HomeMy WebLinkAboutSite Certifications - 06/26/2020
June 19, 2020
Wes Lamarque
City of Fort Collins
700 Wood Street
Fort Collins, CO 80522
RE: Permit: B1905428 – Bucking Horse Filing Two – Major Amendment
Fort Collins, Colorado
Dear Mr. Lamarque:
This Overall Site and Drainage Certification Letter is provided to verify as-constructed conditions for
Bucking Horse Filing Two – Major Amendment. Washburn Land Surveying completed survey work
June 10, 2020, to verify general compliance with the Final Utility Plans for Bucking Horse Filing Two -
Major Amendment dated June 6, 2019, by Northern Engineering.
Included in this drainage certification submittal are the following:
Appendix A - City of Fort Collins Overall Site and Drainage Certification Form.
Appendix B - City of Fort Collins During Construction Inspection Checklist and photographs provided
by contractor.
Appendix C - As-constructed Rain Garden worksheet.
Appendix D - As-constructed record drawings for Grading and Rain Garden Cross-Sections Sheets.
Appendix E – FEMA Elevation Certificate
We have concluded, based on the attached information and personal site inspection, that the drainage
features for the project site have been constructed in substantial compliance with the above referenced
Final Utility Plans, with the following exceptions:
· Item II.A: No major drainage channels exist on site.
· Item III.A.2: There exists a small section of drainage swale on the west side of the building
flatter than 2% slope. Due to the small area draining to swale, the Northern Engineering
anticipates no issues with drainage.
· Item II.A.6: No major drainage channels exist on site and no analysis was done.
· Item III.A: Only private storm drainage pipes were constructed on this project.
· Item III.B.3: Northern Engineering did not observe construction. Northern Engineering was
unable to verify the joint types or construction methods used for the storm drain pipes.
· Item IV.A and IV.A.2: Pan on the west side of the parking lot has a small depression of
approximately 0.07’ just north of the existing inlet. Due to the small impacted area and limited
expected ponding it is not thought that this will be an issue. The contractor has been advised
that this deficiency may result in shorter life span and potentially require additional
maintenance, no mitigation is needed as it does not affect the overall drainage of the site.
· Item XIII.B: Rain gardens were designed to be retrofitted into existing areas containing area
inlets from the original Bucking Horse Filing Two – Tract C design parking lot. During
construction, slight discrepancies were discovered between the original topo of the existing
parking lot and during construction elevations. Actual area to construct was also limited by
City required lighting and trees. This resulted in ~50 cubic feet deficiency from the initial design
required volume to be treated in the rain gardens (see attached as-built Rain Garden
worksheet). However, this will not be a problem as the rain gardens will still have the capacity
to treat well over the City required 50% of the new impervious area (~11,100 sf). Contractor has
also observed rain gardens efficiently functioning during several high intensity rainfalls in the
past few weeks.
· Item XIII.D: A missing clean out cover was noted on site visit. Contractor has stated that the
item is on back-order and will be installed when delivered.
· Item XV: Inlet protection was still in place during site visit.
Please feel free to contact me with any questions you may have.
Northern Engineering Services, Inc.
Benjamin Ruch, PE
Project Engineer
Appendix A
Overall Site and Drainage Certification Form
Appendix B
During Construction Inspection Checklist
1/19 Page 1 of 2
DURING CONSTRUCTION INSPECTION CHECKLIST
To be completed by Construction Superintendent
This checklist is to be completed during construction and included with the Overall Site and Drainage Certification.
• Use “Yes” for items completed as described.
• Use “N/A” for items that are not applicable to the site being certified.
• If any blanks are “No,” attach an explanation referencing the item number below.
Project Name: Sunshine House at Bucking Horse Date: 6/2/20
Building Permit Numbers: B1905428
I. Compaction
A. All berms and embankments meet the compaction requirements as specified in the project geotechnical report or comply with the
City’s standard, which is “soils should be compacted within a moisture content range of 2% below to 2% above optimum moisture content
and compacted to 95% of the Maximum Standard Proctor Density (ASTM D698).” Compaction requires verification during construction.
Provide testing log from contractor/engineer.
II. Storm Drain Pipe Installation Requirements
A. The pipe trenches have been compacted in accordance with Section 02225-3.07.A.1. of the Fort Collins Development Construction
Standards for Water, Wastewater, Stormwater (e.g., the trenches in the roadways are to be 95% of maximum density and all other areas
are to be at 90%, both in accordance with ASTM D698).
III. Energy Dissipation and Erosion Protection - FCSCM Chapter 9, Section 7.0
A. Riprap
1. The riprap bedding is a granular bedding of the gradation and thickness indicated on the approved construction plans.
2. A filter fabric was installed instead of granular bedding and is the material shown on the approved construction plans or was an
approved equal. Provide documentation for an approved equal.
3. The riprap is the gradation shown on the approved construction plans with a D50 of .
4. The riprap thickness is as shown on the approved construction plans and extends to the horizontal limits shown.
5. The riprap is buried to the depth indicated on the approved construction plans. (A minimum of 6 inches of soil is required.)
B. Permanent Erosion Control Fabric - FCSCM Vol.1, Ch.7
1. All fabric was installed per manufacturer’s specifications.
1/19 Page 2 of 2
IV. Other Permanent BMPs
A. All cut-off walls have been installed in accordance with the approved construction plans. (Cut-off walls are required for irrigation
ditch crossings of storm drain pipes.)
V. Extended Detention Basins
A. Installation of this facility was verified via inspection by a City-Stormwater Inspector at the point of installation of the water quality
control box(es). Provide date of inspection and name of inspector:
Included certification sheet(s):
Please check the appropriate box(es) for the Low Impact Development
(LID) facilities found on this site and complete the corresponding
certification sheets.
☐ Permeable Interlocking Concrete Pavers
☒ Bioretention Cells (Rain Gardens)
☐ Sand Filters
☐ Vegetated Buffers
☐ Underground Infiltration
☐ Other LID – For certification of Dry Wells, Tree Filters,
Constructed Wetland Channels & Ponds, etc., contact City Staff
to determine requirements to exhibit the LID facility has been
constructed and functions as intended per the approved
drainage report.
*Please provide photographic documentation of the installation of all
stages of all LID facilities.
**Please contact the City Stormwater Inspector at
stormwaterinspection@fcgov.com to discuss inspection requirements
for each LID facility and request inspections.
***All facilities being certified must be “clean” – free of sediment &
construction debris – prior to certification or acceptance of the facility.
Completed by:
Name: Mike Campana
Title: Project Manager
Email: mdcampana@gmail.com
Phone: 970-690-3391
Company: Bellisimo, Inc
Address: 3702 Manhattan Ave
Fort Collins, CO
1/19 Page 1 of 2
Permeable Interlocking Concrete Pavers
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Stormwater Inspection
Pre-construction meeting was held with City-Stormwater
Inspector to discuss installation, inspection, checklist, and
protection from sedimentation
☐ ☐ ☐
Record date, inspector name, meeting
location (i.e. DCP, initial erosion control
inspection, etc.)
Sub-surface inspection(s): Installation of this facility was
verified via inspection by a City-Stormwater Inspector at the
point of installation of the outlet, underdrain, geomembrane
layer, and sub-base courses (per design in Final Plan
Documents)
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Surface inspection(s): Installation of this facility was verified via
inspection by a City-Stormwater Inspector at the point of
installation of the pavers and joint fill material
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Excavation
Heavy equipment did not encroach into the excavated area
(prevents over-compaction) ☐ ☐ ☐
Bottom of cell was “ripped” after excavation ☐ ☐ ☐ Provide photographs before and after
“ripping”
Bottom surface of cell is flat and level ☐ ☐ ☐ Provide photograph
Impermeable Liner
Impermeable liner meets design specifications ☐ ☐ ☐ Provide specifications of delivered
material
Impermeable liner is attached to concrete perimeter wall ☐ ☐ ☐ Provide photograph
Impermeable liner is buried with no exposure ☐ ☐ ☐
Any penetrations of the impermeable liner have been sealed
and checked for water-tightness ☐ ☐ ☐ Provide photograph (if necessary)
Edge Restraint and Concrete Cut-Off Wall
The required edge restraint meets design specifications ☐ ☐ ☐ Provide specification of installation
Concrete cut-off wall meets design specifications for: ☐ ☐ ☐ Provide specification of installation
- Dimensions ☐ ☐ ☐
- Reinforcement ☐ ☐ ☐
- Footings ☐ ☐ ☐
Underdrain System
Underdrain pipe meets design specifications ☐ ☐ ☐ Provide photograph
At least one cleanout is provided per underdrain lateral ☐ ☐ ☐ Provide photograph
1/19 Page 2 of 2
Cleanout pipe is solid (not perforated/slotted) ☐ ☐ ☐ Provide photograph
Cleanout covers are installed and watertight ☐ ☐ ☐ Provide photograph
Verify the underdrain is NOT wrapped in geotextile fabric ☐ ☐ ☐ Provide photograph
Verify there is no orifice plate on the underdrain outfall ☐ ☐ ☐ Provide photograph
Underdrain integrity tested after backfilling using TV and/or
water test ☐ ☐ ☐ Provide documentation of test results
Aggregate
Sub-base Course(e.g., #2/4):
- Has 90% fractured faces
- Is thoroughly washed (virtually free of fine sediment)
- Is installed to the required design depth
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Basecourse (e.g., #57):
- Has 90% fractured faces
- Is thoroughly washed (virtually free of fine sediment)
- Is installed to the required design depth
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Leveling Course / Joint Fill (e.g., crushed #89):
- Has 90% fractured faces
- Is thoroughly washed (virtually free of fine sediment)
- Is dry screened
- Is installed to the required design depth and to the top
of the paver joints
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Aggregate materials are installed and compacted according to
manufacturer’s and/or design specifications ☐ ☐ ☐ Provide photographs and documentation
of compaction
Protection During Construction
PICP area is protected from construction site sediment,
including runoff from the upstream catchment and
construction equipment traffic ☐ ☐ ☐
Specify how the area was covered and/or
otherwise protected to prevent
construction runoff from entering the
pavement
Close Out
Cracked/broken paver units have been removed and replaced ☐ ☐ ☐
Paver height offsets are no more than 1/4” between adjacent
units & surface contains no deformations
(depressions/settlement) exceeding 1/2"
☐ ☐ ☐
Upstream catchment is stabilized prior to diverting runoff into
PICP system ☐ ☐ ☐
1/19 Page 1 of 3
Bioretention Cells (Rain Gardens)
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Stormwater Inspection
Pre-construction meeting was held with City-Stormwater
Inspector to discuss installation, inspection, checklist, and
protection from sedimentation ☒ ☐ ☐
Record date, inspector name, meeting
location (i.e. DCP, initial erosion control
inspection, etc.)
Chandler, Wes,
Bellisimo, Martin and
Sons met onsite
5/22/20
Underdrain and basecourse inspection(s): Installation of this
facility was verified via inspection by a City-Stormwater
Inspector at the point of installation of the outlet, underdrain,
geomembrane layer, and base course (per design in Final Plan
Documents)
☒ ☐ ☐
Record date(s) of inspection and
inspector’s name
5/29/20, Chandler
Pea gravel and BSM inspection(s): Installation of this facility
was verified via inspection by a City-Stormwater Inspector at
the point of installation of the pea gravel and bioretention
sand media
☒ ☐ ☐
Record date(s) of inspection and
inspector’s name
Pea Gravel 5/29/20,
Chandler and BSM
6/2/20 Chandler
Excavation
Heavy equipment did not encroach into the excavated area
(prevents over-compaction) ☒ ☐ ☐
Bottom of cell was “ripped” after excavation ☒ ☐ ☐ Provide photographs before and after
“ripping”
Bottom surface of cell is flat and level ☒ ☐ ☐ Provide photograph
Excavated area is protected/surrounded by sediment/runoff
control measures during construction ☐ ☐ ☒ Provide photograph
Intake
Upstream catchment drains to inlet/bioretention cell per plan
and flows are fully captured ☒ ☐ ☐
Forebay
Forebay is installed according to design specifications ☐ ☐ ☒ Provide photograph
There is a minimum 3” drop at the forebay entrance ☐ ☐ ☒ Provide photograph
Forebay will drain fully and not hold standing water ☐ ☐ ☒
Outlet Structure/Overflow
Emergency overflow elevation is confirmed
☒ ☐ ☐
Measure and record distance from
overflow to top of media filter; provide
photograph
12”
Overflow inlet elevation is set above bioretention media per
plan ☒ ☐ ☐ Provide photograph 12”
1/19 Page 2 of 3
Overflow inlet invert elevation is at least 3 inches below
containment wall/berm (to direct overflow into inlet) ☒ ☐ ☐
Measure and record distance between
inlet and top of containment wall/berm;
provide photograph
See as-Built shots
Overflow path and check dams, if used, are armored to protect
from erosion and maintain elevations ☐ ☐ ☒ Provide photograph
Impermeable Liner
Impermeable liner meets design specifications
☐ ☐ ☒
Provide specifications of delivered
material
Per discussions and
email with Wes and
Norhtern the liner was
not installed or needed.
Impermeable liner is appropriately anchored ☐ ☐ ☒ Provide photograph
Impermeable liner is buried with no exposure ☐ ☐ ☒
Any penetrations of the impermeable liner have been sealed
and checked for water-tightness ☐ ☐ ☒ Provide photograph (if necessary)
Underdrain System
Underdrain pipe meets design specifications ☒ ☐ ☐ Provide photograph
At least one cleanout is provided per underdrain lateral ☒ ☐ ☐ Provide photograph
Cleanout pipe is solid (not perforated/slotted) ☒ ☐ ☐ Provide photograph
Cleanout covers are installed and watertight ☒ ☐ ☐ Provide photograph
Verify the underdrain is NOT wrapped in geotextile fabric ☒ ☐ ☐ Provide photograph
Verify there is no orifice plate on the underdrain outfall ☒ ☐ ☒ Provide photograph
Underdrain integrity tested after backfilling using TV and/or
water test ☐ ☒ ☐ Provide documentation of test results
Filter Media and Aggregate
Reservoir aggregate layer (ASTM #57 or #67):
- meets design specifications
- is installed to the required design depth
☒ ☐ ☐
Provide load ticket, photographs, and
record depth installed
8”
Diaphragm aggregate layer (“Pea Gravel” with gradation ASTM
#8, #89, or #9):
- meets design specifications
- is installed to the required design depth
☒ ☐ ☐
Provide load ticket, photographs, and
record depth installed
4”
Bioretention Sand Media (BSM) composition:
- meets design specifications
- is installed to the required design depth
☒ ☐ ☐
Provide load ticket, photographs, and
record depth installed
18”
BSM was “machine mixed” by supplier prior to delivery ☒ ☐ ☐ Provide load ticket
BSM is installed flat and level ☒ ☐ ☐ Provide photograph
Other Structural Components
Containment wall/berm is continuous and level ☒ ☐ ☐
1/19 Page 3 of 3
Landscaping
Verify final landscaping is free of sod ☒ ☐ ☒ If sod is used, it must be shown to be
“sand-grown”
No sod per plan
Final landscaping (non-floatable mulch) is flat and level
☒ ☐ ☐
Provide photograph Rock cobble at
perimeter on slopes
only not in the BSM
Vegetation is planted according to landscape design
specifications and final landscaping plan ☒ ☐ ☐ Provide photograph
Verify that weed barrier is NOT installed ☒ ☐ ☐ Only on side slope
under rock cobble
Temporary irrigation installed
☐ ☐ ☒
If N/A, then verify that permanent
irrigation is installed to establish/maintain
vegetation
Close Out
Upstream catchment stabilized prior to diverting runoff into
bioretention cell ☐ ☐ ☒
1/19 Page 1 of 1
Vegetated Buffers
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Construction
Buffer area was sectioned off to eliminate site disturbance and
compaction during construction ☐ ☐ ☒ Provide photograph(s)
Level spreader has been installed per plan (if applicable) ☐ ☐ ☒ Provide photograph
Soils in the buffer area have been amended ☐ ☐ ☒ Record soil amendment certification with
Environmental & Regulatory Affairs
Vegetation is planted according to landscape design
specifications and final landscaping plan ☐ ☐ ☒ Provide photograph
1/19 Page 1 of 3
Sand Filters
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Stormwater Inspection
Pre-construction meeting was held with City-Stormwater
Inspector to discuss installation, inspection, checklist, and
protection from sedimentation
☐ ☐ ☐
Record date, inspector name, meeting
location (i.e. DCP, initial erosion control
inspection, etc.)
Underdrain and basecourse inspection(s): Installation of this
facility was verified via inspection by a City-Stormwater
Inspector at the point of installation of the outlet, underdrain,
geomembrane layer, and base course (per design in Final Plan
Documents)
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Pea gravel and filter media inspection(s): Installation of this
facility was verified via inspection by a City-Stormwater
Inspector at the point of installation of the pea gravel and filter
media
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Excavation
Heavy equipment did not encroach into the excavated area
(prevents over-compaction) ☐ ☐ ☐
Bottom of cell was “ripped” after excavation ☐ ☐ ☐ Provide photographs before and after
“ripping”
Bottom surface of cell is flat and level ☐ ☐ ☐ Provide photograph
Excavated area is protected/surrounded by sediment/runoff
control measures during construction ☐ ☐ ☐ Provide photograph
Intake
Upstream catchment drains to inlet/sand filter per plan and
flows are fully captured ☐ ☐ ☐
Forebay (If Applicable)
Forebay is installed according to design specifications ☐ ☐ ☐ Provide photograph
There is a minimum 3” drop at the forebay entrance ☐ ☐ ☐ Provide photograph
Forebay will drain fully and not hold standing water ☐ ☐ ☐
Outlet Structure/Overflow
Overflow inlet elevation is set above sand filter media per plan
(typically 1 to 3 feet) ☐ ☐ ☐ Provide photograph
Overflow inlet invert elevation is at least 3 inches below
containment wall/berm (to direct overflow into inlet) ☐ ☐ ☐
Measure and record distance between
inlet and top of containment wall/berm;
provide photograph
1/19 Page 2 of 3
Overflow path and check dams, if used, are armored to protect
from erosion and maintain elevations ☐ ☐ ☐ Provide photograph
Impermeable Liner (If Applicable)
Impermeable liner meets design specifications ☐ ☐ ☐ Provide specifications of delivered
material
Impermeable liner is appropriately anchored to the perimeter
wall ☐ ☐ ☐ Provide photograph
Impermeable liner is buried with no exposure ☐ ☐ ☐
Any penetrations of the impermeable liner have been sealed
and checked for water-tightness ☐ ☐ ☐ Provide photograph (if necessary)
Underdrain System
Underdrain pipe meets design specifications ☐ ☐ ☐ Provide photograph
At least one cleanout is provided per underdrain lateral ☐ ☐ ☐ Provide photograph
Cleanout pipe is solid (not perforated/slotted) ☐ ☐ ☐ Provide photograph
Cleanout covers are installed and watertight ☐ ☐ ☐ Provide photograph
Verify the underdrain is NOT wrapped in geotextile fabric ☐ ☐ ☐ Provide photograph
Verify there is no orifice plate on the underdrain outfall ☐ ☐ ☐ Provide photograph
Underdrain integrity tested after backfilling using TV and/or
water test ☐ ☐ ☐ Provide documentation of test results
Filter Media
Filter media composition (e.g. ASTM C 33 Sand):
- meets design specifications
- is installed to the required design depth
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Pea gravel layer:
- meets design specifications
- is installed to the required design depth
☐ ☐ ☐
Provide load ticket, photographs, and
record depth installed
Filter Media is installed flat and level ☐ ☐ ☐
Other Structural Components
Containment wall/berm is continuous and level ☐ ☐ ☐
Landscaping
Verify final landscaping is free of sod ☐ ☐ ☐ If sod is used, it must be shown to be
“sand-grown”
Final landscaping (non-floatable mulch) is flat and level ☐ ☐ ☐ Provide photograph
Vegetation is planted according to landscape design
specifications and final landscaping plan ☐ ☐ ☐ Provide photograph
Verify that weed barrier is NOT installed ☐ ☐ ☐
1/19 Page 3 of 3
Temporary irrigation installed
☐ ☐ ☐
If N/A, then verify that permanent
irrigation is installed to establish/maintain
vegetation
Close Out
Upstream catchment stabilized prior to diverting runoff into
sand filter cell ☐ ☐ ☐
1/19 Page 1 of 2
Underground Infiltration
Item/Activity Yes No N/A Submittal Requirements Submitted?/Response
Stormwater Inspection
Manufacturer’s representative pre-construction meeting: A
pre-construction meeting was completed with the
manufacturer’s representative and installers
☐ ☐ ☐
Record date and who was present at the
meeting
Pre-construction meeting was held with City-Stormwater
Inspector to discuss installation, inspection, checklist, and
protection from sedimentation
☐ ☐ ☐
Record date, inspector name, meeting
location (i.e. DCP, initial erosion control
inspection, etc.)
Inspection(s): Installation of this facility was verified via
inspection by a City-Stormwater Inspector at the point at which
the chambers had been laid/prior to backfilling.
Correct fabric placement was confirmed.
☐ ☐ ☐
Record date(s) of inspection and
inspector’s name
Excavation
Heavy equipment did not travel across underground cell area
during excavation (prevents over-compaction) ☐ ☐ ☐
Bottom of cell was “ripped” after excavation ☐ ☐ ☐ Provide photographs before and after
“ripping”
Bottom of cell is flat and level, or graded per approved grading
plans ☐ ☐ ☐ Provide photograph
Non-woven fabric is installed per manufacturer’s specifications
and was not damaged during construction (around system) ☐ ☐ ☐ Provide photograph
Woven fabric is installed per manufacturer’s specifications and
was not damaged during construction (beneath chambers) ☐ ☐ ☐ Provide photograph
Excavated area is protected/surrounded by sediment/runoff
control BMPs during construction ☐ ☐ ☐ Provide photograph
Impermeable Liner
Impermeable liner meets design specifications ☐ ☐ ☐ Provide specifications of delivered
material
Impermeable liner is not exposed ☐ ☐ ☐
Any penetrations of the impermeable liner have been sealed
and checked for water-tightness. ☐ ☐ ☐ Provide photograph (if necessary)
Aggregate
Foundation and embedment materials are installed and
compacted according to design and manufacturer’s
specifications
☐ ☐ ☐
Provide load ticket and photograph(s)
Underdrain System
1/19 Page 2 of 2
Underdrain pipe meets design specifications ☐ ☐ ☐ Provide photograph
At least one cleanout is provided per underdrain lateral ☐ ☐ ☐ Provide photograph
Cleanout pipe is solid (not perforated/slotted) ☐ ☐ ☐ Provide photograph
Cleanout covers are installed and watertight ☐ ☐ ☐ Provide photograph
Verify the underdrain is NOT wrapped in geotextile fabric ☐ ☐ ☐ Provide photograph
Verify there is no orifice plate on the underdrain outfall ☐ ☐ ☐ Provide photograph
Underdrain integrity tested after backfilling using TV and/or
water test ☐ ☐ ☐ Provide documentation of test results
Manifold system
Overflow weir elevation is set at/above water quality storm
elevation ☐ ☐ ☐ Record weir elevation on survey
Maintenance access is provided for each Isolator Row ☐ ☐ ☐
At least one inspection port has been provided for each Isolator
Row (located in middle third of each row) ☐ ☐ ☐
Upstream catchment drains to inlet/intake properly ☐ ☐ ☐
Underground Detention Chambers
All chambers were installed per approved Utility Plans and
manufacturer’s specifications ☐ ☐ ☐ Photograph
Close Out
Upstream catchment is stabilized prior to diverting runoff into
Underground Detention system ☐ ☐ ☐
All Isolator Rows, chambers, and pipes are cleaned and
sediment/debris has been removed ☐ ☐ ☐
B
Rain Garden at end of parking lot
Dirt Sub-grade: 87.24
Reservoir Agg FG: 87.68
Diaphragm Agg FG: 88.01
T
6" perforated for under drain only
clean-out risers are non-perforated
T
BSM
B
B
B
B
B
B
Elevation of dirt sub grade bottom
of Rain Garden: 87.24
B
A
B
B A
12" from
FG of overflow
inlet to top of BSM
30" Profile for:
18" of BSM
4" of Diaphragm aggregate
8" of reservoir aggregate
B
B
B
B
Typical Non-perforated Clean-out riser
B
B
B
B
B
Top of reservoir aggregate layer 8"
Elevation: 87.68
B
Top of Diaphragm aggregate @88.01
leaving 18" for BSM
B
B
B
B
Top of Diaphragm aggregate layer 4"
Elevation: 88.01
B
Top of BSM FG
Larrrrr,r ioutrty Ta>
5i2ltt212() I l 4() AM Sales Recuipt #199251)
itore t Tt Uzk lO
HAGEMAN EARTH CYCLE
3501 East ProsPect Road
Fort Collrns, CO 80525
9/0''/t1 7113
wwlv ha gernanearthcYcle cLrtn
Bill To: Marlin & Sons
Martltr & Sons
8808 Weld Courlty Rd ''l
Be(lloLtd CO 80513
(lashrer CaseY
DclCIl[,tlt)rl I Qty F'ttce Lx1 Prtce
BSlr/l ilettrrrltorr t'c 14 64 S.-lir OO 511 2 40 T
6SM Reterttrorl F'c 14 14 S35 00 'i4!4 !)0 I
Srrl.rtotal $1 007 30
3/%Tax +SaJl27
rssrrrJ .1!ll eetrent (rllelchant agleelrlellt
lf credit voucher)
Thank yoll for Yout htlsltressl
COMF'ANIONS Wl I H I'JAI URE
Vehicle MNSOIO - MARTIN & SONS
Carrier
Trailer
I llllll lllll illtt llltt lllll lllll lllll lllll lllll lllll lllll lill llll
16310 Taft Sand & Gravel
1801 North l.aft Hill Road
Fort Collins, CO 80521 Ticket 32005635
Dafc DEL/PU Disoatch Scale
512912020 P 1
Time Due Time ln Ttme OC!
1 3:33
Silo #
000 0:00
Customer No Order No
639986 6001 3614
Product
oo38 - SSTONE
Snippea foAaY Job To Datt
1 LDS (14.14 Ton) 180"14 Ton
Ship To
Dest lD
lnstruct
639986 - MARTIN & SONS EXCAVATING
AGG VARIOUS
1 8868 WELD CO ROAD 3
. 2482 MILEHOUSE AVE
fi .i,' t- -- a 7 t -.nl ,r;:;,w" / /i,;) io' ufl;e
liul/4L
vartin tt'tanetta Standard Terms and Conditions apply (copy avai!abie at Site Office)
Rain Garden nearest Miles House Ave
A
Dirt Sub-grade: 87.87
Reservoir Agg FG: 88.42
Diaphragm Agg FG: 88.75
6" perforated for under drain only
clean-out risers are non-perforated
T
BSM
T
A
A
A
A
A
A
A
12" from
FG of overflow
inlet to top of BSM
30" Profile for:
18" of BSM
4" of Diaphragm aggregate
8" of reservoir aggregate
A
Elevation of dirt sub grade bottom
of Rain Garden: 87.87
A
Elevation of dirt sub grade bottom
of Rain Garden: 87.87
A
A
A
A
A
A
A
A
Typical Non-perforated Clean-out riser
A
A
A
A
A
A
A
A
A
Top of reservoir
aggregate layer 8"
Elevation: 88.42
A
A
A
A
Top of Diaphragm aggregate @88.75
leaving 18" for BSM
A
Top of BSM FG
A
Larrrrr,r ioutrty Ta>
5i2ltt212() I l 4() AM Sales Recuipt #199251)
itore t Tt Uzk lO
HAGEMAN EARTH CYCLE
3501 East ProsPect Road
Fort Collrns, CO 80525
9/0''/t1 7113
wwlv ha gernanearthcYcle cLrtn
Bill To: Marlin & Sons
Martltr & Sons
8808 Weld Courlty Rd ''l
Be(lloLtd CO 80513
(lashrer CaseY
DclCIl[,tlt)rl I Qty F'ttce Lx1 Prtce
BSlr/l ilettrrrltorr t'c 14 64 S.-lir OO 511 2 40 T
6SM Reterttrorl F'c 14 14 S35 00 'i4!4 !)0 I
Srrl.rtotal $1 007 30
3/%Tax +SaJl27
rssrrrJ .1!ll eetrent (rllelchant agleelrlellt
lf credit voucher)
Thank yoll for Yout htlsltressl
COMF'ANIONS Wl I H I'JAI URE
Vehicle MNSOIO - MARTIN & SONS
Carrier
Trailer
I llllll lllll illtt llltt lllll lllll lllll lllll lllll lllll lllll lill llll
16310 Taft Sand & Gravel
1801 North l.aft Hill Road
Fort Collins, CO 80521 Ticket 32005635
Dafc DEL/PU Disoatch Scale
512912020 P 1
Time Due Time ln Ttme OC!
1 3:33
Silo #
000 0:00
Customer No Order No
639986 6001 3614
Product
oo38 - SSTONE
Snippea foAaY Job To Datt
1 LDS (14.14 Ton) 180"14 Ton
Ship To
Dest lD
lnstruct
639986 - MARTIN & SONS EXCAVATING
AGG VARIOUS
1 8868 WELD CO ROAD 3
. 2482 MILEHOUSE AVE
fi .i,' t- -- a 7 t -.nl ,r;:;,w" / /i,;) io' ufl;e
liul/4L
vartin tt'tanetta Standard Terms and Conditions apply (copy avai!abie at Site Office)
Appendix C
As-Constructed Rain Garden Work Sheet
Sheet 1 of 2
Designer:
Company:
Date:
Project:
Location:
1. Basin Storage Volume
A) Effective Imperviousness of Tributary Area, Ia Ia =100.0 %
(100% if all paved and roofed areas upstream of rain garden)
B) Tributary Area's Imperviousness Ratio (i = Ia/100)i = 1.000
C) Water Quality Capture Volume (WQCV) for a 12-hour Drain Time WQCV = 0.40 watershed inches
(WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i)
D) Contributing Watershed Area (including rain garden area) Area = 17,014 sq ft
E) Water Quality Capture Volume (WQCV) Design Volume VWQCV =567 cu ft
Vol = (WQCV / 12) * Area
F) For Watersheds Outside of the Denver Region, Depth of d6 = in
Average Runoff Producing Storm
G) For Watersheds Outside of the Denver Region, VWQCV OTHER =cu ft
Water Quality Capture Volume (WQCV) Design Volume
H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER =cu ft
(Only if a different WQCV Design Volume is desired)
2. Basin Geometry
A) WQCV Depth (12-inch maximum)DWQCV =12 in
B) Rain Garden Side Slopes (Z = 4 min., horiz. dist per unit vertical) Z = 4.00 ft / ft
(Use "0" if rain garden has vertical walls)
C) Mimimum Flat Surface Area AMin =340 sq ft
D) Actual Flat Surface Area AActual =363 sq ft
E) Area at Design Depth (Top Surface Area)ATop =670 sq ft
F) Rain Garden Total Volume VT=517 cu ft TOTAL VOLUME < DESIGN VOLUME
(VT= ((ATop + AActual) / 2) * Depth)
3. Growing Media
4. Underdrain System
A) Are underdrains provided?
B) Underdrain system orifice diameter for 12 hour drain time
i) Distance From Lowest Elevation of the Storage y =ft
Volume to the Center of the Orifice
ii) Volume to Drain in 12 Hours Vol12 =N/A cu ft
iii) Orifice Diameter, 3/8" Minimum DO =N/A in
Design Procedure Form: Rain Garden (RG)
B. Ruch
Northern Engineering
June 17, 2020
Bucking Horse Sunshine House (Bucking Horse Filing 2 Major Amendment)
Fort Collins, CO
UD-BMP (Version 3.06, November 2016)
Choose One
Choose One
18" Rain Garden Growing Media
Other (Explain):
YES
NO
AB_UD-BMP_v3.06_RG WQVol.xlsm, RG 6/17/2020, 3:18 PM
Sheet 2 of 2
Designer:
Company:
Date:
Project:
Location:
5. Impermeable Geomembrane Liner and Geotextile Separator Fabric
A) Is an impermeable liner provided due to proximity
of structures or groundwater contamination?
6. Inlet / Outlet Control
A) Inlet Control
7. Vegetation
8. Irrigation
NO SPRINKLER HEADS ON FLAT SURFACE
A) Will the rain garden be irrigated?
Notes:
Design Procedure Form: Rain Garden (RG)
B. Ruch
Northern Engineering
June 17, 2020
Bucking Horse Sunshine House (Bucking Horse Filing 2 Major Amendment)
Fort Collins, CO
Choose One
Choose One
Choose One
Sheet Flow- No Energy Dissipation Required
Concentrated Flow- Energy Dissipation Provided
Plantings
Seed (Plan for frequent weed control)
Sand Grown or Other High Infiltration Sod
Choose One
YES
NO
YES
NO
AB_UD-BMP_v3.06_RG WQVol.xlsm, RG 6/17/2020, 3:18 PM
Appendix D
Record Drawings
FW
S
UD
FDC
E E
E
E F W
/
/
/
/
/
/
///////////////////////////////////////////////
UD
UD
UD
DS
DS
DS
DS
DS
DS
DS
DS
DSDS
DS
DS DS
DS
DS
CO
CO
S
S
W W W W W W W W W W W W W W W W W W W
W
W
W
SS SS SS SS SS SS SS SS SS SS SS SS SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
CO
COS
SS
S
HY
D
IR
R
S
X
X
X
X
X
X
X
X
X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
MILES HOUSE AVENUE
TRACT B
FUTURE CITY PARK
TRACT C
9' UTILITY EASEMENT
EXISTING 5' SIDEWALK
24' EMERGENCY
ACCESS EASEMENT
9' UTILITY EASEMENT
PROPOSED 4.5' SIDEWALK
PR
O
P
O
S
E
D
5
.
5
'
SI
D
E
W
A
L
K
EX
I
S
T
I
N
G
5
0
'
F
L
-
F
L
AD BASIN 4.1
INV. OUT=4888.01 (NW)
FG=4892.92
AD BASIN 9
INV.=4889.15
FG=4892.05
AD BASIN 5
INV.=4888.35
FG=4891.97
AD 45° BEND 8
INV.=4888.67
FG=4892.21
AD 45° BEND 6
INV.=4888.54
FG=4892.71
AD BASIN 7
INV.=4888.65
FG=4891.80
EX INLET A3
INV. IN=4885.88 (SW)
INV. IN=4887.88 (NW)
INV. IN=4887.88 (SE)
INV. OUT=4885.88 (NE)
EX. GRATE=4890.91
PROP. GRATE=4891.22
EX INLET A1
INV. IN=4885.26 (SW)
INV. OUT=4885.26 (NE)
GRATE=4890.61
EX INLET A2
INV. IN=4885.37 (SW)
INV. IN=4887.35 (SE)
INV. IN=4887.35 (NW)
INV. OUT=4885.37 (NE)
EX. GRATE=4890.40
PROP. GRATE=4890.68
AD TEE 4
INV.=4887.93
FG=4892.54
INSERTA TEE CONNECTION
INV. IN=4885.17 (SW)
INV. IN=4887.17 (SE)
INV. OUT=4885.17 (NE)
FG=4891.34
AD 45° BEND 1
INV.=4887.55
FG=4892.98
EX FES A
INV. IN=4884.65 (SW)
12
7
.
0
2
L
F
EX
.
3
6
"
R
C
P
@
0
.
4
1
%
30
.
4
7
L
F
EX
.
3
6
"
R
C
P
@
0
.
3
6
%
10
8
.
6
3
L
F
EX
.
3
6
"
R
C
P
@
0
.
4
7
%
68
.
6
4
L
F
EX
.
3
6
"
R
C
P
@
0
.
3
8
%
23.17 LF
EX. 36" RCP
@ 0.41%
77.66 LF
12" HDPE
@ 0.50%
10.11 LF
12" HDPE
@ 0.50%
15.64 LF
8" HDPE
@ 0.50%
84.20 LF
8" HDPE
@ 0.50%
37.53 LF
8" HDPE
@ 0.50%
23.13 LF
8" HDPE
@ 0.50%
4.11 LF 8" HDPE @ 0.50%
47.75 LF
8" HDPE
@ 1.00%
2.
0
%
2.
0
%
2.
0
%
2.0%
2.0%
6:1
4:1
4:
1
4:
1
4:1
4:1
2.
0
%
2.0
%
1.
9
%
25.
0
%
6.7
%
4.3%
0.9%
1.2%
2.
5
%
2.0%
WET TAP EXISTING
8"x6" TEE w/ TB
& 6" GV (NE)
N:15915.78
E:13480.17
15.29 LF
6" PERF. HDPE
@ 0.50%
RG BASIN 1A
INV. OUT=4887.42 (SE)
RIM=4890.68
9.47 LF
6" HDPE
@ 0.50%
RG BASIN 1B
INV. OUT=4887.40 (NW)
RIM=4890.68
11.68 LF
6" HDPE
@ 0.50%
RG BASIN 2A
INV. OUT=4887.94 (SE)
RIM=4891.22
14.37 LF
6" HDPE
@ 0.50%
RG BASIN 2B
INV. OUT=4887.96 (NW)
RIM=4891.22
TRACT D
NATIVE UPLAND
HABITAT AREA/
EXISTING DETENTION
POND 215
1.0%1.0%
POND 215
100-YR WSEL = 4888.5
5.0%
3.0%
2.0%
2.0%
2.
0
%
2.0%
2.0%
2.0%
24' EMERGENCY
ACCESS EASEMENT
2.0%
2.0%2.0%2.0%
2.0%
5.
0
%
5.
0
%
4.0
%
3.5%
2.0%
2.0%
2.0%
17.95 LF
12" HDPE
@ 0.50%
AD BASIN 2
INV.=4887.64
FG=4891.19
45.34 LF
8" HDPE
@ 0.50%
AD 45° BEND 3.3
INV.=4888.16
FG=4892.20
AD 45° BEND 3.4
INV.=4888.18
FG=4892.30
42.42 LF
8" HDPE
@ 0.50%
AD BASIN 3.6
INV.=4888.55
FG=4891.97
43.96 LF
8" HDPE
@ 0.50%
AD TEE 3.7
INV.=4888.77
FG=4892.82
5.13 LF
8" HDPE
@ 2.00%
AD BASIN 3.7-1
INV.=4888.88
FG=4891.97 3.69 LF
8" HDPE
@ 0.50%
AD 90° BEND 3.9
INV.=4888.93
FG=4892.84
AD BASIN 3.10
INV.=4889.01
FG=4891.97
46.93 LF
8" HDPE
@ 0.50%
AD TEE 3
INV.=4887.69
FG=4892.10
5.00 LF
8" HDPE
@ 0.50%
3.99 LF
8" HDPE
@ 2.00%
2.
0
%
2.
0
%
21.17 LF
8" HDPE
@ 0.50%
AD BASIN 3.1
INV.=4887.80
FG=4891.97
10.16 LF
4" HDPE
@ 2.00%
36.63 LF
3" PERF. HDPE
@ 1.00%
AD BASIN 3.1-1
INV.=4888.00
FG=4892.57
AD BASIN 3.1-2
INV.=4890.87
FG=4892.37
AD BASIN 3.2-2
INV.=4890.98
FG=4892.48
17.99 LF
3" PERF. HDPE
@ 1.00%
AD TEE 3.2
INV.=4888.03
FG=4893.04
26.46 LF
8" HDPE
@ 0.50%
21.48 LF
4" HDPE
@ 2.00%
AD BASIN 3.2-1
INV.=4888.46
FG=4892.52
AD BASIN 3.5-2
INV.=4890.11
FG=4891.61
21.19 LF
3" PERF. HDPE
@ 1.00%AD CONTINUE
INV.=4889.90
FG=4891.47
13.94 LF
3" PERF. HDPE
@ 1.00%
AD BASIN 3.5-1
INV.=4889.45
FG=4891.60
52.41 LF
4" HDPE
@ 2.00%
AD TEE 3.5
INV.=4888.40
FG=4893.00
36.85 LF
4" HDPE
@ 2.00%AD BASIN 3.6-1
INV.=4889.29
FG=4891.85
AD BASIN 3.6-2
INV.=4890.52
FG=4892.25
17.32 LF
3" PERF. HDPE
@ 1.00%
AD BASIN 3.8-2
INV.=4890.40
FG=4891.90
47.27 LF
3" PERF. HDPE
@ 1.00%
AD BASIN 3.8-1
INV.=4888.29
FG=4891.78
AD TEE 3.8
INV.=4888.79
FG=4892.88
49.69 LF
4" HDPE
@ 2.00%
27.78 LF
8" HDPE
@ 0.50%
45° BEND w/ TB
N:15942.32
E:13509.70
APPROXIMATE LOCATION
EXISTING TRANSFORMER
EXISTING
FLUSH CURB
PROPOSED
SAWCUT
EXISTING 18" VERTICAL
CURB & GUTTER
EXISTING CONCRETE
PARKING LOT
PROPOSED
TRASH ENCLOSURE
PROPOSED 18" OUTFALL
VERTICAL CURB & GUTTER
PROPOSED
FENCE
MATCH EXISTING
CURB & GUTTER
EXISTING
ACCESS RAMPS
EXISTING
DRIVEWAY
PROPOSED
CONCRETE PAVING
PROPOSED
CONCRETE PAVING
EXISTING 30" VERTICAL
CURB & GUTTER
PROPOSED 18" OUTFALL
VERTICAL CURB & GUTTER
CURRENT FEMA MAPPED
500-YR FLOODPLAIN LIMITS
EXISTING 15"
SANITARY SEWER
EXISTING
8" WATER
EXISTING FH
EXISTING 1.5"
IRRIGATION SERVICE
EXISTING 4"
SANITARY SEWER EXISTING 1"
WATER METER
& CURB STOP
EXISTING
SANITARY SERVICE
PROPOSED RAIN GARDEN
(SEE SHEET C301 DETAIL)
EXISTING
INLET
PROPOSED ELECTRIC
PROPOSED
ACCESS RAMP
PROPOSED 6"
FIRE SERVICE
PROPOSED
CONCRETE
DIVIDING WALL
EXTENDING TO
BOTTOM OF
BIOMEDIA
PROPOSED
ELECTRIC METER
PROPOSED
CONCRETE
DIVIDING WALL
EXTENDING TO
BOTTOM OF
BIOMEDIA
PROPOSED RAIN GARDEN
(SEE SHEET C301 DETAIL)
PROPOSED 1" WATER SERVICE
INSTALL CLEANOUT AND
EXTEND EXISTING
SANITARY SERVICE
EXISTING
INLET GRATE
TO BE RAISED
EXISTING
INLET GRATE
TO BE RAISED
PROPOSED
UTILITY
EASEMENT
FW
S
FFE=93.14
(91.77)
(91
.
3
9
)
(91
.
3
9
)
(91
.
3
6
)
(9
1
.
3
8
)
(90.92)
(90
.
8
3
)
(90
.
7
6
)
(90
.
9
7
)
(9
0
.
4
9
)
(9
0
.
5
6
)
(9
1
.
0
6
)
(90
.
9
2
)
(91
.
2
9
)
(91
.
7
3
)
(91
.
7
8
)
(90
.
5
3
)
89.68
89.68 89.68
89.6
8
90
.
2
2
90.22
90.2
2
89.4
1
(88
.
2
9
)
(92
.
5
0
)
(92
.
6
5
)
(92
.
5
8
)
91.1
6
92.4
8
93.3
7
94.4
9
94.5
3
92.1
5
90.
3
4
91.5
8
91.8
6
91.9
0
91
.
1
6
91.53
91
.
2
3
90.95
90.63
90.9
1
90.72
90.5
4
91.8
6
92.0
7
(91
.
9
3
)
91.9
5
91.9
7
92.1
9
92.2
4
92.4
4
92.4
4
91.61
92
.
7
2
92
.
7
7
92.4
7
92.5
2
92.99
93.1
4
91.6
4
92.3
5 92.0
8
90.8
4
(87
.
9
6
)
91.0
1
96.70
93.1
8
91.4
5
(88
.
8
2
)
(88
.
5
8
)
93.1
4
93.1
4
93.1
4
92.47
93.
1
4
93.04
91.97
92.55
92.7
8
92.47 92.29
93.0
4
92.9
6
92
.
3
3
92.3
6
92.06
92
.
2
8
92.58
92
.
7
6
92.05
91
.
8
0
92
.
3
8
92.90 93.04
91.
0
4
90
.
8
3
91.9
7
93
.
1
4
93
.
1
4
92.12
91.78
89.2
8
90.00
92.
7
5
92
.
7
6
91.1
2 90
.
8
8
90.5
3
92.7
0
92
.
7
2
92.4
4
90.71
90
.
6
2
90.5
2
90.58
90.8
7
92.47
92
.
4
8
92
.
7
1
93.1
4
92.91
92.45
91.9
7
92.56
93.1
4
93.1
4
93.0
0
92.47
91.19
91.8
1
91.10
92
.
3
4
92.10
92.
3
4
92.64
90.44
92.5
8
92.66 92.2
5
93.0
7
92.8
9
92.2
6
93
.
1
4
92.
4
7
93.
0
6
93.06
93.06
93.0
6
93.1
4
93.0
6
92.9
9
92.0
4
91.8
3
91.8692.70
93.1
4
92
.
4
9
93.1
4
93.1
4
91.9
7
92
.
4
7
93.1
4
93.0
6
93.14
92.47
91
.
9
7
92.8
8
93.1
4
93.14
91
.
9
7
92.4
7
92
.
8
5
93
.
1
4
92
.
9
8
93
.
1
4
93.1
4
93.
0
0
92
.
1
7
92
.
4
4
(90.8
6
)
92.4
7
93.14 93.14
93
.
1
0
92.2
4
90
.
2
2
(91
.
2
2
)
(9
0
.
6
8
)
(9
1
.
3
0
)
91.7
6
91.69
92.
6
2
90.3
9
90.4
6 90.6
6
91
.
0
2
90.7
6
91
.
3
1
91
.
5
8
91
.
5
8
90.36
91.
5
9
90.32
90.
5
6
91.
4
9
90.
1
5
90.
2
1
91
.
6
0
90.39
92.05 92
.
6
1
93.09
92.80
92.73
92.81
93.0
3
91.
8
9
92.2
0
92
.
4
1
92
.
6
2
92.41
91.71
90.45
91.23
91.69
88.32
88.
9
2
89.67
90.07
89.0
9
93.16
93.97
95.9
5
90.97
91.9
1
91.21
88.15
92.2
8
91.7792.1
9
92.84
92.52
92.40
92.
9
8
92.
3
5
92.
7
8
93.00
93.02
92.97
92
.
5
5
92.96
92.86
92.75
92.32
91
.
9
8
93.03
93.05
92.
1
9
93.05
92.5
7
92.52
92
.
3
4
92.21
92.45
92.4
3
92.3
2
92
.
6
6
94.52
94.76
92.35
92.6
4
92.63
92
.
9
0
92.9893.
0
6
92.4
6
92.00
92.
8
2
92.57
92.85
92.60
92.
8
2
92.82
92.7892.63
92.58
91.8
5
92.26
91
.
1
7
91.39
92.35
91.98
90
.
9
5
90.94
91.
1
4
89.
6
5
91.
2
5
90.
6
7
89.76
89.5
7
91
.
0
9
91
.
6
0
90.
1
5
91.14
91.67
91.71
93.11
92.96
92.9
2
93
.
0
8
92
.
8
8
92.9
6
92.9
5
92.83
92.3292.48
92.
2
5
92.4
6
92.92
92
.
6
8
92.8
2
92.66
93.06
92.42
89.72
91.22
91.93
92
.
9
9
92.69
92.95
92.
6
4
93.0
4
92.
5
7
92.
9
4
92.72
92.98
92.
6
4
92.
2
2
92
.
0
1
92
.
0
7
92
.
2
5
92
.
1
4
91
.
1
2
91
.
2
5
91
.
1
1
90
.
8
0
90
.
8
9
90
.
8
5
90.
9
5
91.3
2
91
.
4
8
91.37
91
.
5
2
91.0
8
91.1
8
90
.
8
7
91
.
0
1
AD R
I
M
-
3
.
5
5
I
N
V
91.9
8
89.74
88.67
88.64
88.83
89.60
92.13
92.62
92.64
91.18
90.01
91.21
91
.
3
6
91
.
0
4
92
.
2
8
91
.
8
7
Sheet
BU
C
K
I
N
G
H
O
R
S
E
F
I
L
I
N
G
T
W
O
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
FO
R
T
C
O
L
L
I
N
S
:
3
0
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
,
8
0
5
2
1
GR
E
E
L
E
Y
:
8
2
0
8
t
h
S
t
r
e
e
t
,
8
0
6
3
1
97
0
.
2
2
1
.
4
1
5
8
no
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
of 10
C300
GR
A
D
I
N
G
&
U
T
I
L
I
T
Y
P
L
A
N
5
NORTH
( IN FEET )
1 inch = ft.
Feet02020
20
40 60
NOTES:
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN
SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE
EXISTENCE OF ALL UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING NEW
CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES
AND SHALL BE RESPONSIBLE FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.ALL WATER FITTINGS AND VALVES ARE ONLY GRAPHICALLY REPRESENTED AND ARE NOT TO SCALE.
3.UTILITY SERVICES ARE SHOWN IN A SCHEMATIC FASHION ONLY. EXACT LOCATIONS SHALL BE PER THE
REQUIREMENTS OF THE RESPECTIVE UTILITY PROVIDERS, AND ARE SUBJECT TO CHANGE IN THE FIELD.
4.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS, UTILITY EASEMENTS,
OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
5.LIMITS OF STREET CUT ARE APPROXIMATE. FINAL LIMITS ARE TO BE DETERMINED IN THE FIELD BY THE
CITY ENGINEERING INSPECTOR. ALL REPAIRS TO BE IN ACCORDANCE WITH CITY STREET REPAIR
STANDARDS.
6.ANY DAMAGED CURB, GUTTER AND SIDEWALK EXISTING PRIOR TO CONSTRUCTION, AS WELL AS STREETS,
SIDEWALKS, CURBS AND GUTTERS, DESTROYED, DAMAGED OR REMOVED DUE TO CONSTRUCTION OF THIS
PROJECT, SHALL BE REPLACED OR RESTORED TO CITY OR FORT COLLINS STANDARDS AT THE
DEVELOPER'S EXPENSE PRIOR TO THE ACCEPTANCE OF COMPLETED IMPROVEMENTS AND/OR PRIOR TO
THE ISSUANCE OF CERTIFICATE OF OCCUPANCY.
7.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF MANHOLES AND INLET BOX STRUCTURES.
SPECIFIED LENGTH OF PIPE INCLUDES THE LAYING LENGTH OF FLARED END SECTIONS.
8.CONTRACTOR SHALL BE RESPONSIBLE FOR ANY NECESSARY FIELD LOCATES AND POTHOLING OF
SUBSURFACE UTILITIES. ENGINEER AND CITY SHALL BE NOTIFIED OF ANY POTENTIAL CONFLICTS.
9.CONTRACTOR SHALL COORDINATE ANY NECESSARY TELEPHONE, CABLE, FIBER, GAS, AND ELECTRIC
LOWERINGS (OR RE-ROUTING) WITH THE RESPECTIVE UTILITY PROVIDERS.
10.CONTRACTOR TO COORDINATE FINAL LOCATION OF ALL GAS AND ELECTRIC METERS WITH ARCHITECT AND
UTILITY PROVIDERS.
11.ALL NEW AREA DRAIN INFRASTRUCTURE IS TO BE PRIVATELY OWNED AND MAINTAINED.
12.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN
SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE
EXISTENCE OF ALL UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING NEW
CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES
AND SHALL BE RESPONSIBLE FOR FOR ALL UNKNOWN UNDERGROUND UTILITIES.
13.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS, UTILITY EASEMENTS,
OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
14.ALL CURB SPOTS SHOWN ARE FLOWLINE ELEVATIONS. ALL OTHER SPOTS ARE FINISHED GRADE
ELEVATIONS.
15.ALL PROJECT DATA IS ON THE CITY OF FORT COLLINS VERTICAL DATUM NAVD88. SEE COVER SHEET FOR
BENCHMARK REFERENCES.
16.THE CONTRACTOR IS RESPONSIBLE FOR FIELD LOCATING AND VERIFYING ELEVATIONS OF ALL CURBS AND
GUTTERS AT THE POINTS OF CONNECTION SHOWN ON THE PLANS PRIOR TO INSTALLING ANY OF THE NEW
IMPROVEMENTS. IF A CONFLICT EXISTS AND/OR A DESIGN MODIFICATION IS REQUIRED, THE CONTRACTOR
SHALL COORDINATE WITH THE ENGINEER TO MODIFY THE DESIGN.
17.ADD 4800-FT TO PROPOSED CONTOURS, SPOT ELEVATIONS, AND FFE LABELS, WHERE TRUNCATED.
18.SOME EXISTING INFORMATION SHOWN ON THESE PLANS IS BASED ON DESIGN INFORMATION FOR BUCKING
HORSE FILING TWO. CONTRACTOR TO VERIFY ALL RELEVANT EXISTING DATA PRIOR TO CONSTRUCTION
AND SHALL NOTIFY ENGINEER OF ANY DISCREPANCIES.
19.THE LOWEST FLOOR AND ALL HVAC, ELECTRICAL, AND MECHANICAL SHALL BE ELEVATED TO 4893.0 FEET
(NAVD 88) OR HIGHER. A FEMA ELEVATION CERTIFICATE SHALL BE SUBMITTED AND APPROVED PRIOR TO
ISSUANCE OF THE CERTIFICATE OF OCCUPANCY.
EXISTING WATER MAIN
LEGEND:
W
EXISTING STORM SEWER
EXISTING SANITARY SEWER SS
PROPOSED CURB & GUTTER
EXISTING FIRE HYDRANT
EASEMENT LINE
PROPERTY BOUNDARY
EXISTING LOTLINE
PROPOSED STORM SEWER
EEXISTING ELECTRIC
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
PROPOSED CONTOUR
EXISTING CONTOUR
PROPOSED SPOT ELEVATION 33.43
PROPOSED SLOPES 2.0%
(47.45
)
EXISTING SPOT ELEVATION
PROPOSED FIRE SERVICE F
PROPOSED SWALE
EXISTING LIGHTING
PROPOSED LIGHTING
UDPROPOSED UNDERDRAIN
MINIMUM FINISHED FLOOR ELEVATION
(FFE) = B (FFE VARIES, SEE PLAN)
MINIMUM MECH./ELEC. EQUIPMENT
ELEVATION = A
MECH. /
ELEC.
EQUIPMENT
DETAIL
NTS
SLAB-ON-GRADE
BUCKING HORSE FILING TWO - SUNSHINE HOUSE
ELEV. DESIGNATION PROJECT ELEV.
(NAVD 88)
100-YR FLOOD ELEVATION 4888.33 FT
500-YR FLOOD ELEVATION 4888.69 FT
A 4893.00 FT
B 4893.00 FT
PROPOSED WATER SERVICE W
PROPOSED SANITARY SERVICE S
INLET SCHEDULE
ID DIA (IN)GRATE STRUCTURE TYPE
AD BASIN 2 12 DOMED BASIN
AD BASIN 3.1 12 DOMED BASIN
AD BASIN 3.1-1 8 SOLID BASIN
AD BASIN 3.1-2 8 SOLID INLINE
AD BASIN 3.2-1 8 SOLID BASIN
AD BASIN 3.2-2 8 SOLID INLINE
AD BASIN 3.5-1 8 SOLID BASIN
AD BASIN 3.5-2 8 SOLID INLINE
AD BASIN 3.6 12 DOMED BASIN
AD BASIN 3.6-1 8 SOLID BASIN
AD BASIN 3.6-2 8 SOLID INLINE
AD BASIN 3.7-1 8 DOMED INLINE
AD BASIN 3.8-1 8 SOLID BASIN
AD BASIN 3.8-2 8 SOLID INLINE
AD BASIN 3.10 8 DOMED INLINE
AD BASIN 4.1 8 DOMED INLINE
AD BASIN 5 8 DOMED TEE w/ RISER PIPE
AD BASIN 7 8 DOMED TEE w/ RISER PIPE
AD BASIN 9 8 DOMED INLINE
RG BASIN 1A 6 DOMED INLINE
RG BASIN 1B 6 DOMED INLINE
RG BASIN 2A 6 DOMED INLINE
RG BASIN 2B 6 DOMED INLINE
INLET SCHEDULE
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
1
UT
I
L
I
T
Y
R
E
C
O
R
D
D
R
A
W
I
N
G
BR
R
02
/
0
3
/
2
0
02.03.20
RECORD INFO.ONLY(SEE NOTE)
2
GR
A
D
I
N
G
&
D
R
A
I
N
A
G
E
R
E
C
O
R
D
D
R
A
W
I
N
G
BR
R
06
/
1
7
/
2
0
RG BASIN 2B
INV. OUT=4887.96 (NW)
GRATE=4891.22
RG BASIN 2A
INV. OUT=4887.94 (SE)
GRATE=4891.22
EX INLET A3
INV. IN=4885.88 (SW)
INV. IN=4887.88 (NW)
INV. IN=4887.88 (SE)
INV. OUT=4885.88 (NE)
EX. GRATE=4890.91
PROP. GRATE=4891.22
RG BASIN 1A
INV. OUT=4887.42 (SE)
GRATE=4890.68
RG BASIN 1B
INV. OUT=4887.40 (NW)
GRATE=4890.68
EX INLET A2
INV. IN=4885.37 (SW)
INV. IN=4887.35 (SE)
INV. IN=4887.35 (NW)
INV. OUT=4885.37 (NE)
EX. GRATE=4890.40
PROP. GRATE=4890.68
10
8
.
6
3
L
F
36
"
R
C
P
@
0
.
4
7
%
9.47 LF
6" PERF. HDPE
@ 0.50%
15.29 LF
6" PERF. HDPE
@ 0.50%
11.68 LF
6" PERF. HDPE
@ 0.50%
14.37 LF
6" PERF. HDPE
@ 0.50%
(91.4
3
)
(9
1
.
3
8
)
(91.3
6
)
(91.42)
(91
.
2
2
)
(9
0
.
7
6
)
(90.94)
(9
0
.
7
6
)
(9
0
.
8
2
)
(90.92)
(9
0
.
6
8
)
(9
1
.
3
0
)
RAISE EXISTING INLET GRATE
SEE RAIN GARDEN NOTES
RAISE EXISTING INLET GRATE
SEE RAIN GARDEN NOTES
89
.
6
8
89
.
6
8
89.68 89.6
8
90.22 90.2
2
90.
2
2
90.22
EXISTING
STORM DRAIN
2
2
1
1
UD
UD
91.49
90.
1
5
90
.
2
1
91
.
5
7
91.
6
0
91.
5
9
91
.
6
5
90.5
6
90
.
3
6
91.58
89.
6
5
90.
0
4
90.
9
4
90.9
5
89.
7
6
89.
5
7
91.
0
9
91.
1
4
91.
1
4
91.
6
4
90.3
9
89.7
2
4880
4885
4890
4895
4900
4905
4880
4885
4890
4895
4900
4905
9+75 10+00 10+50
RG
B
A
S
I
N
1
A
ST
A
1
0
+
0
0
.
0
0
GR
A
T
E
E
L
4
8
9
0
.
6
8
IN
V
.
O
U
T
4
8
8
7
.
4
2
(
S
E
)
15.29 LF
6" PERF. HDPE
@ 0.50%
9.47 LF
6" PERF. HDPE
@ 0.50%
EX
I
N
L
E
T
A
2
ST
A
1
0
+
1
5
.
2
9
EX
.
G
R
A
T
E
E
L
4
8
9
0
.
4
±
PR
O
P
.
G
R
A
T
E
.
E
L
4
8
9
0
.
6
8
IN
V
.
I
N
4
8
8
5
.
3
7
(
S
W
)
IN
V
.
I
N
4
8
8
7
.
3
5
(
S
E
)
IN
V
.
I
N
4
8
8
7
.
3
5
(
N
W
)
IN
V
.
O
U
T
4
8
8
5
.
3
7
(
N
E
)
EXISTING
GROUND
PROPOSED
GROUND
SEE RAIN
GARDEN NOTES
RG
B
A
S
I
N
1
B
ST
A
1
0
+
2
4
.
7
6
GR
A
T
E
E
L
4
8
9
0
.
6
8
IN
V
.
O
U
T
4
8
8
7
.
4
0
(
N
W
)
PROPOSED
CONCRETE
DIVIDING WALL
EXTEND WALL TO
BOTTOM OF
BIOMEDIA
RAIN GARDEN
BIO-MEDIA
SEE DETAIL
4880
4885
4890
4895
4900
4905
4880
4885
4890
4895
4900
4905
9+75 10+00 10+50
RG
B
A
S
I
N
2
A
ST
A
1
0
+
0
0
.
0
0
GR
A
T
E
E
L
4
8
9
1
.
2
2
IN
V
.
O
U
T
4
8
8
7
.
9
4
(
S
E
)
11.68 LF
6" PERF. HDPE
@ 0.50%14.37 LF
6" PERF. HDPE
@ 0.50%
EX
I
N
L
E
T
A
3
ST
A
1
0
+
1
1
.
6
8
EX
.
G
R
A
T
E
E
L
4
8
9
0
.
9
±
PR
O
P
.
G
R
A
T
E
.
E
L
4
8
9
1
.
2
2
IN
V
.
I
N
4
8
8
5
.
8
8
(
S
W
)
IN
V
.
I
N
4
8
8
7
.
8
8
(
N
W
)
IN
V
.
I
N
4
8
8
7
.
8
8
(
S
E
)
IN
V
.
O
U
T
4
8
8
5
.
8
8
(
N
E
)
PROPOSED
GROUND
EXISTING
GROUND
SEE RAIN
GARDEN NOTES
RG
B
A
S
I
N
2
B
ST
A
1
0
+
2
6
.
0
6
GR
A
T
E
E
L
4
8
9
1
.
2
2
IN
V
.
O
U
T
4
8
8
7
.
9
6
(
N
W
)
PROPOSED
CONCRETE
DIVIDING WALL
EXTEND WALL TO
BOTTOM OF
BIOMEDIA
RAIN GARDEN
BIO-MEDIA
SEE DETAIL
PROFILE SCALE:
SECTION 1-1
RAIN GARDEN NOTES:
EXISTING INLETS DO NOT PROVIDE REQUIRED 12" PONDING. EXISTING INLETS SHALL BE RAISED TO
PROVIDE REQUIRED WATER QUALITY VOLUME.
C301
RA
I
N
G
A
R
D
E
N
C
R
O
S
S
-
S
E
C
T
I
O
N
S
6
NORTH
( IN FEET )
1 inch = ft.
Feet01010
10
20 30
NOTES:
LEGEND:
EXISTING STORM SEWER
PROPOSED CURB & GUTTER
EASEMENT LINE
CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU
DIG, GRADE, OR EXCAVATE FOR THE MARKING OF
UNDERGROUND MEMBER UTILITIES.
CALL UTILITY NOTIFICATION CENTER OF
COLORADO
Know what'sbelow.
before you dig.Call
R
PROPOSED CONTOUR
EXISTING CONTOUR
PROPOSED SPOT ELEVATION 33.43
PROPOSED SLOPES 2.0%
(47.45
)
EXISTING SPOT ELEVATION
PROPOSED LIGHTING
UDPROPOSED UNDERDRAIN
PROFILE SCALE:
SECTION 2-2
PROPOSED RAIN GARDEN
1.THE SIZE, TYPE AND LOCATION OF ALL KNOWN UNDERGROUND UTILITIES ARE APPROXIMATE WHEN
SHOWN ON THESE DRAWINGS. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE
EXISTENCE OF ALL UNDERGROUND UTILITIES IN THE AREA OF THE WORK. BEFORE COMMENCING NEW
CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ALL UNDERGROUND UTILITIES
AND SHALL BE RESPONSIBLE FOR FOR ALL UNKNOWN UNDERGROUND UTILITIES.
2.REFER TO THE PLAT FOR LOT AREAS, TRACT SIZES, EASEMENTS, LOT DIMENSIONS, UTILITY EASEMENTS,
OTHER EASEMENTS, AND OTHER SURVEY INFORMATION.
3.PIPE LENGTHS ARE CALCULATED FROM THE CENTER OF BASINS AND FITTINGS.
4.CONTRACTOR SHALL BE RESPONSIBLE FOR ANY NECESSARY FIELD LOCATES AND POTHOLING OF
SUBSURFACE UTILITIES. ENGINEER AND CITY SHALL BE NOTIFIED OF ANY POTENTIAL CONFLICTS.
5.CONTRACTOR SHALL COORDINATE ANY NECESSARY TELEPHONE, CABLE AND ELECTRIC LOWERINGS (OR
RE-ROUTING) WITH THE RESPECTIVE UTILITY PROVIDERS TO FACILITATE THE INSTALLATION OF THE
PROPOSED UNDERDRAINS AND RAIN GARDEN SOIL SECTIONS.
6.ALL CURB SPOTS SHOWN ARE FLOWLINE ELEVATIONS. ALL OTHER SPOTS ARE FINISHED GRADE
ELEVATIONS.
7.REFER TO RAIN GARDEN DETAIL FOR ADDITIONAL INFORMATION.
8.REFER TO LANDSCAPE PLANS FOR ADDITIONAL INFORMATION.
Sheet
BU
C
K
I
N
G
H
O
R
S
E
F
I
L
I
N
G
T
W
O
E
N
G
I
N
E
E
R
N
G
I
E
H
T
R
O
N
R
N
FO
R
T
C
O
L
L
I
N
S
:
3
0
1
N
o
r
t
h
H
o
w
e
s
S
t
r
e
e
t
,
S
u
i
t
e
1
0
0
,
8
0
5
2
1
GR
E
E
L
E
Y
:
8
2
0
8
t
h
S
t
r
e
e
t
,
8
0
6
3
1
97
0
.
2
2
1
.
4
1
5
8
no
r
t
h
e
r
n
e
n
g
i
n
e
e
r
i
n
g
.
c
o
m
of 10
THE
S
E
R
E
C
O
R
D
D
R
A
W
I
N
G
S
,
P
R
O
D
U
C
E
D
B
Y
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
SER
V
I
C
E
S
,
I
N
C
.
,
A
R
E
B
A
S
E
D
I
N
W
H
O
L
E
,
O
R
I
N
P
A
R
T
,
U
P
O
N
I
N
F
O
R
M
A
T
I
O
N
PRO
V
I
D
E
D
B
Y
O
T
H
E
R
S
.
N
O
R
T
H
E
R
N
E
N
G
I
N
E
E
R
I
N
G
S
E
R
V
I
C
E
S
,
I
N
C
.
A
S
S
U
M
E
S
NO L
I
A
B
I
L
I
T
Y
F
O
R
T
H
E
A
C
C
U
R
A
C
Y
O
R
C
O
M
P
L
E
T
E
N
E
S
S
O
F
T
H
I
S
I
N
F
O
R
M
A
T
I
O
N
.
REC
O
R
D
D
R
A
W
I
N
G
06.17.20
RECORD INFO.ONLY(SEE NOTE)
1
GR
A
D
I
N
G
&
D
R
A
I
N
A
G
E
R
E
C
O
R
D
D
R
A
W
I
N
G
BR
R
06
/
1
7
/
2
0
Appendix E
FEMA Elevation Certificate