#$%&'()#*+,+--%+,.#/0/# # # $1#2""3-.#45#6&+3&%7#859:#
;/# 0<=! 7#>?#%-@3%-=-+?"#A<%#!!+,#"!-(A-'#+#BC"<+#88#D-(?<+"/##B%&>+,"#+'(&?-#
,-+-%& #&%%&+,-=-+?#<A#!!+,.#A??+,".#&+'#"!-(& ?-"/#
E
;/# F&G%(&?-#A &"+,#A%<=#"+, -#!-(-#<A#=-?& #3+ -""# &%,-#!&+".#"3=!".#<%#<?-%#'%&+&,-#
"&!-"#&%-#%-@3%-'/##6<+#A &"+,#&((<%'+,#?<#?-#A< <>+,#A#%-@3%-'H#
9/# I-&'#D--?"H##J3%+#K<+?"#<A#L/5M GN"@/#A?/# -&'#"--?".#5/5O4:M+(#?()+-""#
<%#?()-%/##D< '-%#K<+?"#<A#P/5M GN"@/#A?/# -&'#"--?".#5/5L8QM+(#?()+-""#<%#
?++-%/#
8/# 0<!!-%#D--?"H##D< '-%#K<+?"#<A#(<!!-%#"--?"/#
J/# 2+"?& #"--?#A &"+,#<+#!!-".#" --C-".#&+'#"!-(& ?-"#!&""+,#?%<3,#<%#-=G-''-'#+#A <<%"#
&+'#%<<A"#>?#>&?-%!%<<A#=-=G%&+-/#
9/# !-#F &"+,H##D --C-#?7!-.#=&?(+,#?-#!!-#"R-.#>?#&#=+=3=# -+,?#<A#
95#+(-"#&+'#>?#")%?#<%#A &+,-#-S?-+'+,#&?# -&"?#:#+(-"#&%<3+'#!!-/#
8/# D --C-#F &"+,H##F &?#"--?.#>?#")%?#<%#A &+,-#-S?-+'+,#&?# -&"?#:#+(-"#
&%<3+'#" --C-/#
4/# *=G-''-'#D!-(& ?7#F &"+,H##F &?#"--?.#>?#")%?#<%#A &+,-#-S?-+'+,#&?#
-&"?#:#+(-"##&%<3+'#"!-(& ?7/#
0/# D-?#A &"+,#<+#A <<%"#&+'#%<<A"#+#"< '#(<&?+,#<A#G?3=+<3"#(-=-+?/#
B/# D-(3%-#A &"+,#+?<#" --C-#&+'#"!-(& ?7#( &=!+,#%+,#<%#'-C(-/#
*/# F&G%(&?-#&+'#+"?& #A &"+,#&+'#!&+".#"3=!".#&+'#<?-%#'%&+&,-#"&!-"/#
;/# %<?-(?#'%&+"#'3%+,#%-=&+'-%#<A#(<+"?%3(?<+#!-%<'#?<#&C<'#( <,,+,#>?#'%?#<%#'-G%"#&+'#
?<#!%-C-+?#'&=&,-#A%<=#?%&AA(#<%#(<+"?%3(?<+#><%)/#
J/# &(-#! 3,"#+#-+'"#<A#3+(<=! -?-'#!!+,#&?#-+'#<A#-&(#'&7#<%#>-+#><%)#"?<!"/#
!"