HomeMy WebLinkAboutSite Certifications - 07/21/2017Mr. Wes Lamarque
City of Fort Collins Stormwater Utility
700 Wood St.
Fort Collins, CO
June 15, 2017
RE: Site and Grading Certification for Manhattan Townhomes
Dear Mr. Lamarque,
This drainage certification letter is provided to verify as-constructed conditions for Manhattan
Townhomes. Northern Engineering completed survey work October 21, 2016 to verify general
compliance with the Final Utility Plans for Manhattan Townhomes, dated 9/15 by Northern Engineering.
Building permit numbers include B1508758, B1508759, B1508760, B1508761, B1508762, B1508763,
B1508764, B1508796, B1508800, B1508802, B1508803, B1508805, B1600051, B1600054, B1600060,
B1600061, B1602529, B1602530, B1602522, B1602523, B1602524, B1602533, B1602680, B1602681,
B1602682, B1602683, B1602684, B1602685, B1602686, B1602687, B1602688, B1604233, B1604234,
B1604235, B1604236, and B1604237.
Included in this drainage certification submittal are the following:
Attachment 1 - City of Fort Collins Overall Site and Drainage Certification Form.
Attachment 2 - City of Fort Collins During Construction Inspection Checklist and photographs provided
by contractor.
Attachment 3 - As-constructed record drawings for Grading and Storm Drain Plan and Profile Sheets.
The as-built area of LID treatment is in Table 1. The as-built rain gardens and permeable pavers will
provide water quality treatment within the site.
Table 1: Area of LID Treatments
LID Treatment
Design Water
Quality Area (ac.)
As-built Water
Quality Area (ac.)
Paver LID Treatment 0.136 0.115
Rain Garden Treatment 0.041 0.034
We have concluded, based on the attached information and personal site inspection, that the drainage
features for the project site have been constructed in substantial compliance with the above referenced
Final Utility Plans, with the following exceptions:
•Item II.A.1: Drainage swales were installed per the approved utility plans. Privately maintained
swales are not located within a drainage easement.
Accepted 7/21/2017 WL
• Item II.A.2: Drainage swales were installed per the approved utility plans. The minimum
longitudinal slope on the approved utility plans is 1.0%.
• Item V.A: All storm inlets were constructed per the approved utility plans except Storm Basins
1-3.1 and 1-3.2. The north permeable paver and underdrain system was not installed per Paver
Extent Revision Memo dated May 24, 2016.
• Item V.A.1: All storm inlets were constructed per the approved utility plans except Storm Basins
1-3.1 and 1-3.2. The north permeable paver and underdrain system was not installed per Paver
Extent Revision Memo dated May 24, 2016.
• Item V.A.4: All storm inlets except Storm Basins 1-2, 1-6, and 2-4 were constructed within 0.2
feet of the approved utility plans. Storm Basins 1-2, 1-6, and 2-4 were constructed at the inverts
that result in a steeper pipe slope than the slope listed on the approved utility plans and
improving the flow capacity.
• Item VII.A: All storm inlets were constructed per the approved utility plans except Storm Basins
1-3.1 and 1-3.2. The north permeable paver and underdrain system was not installed per Paver
Extent Revision Memo dated May 24, 2016.
• Item VII.A.2: According to the Contractor, the underdrain was installed per the design drawings.
Northern Engineering did not observe installation of underdrain and was unable to verify
perforated pipe sections.
• Item VII.A.5: According to the Contractor, the underdrain was installed per the design drawings.
Northern Engineering did not observe installation of underdrain and was unable to verify type,
depth, and width of backfill material.
• Item VII.A.5: According to the Contractor, the underdrain was installed per the design drawings.
Northern Engineering did not observe installation of underdrain and was unable to verify if the
underdrain was wrapped with geotextile fabric.
• Item X.A.1: The flowline grade of the inverted private drive, south of Lots 33 and 34, was
constructed with a flowline slope of 0.1%. This was brought to the Developer’s attention.
Therefore, the drainage within the private drive in front of Lots 33 and 34 will not be certified by
Northern Engineering
• Item X.A.1: The flowline grade in the curb and gutter at the north entrance was constructed
with a flowline slope of 0.1%. This was brought to the Developer’s attention. Therefore, the
drainage within the curb and gutter at the northeast corner of Lot 8 will not be certified by
Northern Engineering
• Item XIII.A.3: Open areas along the west property line would need additional reseeding.
Please feel free to contact me with any questions you may have.
Thank you,
NORTHERN ENGINEERING
Frederick S. Wegert, PE
Project Engineer
Attachment 1
12/15 Page 1
OVERALL SITE and DRAINAGE CERTIFICATION
Commercial, Multi-Family and Subdivision Certification Form and Checklist
Project Name:
Date:
Building Permit Numbers:
(Commercial or multi-family)
Per the requirement in Fort Collins Stormwater Criteria Manual (FCSCM) Volume 1, Section 6.11, please fill in
all applicable items in this Certification Form for Commercial, Multi-Family and Overall Single Family sites.
NOTE: several items must be verified during construction. A copy of the approved grading plan must be
submitted with the as-built grading plan. (As-built elevations must be written in red next to the approved
elevations.)
•Use “Yes” for items completed as described.
•Use “N/A” for items that are not applicable to the site being certified.
•If any blanks are “No,” attach an explanation referencing the item number below.
Attach an explanation or description of the as-built condition for any items listed or for anything not listed but
shown on the approved construction plans.
Provide an as-built redline or Mylar drawing with the following:
I.Water Quality and Quantity Detention Basin Certification - FCSCM Vol.2, Ch.10
For multiple detention basins on a site, provide the following for each basin separately:
A. Volume: As-built topographic verification is attached at 1-foot (or less) contour intervals and
volume verification calculations for the water quality capture volume and the 100-year detention storage
volume.
1. Detention basin topography was prepared by a professional land surveyor registered in the state
of Colorado.
2.Both proposed and as-built contours are shown on the same plan sheet (dashed lines for
proposed and solid lines for as-built).
3.All critical spot elevations as shown on the approved construction plans have been verified and
the as-built elevations are shown on the plan sheet.
4.Stage-storage-discharge tables are provided on a separate document.
5.Verification that designed drain time is in compliance with Colorado Revised Statute § 37-92-
602(8) is attached and has been uploaded to the Statewide Compliance Portal
(tinyurl.com/COCompliancePortal) for approval. Uploaded documents must include:
a.The cover sheet from the approved drainage report
b.The stamped certification page from the approved drainage report
c.As-built topographic survey
d.Stamped certification page from the Overall Site & Drainage Certification
e.PDF output from the Stormwater Detention and Infiltration Design Data Speadsheet
12/15 Page 2
B.Water Quality and Quantity Detention Basin Grading: Attached is as-built verification that there is
a minimum 2% positive fall into the concrete trickle pans or flow-line(s) from all areas in the bottom of
the detention pond. If there is a “soft pan” in the flow-line, all areas still must meet the minimum 2%
grade requirement.
1.Low Flow: Choose one of the following detention basin low flow options as applicable:
a. Turf swale for low flow path in detention basin.
There is a minimum 2% grade in the flow-line(s) of the detention basin. The flattest as-built grade
is .
b.Concrete pan for low flow in detention basin.
There is a concrete pan installed that meets the grades as shown on the approved construction
plans. (Show as-built spot elevations.)
c.Soft pan for low flow in detention basin.
•Verify and document the soft pan material gradation, trench width and depth - to be verified
during construction by engineer. Picture documentation is preferred or engineer’s statement of
visual inspection and compliance. (Choose one below.)
o There is a soft pan with an underdrain installed that meets the design on the approved
construction plans. (Show the underdrain grades, bedding material, geotextile, spot elevations,
bends, cleanouts, etc.)
o There is soft pan installed without an underdrain but there is a type A or B soil. The soil
type must be documented by supplying verification from a registered professional geotechnical
engineer.
NOTE: Spot elevations are to be within 0.2 ft. +/-.
2. Side Slopes: The as-built side slopes of the detention basin have been calculated and are shown.
Indicate the side slope with an arrow and a numerical value (e.g., 6.25:1). The maximum slope allowed
is 4:1. Small areas of 3:1 may be acceptable, but slopes steeper than 3:1 must be stabilized or re-
graded. Provide documentation if a variance was granted for steeper slopes during the design process.
3.Spillway Certification: The following items must be field verified:
a.The location of the spillway is indicated on the as-built plan.
b.The width of the spillway is indicated on the as-built plan.
c.The elevation(s) of the spillway is shown on the as-built plan.
d.A concrete ribbon defines the location and grade of the spillway.
e.There is downstream scour protection in the spillway as per the construction plans. Indicate
type: (riprap size “D50” gradation and bedding type, geotextile, buried
riprap with inches of bury, etc.).
f.There are no obstructions in the spillway, such as trees, bushes, sidewalks, landscape
features, rocks, etc.
12/15 Page 3
4.Outlet Structure Certification
a.The orifice plate for the approved release rate is installed with the correct size and location of
the orifice.
b.The orifice plate for the water quality outlet is installed with the correct hole size, number of
rows and columns of holes.
c.The bottom hole on both the water quality and quantity outlets are at the bottom of the plate
so no water ponds in front of the plate.
d.The well screen is the correct material and is installed as shown on the construction plans.
e.100-year overflow grate elevation is . (Elev. A on detail D-46)
f.The top elevation of the water quality capture volume is . (Elev. B on detail
D-46)
g.Overflow grate is made of the correct material, has the correct bar spacing, is hinged at the
top and bolted at the bottom.
h.The bottom of the outlet box has no obstructions or misalignments that will cause it to retain
runoff water and is sloped at 2% towards outlet.
II.Channels/Swales - FCSCM Vol.1, Ch.7, Sect.3&4
A. Capacity: The as-built capacity of all the major channels and swales has been verified. They meet
or exceed capacity requirements shown in the approved drainage study for this project.
1.All swales are located within the drainage easements as shown on the construction plans.
2.Longitudinal slopes and side-slopes (cross-sections) have been verified. Design criteria requires
longitudinal slopes of 2% min. (on vegetated swales) and side-slopes no steeper than 4:1. If these
criteria are not met, the certification engineer will write a justification and propose mitigation for each
instance or have the issues corrected. If variances to these criteria have previously been approved and
are shown on the construction plans, no justification is needed.
3.As-built spot elevations on channels/swales are shown that correspond to spot elevations
shown on the approved construction plans.
4.All permanent erosion control measures are installed as shown on the approved construction
plans (e.g., drop structures, riprap, TRMs, etc.). (Include pictures and verification of the materials used
as part of this verification.)
5.All pans, curbs, storm pipes or other appurtenances appropriately tie into each other in the
system. (Pictures at tie-in points suggested.)
6.The minimum freeboard is provided for all channels and swales as shown on the approved
construction plans or as identified in the approved drainage study. (Show the freeboard provided on
the cross-sections as on the construction plan set or attached as separate documentation.)
7.The low flow portion of all channels or swales is clear of obstructions. (No landscaping, trees,
shrubs, sod, etc. infringe on the low flow portion of channels or swales.)
12/15 Page 4
III.Storm Pipes (aka storm drains) - FCSCM Vol.1, Ch.6, Sec. 4
A. Storm Drain Pipe Capacity: The as-built capacity of all pipes installed on this project has been
verified and meets or exceeds the capacity requirements shown in the approved drainage study for this
project.
1.All storm drain pipe sizes and materials have been verified and are in conformance with the
approved construction plans. (Indicate on the plan and profile sheets that they have been verified.)
Material and size substitutions must be approved prior to installation. If a pipe size or material was
changed during construction, the certification engineer must attach the approval documents or supply
them with this certification. Approval documents must include a calculation documenting the capacity
equivalency (equal or greater) of the substituted size.
2.The longitudinal slope of the pipe is as shown on the approved construction plans. The
acceptable minimum slope is 0.4%. All slopes flatter than the designed slope on the construction plans
must be justified with capacity calculations on an attached sheet.
3.The as-built invert elevations have been verified and are shown on the plan and profile sheets of
the approved construction plans.
B.Storm Drain Pipe Installation Requirements: All pipes are installed in accordance with the
approved construction plans.
1.The minimum cover requirements for all pipes have been met as shown on the approved
construction plans. These will be called out in critical locations.
2.All encasements and clearances as specified on the approved construction plans have been met.
3.Any specific joint types or construction methods specified on the approved construction plans
have been met. (List on a separate sheet and attach to this certification.)
IV.Concrete Pans - FCSCM Vol.1, Ch.7, Sec.4.1.3.4
A. Construction/Installation: All concrete pans have been constructed in accordance with the
approved construction plans.
1.The concrete pans are the correct size/width as shown on the approved construction plans.
2.The longitudinal slopes of the pans are as shown on the approved construction plans. The
certification engineer must justify or mitigate longitudinal slopes less than the minimum of 0.4% unless
a flatter slope was approved and is shown on the approved construction plans. Provide mitigation or
justification by separate document.
3.The cross-section of the pan is as shown on the construction plans. (Specifically, the pan cross-
section is “V” shaped and meets the side slope shown on the detail.)
4.The concrete pans are a minimum of 6 inches thick without reinforcement and a minimum of 4
inches thick with a minimum of 6X6-W14xW14 reinforcement per detail D20B and D20C. (Provide
documentation of the reinforcement used if different than shown on the details or on the approved
construction plans.)
5.The spot elevations shown on the concrete pan(s) have been verified and are shown on the as-
built drawings.
12/15 Page 5
V. Storm Drain Inlets - FCSCM Vol.1, Ch.6, Sec. 3
A. Construction/Installation: All storm drain inlets have been constructed in accordance with the
approved construction plans.
1.The size and type of inlets are consistent with the inlets shown on the approved construction
plan. Indicate by writing “Verified” on each inlet on the plan sheet or list on a separate document the
inlet number(s), type and size (length). If the inlet installed is other than the one on the approved
construction plan detail sheet, provide the name and source of the detail with justification for equal or
better capacity.
2.The size of the inlet opening is consistent with the approved detail. (Check height and width.)
3.The elevation of the grate (if applicable) is at the elevation shown on the street profile or as
indicated by a spot elevation on the construction plans.
4.The as-built invert elevations of all pipes entering and leaving the inlet are shown on the plan
and profile sheets within construction tolerance of 0.2 feet. If substantially different, provide
justification and capacity calculations to show the capacity is not affected or propose mitigation.
5.The as-built size of the inlet box is as shown on the construction plans or an explanation or
justification is attached.
6.All inlet covers are stenciled or stamped with the following designation: NO DUMPING – DRAINS
TO POUDRE RIVER.
VI.Culverts - FCSCM Vol.2, Ch.9
A. Construction/Installation: All culverts have been constructed and/or installed in accordance with
the approved construction plans.
1.All culvert sizes have been verified as indicated on the as-built construction plans as correct.
2.The culvert material type for all culverts installed is as on the approved construction plans and is
indicated on the as-built plans.
3.The as-built invert “in and out” elevations have been verified and are indicated on the as-built
construction plans.
4.The culvert headwalls or wing walls have been installed as shown on the approved construction
plans. Headwalls or wing walls may be needed in the as-built conditions onsite if the slopes adjacent to
the culvert are greater than 4:1. Please note areas needing stabilization in the certification narrative.
An alternative to consider is a turf reinforcement mat (TRM).
VII.Sub-Drains
A. Construction/Installation: All sub-drains shown on the construction plans have been installed in
accordance with those plans. Sub-drains installed with the sanitary sewer are to be verified on the
sanitary sewer plan and profile sheets of the construction plans. (NOTE: Indicate any sub-drains installed
after the plans were approved on the as-built plans.)
1.The size of the sub-drains are as approved on the construction plans and are indicated on the as-
built plans.
2.The type of sub-drain, in particular the perforated and non-perforated sections of the drain, are
as indicated on the approved construction plans.
12/15 Page 6
3.The cover requirements per the construction plans are provided.
4.The cleanouts have been installed at the locations shown on the construction plans and are
accessible for cleaning. (Cleanouts can be buried a maximum of 6 inches deep with their locations
marked.)
5.The backfill materials for sub-drains are as shown on the approved construction plans. (This
includes the type, depth and width.)
6.The geo-textile liner completely wraps the sub-drain and the permeable backfill material unless
shown otherwise on the approved construction plans. (Sub-drain pipe wrapped in a sock filter material
is accepted only if approved prior to installation.)
VIII.Curb Cuts
A. Construction: All curb cut openings are constructed in accordance with the approved construction
plans.
1.The size (width) of the curb cut opening is as shown on the approved construction plans.
2.The curb cut openings tie into a downstream swale, pipe, or other appurtenances with a smooth
transition and there no obstructions such as riprap or sod impeding the flow downstream of the curb
cut.
IX.Sidewalk Culverts & Chases
A. Construction/Installation: All sidewalk culverts have been installed at the locations shown on the
approved construction plans.
1.The size (width and length) of the culverts are as shown on the approved construction plans.
2.The cover plate is a minimum 5/8-inch galvanized plate bolted to a galvanized angle iron per the
detail shown on the approved construction plans or per the City’s detail.
3.The sidewalk culvert invert “in and out” elevations have been verified and are indicated on the
as-built plans.
4.The sidewalk culvert opening is as shown on the approved construction plans or per the City’s
detail.
5.There is a smooth transition both on the inlet and outlet ends of the sidewalk culvert with no
obstructions such as riprap or sod impeding the flow into or out of the sidewalk culvert.
X. Site Grading
A. Construction: All common open spaces have been graded in accordance with the approved
construction plans.
1.The grading on all common open spaces bordering private lots has been verified as correct and
the as-built rear lot corner elevations have been shown on the as-built plans.
12/15 Page 7
2.The as-built contours for “overlot grading” are shown on the as-built construction plans for all
common open spaces, tracts, outlots, etc. If not in compliance, please attach a narrative describing the
situation for noncompliance and when it may be corrected. An escrow for overlot grading may be
required. (NOTE: Residential Lot Grading Certification is a separate process from this Overall Site
Certification. It is understood that residential lots will be brought to final grade once the foundation is
backfilled so they may be lower than the plan shows at this Overall Site Certification stage.)
3.All turf reinforcement mats (TRMs) have been installed as shown on the approved construction
plans and the slopes are stabilized.
XI.Riprap - FCSCM Vol.1, Ch.7, Sec.4.4.4.3
A. Construction: All riprap has been installed in the locations and sizes indicated on the approved
construction plans.
XII.Permanent Erosion Control Fabric - FCSCM Vol.1, Ch.7
A. Construction: All fabric has been installed in the locations and sizes indicated on the approved
construction plans.
1.All fabric was installed per the details on the approved construction plans.
XIII.Post-Construction Site Cleanup - FCSCM Vol.3, Ch.7
A. Construction: All construction debris and obstructions of any kind have been removed from
drainage paths.
1.All construction debris has been removed except in staging area(s).
2.All ruts have been smoothed out in all construction areas.
3.All areas needing reseeding have been identified and future stabilization goals have been
coordinated with the Erosion Control Inspector and in accordance with FCSCM Vol.2 Chapter 12. Note
the area needing stabilization in the narrative.
XIV.Certification of Other Permanent BMPs - FCSCM Vol.2, Ch.8, Sec.2 & FCSCM Vol.2, Ch.12
A.The construction of channel drop structures is in accordance with the approved plan both in
location, horizontal dimensions and cross-section.
XV.Certification of LID and Water Quality Facilities - FCSCM Vol.3, Ch.4
A.Attached are the During Construction Inspection Checklist for Low Impact Development (LID) and
other items to be verified during construction, along with pictures and other required documentation.
Attachment 2
Attachment 3
FES
FESFES
CA
B
L
E
CA
B
L
E
VA
U
L
T
EL
E
C
CA
B
L
E
VA
U
L
T
CA
B
L
E
VA
U
L
T
EL
E
C
VA
U
L
T
CA
B
L
E
WV
HYD
VA
U
L
T
EL
E
C
C
C
WV
VA
U
L
T
EL
E
C
V.
P
.
V.
P
.
V.
P
.
S
h2
o
h2
o
h2
o
SS
SS
SS
SS
SS SS SS SS SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
E
W
W
G
G
G
G G G G G G
G
CTV
CTV
CTV
CTV CTV CTV CTV
CTV
CTV
CTV
CTV
CTV
CTV
E
E
W W
W
W
W
W
W
W
W W W W W W
W
W
W
W
W
W
W
W
W
W
FO
FO
FO
FO
FO FO FO FO FO FO
FO
FO
FO
FO
FO
FO
FO
FO
FO
CTV
CTV
CTV
CTV
CTV
CTV
CTV
CTV
CTV
CTV
CTV CTV CTV CTV CTV
CTV
CTV
CTV
CTV
E
E
E
E E E E E E
E
E
E
E
E
E
E
E
E
E
CT
V
CT
V
G
G
G
G
G
G
G
G
G
G
G
G
G
G
CTV
CT
V
CT
V
CTV
CTV
CTV
CTV
CTVCTV
FO
FO
FO
FO
FO FO FO FO FO
FO
FO
FO
FO
FO
FO
FO
FO
CTV
X
X
X
X
X
X
X
X
X
XXXXXXX
X
X
X
X
X
XXXXXXX
/ / / / / /
/
/
/ / / / /
/
/
/
/ / / / /
/
/
/
/ / / /
/
/
/
/
/ / / /
/
/
/
/
/ / / /
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / /
/
/ / / / / / / // / / / / / / // / / / / / / // / / / / / / /
/ / / / / / /
/
/ / / / / / /
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
X
X
X
X
X
X
X
X X X X X X
X
X
X
X
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WV
WV
WV
W
W
W
W
W W W
W
W
G
G
G
G
G
G
G
D
D
D
S
S
S
S
X
X
X
X
X
X
X
X
/ /
/
/
/
/
/
/
/ / / / / /
/
/
/ / / / / /
/
/
/ / / / / /
/
/
/ /
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
EM
EM
GM
EM
GM GM
EM
GM
GM
EM
EM
GM
EM
GM/ / / / / / / /
T
S
W
S
S
S
S
S
W
W
W
W
W
S
SSSSSWWWW W
W
W
W
W
S
S
SSSSS
WWWWW
WWWWWWSSSSS S
E
E
E
E
G
G
G
G
G
G
G
G
G
S
S
S
W
IR
W
W
SS
W
WS
W
W
W
S
S
S
SW
G
G
G
G
G
G
SD
SD
SD
SD
SD
SD
SD
SD
W
E
E
E
E
E
E
E
E
MANHATTAN AVE
EXISTING 4"
SANITARY
SERVICE
EXISTING 4"
SANITARY
SERVICE
EXISTING 4"
SANITARY
SERVICE
EXISTING 4"
SANITARY
SERVICE
GAS METER (TYP.)
CUT IN 8"x6" SWIVEL TEE
w/ TB & 6" GV (S)
N:111961.46
E:193115.36
17.72 LF 6" PVC
S04°11'27"E
FIRE HYDRANT
N:111943.78
E:193116.65
ELEC. METER (TYP.)
ELEC. METER (TYP.)149± LF 2" W.S.
1"x3/4" TEE W/
STIFFENER (TYP.)
3/4" WATER
SERVICE (TYP.)
3/4" WATER
SERVICE (TYP.)
3/4" WATER
SERVICE (TYP.)
3/4" WATER
SERVICE (TYP.)
3/4" WATER
SERVICE (TYP.)
3/4" WATER
SERVICE (TYP.)
GAS SERVICE
ELECTRIC SERVICE
4" PVC @ 2.00%
SANITARY SERVICE (TYP.)
4" PVC @ 2.00%
SANITARY SERVICE (TYP.)
4" PVC @ 2.00%
SANITARY
SERVICE (TYP.)
4" PVC @ 2.00%
SANITARY SERVICE (TYP.)
4" PVC @ 2.00%
SANITARY SERVICE (TYP.)
EXISTING 4"
CULVERT
EXISTING 3'
CONCRETE PAN
EX
I
S
T
I
N
G
3
0
'
UT
I
L
I
T
Y
A
L
I
G
N
M
E
N
T
EX
I
S
T
I
N
G
P
R
I
V
A
T
E
6
"
P
V
C
W
A
T
E
R
2" WATER SERVICE TAP
EXISTING 8" PVC WATER
EXISTING 21"
RCP STORM
EXISTING 36"
RCP STORM
EXISTING INLET
EXISTING GAS
GAS SERVICE
ELECTRIC SERVICE
ELECTRIC SERVICE
OWNER
CAMPANA ADVENTURES LLC
3726 MANHATTAN AVE
FORT COLLINS, CO 80526
N:112133.64
E:193096.40
N:112133.63
E:193227.51
N:111774.02
E:193339.38
N:111567.95
E:193328.99
N:111581.70
E:193056.17
OWNER
CITY OF FORT COLLINS
STORM DRAIN 1
SEE THIS SHEET
LOT 1 LOT 2 LOT 3 LOT 4 LOT 5 LOT 6 LOT 7 LOT 8 LOT 9 LOT 10 LOT 11 LOT 12
LOT 13
LOT 14
LOT 15
LOT 16
LOT 21
LOT 20
LOT 19
LOT 17
LOT 22
LOT 23
LOT 24
LOT 25
LOT 27
LOT 28
LOT 29
LOT 30
LOT 31
LOT 32LOT 33LOT 34LOT 35LOT 36
TRACT A
TRACT B
TRACT C
TRACT D
2" IRRIGATION
TAP
GAS METER (TYP.)
N:111841.56
E:193197.76N:111945.51
E:193185.67
N:112118.87
E:193175.02
N:111714.55
E:193225.58
N:111785.09
E:193309.92
N:111631.30
E:193320.05
N:111639.79
E:193180.54
TRACT B
TRACT
D
1' SIDEWALK CHASE
PROPOSED SUBDRAIN
PROPOSED SUBDRAIN
SEE SHEET SG1
3/4" WATER
SERVICE (TYP.)
SANITARY LINE A
SEE SHEET SS1
DRAIN BASIN
w/ SOLID GRATE
EX
I
S
T
I
N
G
8
"
P
V
C
W
A
T
E
R
EXISTING
FH
CONNECT TO
EXISTING TEE
N:111653.71
E:193236.91
35
.
1
5
L
F
8
"
P
V
C
S8
6
°
5
8
'
5
6
"
E
97
.
6
0
L
F
8
"
P
V
C
S7
4
°
0
4
'
4
4
"
E
8.80 LF 8" PVC
N60°55'16"E
CONNECT TO
EXISTING 8" WATER,
45° BEND w/ TB
N:111678.05
E:193100.25
45° BEND w/ TB
N:111682.33
E:193107.95
11.25° BEND w/ TB
N:111655.56
E:193201.81
ELECTRIC
TRANSFORMER
DRAIN BASIN
w/ SOLID GRATE
PROPOSED SUBDRAIN
SEE SHEET SG1
PR
I
V
A
T
E
D
R
I
V
E
PRIVATE DRIVE
PR
I
V
A
T
E
D
R
I
V
E
PROPOSED RAIN GARDEN 3
SEE SHEET RG1
PROPOSED
RAIN GARDEN 2
SEE SHEET RG1
PROPOSED
RAIN GARDEN 2
SEE SHEET RG1
PRIVATE DRIVE
LOT 26
PROPOSED RAIN
GARDEN OUTFALL
SEE SHEET RG1
1' SIDEWALK CHASE
LOT 18
////////////
W
WV
WV
WVWV
HYD
WV
HYD CS
CS
C.O.
C.O.
C.O.
C.O.
CS
CS
CS
CS
C.O.
C.O.
CS
CS
C.O.
C.O.
C.O.
C.O.
CSCS
CS
C.O.
CS
C.O.
CS
C.O.
CS
C.O.
CS
CSC.O.
CSC.O.
CSC.O.
CSC.O.
CSC.O.
CSCS
C.O.
CS
C.O.
CS
C.O.
CS
C.O.
CS
C.O.CS
C.O.CSCS
C.O.CS
C.O.CS
C.O.CS
C.O.CS
C.O.
C.O.
C.O.C.O.C.O.
C.O.C.O.
CSCSCSCSCS
5035
5040
5045
5050
5055
5060
5065
5035
5040
5045
5050
5055
5060
5065
9+5010+0011+00
PROPOSED
GROUND
EXISTING
GROUND
33.51 LF
15" RCP
@ 0.50%
IN
L
E
T
1
-
2
ST
A
1
0
+
3
3
.
5
1
FL
.
E
L
5
0
4
7
.
5
±
IN
V
.
O
U
T
5
0
4
4
.
6
7
(
S
E
)
FE
S
1
ST
A
1
0
+
0
0
.
0
0
IN
V
.
I
N
5
0
4
4
.
5
1
(
N
W
)
100-YR
HGL
U1
UT
I
L
I
T
Y
P
L
A
N
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
NORTH
Sheet
Of 23 Sheets
MA
N
H
A
T
T
A
N
T
O
W
N
H
O
M
E
S
,
S
E
C
O
N
D
F
I
L
I
N
G
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
10/9/15
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE
APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY
OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL UNDERGROUND UTILITIES IN
THE AREA OF THE WORK. BEFORE COMMENCING NEW CONSTRUCTION, THE
CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES
AND SHALL BE RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.ALL WATER AND SEWER CONSTRUCTION SHALL BE PER THE CITY OF FORT COLLINS
STANDARD CONSTRUCTION SPECIFICATIONS LATEST EDITION.
3.ALL WATER FITTINGS AND VALVES ARE ONLY GRAPHICALLY REPRESENTED AND ARE
NOT TO SCALE.
4.UTILITY SERVICES ARE SHOWN IN A SCHEMATIC FASHION ONLY. EXACT LOCATIONS
SHALL BE PER THE REQUIREMENTS OF THE RESPECTIVE UTILITY PROVIDERS, AND ARE
SUBJECT TO CHANGE IN THE FIELD.
5.MAINTAIN 10' HORIZONTAL AND 18" VERTICAL MINIMUM SEPARATION BETWEEN ALL
SANITARY SEWER MAINS, WATER MAINS & SERVICES.
6.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS,
UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
7.LIMITS OF STREET CUT ARE APPROXIMATE. FINAL LIMITS ARE TO BE DETERMINED IN
THE FIELD BY THE CITY ENGINEERING INSPECTOR. ALL REPAIRS TO BE IN
ACCORDANCE WITH CITY STREET REPAIR STANDARDS.
8.ANY DAMAGED CURB, GUTTER AND SIDEWALK EXISTING PRIOR TO CONSTRUCTION, AS
WELL AS STREETS, SIDEWALKS, CURBS AND GUTTERS, DESTROYED, DAMAGED OR
REMOVED DUE TO CONSTRUCTION OF THIS PROJECT, SHALL BE REPLACED OR
RESTORED TO CITY OR FORT COLLINS STANDARDS AT THE DEVELOPER'S EXPENSE
PRIOR TO THE ACCEPTANCE OF COMPLETED IMPROVEMENTS AND/OR PRIOR TO THE
ISSUANCE OF THE FIRST CERTIFICATE OF OCCUPANCY.
9.ALL DISCHARGE BASIN LIDS SHALL BE TRAFFIC RATED.
10.ALL INDIVIDUAL WATER SERVICE LINES ARE TO BE INSTALLED WITH A CURB STOP
OUTSIDE OF THE BUILDING AND A METER WITHIN THE INDIVIDUAL UNITS.
11.REFER TO PLUMBING PLANS FOR ALL WATER SERVICE AND SANITARY SEWER SERVICE
LOCATIONS. IF CONFLICT OCCURS, BOTH THE PLUMBING ENGINEER AND CIVIL
ENGINEER SHALL BE CONTACTED PRIOR TO INSTALLATION OR ORDERING OF
MATERIALS.
12.ALL SANITARY SEWER SERVICE CONNECTION INVERTS AND LOCATIONS BASED ON
BEST AVAILABLE DATA. CONTRACTOR TO VERIFY LOCATION PRIOR TO CONSTRUCTION
AND NOTIFY ENGINEER OF ANY DISCREPANCIES.
13.ALL WATER SERVICES TO BE 3/4".
14.ALL SANITARY SERVICES TO BE 4".
15.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND INLET BOX
STRUCTURES. SPECIFIED LENGTH OF PIPE INCLUDES THE LAYING LENGTH OF FLARED
END SECTIONS.
16.ALL RCP SHALL BE CLASS III OR GREATER. PIPE MATERIAL, BEDDING, AND
INSTALLATION WITHIN PUBLIC RIGHTS-OF-WAY SHALL BE GOVERNED BY THE CITY OF
FORT COLLINS. ALTERNATES (SUCH AS ADS N-12 OR HP SANITITE) OUTSIDE OF THE
R.O.W. SHALL BE APPROVED IN ADVANCE BY THE ENGINEER. ALL JOINTS SHALL BE
'WATERTIGHT' USING APPROPRIATE GASKETS OR JOINT WRAPS (PER ASTM C443/C877
FOR RCP AND PER ASTM F477 / D3212 FOR PLASTIC PIPE). STORM DRAINS SHOWN ON
THIS DRAWING AS POLYVINYL CHLORIDE (PVC) SHALL BE SDR-35 OR APPROVED EQUAL.
17.CONTRACTOR SHALL BE RESPONSIBLE FOR ANY NECESSARY FIELD LOCATES AND
POTHOLING OF SUBSURFACE UTILITIES. ENGINEER AND CITY SHALL BE NOTIFIED OF
ANY POTENTIAL CONFLICTS.
18.CONTRACTOR SHALL COORDINATE ANY NECESSARY TELEPHONE, CABLE AND
ELECTRIC LOWERINGS (OR RE-ROUTING) WITH THE RESPECTIVE UTILITY PROVIDERS
TO FACILITATE THE INSTALLATION OF THE PROPOSED STORM DRAIN AND UTILITY
SERVICES.
EXISTING WATER MAIN
LEGEND:
W
G
T
E
EXISTING STORM SEWER
PROPOSED ELECTRIC
EXISTING TELEPHONE
EXISTING GAS
SPROPOSED SEWER SERVICE & CLEAN OUT
EXISTING SANITARY SEWER SS
PROPOSED CURB & GUTTER
PROPOSED WATER SERVICE & CURB STOP
PROPOSED FIRE HYDRANT
EXISTING FIRE HYDRANT
EASEMENT LINE
PROPERTY BOUNDARY
PROPOSED LOTLINE
APPROXIMATE GAS METER LOCATION GM
W
PROPOSED WATER MAIN
PROPOSED SANITARY SEWER
PROPOSED STORM SEWER
PROFILE SCALE:
APPROXIMATE ELECTRIC METER LOCATION EM
STORM DRAIN 1
INLET ID INLET TYPE
1 Single Combination Inlet
EXISTING WETLAND
PROPOSED IRRIGATION TAP IR
SDPROPOSED SUBDRAIN
TPROPOSED TELEPHONE
GPROPOSED GAS
CTVEXISTING CABLE
EEXISTING ELECTRIC
PROPOSED STREET LIGHT
1
RE
C
O
R
D
D
R
A
W
I
N
G
MC
R
07
/
1
5
/
1
6
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
AS-BUILT SANITARY SEWER SERVICE
AS-BUILT WATER SERVICE
CS
C.O.
h2
o
SS
SS
SS
SS
SS SS SS SS SS SS SS SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
X
X
X
X
W
X
X
X
X
X
X
X
XXXXXXXXXX
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SSSS
SS
SS
SS
W
W
W W W W W
W
W
W
W
S
S
S
5045
5044
5045
5046
5047
5048
5048
5048
5049
5049
5049
50
4
6
/ /
/
/
/
/
/
/
/ / / / / /
/
/
/ / / / / /
/
/
/ / / / / /
/
/
/ / / / / /
/
/
/ /
/
/
/
/
/
/
/ / / / / /
/
/
/ / / / / / /
/
/ / / / / / / /
/ / / / / / / /
/ /
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
SSW
W
W
W
W
S
S
SSSSS
WWWWW
WWWWWWSSSSS S
S
S
S
W
SD
SD
SD
48.1
1
48
.
0
8
47
.
5
5
47
.
5
5
48.1
0
47.55
47
.
5
5
48.0
9
47.87
48.62
48.6
4
47.8
7
47
.
8
7
48.6
0
48.6
2
47
.
8
7
48.5
3
47.95
48
.
5
1
47.
9
5
48.
5
1
47
.
9
6
47.94
48.
5
2
INSTALL 5'x5' BURIED
RIPRAP PAD
30.69 LF
6" PERF. HDPE
@ 0.50%
80.57 LF 6" HDPE @ 0.5
0
%
15.49 LF 6" PERF. HDPE @ 0.50%
21.03 LF
8" HDPE
@ 0.50%
46.73
L
F
6
"
P
E
R
F
.
H
D
P
E
@
0
.
5
0
%
118.11 LF 6" HDPE @ 0
.
5
0
%
14.44 LF
6" HDPE
@ 0.50%
22.01 LF
8" HDPE
@ 0.64%
11.74 LF
6" HDPE
@ 3.50%
PROPOSED SUBDRAIN
SEE SHEET SG1
PERMEABLE
PAVERS
TRACT B
PRIVATE DRIVE
EXISTING 30'
UTILITY ALIGNMENTOWNER
CITY OF FORT COLLINS
EXISTING 4"
SANITARY SERVICE
EXISTING 8"
SANITARY SEWER
PROPOSED 4"
SANITARY SERVICE
EXISTING 4"
SANITARY SERVICE
EXISTING 4"
SANITARY SERVICE
BASIN 1-1.2
INV.=5045.08
FG=5047.82
BASIN 1-1.1
INV.=5044.85
FG=5047.69
BASIN 1-3
INV. IN=5046.55 (W)
INV. IN=5044.95 (N)
INV. OUT=5044.95 (S)
FG=5048.87
BASIN 1-5
INV.=5045.61
FG=5048.23
BASIN 1-6
INV.=5045.76
FG=5048.23
BASIN 1-2.1
INV. OUT=5045.33 (E)
FG=5048.24
BASIN 1-2
INV. IN=5044.54 (N)
INV. IN=5045.25 (W)
INV. OUT=5044.54 (S)
FG=5048.13
22.5° BEND 1-4
INV.=5045.54
FG=5048.39
BASIN 1-1
INV.=5044.44
FG=5048.13
PIPE END 1
w/ CONCRETE COLLAR
FG=5045.39
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
48.4
3
AB
47.69
AB
47.6
4
AB
47.
9
7
AB
47.59
AB
47.94
AB
48
.
8
0
AB
48.
0
2
AB
48
.
1
2
AB
48.
5
2
AB
48.70
AB
47.
8
7
AB
48.8
4
AB
48.90
AB
48.22
AB
48.29
AB
47.1
4
AB
47.52
AB
47.82
AB
48
.
3
8
AB
46.
9
4
AB
46.96
AB
47.64
AB
47.6
1
AB
48.53
AB
47.
5
0
AB
47.6
6
AB
48.07
AB
48.3
6
AB
48.41
AB
48.26
AB
48.2
9
AB
46.89
AB
47.
0
0
AB
47
.
9
7
AB
RG1
PL
A
N
&
D
E
T
A
I
L
S
RA
I
N
G
A
R
D
E
N
O
U
T
F
A
L
L
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
NORTH
PROPOSED RAIN GARDEN
Sheet
Of 23 Sheets
MA
N
H
A
T
T
A
N
T
O
W
N
H
O
M
E
S
,
S
E
C
O
N
D
F
I
L
I
N
G
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
10/9/15
REFER TO THE LANDSCAPE
PLANS FOR PLANTING WITHIN
THE BIO-RETENTION AREA
12" BIO-RETENTION
SAND MEDIA
6" PERFORATED
HDPE UNDERDRAIN
NOTES:
1.REFER TO THE BIORETENTION SAND MEDIA SPECIFICATIONS FOR MORE
INFORMATION ON THE SOIL MIX.
2.BIORETENTION SAND MEDIA SHALL BE PROVIDED BY HAGEMAN EARTH
CYCLE OR APPROVED EQUAL.
3.THE SOIL SECTION AS SHOWN ON THIS DETAIL SHALL BE PLACED IN ALL
RAIN GARDEN LOCATIONS.
MIN. 10" GRAVEL LAYER
MEETING CDOT #4
COARSE AGGREGATE
SPECIFICATION.
6" PEA GRAVEL
TYPICAL RAIN GARDEN SECTION
REFER TO THE LANDSCAPE
PLANS FOR PLANTING WITHIN
THE BIO-RETENTION AREA BIO-RETENTION
SAND MEDIA
6" PERFORATED
HDPE UNDERDRAIN
GRAVEL LAYER
PEA GRAVEL
BIORETENTION SOIL LAYERING (RAIN GARDEN)
CDOT CLASS B GEOTEXTILE
SEPARATOR FABRIC
(TYPICAL SIDES)
CITY OF FORT COLLINS
BIORETENTION SAND MEDIA SPECIFICATION
PART 1 - GENERAL
A.Bioretention Sand Media (BSM) shall be uniformly mixed,
uncompacted, free of stones, stumps, roots, or other similar objects
larger than two inches. No other materials or substances shall be
mixed or dumped within the bioretention area that may be harmful to
plant growth or prove a hindrance to the facility's function and
maintenance.
B.BSM shall be free of plant or seed material of non-native, invasive
species, or weeds.
C.Fully mixed BSM shall be tested prior to installation and meet the
following criteria:
1.P-Index of less than 30
2.pH of 5.5-6.5. Should pH fall outside of the acceptable range, it
may be modified with lime (to raise) or iron sulfate plus sulfur (to
lower). The lime or iron sulfate must be mixed uniformly into the
BSM prior to use in the bioretention facility.
3.Cation Exchange Capacity (CEC) greater than 10
4.Phosphorous (Phosphate, P2O5) not to exceed 69 ppm
5.BSM that fails to meet the minimum requirements shall be replaced
at the Contractor's expense.
D.BSM shall be delivered fully mixed in a drum mixer. Onsite mixing of
piles will not be allowed. Mixing of the BSM to a homogeneous
consistency shall be done to the satisfaction of the Owner.
PART 2 - SOIL MATERIALS
A.Sand
1.BSM shall consist of 60-70% sand by volume meeting ASTM C-33.
B.Shredded Paper
1.BSM shall consist of 5-10% shredded paper by volume.
2.Shredded paper shall be loosely packed, approximate bulk density
of 50-100 lbs/CY.
3.Shredded paper shall consist of loose leaf paper, not shredded
phone books, and shall be thoroughly and mechanically mixed to
prevent clumping.
C.Topsoil
1.BSM shall consist of 5-10% topsoil by volume.
2.Topsoil shall be classified as sandy loam, loamy sand, or loam per
USDA textural triangle with less than 5% clay material.
3.Onsite, native material shall not be used as topsoil.
4.Textural analysis shall be performed on topsoil, preferably at its
source, prior to including topsoil in the mix. Topsoil shall be free of
subsoil, debris, weeds, foreign matter, and any other material
deleterious to plant health.
5.Topsoil shall have a pH range of 5.5 to 7.5 and moisture content
between 25-55%.
6.Contractor shall certify that topsoil meets these specifications.
D.Leaf Compost
1.BSM shall consist of 10-20% leaf compost by volume.
2.Leaf compost shall consist of Class 1 organic leaf compost
consisting of aged leaf mulch resulting from biological degradation
and transformation of plant-derived materials under controlled
conditions designed to promote aerobic decomposition.
3.The material shall be well composted, free of viable weed seeds
and contain material of a generally humus nature capable of
sustaining growth of vegetation, with no materials toxic to plant
growth.
4.Compost shall be provided by a local US Composting Council Seal
of Testing Assurance (STA) member. A copy of the provider's
most recent independent STA test report shall be submitted to and
approved by the Owner prior to delivery of BSM to the project site.
5.Compost material shall also meet the following criteria:
a.100 percent of the material shall pass through a 1/2 inch
screen
b.PH of the material shall be between 6.0 and 8.4
c.Moisture content shall be between 35 and 50 percent
d.Maturity greater than 80 percent (maturity indicator expressed
as percentage of germination/vigor, 80+/80+)
e.Maturity indicator expressed as Carbon to Nitrogen ration < 12
f.Maturity indicator expressed as AmmoniaN/NitrateN Ratio <4
g.Minimum organic matter shall be 40 percent dry weight basis
h.Soluble salt content shall be no greater than 5500 parts per
million or 0-5 mmhos/cm
i.Phosphorus content shall be no greater than 325 parts per
million
j.Heavy metals (trace) shall not exceed 0.5 parts per million
k.Chemical contaminants: meet or exceed US EPA Class A
standard, 40 CFR 503.13, Tables 1 & 3 levels
l.Pathogens: meet or exceed US EPA Class A standard, 40
CFR 503.32(a) levels
PART 3 - EXECUTION
A.General
1.Refer to project specifications for excavation requirements.
B.Placement Method
1.BSM material shall be spread evenly in horizontal layers.
2.Thickness of loose material in each layer shall not exceed
9-inches.
3.Compaction of BSM material is not required.
BIORETENTION SAND MEDIA SPECIFICATIONS
LEGEND:
PROPOSED SUBDRAIN
PROPOSED STORM
SD
PROPOSED FINISHED GRADE SPOT ELEVATION 33.43
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE
APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY
OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL UNDERGROUND UTILITIES IN
THE AREA OF THE WORK. BEFORE COMMENCING NEW CONSTRUCTION, THE
CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES
AND SHALL BE RESPONSIBLE FOR FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS,
UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
3.ALL DISCHARGE BASIN LIDS SHALL BE PEDESTRIAN RATED.
4.REFER TO PLUMBING PLANS FOR ALL WATER SERVICE AND SANITARY SEWER SERVICE
LOCATIONS. IF CONFLICT OCCURS, BOTH THE PLUMBING ENGINEER AND CIVIL
ENGINEER SHALL BE CONTACTED PRIOR TO INSTALLATION OR ORDERING OF
MATERIALS.
5.ALL SANITARY SEWER SERVICE CONNECTION INVERTS AND LOCATIONS BASED ON
BEST AVAILABLE DATA. CONTRACTOR TO VERIFY LOCATION PRIOR TO CONSTRUCTION
AND NOTIFY ENGINEER OF ANY DISCREPANCIES.
6.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND INLET BOX
STRUCTURES. SPECIFIED LENGTH OF PIPE INCLUDES THE LAYING LENGTH OF FLARED
END SECTIONS.
7.CONTRACTOR SHALL BE RESPONSIBLE FOR ANY NECESSARY FIELD LOCATES AND
POTHOLING OF SUBSURFACE UTILITIES. ENGINEER AND CITY SHALL BE NOTIFIED OF
ANY POTENTIAL CONFLICTS.
8.CONTRACTOR SHALL COORDINATE ANY NECESSARY TELEPHONE, CABLE AND
ELECTRIC LOWERINGS (OR RE-ROUTING) WITH THE RESPECTIVE UTILITY PROVIDERS
TO FACILITATE THE INSTALLATION OF THE PROPOSED STORM DRAIN AND UTILITY
SERVICES.
9.ALL CURB SPOTS SHOWN ARE FLOWLINE ELEVATIONS. ALL OTHER SPOTS ARE
FINISHED GRADE ELEVATIONS.
RAIN GARDEN BASIN
12" - 30" DRAIN
BASIN
12" - 30" INLINE
DRAIN
NON TRAFFIC INSTALLATION
BACKFILL MATERIAL BELOW AND TO
SIDES OF STRUCTURE SHALL BE NATIVE SOIL
AND BE PLACED UNIFORMLY IN 12" LIFTS AND
COMPACTED TO A MIN OF 90%
REV B7001-110-111DWG NO.1 OF 1SHEET1:25SCALEDWG SIZE A
3130 VERONA AVE
BUFORD, GA 30518
PHN (770) 932-2443
FAX (770) 932-2490
www.nyloplast-us.com
12 IN - 30 IN DB & ID NON TRAFFIC INSTALLATION
TITLE
PROJECT NO./NAME
MATERIAL
DATE
APPD BY
9-30-99DATE
CJADRAWN BYTHIS PRINT DISCLOSES SUBJECT MATTER IN WHICH
NYLOPLAST HAS PROPRIETARY RIGHTS. THE RECEIPT
OR POSSESSION OF THIS PRINT DOES NOT CONFER,
TRANSFER, OR LICENSE THE USE OF THE DESIGN OR
TECHNICAL INFORMATION SHOWN HEREIN
REPRODUCTION OF THIS PRINT OR ANY INFORMATION
CONTAINED HEREIN, OR MANUFACTURE OF ANY
ARTICLE HEREFROM, FOR THE DISCLOSURE TO OTHERS
IS FORBIDDEN, EXCEPT BY SPECIFIC WRITTEN
PERMISSION FROM NYLOPLAST.
9-30-99
CJA
NOTE:
1.ALL DRAINS SHALL INCLUDE SUMP INSERT
REV B7001-110-206DWG NO.1 OF 1SHEET1:8SCALEDWG SIZE A
3130 VERONA AVE
BUFORD, GA 30518
PHN (770) 932-2443
FAX (770) 932-2490
www.nyloplast-us.com
12 IN DOME GRATE ASSEMBLY
TITLE
PROJECT NO./NAME
MATERIAL
DATE
APPD BY
3-6-06DATE
EBCDRAWN BYTHIS PRINT DISCLOSES SUBJECT MATTER IN WHICH
NYLOPLAST HAS PROPRIETARY RIGHTS. THE RECEIPT
OR POSSESSION OF THIS PRINT DOES NOT CONFER,
TRANSFER, OR LICENSE THE USE OF THE DESIGN OR
TECHNICAL INFORMATION SHOWN HEREIN
REPRODUCTION OF THIS PRINT OR ANY INFORMATION
CONTAINED HEREIN, OR MANUFACTURE OF ANY
ARTICLE HEREFROM, FOR THE DISCLOSURE TO OTHERS
IS FORBIDDEN, EXCEPT BY SPECIFIC WRITTEN
PERMISSION FROM NYLOPLAST.
3-6-06
CJA
8" DOME: PART #7001-110-197
10" DOME: PART #7001-110-201
12" DOME: PART #7001-110-206
15" DOME: PART #7001-110-211
QUALITY: MATERIAL SHALL CONFORM TO ASTM A536 GRADE 70-50-05
PAINT: CASTINGS ARE FURNISHED WITH A BLACK PAINT
LOCKING DEVICE AVAILABLE UPON REQUEST SEE DRAWING NO.
7001-110-229
DUCTILE IRON
D
U
C
T
I
L
E
I
RON-DO NOT P O L L U T DRAINS
TO
W
A
T
E
R
W
A
Y
S
E
NYLOP LAST
2.47
5.00
.93
TYPICAL DOME GRATE ASSEMBLY
4"
4"
2"
4"
4"
2"
6"
OUTLET
PIPE
FRONT VIEWSIDE VIEW
CONCRETE COLLAR
EXISTING WATER MAIN W
SPROPOSED SEWER SERVICE & CLEAN OUT
EXISTING SANITARY SEWER SS
PROPOSED WATER SERVICE & CURB STOP W
PROPOSED WATER MAIN
PROPOSED SANITARY SEWER
BASIN ID INLET TYPE
1-1 12" Basin w/ Solid Lid
1-1.1 12" Basin w/Dome Grate
1-1.2 12" Basin w/Dome Grate
1.2 12" Basin w/Dome Grate
1-2.1 12" Basin w/Dome Grate
1-3 12" Basin w/ Solid Lid
1-3.1 12" Basin w/ Solid Lid
1-3.2 12" Basin w/Dome Grate
1-5 12" Basin w/Dome Grate
1-6 12" Basin w/Dome Grate
2-1 12" Basin w/ Solid Lid
2-2 12" Basin w/ Solid Lid
2-3 12" Basin w/ Solid Lid
1
RE
C
O
R
D
D
R
A
W
I
N
G
MC
R
07
/
1
5
/
1
6
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
FES
FES
FESCABLE
CABLE
VAULT
CABLE
VAULT
CABLE
WV
HYD
S
h2o
h2o
SS
SS
SS
SS
SS
SS
CT
V
CT
V
CT
V
W
W
W
W
W
W
W
W
W
W
W
FO
FO
FO
FO
FO
FO
CT
V
CT
V
CT
V
CT
V
CT
V
CT
V
E
E
E
E
E
E
E
CTV
CTV
G
G
G
G
G
G
G
CT
V
CTV
CTV
CT
V
CT
V
CT
V
CT
V
CT
V
CT
V
FO
FO
FO
FO
X X X X X X X X X
X
X
X
X
X
X
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/
/
/
/
/
/
/
/
X
X
X
X
SS
WV
WV
WV
W W
G
G
G
G
G
G
D
EM
EM
EM
EM
/
/
/
/
/
/
/
/
T
S
W
S S S S
S
WWWW
W
S
S
S
W
W
W
G
G
G
G G G G G
W
WS
S
W
W
S
WW
W
S
SS
S
W
G
SD
SD
SD
SD SD SD
W
E
E
E
E
E
MA
N
H
A
T
T
A
N
A
V
E
SSMH A
STA 10+00.00
N: 111639.54
E: 193353.68
162.37 LF 8" PVC @ 1.40%
SSMH A1
STA 11+62.37
N: 111648.09
E: 193191.54
72.84 L
F
8
"
P
V
C
@
0
.
5
0
%
SSMH A2
STA 12+35.21
N: 111668.07
E: 193121.49
EXISTING 20'
UTILITY EASEMENT
EXISTING 8"
SANITARY SEWER
CUT IN MANHOLE
EXISTING 4"
SANITARY SERVICE
SEE SHEET U1
SANITARY SERVICE A4
INV. OUT=5041.52 (S)
FG=5050.67
24.37 LF 4" PVC @ 2.00%
PROPOSED 3/4"
WATER SERVICE (TYP.)
CONNECTION 6
INV. OUT=5038.98 (E)
FG=5047.01
PROPOSED GAS
SERVICE (TYP.)
PROPOSED ELECTRIC
SERVICE (TYP.)
PROPOSED 3/4"
WATER SERVICE (TYP.)
PROPOSED
SUBDRAIN
PROPOSED 3/4"
WATER SERVICE (TYP.)
EXISTING PRIVATE 6" PVC WATER
TR
A
C
T
D
TR
A
C
T
B
TR
A
C
T
D
N:111567.95
E:193328.99
N:111581.70
E:193056.17
EXISTING 30'
SANITARY ALIGNMENT
STORM DRAIN 1
SEE SHEET U1
PROPOSED ELECTRIC
TRANSFORMER
PRIVATE DRIVE
8" PVC
W
A
T
E
R
5025
5030
5035
5040
5045
5050
5055
5060
5065
5025
5030
5035
5040
5045
5050
5055
5060
5065
9+5010+0011+0012+0012+50
SS
M
H
A
ST
A
1
0
+
0
0
.
0
0
RI
M
5
0
4
3
.
0
±
IN
V
.
I
N
5
0
3
7
.
6
6
(
S
)
IN
V
.
I
N
5
0
3
7
.
8
6
(
W
)
IN
V
.
O
U
T
5
0
3
7
.
6
6
(
N
)
162.37 LF 8" PVC @ 1
.
4
0
%
SS
M
H
A
1
ST
A
1
1
+
6
2
.
3
7
RI
M
5
0
4
8
.
1
±
IN
V
.
I
N
5
0
4
0
.
3
3
(
W
)
IN
V
.
O
U
T
5
0
4
0
.
1
3
(
E
)
72.84 LF 8" PVC @ 0.50%
SS
M
H
A
2
ST
A
1
2
+
3
5
.
2
1
RI
M
5
0
4
8
.
5
±
IN
V
.
I
N
5
0
4
1
.
0
3
(
N
)
IN
V
.
O
U
T
5
0
4
0
.
7
0
(
E
)
PROPOSED
GROUND
EXISTING
GROUND
CO
N
T
R
A
C
T
O
R
T
O
V
E
R
I
F
Y
LO
C
A
T
I
O
N
P
R
I
O
R
T
O
CO
N
S
T
R
U
C
T
I
O
N
.
SS1
PL
A
N
&
P
R
O
F
I
L
E
SA
N
I
T
A
R
Y
S
E
W
E
R
L
I
N
E
A
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
NORTH
Sheet
Of 23 Sheets
MA
N
H
A
T
T
A
N
T
O
W
N
H
O
M
E
S
,
S
E
C
O
N
D
F
I
L
I
N
G
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
10/9/15
SANITARY SEWER LINE A
PROFILE SCALE:
EXISTING WATER MAIN
LEGEND:
W
G
T
E
EXISTING STORM SEWER
PROPOSED ELECTRIC
EXISTING TELEPHONE
EXISTING GAS
SPROPOSED SEWER SERVICE & CLEAN OUT
EXISTING SANITARY SEWER SS
PROPOSED CURB & GUTTER
PROPOSED WATER SERVICE & CURB STOP
PROPOSED FIRE HYDRANT
EXISTING FIRE HYDRANT
EASEMENT LINE
PROPERTY BOUNDARY
PROPOSED LOTLINE
APPROXIMATE GAS METER LOCATION GM
W
PROPOSED WATER MAIN
PROPOSED SANITARY SEWER
PROPOSED STORM SEWER
APPROXIMATE ELECTRIC METER LOCATION EM
EXISTING WETLAND
SDPROPOSED SUBDRAIN
TPROPOSED TELEPHONE
GPROPOSED GAS
CTVEXISTING CABLE
EEXISTING ELECTRIC
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE
APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING
NEW CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING
ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE FOR ALL UNKNOWN
UNDERGROUND UTILITIES.
2.SEWER CONSTRUCTION SHALL BE PER CITY OF FORT COLLINS STANDARD
CONSTRUCTION SPECIFICATIONS.
3.ALL MANHOLE RIM ELEVATIONS ARE TO BE ADJUSTED TO 14" BELOW FINISHED
GRADE. CONE SECTIONS SHALL BE ROTATED TO PREVENT LIDS BEING LOCATED
WITHIN VEHICLE OR BICYCLE WHEEL PATHS.
4.ALL WATER FITTINGS AND VALVES ARE ONLY GRAPHICALLY REPRESENTED AND
ARE NOT TO SCALE.
5.UTILITY SERVICES ARE SHOWN IN A SCHEMATIC FASHION ONLY. EXACT LOCATIONS
SHALL BE PER THE REQUIREMENTS OF THE RESPECTIVE UTILITY PROVIDERS, AND
ARE SUBJECT TO CHANGE IN THE FIELD.
6.MAINTAIN 10' HORIZONTAL AND 18" VERTICAL MINIMUM SEPARATION BETWEEN ALL
SANITARY SEWER MAINS, WATER MAINS, SERVICES AND UNDERDRAINS.
7.ALL SINGLE-FAMILY SANITARY SEWER SERVICES TO BE 4" PVC @ 2%.
8.ALL SANITARY MANHOLES TO BE 4'Ø
9.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS,
UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
1
RE
C
O
R
D
D
R
A
W
I
N
G
MC
R
07
/
1
5
/
1
6
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/
/
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
XXXXXXXXXXX
DRAIN BASIN 1-3.1
w/ SOLID GRATE
INV.=5047.53 (E)
FG=5049.28
DRAIN BASIN 1-3.2
INV.=5047.84 (E)
FG=5049.55
19
.
5
7
L
F
6
"
H
D
P
E
@
5
.
0
0
%
30
.
9
8
L
F
6
"
P
E
R
F
.
P
V
C
@
1
.
0
0
%
49.4
8
49.2
0
49.4
2
49.4
4
49.5
2
49.5
5
49.6
5
49.6
3
49.6
8
49.7
0
48.0
8
SUB
47.8
6
SUB
48.
0
8
SU
B
48.0
6SUB
48.0
9
SUB
48
.
1
0
SU
B
48.3
0
SUB
48.2
7
SUB
48.2
7
SUB48.
2
9
SU
B
CONCRETE
w/ THICKENED
EDGE
CONCRETE
w/ THICKENED
EDGE
CONCRETE
w/ THICKENED
EDGE
LOT 6
LOT 7
LOT 8 LOT 9
TRACT B
TR
A
C
T
C
48.0
9SUB
47.7
8
SUB
1.
0
%
1.
0
%
1.0%
1.0%
PRIVATE DRIVE
PR
I
V
A
T
E
D
R
I
V
E
PROPOSED RAIN
GARDEN OUTFALL
SEE SHEET RG1
BASIN 1-3
INV. IN=5046.55 (W)
INV. IN=5044.95 (N)
INV. OUT=5044.95 (S)
FG=5048.87
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
TR
A
C
T
D
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
/
T
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD SD SD SD SD SD SD SD SD SD
X
X
X
X
X
X
X
X
X
X
DRAIN BASIN 2-3
INV.=5046.78 (E)
FG=5048.59
DRAIN BASIN 2-1
w/ SOLID GRATE
INV.=5045.19 (E)
FG=5046.94
DRAIN BASIN 2-2
INV.=5046.27 (E)
FG=5048.07
PIPE END 2
FG=5043.02
35.99 LF 6" HDP
E
@
9
.
7
0
%
107.95 LF 6" PERF. PVC @ 1.00%
101.62
L
F
6
"
P
V
C
@
0
.
5
0
%
46.0
3SUB
45
.
4
4
SU
B
45.6
4SUB
46.8
1
SUB
46.8
2
SUB
47.2
7
SUB
47.0
7
SUB
46.52
SUB
47.5
3
46.94
46.9
7
48.1
5
48.3
0
48.
6
3
48.
6
5
PERMEABLE
PAVERS
CONCRETE
w/ THICKENED
EDGE
48
.
0
9
1.0
%
46.7
4
SUB
48
.
1
5
PRIVATE DRIVE
LOT 21 LOT 20 LOT 19 LOT 18 LOT 17
LOT 22
LOT 23
LOT 24
LOT 25
LOT 26 LOT 27 LOT 28 LOT 29 LOT 30 LOT 31
LOT 32
TRACT B
TRACT D
CONCRETE
w/ THICKENED
EDGE
CONCRETE
w/ THICKENED
EDGE
46
.
5
2
SU
B
45.4
4SUB
47.0
3
SUB
1.
0
%
1.0%
0.5%PR
I
V
A
T
E
D
R
I
V
E
1.
0
%
1.0
%
1.0
%
1.0
%
1.
0
%
PVC GEOMEMBRANE
PVC GEOMEMBRANE
PVC GEOMEMBRANE
LEGEND:
PROPOSED SUBGRADE SPOT ELEVATION 33.43
PROPOSED SUBGRADE SLOPES
NOTES:
2.0%
EXISTING SPOT ELEVATION
PROPOSED SUBDRAIN
PROPOSED PVC STORM
SD
PROPOSED FINISHED GRADE SPOT ELEVATION 33.43
(33.43
)
SUB
SG1
SU
B
G
R
A
D
E
P
L
A
N
Sheet
Of 23 Sheets
MA
N
H
A
T
T
A
N
T
O
W
N
H
O
M
E
S
,
S
E
C
O
N
D
F
I
L
I
N
G
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
10/9/15
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
NORTH
NORTH
NORTH PAVER AREA
SOUTH PAVER AREA
1.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS,
UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
2.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE
APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY
OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL UNDERGROUND UTILITIES IN
THE AREA OF THE WORK. BEFORE COMMENCING NEW CONSTRUCTION, THE
CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES AND
SHALL BE RESPONSIBLE FOR FOR ALL UNKNOWN UNDERGROUND UTILITIES.
3.ALL CURB SPOTS SHOWN ARE FISHED GRADE ELEVATIONS UNLESS OTHERWISE NOTED.
4.CONTRACTOR SHALL NOTIFY THE DESIGN ENGINEER AND THE CITY OF FORT COLLINS
STORMWATER UTILITY A MINIMUM OF ONE WEEK IN ADVANCE SO AS TO ALLOW FOR FIELD
OBSERVATION AND DOCUMENTATION OF THE FOLLOWING SYSTEM ITEMS IN THE
PERMEABLE PAVER AREA:
- SUBGRADE
- INSTALLATION OF GEOTEXTILE FABRIC
- INSTALLATION OF UNDERDRAIN
- PLACEMENT AND COMPACTION OF SUB-BASE MATERIAL
- INSTALLATION OF EDGE RESTRAINT(S)
- PLACEMENT AND COMPACTION OF BASE MATERIAL
- PLACEMENT OF SETTING BED
- PLACEMENT OF UNIT PAVERS
- PLACEMENT AND SWEEPING OF JOINT FILLER
5.SUBGRADE AREAS ARE TO BE FIELD SURVEYED BY A LICENSED PROFESSIONAL. THE
DESIGN ENGINEER MUST CONFIRM THE SUBGRADE ELEVATIONS AND DIMENSIONS PRIOR
TO PLACEMENT OF GEOTEXTILE FABRIC, SUB-BASE, OR ANY OTHER MATERIAL.
6.EDGE RESTRAINTS AND CURBS SHALL BE PROVIDED BY THE GENERAL CONTRACTOR OR
THE EARTHWORK CONTRACTOR PRIOR TO PLACEMENT OF GEOTEXTILE FABRIC AND
SUB-BASE.
7.INSTALLATION OF PERMEABLE INTERLOCKING CONCRETE PAVEMENT (PICP) SYSTEM
SHALL FOLLOW THE GUIDELINES OF ICPI TECH SPEC NO. 18 AND FULL ICPI
SPECIFICATIONS. WORK SHALL BE PERFORMED BY A QUALIFIED CONTRACTOR.
QUALIFIED CONTACTOR SHALL MEAN AN ICPI 'CERTIFIED PAVER INSTALLER' HOLDING A
CURRENT PICP SPECIALIST DESIGNATION.
8.GENERAL CONTRACTOR SHALL CONVENE A PRE-CONSTRUCTION MEETING TO ENSURE
THAT ALL SUBCONTRACTORS HAVE AN UNDERSTANDING OF HOW THE PICP SYSTEM IS
INTENDED TO FUNCTION. CONTRACTOR SHOULD DISCUSS THE PROPOSED SEQUENCE
OF CONSTRUCTION AND IDENTIFY ACTIVITIES THAT MAY REQUIRE PROTECTION OF THE
PERMEABLE PAVEMENT SYSTEM.
9.THE CONTRACTOR SHOULD PROVIDE SLACK IN GEOTEXTILE FABRIC TO ENSURE PROPER
INSTALLATION AND AGGREGATE PLACEMENT WITHOUT DAMAGE. PROVIDE SUFFICIENT
SLACK SO THE FABRIC IS NOT TORN WHEN ROCK IS PLACED. IF TEARS ARE SEEN OR
DISCOVERED, REPAIR THEM AS RECOMMENDED BY MANUFACTURER WITH NO LESS THAN
18 INCHES OF OVERLAP ON ALL SIDES OF THE TEAR.
10.THE CONTRACTOR SHALL, AT ALL TIMES DURING AND AFTER SYSTEM INSTALLATION,
PREVENT SEDIMENT, DEBRIS, AND DIRT FROM ANY SOURCE FROM ENTERING THE
PERMEABLE PAVEMENT SYSTEM. LOOSE MATERIALS SHALL NOT BE STORED ON THE
PERMEABLE PAVEMENT AREA. MUD AND SEDIMENT-LADEN RUNOFF SHOULD BE KEPT
AWAY FROM THE PAVEMENT AREA. TEMPORARILY DIVERT RUNOFF OR INSTALL
SEDIMENT CONTROL MEASURES AS NECESSARY TO REDUCE THE AMOUNT OF SEDIMENT
RUN-ON TO THE PAVEMENT. SURFACE PROTECTION COULD INCLUDE COVERING AREAS
OF THE PAVEMENT, PROVIDING ALTERNATIVE CONSTRUCTION VEHICLE ACCESS, AND
PROVIDING EDUCATION TO ALL PARTIES WORKING ONSITE.
11.THE CONTRACTOR SHOULD CONSIDER PLACING THE WEARING COURSE AFTER FINE
GRADING AND LANDSCAPING IN ADJACENT AREAS IS COMPLETE. IF THE WEARING
COURSE BECOMES CLOGGED DUE TO CONSTRUCTION ACTIVITIES, CLEAN THE SURFACE
WITH A VACUUM MACHINE TO RESTORE THE INFILTRATION RATE AFTER CONSTRUCTION
IS COMPLETE.
12.BASE BID PAVERS SHALL BE FILTRAPAVE BY BORGERT PRODUCTS. DEFAULT LAYING
PATTERN SHALL BE 45° HERRINGBONE WITH AN UNCUT SAILOR OR SOLDIER COURSE
ALONG THE ENTIRE PERIMETER. CONFIRM PAVER TYPE, COLOR, AND PATTERN WITH
OWNER AND LANDSCAPE ARCHITECT PRIOR TO PURCHASING.
13.CONTRACTOR SHALL PROVIDE A 2% TO 3% OVERSTOCK OF UNCUT PAVERS TO THE
OWNER FOR USE IN FUTURE REPAIRS AND REPLACEMENT.
14.ALL CUT PAVERS USED MUST BE AT LEAST 40% OF THEIR FULL, UNCUT SIZE.
15.SEE SHEET D3 FOR ADDITIONAL DETAILS.
16.CONTRACTOR SHALL COORDINATE ANY NECESSARY TELEPHONE, CABLE AND ELECTRIC
LOWERINGS (OR RE-ROUTING) WITH THE RESPECTIVE UTILITY PROVIDERS TO FACILITATE
THE INSTALLATION OF THE PROPOSED STORM DRAIN AND UTILITY SERVICES.
TM
TYPICAL PAVER SECTION AT UNDERDRAIN
PERMEABLE PAVER OUTFALL
6" SLOTTED UNDERDRAIN
SUB-BASE
COURSE
BASE COURSE
BEDDING COURSE
FILTRAPAVE PAVER
GRANULAR BEDDINGSUBGRADE
FINISHED GRADE
ELEVATION
SUBGRADE
ELEVATION
TM
EXTEND FABRIC
24"-36"
NOTE:
1.CONTRACTOR TO PROVIDE GEOFABRIC CLOAKING AROUND OUTLET PIPE IN ADDITION TO
GEOTEXTILE LINER.
SUB-BASE
COURSE
BASE COURSE
BEDDING COURSE
FILTRAPAVE PAVER
CONCRETE w/
EDGE RESTRAINT
HDPE OUTFALL PIPE
CDOT CLASS B
GEOTEXTILE
SEPARATOR
FABRIC
DISCHARGE BASIN
(SOLID LID)
BASIN ID INLET TYPE
1-1 12" Basin w/ Solid Lid
1-1.1 12" Basin w/Dome Grate
1-1.2 12" Basin w/Dome Grate
1.2 12" Basin w/Dome Grate
1-2.1 12" Basin w/Dome Grate
1-3 12" Basin w/ Solid Lid
1-3.1 12" Basin w/ Solid Lid
1-3.2 12" Basin w/Dome Grate
1-5 12" Basin w/Dome Grate
1-6 12" Basin w/Dome Grate
2-1 12" Basin w/ Solid Lid
2-2 12" Basin w/ Solid Lid
2-3 12" Basin w/ Solid Lid
1
RE
C
O
R
D
D
R
A
W
I
N
G
MC
R
07
/
1
5
/
1
6
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XXXXXXXXXXXXXXXXXXXX
X
X
X
X
X
X
ST
/
/
/
/
/
/
/
/
/ / / / / /
/
/
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/ /
/
/
/
/
/
/
/ / / / /
/
/
/
/ / / / / / / // / / / / / / // / / / / / / // / / / / / / // / / / / / / /
T
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
N:111774.02
E:193339.38
N:111567.95
E:193328.99
48
.
3
0
48.45
48.48
48.24
47.9
6
48.0
5
47
.
6
5
47.7
9
47.4
5
47
.
3
1
47.1
5
46.9
4 47.0
5
48.39
48.3
7
48.23
48.28
48.6
0
48.
7
5
48.75
48.5
9
48.15
48.11
48.19
48.
6
2
48.89
49.3
0
48.50
48.
5
9
49.
1
3
LOT 14
FFE=50.72
LOT 15
FFE=50.72
LOT 16
FFE=50.72
50
.
7
1
50
.
6
3
50.71
50.22
49
.
2
2
49.2
2
50.67
50.62
50.64
49
.
6
7
48.67
48.6
7
48.
6
7
48.67
48.3
0
48.23
47.95
47.49
47.20
46.9
8
47.0
5
47.05
47.30
47.30
47.55
47.55
47.80
47.80
48.0
5
48.05
48.30
49.
0
1
48.
9
8
48.96
49.09
48
.
5
9
48
.
5
9
48
.
5
9
48.5
9
LOT 19
FFE=50.67
LOT 18
FFE=50.67
LOT 17
FFE=50.67
LOT 25
FFE=49.17
LOT 26
FFE=48.80
LOT 27
FFE=48.55
LOT 28
FFE=48.30
LOT 29
FFE=48.05
LOT 30
FFE=47.80
LOT 31
FFE=47.55
LOT 32
FFE=49.09
LOT 33
FFE=49.09
LOT 34
FFE=49.09
LOT 35
FFE=49.09
LOT 36
FFE=49.09
48.26
46.40
46
.
5
8
46.8
2
50.09
49.0
6
48
.
8
8
48.5
5
48.4
3
48.3
2
47.8
8
47.6
5
46.8
4
48.08
47.96
48.09
1.1%
1.1%
2.
0
%
16
.
8
%
TRACT B
0.5
%
1.
0
0
%
47.30
47.30
47.9
2
48.6
6
48.
0
1
47.7
7
48.0
8
TRACT D
1' SIDEWALK CHASE
1.1%
1.2%
1.0%1.0%
48.0
9
48.5
9
1.
0
%
2.
0
%
1.5
%
2.
4
%
0.5%
0.
2
%
2.
0
%
47.6
7
47.49
1.0%
4.
0
%
6:
1
1.6
%
46.7
9 46.4
8
47.
8
9
2.4%
46.46
46.3
9
48
.
5
148.5
8
50
.
0
4
50.5
6
50.0
9
48.79
49.01
49.4
0
49.8
8
PROPOSED
SUBDRAIN
SEE SHEET SG1
48.7
0
2' CURB CUT
PRIVATE DRIVE
PR
I
V
A
T
E
D
R
I
V
E
SOUTH PAVER AREA
SEE SHEET SG1
48.10
48.10
47.
5
4
47
.
5
4
47
.
5
4
47.5
4
48.
1
0
48.1
0
50
.
5
9
50.10
50.13
49.7
9
49.7
4
49
.
6
5
49
.
6
0
49.
4
5
50.0
6
50.5
9
50.5
4
48
.
8
5
49.19
48.5
2
49.7
8
48.6
0
48.66
48.59
48.5
4
48.4
4
49.7
8
49.8
4
49.
5
4
48.58
48.6
6
48.6
6
48.6
6
48.
6
1
47.7
4
46.8
5
46.7
6
46.8
2
46.3
7
46.9
6
46.8
8
46.4
5
46.9
3
47.7
7
48.0
6
48.3
4
48.62
48.5
4
48.2
9
48.14
48.01
48.11
47.11
48.30
47.4
8
46.3
8
46.4
8
46.7
0
46
.
4
2
46.4
2
48.74
48.10
45.98
46.25
48.60
1-6" STEP
1-6" STEP
1-6" STEP
1-6" STEP
1-6" STEP
50.0
9
1' SIDEWALK
CHASE
50.59
50
.
7
2
50.27
3.
0
%
4.4%
50.72
50.72
50.59
50.1
8
50
.
0
3
50.
6
4
50
.
6
4
49.8
6
49.86
49.7
8
49.8
6
49.8
6
49
.
7
8
49.69
49.5
549.4
8
49
.
6
9
3.3%
50.
6
7
50.67
4.3%
3.4%
49.45
49.0
8
49.9
0
50.1
7
49
.
9
6
50.21
50.26
3.3%
1.9
%
1.
5
%
1.0
%
48.4
6
48.3
3
48.3
6
48.4
6
47.3
5
47.2
7
47.50
49.01
48.98 48.98
49.
0
9
49.
0
9
49.09
49.09
48.96
48.9648.98
49.01
49.01
48.98
4.
4
%
48.6
6
48.6
6
48.6
6
48.6
6
48.6
6 48.
5
9
48.9
8
49.09
49.
0
1
49.0
1
4.
0
%
5.
0
%
4.
0
%
5.
0
%
4.8
%
48
.
3
4
48.61
48.5
3
48.26
47.42
48.0
1
47.9
3
47.93
47.6
6 47.2
8
47.3
6
47.30
47.6
9
47.65
47.3047.6
5
47.95
47.9
5
47.1
0
2.
2
%
46
.
6
7
46
.
3
7
46.
2
9
2.
1
%
47.5
5
46.6
7
47.3
0
47.8
0
46
.
4
8
1-6" STEP 46.7
0
46.
4
0
46.4
0
2.0%
2.0%
2.0%
47.
4
9
47.5
5
48.00
46.4
2
1-6" STEP
1-6" STEP
2-6" STEPS
2-6" STEPS
47.8648.30
47
.
6
2
0.
1
%
48.55
48.0
5
46.4
4
46.4
4
1-6" STEP
3-6" STEPS 47
.
8
6
1-6" STEP
3-6" STEPS
48.30
48.8
0
46.4
6
47.9
1
46.4
0
46.4
8
46.4
8
3.5%
48.49
48.08
47.9348.
3
1
48
.
3
9
48.75
46.4
0
2.0%
3-6" STEP
48.6
7
49.1
7
PROPOSED
LANDSCAPE WALL
47
.
2
7
48
.
5
3
INSTALL SOIL RIPRAP PAD
(SEE DETAILS)
48
.
7
0
48.
8
4
49.
7
0
50.
2
9
49.9
3
50.25
48.8
0
48.
3
5
48.51
49.5
2 49.5
8
48.47
48.4
9
48.4
5
48.3
8
48.3
0
49.88
49.93
50.29
48.77 47.7
5
48.8048.8
1
48.7
8
46
.
3
9
46
.
4
0
46.44
46
.
3
8
46.7
9
46.83
46.4
6
46.4
7
48
.
6
2
48.24
48.27
46.62
47.13
48.3
6
48.2
2
47.2
5
47.4
3
47.9
3
48.1
1
48.27
47.6
8
48.3
6
48.2
7
48.10
48.2
4
0.9%
50
.
6
3
50.63
50.
1
7
50.
1
7
49.0
2
49
.
0
0
49
.
0
2
46.9
8
47.3
0
46.7
0
47
.
5
5
47.80
48.30
48
.
0
5
48.05
48
.
3
0
48.36
AB
48.46
AB 48.53
AB
48.47
AB 48.3
5FL A
B
48
.
2
0
FL
A
B
48
.
1
9
FL
A
B
48
.
1
5
FL
A
B
48.2
1FL A
B
48
.
0
5
FL
A
B
47.8
2FL A
B
47.6
2FL A
B
47.3
1FL A
B
47.0
2
FL A
B
47.2
5
FL A
B
46.90
AB
47.12
AB
47.5
1AB
47.7
3AB
48.1
4AB
48.2
6AB
48.36
AB
48.39
AB
48.6
5
AB
48.4
2
AB
48.10
AB
48.
1
2
FL
A
B
48.17
FL A
B
48.
2
0
AB
48.09
AB
48
.
8
8
AB
48.7
1
FL A
B
48.6
3
FL A
B
46.94
47.8
6
AB
48.22
AB
48.29
AB
48.58
AB
48.71
AB
48.54
AB
48.59
AB
48.39
AB
48.50
AB
48.40
AB
48.50
AB
48.35
AB
48.42
AB
48
.
7
0
AB48
.
2
9
AB
48.31
AB
48.9
0
AB
47.90
AB
48.40
AB 49.10
AB
49.20
AB
48.4
0
AB
47.6
5
AB
48.6
8
AB48
.
6
1
AB
48.4
5
AB 48.6
4
AB
49.1
0
AB
48
.
7
0
AB
49.1
0
AB 49.1
0
AB
49.1
0
AB
48.0
0
AB
47.9
9
AB
48.70AB
48.6
6
AB 48
.
6
1
AB
49.09
AB
49.19
AB
49.15
AB
49.17
AB
49.02
AB
50.30
AB49.9
1
AB
49.
3
0
AB
49.
5
8
AB
50.
5
0
AB 50
.
6
0
AB
49
.
9
9
AB
49.54
AB
49.9
5AB
49.95
AB
49.9
9AB
50
.
0
7
AB
50
.
4
0
AB
50.
0
4AB
49.
9
9
AB
50
.
6
0
AB
49.83
AB
50
.
5
0
AB
50.3
2
AB
50.60
AB
50.70
AB50
.
5
0
AB
50.1
9
AB
50
.
5
0
AB
50
.
1
0
AB
48.8
3
AB 48.32
AB
48.84
AB 48.29
AB
48.5
4
FL A
B
48.5
8
AB
48.81
AB
49.1
8
AB
49.7
0
AB
48.3
9AB 48.8
1AB
48.
7
7
AB
48.9
0
AB
48.0
0
AB
48.
3
5
AB
48.38
AB
48.0
4
AB
48.30
AB
46.7
0
AB
46.1
0
AB
48.7
0
AB
46.5
0
AB
46.9
0
AB
46
.
5
0
AB
45.98
AB
46
.
0
3
AB
48.0
0AB
50.2
0AB
48.04
AB
49.10
AB
AS-BUILT
FF=50.70
50.0
2
AB50.1
8
AB50.6
0
AB
50.60
AB50.6
2
AB
49.9
8
AB
50.3
1
AB
49.89
AB
50.08
AB
49.65
AB
50.50
AB
50
.
2
0
AB50.
1
1
AB
50.00
AB
49.50
AB
49.51
AB
48.64
FL
A
B
48
.
8
5
AB
48
.
9
3
AB49.1
3
AB49.4
3
AB50.5
0
AB47.3
3
AB47.1
0 AB47.3
0
AB46.8
3
AB47.0
7
AB46
.
6
2
AB47.1
3
AB46.6
6
AB
46
.
5
6
AB46.7
2
AB
46.
8
0
AB
46.8
1
AB
46
.
7
0
AB47.5
0
AB47.4
0
AB47.7
0
AB
46
.
8
9
AB46.92
AB47
.
6
0
AB47.7
0
AB47
.
6
0
AB46.9
1
AB46.8
8
AB
46
.
8
5
AB47.7
0
AB
46
.
8
9
AB46.
9
0
AB48.
0
0
AB
46.
8
2
AB47.
9
0
AB46.7
4
AB
46.
8
0
AB
48.
3
0
AB
48.
2
0
AB
46.
6
1
AB
47.7
0
AB46.6
5
AB46.5
9
AB
46.
8
4
AB47.99
AB48.15
AB47.78
AB47.59
AB48.35
AB
48.80
AB
48.3
7
48.39
AB
AB48.20
AB48.06
AB
47
.
8
9
AB
48
.
7
0
AB47.4
5
AB47.1
4
AB47.0
3
AB
49
.
4
1
AB
49
.
8
2
1.5%
AS-BUILT
FF=49.06
AS-BUILT
FF=49.07
AS-BUILT
FF=48.65
AS-BUILT
FF=48.93
AS-BUILT
FF=48.32
AS-BUILT
FF=48.13
AS-BUILT
FF=47.86
AS-BUILT
FF=47.90
AS-BUILT
FF=50.86
AB
48.03
0.2%
0.5%
0.0%
0.2%
1.1%
2.8%
AB
48.27
AB
48.26
AB
47.94AB
48.14
AB
48.29 AB48
.
2
7
AB
48.85
AB
48.4
0
0.5%0.1%
0.6%
0.
0
%
0.
5
%
AB46.6
1
AB47.0
7
AB47.3
8
AB46.8
1
AB47.3
9
AB47.0
3
AB46.2
9
AB46.8
9
AB45.7
1
AB F
L46.3
0
AB45.3
0
AB F
L45.5
0
AB F
L45.2
0
AS-BUILT FLOWLINE
(TYP.)
AS-BUILT FLOWLINE
(TYP.)
AB F
L46.1
0
AB H
P46.6
0
AB F
L46.3
0
AB L
P46.0
0
AB F
L46.3
0
AB H
P46.6
0
AB F
L46.0
0
AB FL
45.60
2.7
%
1.7%1.2%
1.
0
%
1.
2
%
1.
2
%
1.
2
%
1.
2
%
2.
0
%
1.
4
%
AB44.3
0
2.6%
3.0%
11.0%
47.11
AB
46.90
AB
48.41
AB
48.07
AB
AB49.5
7
AB
49
.
3
3
AB
48.74
1.3
%
0.
8
%
1.0
%
1.
0
%
G4
DE
T
A
I
L
E
D
G
R
A
D
I
N
G
P
L
A
N
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
NORTH
Sheet
Of 23 Sheets
MA
N
H
A
T
T
A
N
T
O
W
N
H
O
M
E
S
,
S
E
C
O
N
D
F
I
L
I
N
G
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
S
H
E
E
T
G3
MATCHLINE - SEE SHEET G5
LEGEND:
PROPOSED CONTOUR
AS-BUILT CONTOUR
PROPERTY BOUNDARY
PROPOSED SPOT ELEVATION
PROPOSED SLOPES
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE
APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING
NEW CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING
ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE FOR FOR ALL
UNKNOWN UNDERGROUND UTILITIES.
2.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS,
UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
3.ALL CURB SPOTS SHOWN ARE FLOWLINE ELEVATIONS. ALL OTHER SPOTS ARE
FINISHED GRADE ELEVATIONS.
4.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM ELEVATIONS
REQUIRED FOR PROTECTION FROM THE 100-YEAR STORM.
5.SPOT ELEVATIONS DEPICTED ADJACENT TO RETAINING WALLS REPRESENT THE
FINISHED GRADE ELEVATIONS AT THE LOW SIDE AND HIGH SIDE OF EACH WALL.
RETAINING WALLS OVER 4 FEET IN HEIGHT, MEASURED FROM THE LOW SIDE
GRADE TO THE TOP OF THE WALL, WILL REQUIRE A SEPARATE PERMIT THROUGH
THE BUILDING DEPARTMENT. A SEPARATE PERMIT IS NOT REQUIRED FOR
RETAINING WALLS THAT ARE NOT OVER 4 FEET IN HEIGHT, MEASURED FROM THE
LOW SIDE GRADE TO THE TOP OF THE WALL, PROVIDED THE HORIZONTAL
DISTANCE TO THE NEXT UPHILL RETAINING WALL IS AT LEAST EQUAL TO THE
TOTAL HEIGHT OF THE LOWER RETAINING WALL (UNLESS SUPPORTING A
SURCHARGE OR IMPOUNDING CLASS I, II OR IIIA LIQUIDS). REFER TO LANDSCAPE
PLAN DETAIL A, SHEET 10 FOR WALLS BELOW 4 FEET IN HEIGHT. WALLS GREATER
THAN 4 FEET IN HEIGHT WILL BE DESIGNED BY OTHERS UNDER SUBSEQUENT
BUILDING PERMIT APPLICATION(S).
NOTES:
EXISTING SPOT ELEVATION
PROPOSED UNDERDRAIN
PROPOSED STORM
PROPOSED VERTICAL
CURB AND GUTTER
PROPOSED SWALE
SD
KEYMAP
X
X
XX
X
G2
G3
G4G5
1
RE
C
O
R
D
D
R
A
W
I
N
G
MC
R
07
/
1
5
/
1
6
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
FESF
ES
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
/ / / / / /
/
/
/ / / / / /
/
/
/ / / / /
/
/
/
/ / / / /
/
/
/
/ / / / /
/
/
/
/ / / / /
/
/
/
/ / / / /
/
/
/
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / / /
/ / / / / / /
/
/ / / / / / /
/
/ / / / / / /
/
/ / / / / / /
/
/ / / / / /
/
/
X
X
X
X
X
X
X
X
X
X
X
T
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
SD
N:111581.70
E:193056.17
48.39
48.3
7
48.23
48.28
48.6
0
48.
7
5
48.75
48.7
3
48.7
1
48.
6
0
48.8
0
48.73
48.73
48.7
5
48.75
48.5
9
48.15
48.11
48.19
48
.
6
2
48.89
49.3
0
LOT 16
FFE=50.72
LOT 21
FFE=50.67
48.3
0
48.28
48.6
9
50.71
50.22
50.17
50
.
6
4
50.67
50.62
50.64
49
.
6
7
48.67
48.6
7
48.67
48.6
7
48.6
7
48
.
6
7
48.
6
7
48.67
48.3
0
48.23
47.95
48.0
5
48.05
48.30
LOT 20
FFE=50.67
LOT 19
FFE=50.67
LOT 18
FFE=50.67
LOT 17
FFE=50.67
LOT 22
FFE=49.17
LOT 23
FFE=49.17
LOT 24
FFE=49.17
LOT 25
FFE=49.17
LOT 26
FFE=48.80
LOT 27
FFE=48.55
48
.
3
8
46.9
1
46.50
48.26
47.10
46.40
49
.
9
9
50.09
49.0
6
49.87
48
.
8
8
48.08
47.96
48.09
48
.
4
1
2.0
%
1.1%
1.1%
6.
7
%
7.4
%
6.8%
0.5
%
48.70
48.01
47.9
2
48
.
7
0
STORM DRAIN 1
SEE SHEET U1
TRACT
D
1' SIDEWALK CHASE
1.1%
1.2%
1.0%
1.0%
0.5
%
1.3
%
1.6
%
47.7
5
46.7
9 46.4
8
47.
8
9
2.4%
46.46
50.0
9
50
.
0
4
50.5
6
50.0
9
48.79
49.01
49.4
0
49.8
8
PROPOSED
SAWCUT LINE
PROPOSED
SAWCUT LINE
PROPOSED
SUBDRAIN
SEE SHEET SG1
SOUTH PAVER AREA
SEE SHEET SG1
MANH
A
T
T
A
N
A
V
E
MA
N
H
A
T
T
A
N
A
V
E
50
.
5
9
50.10
50.13
49.7
9
49.7
4
49
.
6
5
49.
6
0
49.
4
5
50.0
6
50.5
9
50.5
6
50.5
9
49.0
2
50.5
4
48
.
8
5
49.19
49.7
8
48.6
0
49.7
8
50.23
49.8
4
49.
5
4
48.14
48.01
48.11
48.30
48.74
48.10
45.98
46.2
5
48.5
0
48.7
0
48.7
9
48.22
47.70
47.50
47.34
49.0
9
48.54
48.5
4
48.60
47
.
1
0
47.0
4
46.5
7
1' SIDEWALK CHASE
1-6" STEP
1-6" STEP
1-6" STEP
1-6" STEP
50.0
9
1' SIDEWALK
CHASE
1-6" STEP
1-6" STEP
2-6" STEPS
2-6" STEPS
50.1
9
50.27
3.
0
%
4.4%
50.72
50.72
50.59
50.1
8
50
.
0
3
49.89
50
.
6
4
50.
6
4
49.8
6
49.86
49.7
8
49.8
6
49.8
6
49
.
7
8
49.69
49.5
549.4
8
49
.
6
9
3.3%
50
.
6
7
50.67
4.3%
3.4%
49.45
49.0
8
49.9
0
50.1
7
49
.
9
6
50.21
50.26
50
.
1
2
49.95
49.84
50.56
50.
5
6
3.3%
4.4%
1.8%
50.67
50.67
49.96
49.45
49.4
5
49.0
849.1
0
1.9
%
1.
5
%
1.0
%
2.3
%
0.5%
2.0%
48.55
48.0
5
46.4
4
46.4
4
1-6" STEP
3-6" STEPS 47
.
8
6
1-6" STEP
3-6" STEPS
48.30
48.8
0
46.4
6
47.9
1
46.4
0
46.4
8
46.4
8
3.5%
48.49
48.08
47.9348.
3
1
48
.
3
9
48.75
46.4
0
2.0%
3-6" STEP
48.6
7
49.1
7
46.50
48.0
4
48.6
7
49.1
7
3-6" STEP
46.6747.04
46.4
2
46
.
8
3
47.4
5
47.54
47.54
48.6
7
49.1
7
1-6" STEP
47.5
4
48.80
48.7
0
48
.
4
0
47.8
4
48.0
9
48.
0
9
49.1
7
48.3
0
48.24
48.2
2
48.2
2
2.0
%
2.0%
48
.
4
8
10
.
6
%
2.2
%
2.3
%
48.0
7
48.
1
4
48.19
48.20
0.5%
1.0%
2.0
%
0.5%
INSTALL SOIL RIPRAP PAD
(SEE DETAILS)
49.6
9
49.
7
0
50.
2
9
49.9
3
50.25
48.8
0
48.51
49.5
2 49.5
8
48.47
49.88
49.93
50.29
50.
1
6
46.44
46.4
6
46.4
7
48
.
6
2
48.24
48.27
46.62
47.13
48.3
6
48.2
2
48.1
1
48.27
48.3
6
48.2
7
48.10
48.2
4
47.79
48.5
4
48.4
5
48.67
48.60
48.6
7
48.6
1
48
.
5
5
48.72
48.7
4
47.72
47.7
4
47.98
47.60
50.63
50.67
50.
1
7
50
.
1
7
48.30
48
.
0
5
48.05
48
.
3
0
4:1
48.6
7
48.6
7
48.67
48.67
49.17
48.
6
7
48.67
48.1
4AB
48.2
6AB
48.36
AB
48.39
AB
48.6
5
AB
48.4
2
AB
48.
7
2
FL
A
B
48.7
7
FL A
B
48.71
FL AB
48.10
AB
48.
1
2
FL
A
B
48.17
FL A
B
48.
2
0
AB
48.09
AB
AB
48.
3
2
AB
48.
2
0
AB
47.
9
7
AB
47.
9
1
AB47.83
AB47.6
2
AB47.
4
1
AB
47.
3
1
AB
47.
7
6
AB
85.
4
2
48
.
8
8
AB
48.7
1
FL A
B
48.6
3
FL A
B
49.09
AB
49.19
AB
49.15
AB
49.17
AB
49.02
AB
50.30
AB49.
9
1
AB
49.
3
0
AB
49.
5
8
AB
50.
5
0
AB 50
.
6
0
AB
49
.
9
9
AB
49.54
AB
49.9
5AB
49.95
AB
49.9
9AB
50
.
0
7
AB
50
.
4
0
AB
50.
0
4AB
49.
9
9
AB
50
.
6
0
AB
49.83
AB
50
.
5
0
AB
50.3
2
AB
50.60
AB
50.70
AB50
.
5
0
AB
50.1
9
AB
50
.
5
0
AB
50
.
1
0
AB
50.30
AB
49
.
7
5
AB
50.14
AB
50.05
AB
49.86
AB
49
.
9
0
AB
50.1
0
AB
50.00
AB
50.0
0AB
50.2
0
AB
49.58
AB
49.11
AB
49.04
AB
48.98
AB
48.84
AB
48
.
7
9
FL
A
B
49.36
AB
48.86
FL AB
48.62
AB
48.8
8
AB
48.3
4
AB
48.84
AB
48.8
3
AB 48.3
2
AB
48.84
AB 48.29
AB
48.5
4
FL A
B
48.58
AB
48.81
AB
49.18
AB
49.7
0
AB
48.50
AB 48.80
AB
48.3
9AB 48.8
1AB
48.5
7AB 48.8
1AB
48.3
0AB
48.69
AB 48.9
0
FL A
B
48
.
8
8
FL
A
B
48.7
0FL A
B
48
.
7
7
AB
48.9
0
AB
48.0
0
AB
48.
3
5
AB
48.38
AB
48.0
4
AB
48.30
AB
46.7
0
AB
46.1
0
AB
48.7
0
AB
46.5
0
AB
46.9
0
AB
46.6
8
AB
46.5
5
AB
46
.
5
0
AB
45.98
AB
46
.
0
3
AB
48.0
0AB
48.9
0AB
47.
2
1AB49.0
6
AB
49.1
4
AB
47.0
8
AB
49.0
0
AB
47.4
8
AB
47.6
7
AB
47.3
8
AB
47.4
5
AB
48.4
7
AB
47.8
0
AB
48.9
0
AB
47.8
7
AB
47.8
5
AB
49.1
3
AB
46.50
AB
47.8
7AB
47.9
0AB
49
.
1
0
AB
48.8
0AB
48
.
8
0
AB
47
.
8
0
AB
47.40
AB
49.22
AB
50.30
AB
50.2
0AB
47.39
AB
AB50.1
8
AB
50.3
8
AB50.6
2
AB
49.9
8
AB
50.3
1
AB
49.89
AB
50.08
AB
49.65
AB
50.50
AB
50
.
2
0
AB50
.
1
1
AB
50.00
AB
49.50
FL
A
B
48
.
9
3
AB49.1
3
AB49.4
3
AB50.5
0
AB46.
9
0
AB48.
0
0
AB
46.
8
2
AB47.
9
0
AB46.7
4
AB
46.
8
0
AB
48.
3
0
AB
48.
2
0
AB
46.
6
1
AB
47.7
0
AB46.6
5
AB46.5
9
AB
46.
8
4
AB48.15
AB48.35
AB
48.80
AB
48.3
7
48.39
AB
AB48.20
AB48.06
AB
47
.
8
9
AB
49
.
4
1
AB
49
.
8
2
AS-BUILT
FF=49.20
AS-BUILT
FF=48.65
AS-BUILT
FF=48.93
AS-BUILT
FF=50.86
AB48.5
2
48.93
AB
0.4%
0.3%
0.3%
0.8%
0.3%
0.3%
0.5%
0.8%
2.8%
AB
48.55
AB
48.51
AB
48.38
AB
48.27
AB
48.26
0.
0
%
0.
5
%
0.
5
%
0.
2
%
47.72
AB
AB47.0
7
AB47.3
8
AB45.7
1
AB45.3
0
AB45.8
0
AB46.6
3
AS-BUILT FLOWLINE
(TYP.)
AB F
L46.1
0
AB H
P46.6
0
AB F
L46.3
0
1.
2
%
2.
0
%
1.
4
%
2.6%
3.0%
AB49.5
7
AB
49
.
3
3
1.3
%
0.
8
%
1.0
%
1.
0
%
G5
DE
T
A
I
L
E
D
G
R
A
D
I
N
G
P
L
A
N
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
NORTH
Sheet
Of 23 Sheets
MA
N
H
A
T
T
A
N
T
O
W
N
H
O
M
E
S
,
S
E
C
O
N
D
F
I
L
I
N
G
30
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
Fo
r
t
C
o
l
l
i
n
s
,
C
o
l
o
r
a
d
o
8
0
5
2
1
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
PH
O
N
E
:
9
7
0
.
2
2
1
.
4
1
5
8
ww
w
.
n
o
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
MA
T
C
H
L
I
N
E
-
S
E
E
S
H
E
E
T
G3
MATCHLINE - SEE SHEET G4
LEGEND:
PROPOSED CONTOUR
AS-BUILT CONTOUR
PROPERTY BOUNDARY
PROPOSED SPOT ELEVATION
PROPOSED SLOPES
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE
APPROXIMATE WHEN SHOWN ON THESE DRAWINGS. IT SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE EXISTENCE OF ALL
UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING
NEW CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING
ALL UNDERGROUND UTILITIES AND SHALL BE RESPONSIBLE FOR FOR ALL
UNKNOWN UNDERGROUND UTILITIES.
2.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS,
UTILITY EASEMENTS, OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
3.ALL CURB SPOTS SHOWN ARE FLOWLINE ELEVATIONS. ALL OTHER SPOTS ARE
FINISHED GRADE ELEVATIONS.
4.THE TOP OF FOUNDATION ELEVATIONS SHOWN ARE THE MINIMUM ELEVATIONS
REQUIRED FOR PROTECTION FROM THE 100-YEAR STORM.
5.SPOT ELEVATIONS DEPICTED ADJACENT TO RETAINING WALLS REPRESENT THE
FINISHED GRADE ELEVATIONS AT THE LOW SIDE AND HIGH SIDE OF EACH WALL.
RETAINING WALLS OVER 4 FEET IN HEIGHT, MEASURED FROM THE LOW SIDE
GRADE TO THE TOP OF THE WALL, WILL REQUIRE A SEPARATE PERMIT THROUGH
THE BUILDING DEPARTMENT. A SEPARATE PERMIT IS NOT REQUIRED FOR
RETAINING WALLS THAT ARE NOT OVER 4 FEET IN HEIGHT, MEASURED FROM THE
LOW SIDE GRADE TO THE TOP OF THE WALL, PROVIDED THE HORIZONTAL
DISTANCE TO THE NEXT UPHILL RETAINING WALL IS AT LEAST EQUAL TO THE
TOTAL HEIGHT OF THE LOWER RETAINING WALL (UNLESS SUPPORTING A
SURCHARGE OR IMPOUNDING CLASS I, II OR IIIA LIQUIDS). REFER TO LANDSCAPE
PLAN DETAIL A, SHEET 10 FOR WALLS BELOW 4 FEET IN HEIGHT. WALLS GREATER
THAN 4 FEET IN HEIGHT WILL BE DESIGNED BY OTHERS UNDER SUBSEQUENT
BUILDING PERMIT APPLICATION(S).
NOTES:
EXISTING SPOT ELEVATION
PROPOSED UNDERDRAIN
PROPOSED STORM
PROPOSED VERTICAL
CURB AND GUTTER
PROPOSED SWALE
SD
KEYMAP
X
X
XX
X
G2
G3
G4G5
1
RE
C
O
R
D
D
R
A
W
I
N
G
MC
R
07
/
1
5
/
1
6
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
Manhattan Townhomes Paver Extent Revision
Date:May 24, 2016
Project:Manhattan Townhomes Project No. 1124-001
Fort Collins, Colorado
Attn:Wes Lamarque
City of Fort Collins Utilities/Stormwater
700 Wood Street
Fort Collins, CO 80521
Mr. Lamarque:
As you know, the City of Fort Collins recently adopted changes to portions of the City code which
pertain to Low Impact Development (LID) requirements for new developments within the City of
Fort Collins. In particular, the City of Fort Collins will now waive the requirement that 25% of all
new pavement be permeable if a project treats 75% or more of the project site using approved LID
techniques.
In the case of Manhattan Townhomes, the original design that was completed prior to the City
Ordinance changes treated 80% of the site using a combination of LID techniques, including rain
gardens and permeable pavements. Since more than 75% of the site is being treated by these
techniques, the project site qualifies for a waiver of the minimum amount of permeable pavements
under the revised ordinance. With this in mind, the project would like to remove the small paver
area at the north entrance that had been provided to meet the 25% requirement. Removal of this
paver area will result in 77% of the project site being treated by an approved LID method, which
exceeds the 75% minimum requirement.
In addition to this memo, we are providing both the originally approved LID Exhibit as well as the
updated LID Exhibit with the north paver area removed for your reference.
Please feel free to contact me if you have any questions.
Sincerely,
Andrew Reese
Project Engineer