October 27, 2017
Mrs. Heather McDowell
City of Fort Collins Stormwater Utility
700 Wood Street
Fort Collins, Colorado 80522
RE: Drainage Certification for Lyric Cinema
Fort Collins, Colorado
Dear Heather:
This drainage certification letter is provided to verify as-constructed conditions for Lyric Cinema.
Landmark, Ltd. completed survey work October 13, 2017, and Northern Engineering visited the site
October 17, 2017, to verify general compliance with the Final Utility Plans for Lyric Cinema, dated
11/23/2016 by Northern Engineering.
Included in this drainage certification submittal are the following:
Attachment 1 - City of Fort Collins Overall Site and Drainage Certification Form.
Attachment 2 - City of Fort Collins During Construction Inspection Checklist and photographs provided
by contractor.
Attachment 3 - As-constructed detention pond calculations.
Attachment 4 - As-constructed record drawings for Grading and Storm Drain Plan and Profile Sheets.
Based on the calculations shown in Attachment 3, the as-built water quality pond volumes are in Table
1.
Table 1: Water Quality & Detention Pond Volumes
Pond
Design Water
Quality Vol.
(ft3)
As-built
Water Quality
Vol. (ft3)
Design
Detention
Vol. (ft3)
Design Max.
Attenuation w/
Offsite Flow (ft3)
As-built
Detention
Vol. (ft3)
Water Quality &
Detention Pond 1,616 1,675 16,555 29,602 30,150
We have concluded, based on the attached information and personal site inspection, that the
drainage features for the project site have been constructed in substantial compliance with the
above referenced Final Utility Plans, with the following exceptions:
FORT COLLINS: 301 North Howes Street, Suite 100, 80521 | 970.221.4158
GREELEY: 820 8 th Street, 80631 | 970.395.9880 | W EB: www.northernengineering.com
• Item I.A.5: Based on permeability tests of the pre-developed
soil conditions within the LID portion of the pond, there exists
a 5 to 7 ½ feet of sandy clay and clayey sand overlaying
cleaner sand and gravel (CTL Thompson, July 29, 2016).
The sandy clay and clayey sand has a permeability of 0.38
ft/day (Test Pit P-4). This low permeability was assumed for
the entire area of the LID portion of the pond (37,56 ft2), and
the resulting infiltration is 0.02 cfs.
Based on conversations with the contractor, the two dry wells
within the LID feature were installed deep into the cleaner
sand and gravel with good infiltration. According to the
permeability tests performed by CTL Thompson, the cleaner
sand and gravel has a permeability of 10 ft/day (Test Pit P-
1). This higher permeability was assumed for both dry wells,
and the resulting infiltration is 0.02 cfs.
The orifice rating curve from the Final Drainage and Erosion
Control Report for Lyric Cinema was adjusted by adding 0.04
cfs throughout the curve. This revised rating curve (see Table
2) was then entered in the State Drain Time Spreadsheet
provided by the City of Fort Collins to determine the drain
time for the detention pond. This results in 97% of the
inflow volume will drain in 20 hours and 99% of the inflow
volume will drain in 62 hours.
• Item I.B.4: The 100-year control orifice was installed per the approved design drawings.
• Item III.A.1: The 21 feet of the Storm Sewer A from Manhole A1 to Manhole A2, located
within the right-of-way, (shown on Sheet C403) was changed to a 19” x 30” elliptical pipe
(24” equivalent) to avoid the gas main in College Avenue.
• Item III.A.2: Storm Sewer A from Manhole A1 to Manhole A2 (shown on Sheet C403) was
constructed with a slope below the design of 0.25% (a slope of 0.23% was constructed).
We have re-analyzed this storm line and compared the hydraulic grade line. As shown
below, there is no minimal change to the 100-year HGL. Base on the revised HGL, we feel
this will convey the design storm hydraulic capacity.
Table 2: Revised Outfall
Rating Curve
User
Defined
User
Defined
Stage [ft] Discharge
[cfs]
0.00 0.04
0.28 0.04
0.53 0.04
0.78 0.06
1.03 0.07
1.28 0.07
1.53 0.07
1.78 0.08
2.03 0.08
2.28 0.08
2.53 0.08
2.78 0.09
3.03 0.09
3.28 0.09
3.50 0.09
FORT COLLINS: 301 North Howes Street, Suite 100, 80521 | 970.221.4158
GREELEY: 820 8 th Street, 80631 | 970.395.9880 | W EB: www.northernengineering.com
• Item III.A.2: Storm Sewer C from Inlet C2 to Inlet C3 (shown on Sheet C405) was
constructed with a slope below the design of 0.40% (a slope of 0.28% was constructed).
We have re-analyzed this storm line and compared the hydraulic grade line. As shown
below, there is no minimal change to the 100-year HGL. Base on the revised HGL, we feel
this will convey the design storm hydraulic capacity.
FORT COLLINS: 301 North Howes Street, Suite 100, 80521 | 970.221.4158
GREELEY: 820 8 th Street, 80631 | 970.395.9880 | W EB: www.northernengineering.com
• Item III.B.2: Northern Engineering did not observe construction of the storm sewer.
Northern Engineering was unable to verify the encasements and clearances specified on the
approved construction plans.
• Item III.B.3: Northern Engineering did not observe construction of the storm sewer.
Northern Engineering was unable to verify the specific joint types and construction methods.
• Item VII.A.2: According to the contractor, the subdrain under the LID was installed per the
approved design drawings. Northern Engineering did not observe construction, and
Northern Engineering was unable to verify if the perforated and non-perforated sections of
the underdrain were constructed per the approved design drawings.
• Item XIII.A.1: Construction debris was not removed at the time of Northern Engineering’s
site inspection.
• Item XIII.A.2: Ruts were not removed at the time of Northern Engineering’s site inspection.
The owner was in the process of removing ruts and installing landscaping at the time of
Northern Engineering’s site inspection.
Please feel free to contact me with any questions you may have.
Thank you,
NORTHERN ENGINEERING SERVICES, INC.
Frederick S. Wegert, PE
Project Engineer
12/15 Page 1
OVERALL SITE and DRAINAGE CERTIFICATION
Commercial, Multi-Family and Subdivision Certification Form and Checklist
Project Name:
Date:
Building Permit Numbers:
(Commercial or multi-family)
Per the requirement in Fort Collins Stormwater Criteria Manual (FCSCM) Volume 1, Section 6.11, please fill in
all applicable items in this Certification Form for Commercial, Multi-Family and Overall Single Family sites.
NOTE: several items must be verified during construction. A copy of the approved grading plan must be
submitted with the as-built grading plan. (As-built elevations must be written in red next to the approved
elevations.)
•Use “Yes” for items completed as described.
•Use “N/A” for items that are not applicable to the site being certified.
•If any blanks are “No,” attach an explanation referencing the item number below.
Attach an explanation or description of the as-built condition for any items listed or for anything not listed but
shown on the approved construction plans.
Provide an as-built redline or Mylar drawing with the following:
I.Water Quality and Quantity Detention Basin Certification - FCSCM Vol.2, Ch.10
For multiple detention basins on a site, provide the following for each basin separately:
A. Volume: As-built topographic verification is attached at 1-foot (or less) contour intervals and
volume verification calculations for the water quality capture volume and the 100-year detention storage
volume.
1. Detention basin topography was prepared by a professional land surveyor registered in the state
of Colorado.
2.Both proposed and as-built contours are shown on the same plan sheet (dashed lines for
proposed and solid lines for as-built).
3.All critical spot elevations as shown on the approved construction plans have been verified and
the as-built elevations are shown on the plan sheet.
4.Stage-storage-discharge tables are provided on a separate document.
5.Verification that designed drain time is in compliance with Colorado Revised Statute § 37-92-
602(8) is attached and has been uploaded to the Statewide Compliance Portal
(tinyurl.com/COCompliancePortal) for approval. Uploaded documents must include:
a.The cover sheet from the approved drainage report
b.The stamped certification page from the approved drainage report
c.As-built topographic survey
d.Stamped certification page from the Overall Site & Drainage Certification
e.PDF output from the Stormwater Detention and Infiltration Design Data Speadsheet
12/15 Page 2
B.Water Quality and Quantity Detention Basin Grading: Attached is as-built verification that there is
a minimum 2% positive fall into the concrete trickle pans or flow-line(s) from all areas in the bottom of
the detention pond. If there is a “soft pan” in the flow-line, all areas still must meet the minimum 2%
grade requirement.
1.Low Flow: Choose one of the following detention basin low flow options as applicable:
a. Turf swale for low flow path in detention basin.
There is a minimum 2% grade in the flow-line(s) of the detention basin. The flattest as-built grade
is .
b.Concrete pan for low flow in detention basin.
There is a concrete pan installed that meets the grades as shown on the approved construction
plans. (Show as-built spot elevations.)
c.Soft pan for low flow in detention basin.
•Verify and document the soft pan material gradation, trench width and depth - to be verified
during construction by engineer. Picture documentation is preferred or engineer’s statement of
visual inspection and compliance. (Choose one below.)
o There is a soft pan with an underdrain installed that meets the design on the approved
construction plans. (Show the underdrain grades, bedding material, geotextile, spot elevations,
bends, cleanouts, etc.)
o There is soft pan installed without an underdrain but there is a type A or B soil. The soil
type must be documented by supplying verification from a registered professional geotechnical
engineer.
NOTE: Spot elevations are to be within 0.2 ft. +/-.
2. Side Slopes: The as-built side slopes of the detention basin have been calculated and are shown.
Indicate the side slope with an arrow and a numerical value (e.g., 6.25:1). The maximum slope allowed
is 4:1. Small areas of 3:1 may be acceptable, but slopes steeper than 3:1 must be stabilized or re-
graded. Provide documentation if a variance was granted for steeper slopes during the design process.
3.Spillway Certification: The following items must be field verified:
a.The location of the spillway is indicated on the as-built plan.
b.The width of the spillway is indicated on the as-built plan.
c.The elevation(s) of the spillway is shown on the as-built plan.
d.A concrete ribbon defines the location and grade of the spillway.
e.There is downstream scour protection in the spillway as per the construction plans. Indicate
type: (riprap size “D50” gradation and bedding type, geotextile, buried
riprap with inches of bury, etc.).
f.There are no obstructions in the spillway, such as trees, bushes, sidewalks, landscape
features, rocks, etc.
12/15 Page 3
4.Outlet Structure Certification
a.The orifice plate for the approved release rate is installed with the correct size and location of
the orifice.
b.The orifice plate for the water quality outlet is installed with the correct hole size, number of
rows and columns of holes.
c.The bottom hole on both the water quality and quantity outlets are at the bottom of the plate
so no water ponds in front of the plate.
d.The well screen is the correct material and is installed as shown on the construction plans.
e.100-year overflow grate elevation is . (Elev. A on detail D-46)
f.The top elevation of the water quality capture volume is . (Elev. B on detail
D-46)
g.Overflow grate is made of the correct material, has the correct bar spacing, is hinged at the
top and bolted at the bottom.
h.The bottom of the outlet box has no obstructions or misalignments that will cause it to retain
runoff water and is sloped at 2% towards outlet.
II.Channels/Swales - FCSCM Vol.1, Ch.7, Sect.3&4
A. Capacity: The as-built capacity of all the major channels and swales has been verified. They meet
or exceed capacity requirements shown in the approved drainage study for this project.
1.All swales are located within the drainage easements as shown on the construction plans.
2.Longitudinal slopes and side-slopes (cross-sections) have been verified. Design criteria requires
longitudinal slopes of 2% min. (on vegetated swales) and side-slopes no steeper than 4:1. If these
criteria are not met, the certification engineer will write a justification and propose mitigation for each
instance or have the issues corrected. If variances to these criteria have previously been approved and
are shown on the construction plans, no justification is needed.
3.As-built spot elevations on channels/swales are shown that correspond to spot elevations
shown on the approved construction plans.
4.All permanent erosion control measures are installed as shown on the approved construction
plans (e.g., drop structures, riprap, TRMs, etc.). (Include pictures and verification of the materials used
as part of this verification.)
5.All pans, curbs, storm pipes or other appurtenances appropriately tie into each other in the
system. (Pictures at tie-in points suggested.)
6.The minimum freeboard is provided for all channels and swales as shown on the approved
construction plans or as identified in the approved drainage study. (Show the freeboard provided on
the cross-sections as on the construction plan set or attached as separate documentation.)
7.The low flow portion of all channels or swales is clear of obstructions. (No landscaping, trees,
shrubs, sod, etc. infringe on the low flow portion of channels or swales.)
12/15 Page 4
III.Storm Pipes (aka storm drains) - FCSCM Vol.1, Ch.6, Sec. 4
A. Storm Drain Pipe Capacity: The as-built capacity of all pipes installed on this project has been
verified and meets or exceeds the capacity requirements shown in the approved drainage study for this
project.
1.All storm drain pipe sizes and materials have been verified and are in conformance with the
approved construction plans. (Indicate on the plan and profile sheets that they have been verified.)
Material and size substitutions must be approved prior to installation. If a pipe size or material was
changed during construction, the certification engineer must attach the approval documents or supply
them with this certification. Approval documents must include a calculation documenting the capacity
equivalency (equal or greater) of the substituted size.
2.The longitudinal slope of the pipe is as shown on the approved construction plans. The
acceptable minimum slope is 0.4%. All slopes flatter than the designed slope on the construction plans
must be justified with capacity calculations on an attached sheet.
3.The as-built invert elevations have been verified and are shown on the plan and profile sheets of
the approved construction plans.
B.Storm Drain Pipe Installation Requirements: All pipes are installed in accordance with the
approved construction plans.
1.The minimum cover requirements for all pipes have been met as shown on the approved
construction plans. These will be called out in critical locations.
2.All encasements and clearances as specified on the approved construction plans have been met.
3.Any specific joint types or construction methods specified on the approved construction plans
have been met. (List on a separate sheet and attach to this certification.)
IV.Concrete Pans - FCSCM Vol.1, Ch.7, Sec.4.1.3.4
A. Construction/Installation: All concrete pans have been constructed in accordance with the
approved construction plans.
1.The concrete pans are the correct size/width as shown on the approved construction plans.
2.The longitudinal slopes of the pans are as shown on the approved construction plans. The
certification engineer must justify or mitigate longitudinal slopes less than the minimum of 0.4% unless
a flatter slope was approved and is shown on the approved construction plans. Provide mitigation or
justification by separate document.
3.The cross-section of the pan is as shown on the construction plans. (Specifically, the pan cross-
section is “V” shaped and meets the side slope shown on the detail.)
4.The concrete pans are a minimum of 6 inches thick without reinforcement and a minimum of 4
inches thick with a minimum of 6X6-W14xW14 reinforcement per detail D20B and D20C. (Provide
documentation of the reinforcement used if different than shown on the details or on the approved
construction plans.)
5.The spot elevations shown on the concrete pan(s) have been verified and are shown on the as-
built drawings.
12/15 Page 5
V. Storm Drain Inlets - FCSCM Vol.1, Ch.6, Sec. 3
A. Construction/Installation: All storm drain inlets have been constructed in accordance with the
approved construction plans.
1.The size and type of inlets are consistent with the inlets shown on the approved construction
plan. Indicate by writing “Verified” on each inlet on the plan sheet or list on a separate document the
inlet number(s), type and size (length). If the inlet installed is other than the one on the approved
construction plan detail sheet, provide the name and source of the detail with justification for equal or
better capacity.
2.The size of the inlet opening is consistent with the approved detail. (Check height and width.)
3.The elevation of the grate (if applicable) is at the elevation shown on the street profile or as
indicated by a spot elevation on the construction plans.
4.The as-built invert elevations of all pipes entering and leaving the inlet are shown on the plan
and profile sheets within construction tolerance of 0.2 feet. If substantially different, provide
justification and capacity calculations to show the capacity is not affected or propose mitigation.
5.The as-built size of the inlet box is as shown on the construction plans or an explanation or
justification is attached.
6.All inlet covers are stenciled or stamped with the following designation: NO DUMPING – DRAINS
TO POUDRE RIVER.
VI.Culverts - FCSCM Vol.2, Ch.9
A. Construction/Installation: All culverts have been constructed and/or installed in accordance with
the approved construction plans.
1.All culvert sizes have been verified as indicated on the as-built construction plans as correct.
2.The culvert material type for all culverts installed is as on the approved construction plans and is
indicated on the as-built plans.
3.The as-built invert “in and out” elevations have been verified and are indicated on the as-built
construction plans.
4.The culvert headwalls or wing walls have been installed as shown on the approved construction
plans. Headwalls or wing walls may be needed in the as-built conditions onsite if the slopes adjacent to
the culvert are greater than 4:1. Please note areas needing stabilization in the certification narrative.
An alternative to consider is a turf reinforcement mat (TRM).
VII.Sub-Drains
A. Construction/Installation: All sub-drains shown on the construction plans have been installed in
accordance with those plans. Sub-drains installed with the sanitary sewer are to be verified on the
sanitary sewer plan and profile sheets of the construction plans. (NOTE: Indicate any sub-drains installed
after the plans were approved on the as-built plans.)
1.The size of the sub-drains are as approved on the construction plans and are indicated on the as-
built plans.
2.The type of sub-drain, in particular the perforated and non-perforated sections of the drain, are
as indicated on the approved construction plans.
12/15 Page 6
3.The cover requirements per the construction plans are provided.
4.The cleanouts have been installed at the locations shown on the construction plans and are
accessible for cleaning. (Cleanouts can be buried a maximum of 6 inches deep with their locations
marked.)
5.The backfill materials for sub-drains are as shown on the approved construction plans. (This
includes the type, depth and width.)
6.The geo-textile liner completely wraps the sub-drain and the permeable backfill material unless
shown otherwise on the approved construction plans. (Sub-drain pipe wrapped in a sock filter material
is accepted only if approved prior to installation.)
VIII.Curb Cuts
A. Construction: All curb cut openings are constructed in accordance with the approved construction
plans.
1.The size (width) of the curb cut opening is as shown on the approved construction plans.
2.The curb cut openings tie into a downstream swale, pipe, or other appurtenances with a smooth
transition and there no obstructions such as riprap or sod impeding the flow downstream of the curb
cut.
IX.Sidewalk Culverts & Chases
A. Construction/Installation: All sidewalk culverts have been installed at the locations shown on the
approved construction plans.
1.The size (width and length) of the culverts are as shown on the approved construction plans.
2.The cover plate is a minimum 5/8-inch galvanized plate bolted to a galvanized angle iron per the
detail shown on the approved construction plans or per the City’s detail.
3.The sidewalk culvert invert “in and out” elevations have been verified and are indicated on the
as-built plans.
4.The sidewalk culvert opening is as shown on the approved construction plans or per the City’s
detail.
5.There is a smooth transition both on the inlet and outlet ends of the sidewalk culvert with no
obstructions such as riprap or sod impeding the flow into or out of the sidewalk culvert.
X. Site Grading
A. Construction: All common open spaces have been graded in accordance with the approved
construction plans.
1.The grading on all common open spaces bordering private lots has been verified as correct and
the as-built rear lot corner elevations have been shown on the as-built plans.
12/15 Page 7
2.The as-built contours for “overlot grading” are shown on the as-built construction plans for all
common open spaces, tracts, outlots, etc. If not in compliance, please attach a narrative describing the
situation for noncompliance and when it may be corrected. An escrow for overlot grading may be
required. (NOTE: Residential Lot Grading Certification is a separate process from this Overall Site
Certification. It is understood that residential lots will be brought to final grade once the foundation is
backfilled so they may be lower than the plan shows at this Overall Site Certification stage.)
3.All turf reinforcement mats (TRMs) have been installed as shown on the approved construction
plans and the slopes are stabilized.
XI.Riprap - FCSCM Vol.1, Ch.7, Sec.4.4.4.3
A. Construction: All riprap has been installed in the locations and sizes indicated on the approved
construction plans.
XII.Permanent Erosion Control Fabric - FCSCM Vol.1, Ch.7
A. Construction: All fabric has been installed in the locations and sizes indicated on the approved
construction plans.
1.All fabric was installed per the details on the approved construction plans.
XIII.Post-Construction Site Cleanup - FCSCM Vol.3, Ch.7
A. Construction: All construction debris and obstructions of any kind have been removed from
drainage paths.
1.All construction debris has been removed except in staging area(s).
2.All ruts have been smoothed out in all construction areas.
3.All areas needing reseeding have been identified and future stabilization goals have been
coordinated with the Erosion Control Inspector and in accordance with FCSCM Vol.2 Chapter 12. Note
the area needing stabilization in the narrative.
XIV.Certification of Other Permanent BMPs - FCSCM Vol.2, Ch.8, Sec.2 & FCSCM Vol.2, Ch.12
A.The construction of channel drop structures is in accordance with the approved plan both in
location, horizontal dimensions and cross-section.
XV.Certification of LID and Water Quality Facilities - FCSCM Vol.3, Ch.4
A.Attached are the During Construction Inspection Checklist for Low Impact Development (LID) and
other items to be verified during construction, along with pictures and other required documentation.
Stormwater Facility Name:
Facility Location & Jurisdiction:
User (Input) Watershed Characteristics User Defined User Defined User Defined User Defined
Watershed Slope =0.010 ft/ft Stage [ft]Area [ft^2]Stage [ft]Discharge [cfs]
Watershed Length-to-Width Ratio =2.00 L:W 0.00 199 0.00 0.04
Watershed Area =1.59 acres 0.25 1,165 0.28 0.04
Watershed Imperviousness =44.4%percent 0.50 2,405 0.53 0.04
Percentage Hydrologic Soil Group A =0.0%percent 0.75 3,229 0.78 0.06
Percentage Hydrologic Soil Group B =0.0%percent 1.00 3,744 1.03 0.07
Percentage Hydrologic Soil Groups C/D =100.0%percent 1.25 4,056 1.28 0.07
1.50 4,300 1.53 0.07
1.75 4,797 1.78 0.08
2.00 5,573 2.03 0.08
2.25 6,358 2.28 0.08
User Input: Detention Basin Characteristics 2.50 7,037 2.53 0.08
WQCV Design Drain Time =40.00 hours 2.75 7,647 2.78 0.09
3.00 8,289 3.03 0.09
3.25 9,072 3.28 0.09
3.50 9,900 3.50 0.09
After completing and printing this worksheet to a pdf, go to:
https://maperture.digitaldataservices.com/gvh/?viewer=cswdif,
create a new stormwater facility, and
attach the pdf of this worksheet to that record.
Routed Hydrograph Results
Design Storm Return Period =WQCV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year
Two-Hour Rainfall Depth =0.53 0.98 1.36 1.71 2.31 2.91 3.67 in
Calculated Runoff Volume =0.025 0.054 0.097 0.139 0.218 0.289 0.390 acre-ft
OPTIONAL Override Runoff Volume =acre-ft
Inflow Hydrograph Volume =0.025 0.053 0.097 0.138 0.217 0.289 0.390 acre-ft
Time to Drain 97% of Inflow Volume =7 13 20 26 37 47 59 hours
Time to Drain 99% of Inflow Volume =8 13 20 27 38 49 62 hours
Maximum Ponding Depth =0.58 0.93 1.39 1.78 2.36 2.79 3.30 ft
Maximum Ponded Area =0.061 0.082 0.096 0.112 0.153 0.178 0.212 acres
Maximum Volume Stored =0.019 0.044 0.085 0.125 0.203 0.274 0.373 acre-ft
Workbook Protected Worksheet Protected
Stormwater Detention and Infiltration Design Data Sheet
Lyric Cinema Pond 1
Fort Collins, Colorado
Asbuilt Lyric Pond SDI CRS Spdsht 2017.10.25.xlsm, Design Data 10/30/2017, 11:54 AM
Doing_Clear_Formatting =Yes
CountA=1
0 1 2 3
#N/A
#N/A
0 1 2 3
#N/A
#N/A
Check Data Set 1 Check Data Set 1
Area
Discharge
Stormwater Detention and Infiltration Design Data Sheet
0
1
2
3
4
5
6
7
8
9
0.1 1 10
FL
O
W
[
c
f
s
]
TIME [hr]
100YR IN
100YR OUT
50YR IN
50YR OUT
25YR IN
25YR OUT
10YR IN
10YR OUT
5YR IN
5YR OUT
2YR IN
2YR OUT
WQCV IN
WQCV OUT
0
0.5
1
1.5
2
2.5
3
3.5
0.1 1 10 100
PO
N
D
I
N
G
D
E
P
T
H
[
f
t
]
DRAIN TIME [hr]
100YR
50YR
25YR
10YR
5YR
2YR
WQCV
Asbuilt Lyric Pond SDI CRS Spdsht 2017.10.25.xlsm, Design Data 10/30/2017, 11:54 AM
Project:
Date:
4972.1 1,616.0 ft3
4974.7 1,674.7 ft3
Crest of Pond Elev.:4975.95 29,602.4 ft3
4975.76
Maximum
Elevation
Minimum
Elevation cu. ft.acre ft cu. ft.acre ft
4971.20 N/A 0.0 0 0.0 0.00 0.0 0.00
4971.25 4971.20 198.6 0.05 5.0 0.00 5.0 0.00
4971.50 4971.25 1,165.1 0.25 170.5 0.00 175.4 0.00
4971.75 4971.50 2,405.4 0.25 446.3 0.01 621.7 0.01
4972.00 4971.75 3,229.2 0.25 704.3 0.02 1,326.1 0.03
4972.25 4972.00 3,743.7 0.25 871.6 0.02 2,197.7 0.05
4972.50 4972.25 4,056.5 0.25 975.0 0.02 3,172.7 0.07
4972.75 4972.50 4,299.6 0.25 1,044.5 0.02 4,217.2 0.10
4973.00 4972.75 4,796.6 0.25 1,137.0 0.03 5,354.2 0.12
4973.25 4973.00 5,573.3 0.25 1,296.2 0.03 6,650.5 0.15
4973.50 4973.25 6,357.7 0.25 1,491.4 0.03 8,141.8 0.19
4973.75 4973.50 7,037.3 0.25 1,674.4 0.04 9,816.2 0.23
4974.00 4973.75 7,647.1 0.25 1,835.5 0.04 11,651.8 0.27
4974.25 4974.00 8,288.6 0.25 1,992.0 0.05 13,643.7 0.31
4974.50 4974.25 9,072.2 0.25 2,170.1 0.05 15,813.8 0.36
4974.75 4974.50 9,899.7 0.25 2,371.5 0.05 18,185.3 0.42
4975.00 4974.75 10,631.5 0.25 2,566.4 0.06 20,751.7 0.48
4975.25 4975.00 11,364.7 0.25 2,749.5 0.06 23,501.2 0.54
4975.50 4975.25 12,015.6 0.25 2,922.5 0.07 26,423.8 0.61
4975.80 4975.50 12,823.8 0.30 3,725.9 0.09 30,149.7 0.69
North Rain Garden Stage Storage Curve
Contour Contour
Surface Area
(ft2)
Depth
Incremental Volume Cummalitive Volume
Existing Pond Stage Storage Curve
1089-001
Fort Collins, Colorado
F. Wegert
Detention Pond
Elev at Design Volume:
Lyric Cinema
10/17/2017
Pond Outlet and Volume Data
100-Year Design Volume:
Volume at WQ Outlet:
Project Number:
Project Location:
Calculations By:
Pond No.:
Water Quality Design Vol.:WQ Outlet Elev.:
Grate Elev. (100-Yr):
10/17/2017 8:18 AM D:\Projects\1089-001\Drainage\Detention\
1089-001_Asbuilt_Stage-Storage_2017.10.13.xlsx\Pond
400 North Link Lane | Fort Collins, Colorado 80524
Telephone: 970-206-9455 Fax: 970-206-9441
July 29, 2016
UR Design
252 Linden Street
Studio 7
Fort Collins, Colorado 80524
Attention: Brian A. Majeski
Subject: Permeability Testing
Proposed Lyric Cinema
1209 North College Avenue
Fort Collins, Colorado
CTL|T Project Number: FC06790-112
CTL|Thompson, Inc. has conducted soil permeability testing at the
proposed Lyric Cinema location. The purpose of our investigation was to
determine the hydraulic conductivity of two different soil types identified in our
Soils and Foundation Investigation (Project No. FC06790-125, report dated
January 26, 2015). This letter presents the results of our testing.
Borings conducted during our Soils and Foundation Investigation
encountered approximately 5 to 7½ feet of sandy clay and clayey sand overlying
cleaner sand and gravel. For our permeability testing, six new borings were
drilled using 4-inch solid stem auger and a truck-mounted drill rig. Three of the
borings were advanced approximately 1 to 3½ feet to bottom into the sandy clay
layer, and three of the borings were advanced to approximately 5½ to 6 feet to
bottom into the sand and gravel layer. The borings were fitted with slotted PVC
pipe to facilitate testing. Approximate locations of the borings are shown on
Figure 1.
Open hole, falling head permeability testing was conducted by adding
approximately 1 to 3 feet of water to each hole and measuring the change in
water depth over consecutive time intervals. A summary of our test results is
provided in Table A.