HomeMy WebLinkAboutPRECISION TECHNOLOGY - FDP200029 - - EROSION CONTROL LETTER/REPORTEROSION CONTROL REPORT (SWMP) 19 OLD TOWN SQUARE #238 | FORT COLLINS, CO 80524 | 970-530-4044 | www.unitedcivil.com P RECISION T ECHNOLOGY Harmony Technology Park Fifth Filing Lot 2 Fort Collins, CO Prepared for: Precision Technology LLC 224 Canyon Avenue Unit 624 Fort Collins, CO 80521 Date: December 9 th , 2020 E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO i U20015 - EC Report CITY OF FORT COLLINS –STORMWATER UTILITY 700 WOOD STREET FORT COLLINS,CO 80521 RE: Precision Technology Erosion Control Report Fort Collins, Colorado Project Number: U20015 Dear Staff: United Civil Design Group, LLC. is pleased to submit this Erosion Control Report (SWMP) for the Precision Technology site in Fort Collins, Colorado. This report outlines what control measures or Best Management Practices (BMPs) will be implemented with the proposed construction, in order to minimize potential pollutants in stormwater discharges. We have prepared this report to accompany the Colorado Department of Public Health and Environment General Permit for Stormwater Discharges Associated with Construction Activity. Please note that this document is intended to be a dynamic document which will be modified and updated through the course of site construction to accurately reflect site conditions at all times. Pollutant sources will be continuously evaluated, BMPs selected, documented, implemented, and pollutant sources re-evaluated. As such, this version of the SWMP was prepared to facilitate initial plan approvals and permitting, but does not necessarily reflect the final version, or the transitions throughout the construction process. It shall be the responsibility of the Qualified Stormwater Manager and/or the permit holder (or applicant thereof) to ensure the plan is properly maintained and followed. The Qualified Stormwater Manager for this project is: If you should have any questions or comments as you review this report, please feel free to contact us at your convenience. Sincerely, United Civil Design Group, LLC Nate Stroud, PE, LSIT Professional Engineer II E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO ii U20015 - EC Report O WNER : A DDRESS : P HONE : E MAIL : Q UALIFIED S TORMWATER M ANAGER : A DDRESS : P HONE : E MAIL : C ONTRACTOR : A DDRESS : P HONE : E MAIL : TO FILLED OUT BY QUALIFIED STORMWATER MANAGER/CONTRACTOR SWMP R EVISION DATES : E STIMATED P ROJECT D ATES : P ROJECT S TART D ATE : P ROJECT C OMPLETION D ATE : CDPHE P ROJECT OR P ERMIT T RACKING N UMBER : E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO iii U20015 - EC Report TABLE OF CONTENTS I. General Location and Description ......................................................................................................................1 A. SWMP Objective........................................................................................................................... 1 B. Location and Project Description ................................................................................................. 2 C. Description of Development ........................................................................................................ 2 D. Floodplains ................................................................................................................................... 2 II. Site Description ..................................................................................................................................................2 A. Construction Activity Description ................................................................................................ 2 B. Proposed Sequence for Major Activities ...................................................................................... 2 C. Area Estimates ............................................................................................................................. 3 D. Soil Description ............................................................................................................................ 3 E. Existing Vegetation ....................................................................................................................... 3 F. Stream Crossings .......................................................................................................................... 3 G. Potential Pollution Sources .......................................................................................................... 3 H. Non-Stormwater Components of Discharge ................................................................................ 4 I. Receiving Waters .......................................................................................................................... 5 III. CMs and BMPs for Stormwater Pollution Prevention .......................................................................................5 A. Erosion and Sediment Controls .................................................................................................... 5 B. Erosion Control Sequencing ......................................................................................................... 7 C. Spill Prevention and Response Plan ............................................................................................. 8 D. Materials Handling ....................................................................................................................... 9 IV. Other Controls ...................................................................................................................................................9 V. Final Stabilization and Long-term Stormwater Quality ................................................................................... 10 VI. Site Inspections ............................................................................................................................................... 10 VII. Maintenance Procedures ............................................................................................................................ 11 VIII. Record Keeping ............................................................................................................................................ 12 IX. References ...................................................................................................................................................... 13 APPENDICES APPENDIX A – Inspection Forms APPENDIX B – Permit Map & Reference Plan Sheets APPENDIX C – Contractor Inserts (Permit, Inspection Reports, Etc.) E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 1 U20015 - EC Report I.GENERAL LOCATION AND DESCRIPTION A.EROSION CONTROL REPORT OBJECTIVE The objective of this Erosion Control Report (SWMP) for the Precision Technolgoy project is to identify the Control Measures (CMs) and Best Management Practices (BMPs) which, when implemented, will meet the requirements of the Colorado Department of Public Health & Environment, Water Quality Control Division. According to the State of Colorado Stormwater Management plan Guidance document, the Erosion Control Report (SWMP) goal is: “To identify possible pollutant sources at the construction site that may contribute pollutants to stormwater, and identify control measures that, when implemented in accordance with good engineering, hydrologic, and pollution control practices, will reduce or eliminate any possible water quality impacts. A stormwater management plan shall be developed for each construction site covered by the Construction Stormwater Permit. The stormwater management plan must be completed and implemented at the time the project breaks ground, and revised as construction proceeds, to accurately reflect the conditions and practices on site.” Pollutant sources should be continuously evaluated, BMPs selected, documented, implemented, and pollutant sources be re- evaluated (and the process continued). A current copy of the SWMP shall be kept onsite at all times. A person familiar with the SWMP and on-site construction activities and clean-up procedures should be designated as the Qualified Stormwater Manager for the site. The Qualified Stormwater Manager will be responsible for, but not limited to, inspections and inspection reports, personnel training, regulatory agency contact, SWMP implementation and revisions, field notebooks, and record keeping of employee activities, contacts, and notifications. References are found in the Appendix regarding some of the requirements, restrictions, and forms related to the SWMP. FIGURE 1:SITE VICINITY MAP Precision Dr Technology PkwyHarmony Rd Ziegler Rd E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 2 U20015 - EC Report B.LOCATION AND PROJECT DESCRIPTION The Precision Technology site (referred herein as “the site”) is the development of Lot 2, Harmony Technology Park Fifth Filing, located in the northwest quarter of Section 4, Township 6 North, Range 68 West of the 6th P.M., City of Fort Collins, Larimer County, Colorado. The property, consisting of approximately 4.65 acres, is located immediately north of Precision Drive, approximately 350-feet east of Technology Parkway and currently exists as vacant land in Harmony Technology Park. The proposed site improvements are limited to the 4.65 acres contained in Lot 2. The property is bounded by Precision Drive to the south, recently developed commercial businesses to the east and west, and an existing detention pond and park in the lot to the north. On site detention will not be provided with this site and was previously included in the Harmony Technology Park Stormwater Plan. A majority of the stormwater on the site currently drains southeast via sheet flow to existing drainage swales which is then collected by storm sewer infrastructure in Precision Drive and ultimately conveyed to a regional detention pond (Pond 110) at the intersection of Lady Moon Drive and Rock Creek Drive. There is also a small portion of the site that drains north via sheet flow to the existing Harmony Commons Pond which combines ponds 101, 301, and 600 from the previously mentioned master plan. Refer to the appendix for more information regarding the existing master plan and detention ponds. C.DESCRIPTION OF DEVELOPMENT The improved site will ultimately consist of pavement, rooftop, and landscaped areas. The proposed improvements have an approximate imperviousness of 71% and is divided into several smaller basins as depicted on the Drainage Plan, which can be found in Appendix B. The planned development for the Precision Technology site consists of the following improvements: The construction of a 106,700-sf apartment building. The construction of associated drive lanes, parking, utilities, bioretention pond, and landscaping. D.FLOODPLAINS The proposed development is not in a FEMA designated or City Designated floodplain. According to the FEMA Flood Insurance Rate Map Panel, the site is zoned as an area outside of the 500-year floodplain. II.SITE DESCRIPTION A.CONSTRUCTION ACTIVITY DESCRIPTION Construction activity includes installation of CMs and BMPs; site grading; storm sewer installation; building construction; concrete and asphalt pavement installation; and landscaping. B.PROPOSED SEQUENCE FOR MAJOR ACTIVITIES The estimated sequence for major construction activities is as follows: • Installation of initial erosion control items • Grading of the site. • Installation of utilities • Building Construction • Construction of concrete curb, gutter and sidewalk • Construction of asphalt and concrete pavement • Landscaping and site stabilization Construction is estimated to begin during the summer of 2021 and be completed during the winter of 2022. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 3 U20015 - EC Report C.AREA ESTIMATES The Precision Technology site is approximately 4.85 acres in size. The limits of disturbance for this Erosion Control Report is contained within this site and is approximately 4.85 acres. This Erosion Control Report does not include additional offsite area (for staging, material storage, overburden stockpiles of dirt, borrow areas, etc.) other than that mentioned above. D.SOIL DESCRIPTION The USDA’s Web Soil Survey shows that the site consists of a “Type C” soil. The Web Soil Survey indicates the site is comprised of Nunn Clay Loam (1 to 3% slopes). The on-site soils provide slow infiltration. E.EXISTING VEGETATION The site is currently covered with native grasses and weeds. The weed/grass cover is good (ie., heavy or dense cover with nearly all ground surfaces protected by vegetation). F.STREAM CROSSINGS No stream crossings exist with this site. G.POTENTIAL POLLUTION SOURCES Potential pollutant sources for this site include the following: 1.Disturbed and stored soils; Soil disturbance is expected on the site from demolition activities, utility trenching, foundation excavations and general earthwork phasing. Sediment transport from disturbed soil areas may be controlled utilizing a variety of CMs and BMPs, including but not limited to, silt fence, inlet filters, sediment control logs, surface roughening, temporary seeding and rock socks. It is also expected that there will be stockpiles of dirt on the site from earth disturbing activities. For this site, stockpiles should be located in areas where silt fence or straw wattles may be placed around the individual stockpiles to contain the runoff (i.e. landscaped or disturbed earth areas). 2.Vehicle tracking of sediments; It is anticipated that the contractor will access the property from Oakridge Drive. A vehicle tracking control pad will be required at each access location on-site during construction to reduce tracking sediment onto the adjacent streets. Construction fencing should be used to limit access to the site as required. At the end of each workday, the Contractor shall sweep or scrape Oakridge Drive of sediment that may have accumulated during the workday. 3.Management of contaminated soils There are no known contaminated soils on the site. However, if the contractor encounters contaminated soils during the construction process, the contractor should stop construction immediately, notify appropriate government authorities, and form a plan to properly contain, remove and remediate the contamination in accordance with all City, County, State and Federal laws and regulations and in accordance with good construction safety and practice. 4.Loading and Unloading operations Loading and unloading will take place on the site. These activities should be, where feasible, limited to paved surfaces within the disturbed limits of the project to minimize contact with exposed soils. BMPs such as construction fence and silt fence in non-paved areas and rock socks in paved areas should be placed to keep sediment from exiting the disturbed area limits. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 4 U20015 - EC Report 5.Outdoor storage activities (building materials, fertilizers, chemicals, etc.); Storage of onsite materials including building materials, fertilizers, waterline, storm sewer, and sanitary sewer will be covered and placed on pallets to prevent direct contact with the ground and potential surface runoff. 6.Vehicle and equipment maintenance; Vehicle and equipment maintenance should be performed offsite where feasible. For onsite vehicle and equipment maintenance, maintenance activities should be completed in designated areas away from adjacent public streets and within in a contained area through the use of curbs or berms. At a minimum, all vehicle and equipment maintenance shall be performed on hard surface or gravel areas at least 50’ from any stormwater feature (i.e. inlet, storm sewer, concentrated runoff, swale, etc.). CMs should include drip pans, drop clothes and/or other containers under vehicles. 7.Significant dust or particulate generating processes; The Contractor shall take appropriate actions to minimize atmospheric pollution and take reasonable precautions which may include, but not be limited to: 1.The use of water for control of dusts for construction processes such as demolition, grading, or the clearing of land. 2.Covering, at all times when in motion, open-bodied trucks transporting materials likely to give rise to airborne dusts. 3.Require lower speeds for vehicles entering, exiting, and driving within the project limits to minimize the amount of dust disturbed by moving vehicles. 8.Routine maintenance activities involving fertilizers, pesticides, detergents, fuels, solvents, oils, etc; Chemicals, fuels, lubricants, and paints stored on-site will be in water-tight containers and covered as necessary and stored in a bermed area, a storage building, or within a vehicle to act as secondary containment. 9.On-site waste management practices (waste piles, liquid wastes, dumpsters, etc.); 1.Waste piles should be located in designated areas and shall be covered or contained through the use of curbs or berms. Liquid wastes should be collected and stored in covered containers and disposed of properly. 2.Solid waste materials, including disposable materials incidental to the major construction activities, will be collected in on site dumpsters. The containers will be emptied periodically and trucked away from the site. Dumpsters should have covers. 10.Concrete truck / equipment washing, including the concrete truck chute and associated fixtures and equipment; A dedicated concrete washout area is necessary for this project. The contractor shall clean out equipment within the washout area so that runoff is not allowed to leave site and enter the public streets or neighboring properties. 11.Dedicated asphalt and concrete batch plants; There will not be dedicated asphalt or concrete batch plants on this site. 12.Non-industrial waste sources such as worker trash and portable toilets; Worker’s trash shall be disposed of in an onsite dumpster. The site should be free of trash at the end of each working day. Portable toilets shall be utilized by construction personnel and serviced regularly by a commercial operator. They shall be located a minimum of 5 feet from the curb or 50 feet from inlets. If sanitary facilities are located on a paved surface, toilets shall be equipped with a containment pan or a secondary containment BMP. Regardless of location all portable toilets shall be anchored per manufacturer recommendations. H.NON-STORMWATER COMPONENTS OF DISCHARGE In the event that groundwater is encountered during trenching or excavation operations, a temporary sediment/retention basin should be constructed to store pumped uncontaminated dewatering flows onsite. Note that the CDPHE may also E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 5 U20015 - EC Report require a separate Construction Dewatering permit. For more information on construction dewatering refer to the Stormwater Fact Sheet which can be found at https://www.colorado.gov/cdphe. The other non-storm water components of discharge include, but are not limited to, water line flushing, irrigation to establish seeding, washing out concrete trucks, and watering for dust mitigation, and compaction. It is important for the contractor to manage the runoff from these items utilizing the CMs and BMPs mentioned in this report (i.e. sediment traps, silt fence, straw wattles, concrete washout areas, surface roughening, etc.). I.RECEIVING WATERS The majority of developed runoff is designed to be collected and conveyed to a proposed bioretention facility and ultimately to existing detention facilities downstream and south of the site. There currently is storm sewer in Precision Drive which will collect runoff from the site in its proposed condition. Erosion Control methods detailed in this report are intended to protect this off-site downstream inlet from collecting excess sediment during construction. III.CMS AND BMPS FOR STORMWATER POLLUTION PREVENTION A.EROSION AND SEDIMENT CONTROLS Once construction activity begins, Control Measures (CMs) and Best Management Practices (BMPs) intended to contain sediment onsite must be constructed, inspected and repaired as necessary. Such controls must be functional before upslope land disturbance takes place. The CMs and BMPs will be installed as shown on the enclosed Erosion Control and Stormwater Management Plans. They must be supplemented as on-site experience proves necessary in order to control sediment, pollutant discharge, and ensure public safety. Erosion Control (SWMP) drawings are located in the Appendix that include the minimum required CMs and BMPs found on the Erosion Control Plans. The Erosion Control (SWMP) drawings should be filled in with the appropriate CMs and BMPs as they are constructed/placed within or removed from the project site. The following temporary and permanent CMs and BMPs will be installed and maintained to control on-site erosion and prevent sediment and other pollutants from traveling off-site during construction. The descriptions below provide some information about each CM or BMP, but further information can be found in Urban Storm Drainage Criteria Manual, Volume 3 – Best Management Practices by Urban Drainage and Flood Control District. CM or BMP Type Abbreviation Description Construction Fence Temporary CF The contractor is to place construction fencing around development as needed to limit access by construction equipment and personal vehicles to designated areas of ingress and egress. Regular Meetings Temporary Regular meetings with on-site workers including builders, suppliers, landscape personnel, etc. should be conducted so that they are kept up to date with site standard operating procedures. Duration and frequency of regular meetings is to be determined by the contractor. Staging Areas Temporary SA Provided during the construction process at least 100’ from any stormwater conveyance. Staging areas include locations for vehicle fueling, concrete truck washout, material storage and transfer, equipment maintenance and cleaning, and other construction activities. These areas will be maintained as isolated locations that allow for contaminants to be concentrated and removed from the site as necessary. Concrete washout areas shall be designed such that washout water cannot leave the location, nor shall storm water runoff wash concrete from the locations. The location of the staging area shown on the Erosion Control drawing is approximate. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 6 U20015 - EC Report Silt Fence Temporary SF Woven synthetic permeable fabric that filters runoff. Silt fence is installed prior to earthmoving activities and is placed downstream of areas where runoff from construction activities is expected to occur, especially along the site perimeter to allow sediment to settle from runoff before water leaves the construction site. Silt fences will be installed per manufacturer’s recommendations. Silt fence encourages sheet flow and is not intended to be used in areas of concentrated flow. If concentrated flow is encountered during the placement of the fence, an alternative BMP shall be used and the SWMP should be updated to reflect this change. Sediment Control Logs Temporary SCL Linear roll made of natural materials such as straw, coconut fiber, of other fibrous material trenched into the ground and held with a wooden stake. Sediment Control Logs are designed to act as a sediment barrier to intercept sheet flow runoff from disturbed areas. They are often used as check dams in drainage swales or small drainage ditches. Inlet Protection Temporary IP/CS Helps prevent soil and debris from the site from entering the storm drain inlets and usually consists of a sediment filter around or upstream of the storm drain inlet. Inlet protection allows storm water to flow into the drain but only after excess sediment has been filtered out. Inlet protection will be used on existing and proposed storm inlets and will be installed at such time as construction of the storm sewer system occurs. Inlet protection for this site will consist rock socks as shown in the Construction Details. Rock Socks Temporary RS Constructed of gravel wrapped via wire mesh or geo textile to form an elongated cylindrical filter. Rock Socks are designed to trap sediment during construction on roadways during events that produce stormwater runoff. Rock Socks are typically utilized at the perimeter of disturbed areas to control sediment loading. Rock Socks are used in inlet protection application when construction of roadways is complete, and they are directly connected to a receiving storm system. Surface Roughening Temporary SR Provided following overlot grading activities to slow the affects of wind erosion. Roughening can be used as a temporary BMP and is a slope protection technique used for creating unevenness on bare soil through the construction of furrows (groove cuts) running across a slope or by utilization of construction equipment to track the soil surface. The primary function of surface roughening is to reduce erosion potential by decreasing runoff velocities, reducing the length of sheet flow trapping sediment, and increasing infiltration of water into the soil. Temporary Seeding Temporary Establishment of a temporary vegetative cover on a graded area that will be exposed for longer than 30 days. Temporary seeding can be used on areas requiring temporary protection that will eventually need permanent vegetation at the completion of the construction or it can be used for areas that will be re-disturbed after a period of inactivity. Vehicle Tracking Control Temporary VTC Stabilized stone pad located at points of ingress and egress on a construction site and acts as a temporary BMP. The stone pad is designed to reduce the amount of mud transported onto public roads by construction traffic by removing mud and sediment from the vehicle’s wheels when it drives over the gravel pad. These areas are limited to the minimum number necessary to provide functional construction access and installed prior grading activities. Whenever the construction entrance exists onto a public road, the road shall be cleaned at the end of each day. Vehicle Tracking Control should also be used at the stockpile E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 7 U20015 - EC Report area exit if it is adjacent to a paved roadway. Fractured rock is preferred over rounded rock. Concrete Washout Area Temporary CWA An area to washout concrete trucks shall be established and maintained through the completion of the concrete work. Wind Borne Sediment and Dust Control Temporary Provided during the construction process to control wind borne sediment. During grading activities, water will be applied to the disturbed soils for the purpose of maintaining cohesion with clay type soils and also to meet moisture requirements for compaction of disturbed soils. Other measures of mitigation for wind erosion may include the timely installation of seed and mulch following the establishment of final grade. Open areas should be kept in a roughened condition (see Surface Roughening above). Grass Lined Swales Permanent Landscaped channels constructed generally below grade to convey runoff or channel water to a desired location. The grass-lined areas allow for infiltration to occur as well as including a flow path across a vegetated surface slowing the conveyance rate of storm water runoff. Permanent Seeding and Planting Permanent Establishment of a permanent perennial vegetation such as trees, shrubs, vines, grasses/sod, or legumes on exposed areas for final permanent stabilization in order to provide stabilization of the soil by holding soil particles in place. It also reduces storm water runoff velocity, maintains sheet flow, protects the soil surface from erosion, promotes infiltration of runoff, and improves wildlife habitat. Preservation of Existing Vegetation Permanent Occur where no construction activity is expected to occur. Preservation of natural vegetation is generally a permanent BMP and is applicable to construction sites with pre-existing vegetation. Only land needed for building activities and vehicle traffic needs is to be cleared. Storm Sewer Outlet Protection Permanent OP Structurally lined aprons or other energy dissipating devices placed at the outlets of pipes or paved channel sections. Outlet protection devices prevent scour at storm water outlets and minimize the potential of downstream erosion by reducing the velocity of storm water flows. Rip- rap and grouted rip-rap, or scour protection matting (as shown on plans) will be used downstream of storm sewer outfalls as pipe outlet protection. Outlet Protection is installed with the storm sewer construction and serves as a permanent structural BMP. B.EROSION CONTROL SEQUENCING A SWMP drawing is located in the Appendix that includes the minimum required CMs and BMPs found on the Erosion Control Plan. This SWMP drawing should be filled in with the appropriate CMs and BMPs by referencing the Erosion Control Sheet as they are constructed/placed within or removed from the project site. The Erosion Control sequencing for construction is as follows: CM or BMP Type Abbreviation Location and Notes PRIOR TO CONSTRUCTION Regular Meetings Temporary N/A Preservation of Existing Vegetation Permanent Areas not disturbed by construction activity. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 8 U20015 - EC Report Silt Fence Temporary SF Parallel to the northern, southern and western sides of the property at disturbed locations on-site. Staging Areas Temporary SA See Overall Grading & Erosion Control Plan Vehicle Tracking Control Temporary VTC One (1) located at access point along Precision Drive Construction Fence Temporary CF N/A DURING CONSTRUCTION Regular Meetings Temporary N/A Wind Borne Sediment and Dust Control Temporary N/A Inlet Protection Temporary IP All Inlets Rock Socks Temporary RS As shown on Overall Grading and Erosion Control Plan Sediment Control Logs Temporary SCL As shown on Overall Grading and Erosion Control Plan Street Sweeping and Cleaning Temporary N/A Concrete Washout Area Temporary CWA As shown on Overall Grading and Erosion Control Plan Surface Roughening Temporary SR As shown on Overall Grading and Erosion Control Plan Temporary Seeding Temporary As shown on Overall Grading and Erosion Control Plan Grass Lined Swales Permanent As shown on Overall Grading and Erosion Control Plan Permanent Seeding and Planting Permanent As shown on Overall Grading and Erosion Control Plan Storm Sewer Outlet Protection Permanent OP All storm sewer outlets. POST CONSTRUCTION All CMs or BMPs All BMPs shall be maintained until final site stabilization. C.SPILL PREVENTION AND RESPONSE PLAN In the event of a spill or accident, the spill shall be contained with a spill kit in order to prevent the contaminants from flowing off-site or soaking into the soil. Site personnel should be briefed in regular meetings of the presence of the spill kit and how the kit should be used in the event of a spill. Once contained, the contaminated materials shall be properly disposed of as approved by the Qualified Stormwater Manager and local, state, and federal jurisdictions. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 9 U20015 - EC Report For fueling areas, an appropriate absorbent (e.g. absorbent pads, oil spill kits, etc.) shall be made available and site personnel should be briefed in regular meetings of the presence of the absorbent and how the absorbent should be used in the event of a spill. Containers shall be available for used absorbents. Concrete washing of concrete trucks or other equipment shall be completed in a specified concrete washout area and in a manner and location that does not allow materials or wash water to be discharged from the site or into a storm drain system or stream. Once construction is completed, or as required during the course of construction, concrete waste and contaminated soil shall be disposed of properly. The Qualified Stormwater Manager and City Inspector should be notified immediately in the event of spills. Depending on the nature of the spill and the material involved, the CDPHE (24-hour spill reporting line 1– 877-518-5608), downstream water users, or other agencies may also need to be notified. Specifically, a release of any chemical, oil, petroleum product, sewage, etc., which may enter waters of the State of Colorado (which include surface water, ground water and dry gullies or storm sewers leading to surface water) must be reported. D.MATERIALS HANDLING The site development will include the appropriate construction staging and stockpiling areas to be identified by the contractor on the SWMP Map. Stormwater runoff generated from the staging areas will be routed to a temporary sedimentation area where runoff will be contained and filtered before being discharged off site. The staging/stockpile area(s) may be moved to a location no closer than 100’ from a stormwater conveyance and the SWMP should be updated with the actual location of the stockpile/staging area(s). If relocated, the Erosion Control Report should be updated with the actual location of the stockpile/staging area(s). Loading and unloading will take place on the site. These activities should be, where feasible, limited to paved surfaces within the disturbed limits of the project to minimize contact with exposed soils. BMPs such as construction fence and silt fence in non-paved areas and rock socks in paved areas should be placed to keep sediment from exiting the disturbed area limits. Chemicals, fuels, lubricants, and paints typical with building construction stored on-site will be in water-tight containers and covered as necessary and stored in a bermed area, a storage building, or within a vehicle to act as secondary containment. Storage of onsite materials including building materials, fertilizers, waterline, sanitary sewer, and storm sewer will be covered and placed on pallets to prevent direct contact with the ground and potential surface runoff. Other hazardous waste disposal (that is not typical to residential or commercial building construction) is not included within this SWMP. Concrete and asphalt batch plants are not anticipated on this site and thus are not included in this SWMP. IV.OTHER CONTROLS The following includes other measures to control pollutants: Solid waste materials, including disposable materials incidental to the major construction activities, will be collected in containers. The containers will be emptied periodically and trucked away from the site. Dumpsters should have covers. Water used to establish and maintain grass, for dust control, and for other purposes during the construction phase must originate from a public water supply or private well approved by the Colorado Department of Public Health and Environment unless otherwise approved. Sanitary facilities shall be provided at the site throughout construction activities. They shall be utilized by construction personnel and serviced regularly by a commercial operator. They shall be located a minimum of 5 feet from the curb or 50 feet from inlets and must be anchored. If sanitary facilities are located on a paved surface, a secondary containment CM will need to be constructed. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 10 U20015 - EC Report Access from paved roads should be limited. CMs such as tarps and drip pans should be used for painting, stucco, dry-wall etc. operations. Super-chlorinated water used for flushing water distribution systems will be de-chlorinated prior to discharging from the site by aeration, retention, dissipation, or chemical treatment. V.FINAL STABILIZATION AND LONG-TERM STORMWATER QUALITY Final stabilization is reached when all soil disturbing activities at the site have been completed and vegetative cover has been established with a density of at least 70 percent of pre-disturbance levels or when equivalent permanent erosion reduction methods have been utilized. Upon final stabilization, temporary CMs and BMPs may be removed, unless they are required to remain in place for future phasing. Primary long-term water quality will be provided through the use of a proposed inlet filter and Saffle Baffle, both being structural/mechanical treatment techniques. Secondary water quality is being provided in areas where grass-lined swales are provided for storm water conveyance as the soft bottom/overbank areas allow for infiltration to occur as well as including a flow path across a vegetated surface slowing the conveyance rate of storm water runoff. Refer to the Permanent Stormwater Quality Exhibit for locations of water quality structures and additional information. VI.SITE INSPECTIONS Regular inspections, testing of equipment, timely maintenance of the equipment, and complete records of the maintenance and inspections of the equipment shall be conducted by the Qualified Stormwater Manager and are essential to the effectiveness of the Erosion Control Report. The maintenance and inspection records will be kept on site and made available to any local, state, or federal officials upon request. Inspections must include the observation of the construction site perimeter, runoff discharge points, disturbed areas, designated haul routes, material and waste storage areas exposed to precipitation, locations where vehicles exit the site, staging areas (including concrete washout areas and fueling areas), erosion and sediment control measures identified in this SWMP, and any other structural CMs or BMPs that may require maintenance. Per the CDPHE, the inspection must include the following requirements: Visually verify whether all implemented control measures are in effective operational condition and are working as designed in their specifications to minimize pollutant discharges. Determine if there are new potential sources of pollutants. Assess the adequacy of control measures at the site to identify areas requiring new or modified control measures to minimize pollutant discharges. Identify all areas of non–compliance with the Construction Stormwater Permit requirements and, if necessary, implement corrective action as described below. Routine inspections must be conducted in accordance with one of the following schedules: 1.At least one inspection every 7 calendar days or 2.At least one inspection every 14 calendar days and within 24 hours after the end of any precipitation or snowmelt event that causes surface erosion. o Note that post-storm inspections may be used to fulfill the 14-day routine inspection requirement. Inspections may be conducted on either the 7-day or 14-day schedule and may switch between these schedules as appropriate for the site; however, the inspection schedule must be noted on the inspection reports. When site conditions make the required schedule impractical, the permittee may petition the City of Loveland or CDPHE to grant an alternate inspection schedule. The alternative inspection schedule may not be implemented prior to written approval by the City and/or CDPHE and incorporation into the plan. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 11 U20015 - EC Report Site inspections must be conducted at least once every 7 calendar days for sites that discharge to a water body designated as an Outstanding Water by the Water Quality Control Commission. The CDPHE does allow for reduced inspection frequencies under the following conditions: Post-Storm Inspections at Temporarily Idle Sites o For permittees choosing to combine 14-day inspections and post-storm-event inspections, if no construction activities will occur following a storm event, post-storm event inspections must be conducted prior to re- commencing construction activities, but no later than 72 hours following the storm event. The delay of any post-storm event inspection must be documented in the inspection record. Routine inspections must still be conducted at least every 14 calendar days. Inspections at Completed Sites/Areas o When the site, or portions of a site are awaiting establishment of a vegetative ground cover and final stabilization, the permittee must conduct a site inspection at least once every 30 days. o Post-storm event inspections are not required. o This reduced inspection schedule is allowed if all of the following criteria are met: All construction activities resulting in ground disturbance are complete; All activities required for final stabilization, in accordance with the plan, have been completed, with the exception of the application of seed that has not occurred due to seasonal conditions or the necessity for additional seed application to augment previous efforts; and The plan has been amended to locate those areas to be inspected on a reduced schedule. Winter Conditions Inspections Exclusion o Inspections are not required for sites that meet all of the following conditions: Construction activities are temporarily halted, Snow cover exists over the entire site for an extended period, and Melting conditions posing a risk of surface erosion do not exist. o When this inspection exclusion is implemented, the following information must be documented in the inspection reports: Dates when snow cover existed; Date when construction activities ceased; and Date melting conditions began. VII.MAINTENANCE PROCEDURES Upon completion of each phase of construction, appropriate measures shall be taken to inspect and maintain existing erosion control features, as described herein or per manufacturers specifications (whichever is more stringent) and install new erosion control elements associated with each phase of construction. Preventative maintenance also involves the regular inspection and testing of equipment, timely maintenance of the equipment, and complete records of the maintenance and inspections of the equipment. The maintenance and inspection records will be kept on site and made available to local, state, or federal officials upon request. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 12 U20015 - EC Report The following includes some maintenance procedures: Erosion and sediment control measures determined, upon inspection, to be in need of repair shall be maintained before the next anticipated storm event or as necessary to maintain continued effectiveness of erosion and sediment control measures. If it is impractical to maintain erosion and sediment control measures before the next storm event, maintenance should be accomplished as soon as practical. Locations where vehicles enter or exit the site shall be inspected for evidence of sediment being tracked off-site by construction traffic. Such sediment shall be removed before it can be conveyed to the receiving storm drains or creeks. Seeded areas will be checked to see that grass coverage is maintained. Areas will be watered, fertilized and reseeded as needed. It is the responsibility of the Operator to maintain effective pollutant discharge controls. Actual physical site conditions or contractor practices could make it necessary to install more control than are shown on the Erosion Control Plan. For example, localized concentrations of surface runoff or unusually steep areas could require additional erosion control devices. Assessing the need for and implementing additional controls will be a continuing aspect of the SWMP until final stabilization. This plan intends to control water-borne and liquid pollutant discharges by some combination of interception, filtration, and containment. Parties implementing this plan must remain alert to the need to periodically refine and update the plan in order to accomplish the intended goals. Sediment that has escaped the construction site must be removed at a frequency sufficient to minimize off-site impacts. VIII.RECORD KEEPING Records should include complete inspection reports for each inspection, maintenance, and/or repair. A record-keeping system is recommended in managing inspection and maintenance reports and should include all maintenance records, spill response, weather conditions, training, correspondence, etc. At a minimum, the following record keeping for the project should include: 1.The permittee must retain a hardcopy of the SWMP at the construction site throughout the life of the project. 2.The SWMP should be considered a "living document" that will be continuously reviewed and modified, including but not limited to: additions, deletions, and changing locations of control measures. These changes will be marked in the plans, dated and initialed at time of occurrence. 3.All inspection and maintenance activities or other repairs will be documented and the records kept for review upon request. A blank copy of the CDPHE Stormwater Inspection Report Template are both provided in Appendix A. 4.Records of spills, leaks or overflows that result in the discharge of pollutants must be documented and maintained. Information that should be recorded for all occurrences include the time and date, weather conditions, reasons for spill, etc. A release of any chemical, oil, petroleum product, sewage, etc., which may enter state waters must be reported immediately to the City inspector and the State of Colorado Spill Hotline at 1-877-518-5608. 5.Incidents of noncompliance, such as uncontrolled releases of pollutants including mud, muddy water or measurable quantities of sediment found off-site will be noted, along with a brief explanation as to measures taken to prevent future violations and measures taken to clean up sediment that has left the site. E ROSION C ONTROL R EPORT P RECISION T ECHNOLOGY F ORT C OLLINS ,CO 13 U20015 - EC Report IX.REFERENCES 1.Final Drainage Report for Precision Technology, United Civil Design Group, LLC., December 2020. 2.Larimer County Urban Area Street Standards, Larimer County, Colorado, Repealed and Reenacted, Effective September 19, 2016. 3.Natural Resources Conservation Service Web Soil Survey at www.websoilsurvey.nrcs.usda.gov/app. 4.Urban Storm Drainage Criteria Manual, Urban Drainage and Flood Control District, Wright Water Engineers, Inc., Denver, Colorado 2002. 5.Fort Collins Stormwater Criteria Manual, City of Fort Collins, adopted in 2011, revised in December 2018. 6.State of Colorado, Stormwater Discharges Associated with Construction Activity, Stormwater Management Plan Preparation Guides, www.colorado.gov. A PPENDIX A I NSPECTION F ORMS 31 | Appendix D: Stormwater Inspection Report Template Facility Name Permittee Date of Inspection Weather Conditions Permit Certification # Disturbed Acreage Phase of Construction Inspector Title Inspector Name Is the above inspector a qualified stormwater manager? (permittee is responsible for ensuring that the inspector is a qualified stormwater manager) YES NO INSPECTION FREQUENCY Check the box that describes the minimum inspection frequency utilized when conducting each inspection At least one inspection every 7 calendar days At least one inspection every 14 calendar days, with post-storm event inspections conducted within 24 hours after the end of any precipitation or snowmelt event that causes surface erosions  This is this a post-storm event inspection. Event Date: _____________________ Reduced inspection frequency - Include site conditions that warrant reduced inspection frequency  Post-storm inspections at temporarily idle sites  Inspections at completed sites/area  Winter conditions exclusion Have there been any deviations from the minimum inspection schedule? If yes, describe below. YES NO INSPECTION REQUIREMENTS* i. Visually verify all implemented control measures are in effective operational condition and are working as designed in the specifications ii. Determine if there are new potential sources of pollutants iii. Assess the adequacy of control measures at the site to identify areas requiring new or modified control measures to minimize pollutant discharges iv. Identify all areas of non-compliance with the permit requirements, and if necessary, implement corrective action *Use the attached Control Measures Requiring Routine Maintenance and Inadequate Control Measures Requiring Corrective Action forms to document results of this assessment that trigger either maintenance or corrective actions AREAS TO BE INSPECTED Is there evidence of, or the potential for, pollutants leaving the construction site boundaries, entering the stormwater drainage system or discharging to state waters at the following locations? NO YES If "YES” describe discharge or potential for discharge below. Document related maintenance, inadequate control measures and corrective actions Inadequate Control Measures Requiring Corrective Action form Construction site perimeter All disturbed areas Designated haul routes Material and waste storage areas exposed to precipitation Locations where stormwater has the potential to discharge offsite Locations where vehicles exit the site Other: ____________________ CONTROL MEASURES REQUIRING ROUTINE MAINTENANCE Definition: Any control measure that is still operating in accordance with its design and the requirements of the permit, but requires maintenance to prevent a breach of the control measure. These items are not subject to the corrective action requirements as specified in Part I.B.1.c of the permit. Are there control measures requiring maintenance? NO YES If “YES” document below Date Observed Location Control Measure Maintenance Required Date Completed INADEQUATE CONTROL MEASURES REQUIRING CORRECTIVE ACTION Definition: Any control measure that is not designed or implemented in accordance with the requirements of the permit and/or any control measure that is not implemented to operate in accordance with its design. This includes control measures that have not been implemented for pollutant sources. If it is infeasible to install or repair the control measure immediately after discovering the deficiency the reason must be documented and a schedule included to return the control measure to effective operating condition as possible. Are there inadequate control measures requiring corrective action? NO YES If “YES” document below Are there additional control measures needed that were not in place at the time of inspection? NO YES If “YES” document below Date Discovered Location Description of Inadequate Control Measure Description of Corrective Action Was deficiency corrected when discovered? YES/NO if “NO” provide reason and schedule to correct Date Corrected REPORTING REQUIREMENTS The permittee shall report the following circumstances orally within twenty-four (24) hours from the time the permittee becomes aware of the circumstances, and shall mail to the division a written report containing the information requested within five (5) working days after becoming aware of the following circumstances. The division may waive the written report required if the oral report has been received within 24 hours. All Noncompliance Requiring 24-Hour Notification per Part II.L.6 of the Permit a. Endangerment to Health or the Environment Circumstances leading to any noncompliance which may endanger health or the environment regardless of the cause of the incident (See Part II.L.6.a of the Permit) This category would primarily result from the discharge of pollutants in violation of the permit b. Numeric Effluent Limit Violations o Circumstances leading to any unanticipated bypass which exceeds any effluent limitations (See Part II.L.6.b of the Permit) o Circumstances leading to any upset which causes an exceedance of any effluent limitation (See Part II.L.6.c of the Permit) o Daily maximum violations (See Part II.L.6.d of the Permit) Numeric effluent limits are very uncommon in certifications under the COR400000 general permit. This category of noncompliance only applies if numeric effluent limits are included in a permit certification. Has there been an incident of noncompliance requiring 24-hour notification? NO YES If “YES” document below Date and Time of Incident Location Description of Noncompliance Description of Corrective Action Date and Time of 24 Hour Oral Notification Date of 5 Day Written Notification * *Attach copy of 5 day written notification to report. Indicate if written notification was waived, including the name of the division personnel who granted waiver. After adequate corrective action(s) and maintenance have been taken, or where a report does not identify any incidents requiring corrective action or maintenance, the individual(s) designated as the Qualified Stormwater Manager, shall sign and certify the below statement: “I verify that, to the best of my knowledge and belief, all corrective action and maintenance items identified during the inspection are complete, and the site is currently in compliance with the permit.” _________________________________ ____________________________________ Name of Qualified Stormwater Manager Title of Qualified Stormwater Manager _________________________________ _____________________________________ Signature of Qualified Stormwater Manager Date Notes/Comments A PPENDIX B P ERMIT M AP &R EFERENCE P LAN S HEETS LIMITS OF OVERALL PROJECT DISTURBANCE (4.85 ACRES)LADYMOON DRIVEHARMONY ROAD ROCK CREEK DRIVE ZIEGLER ROADKECHTER ROAD 0'1000'2000' SCALE: 1" = 1000' 500'C:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\ET\CDPHE DISCHARGE MAP.DWGCDPHE DISCHARGE MAPPATH:DRAWING NAME:SHEET SIZE: 8.5 x 11PRECISION TECHNOLOGY CDPHE DISCHARGE PERMIT MAP JOB NUMBER:U20015 NOTE:THIS EXHIBIT WAS PREPARED FOR INFORMATION ONLY AND THE ENGINEER PREPARING THESE PLANS WILL NOT BE RESPONSIBLE FOR UNAUTHORIZED USE OF THEM.DATE:December 7, 2020 PREPARED FOR:SHEET OF1 1NORTH19 OLD TOWN SQUARE #238 | FORT COLLINS, CO 80524 | (970) 530-4044 | www.unitedcivil.com UNITED CIVIL Design Group RDRDRDRDRDRDRDRDRDOVFRDA1.60.500.951.00A1.50.460.951.00A1.40.450.951.00A1.30.470.951.00A1.20.060.951.00A1.10.100.951.00B1.10.080.951.00B1.20.150.951.00B1.30.100.951.00B1.40.060.951.00B1.50.060.951.00A40.100.951.00A30.160.861.00A20.100.851.00A10.240.250.31D10.100.550.69E10.090.250.31E20.300.780.98A60.520.841.00A50.080.250.31B10.570.460.58C10.100.420.53LOT 2HARMONY TECHNOLOGY PARKFIFTH FILINGLOT 1HARMONY TECHNOLOGY PARKFOURTH FILINGPORTION OF LOT 2HARMONY TECHNOLOGY PARKSECOND FILINGTRACT AHARMONY TECHNOLOGY PARKSIXTH FILINGLOT 1HARMONY TECHNOLOGY PARKFIFTH FILINGPRECISION DRIVEPROPOSED BUILDIINGFFE = 4916.50EXISTING STORM SEWERLOT LINELOT LINELOT LINELOT LINEPOND OUTLET STRUCTUREBIORETENTION POND A DRAINAGE SWALE1.5' SPILL C&G1.5' CATCH C&G1.5' SPILL C&G1.5' CATCH C&GSTORM LINE B(SEE SHEET C3.10)STORM LINE C(SEE SHEET C3.11)1.5' SPILL C&G1.5' CATCH C&GCURB CUTSTORM LINE D(SEE SHEET C3.12)TRENCH DRAINSTORM LINE C2(SEE SHEET C3.10)EXISTING BIORETENTION POND9' UTILITY EASEMENT30' UTILITY & DRAINAGE EASEMENT45' UTILITY & DRAINAGEEASEMENTDRAINAGE EASEMENT24' EMERGENCY ACCESS EASEMENT24' EMERGENCY ACCESS EASEMENTDRAINAGE EASEMENTDRAINAGE EASEMENTCURB CUT64' ROW20' UTILITY EASEMENT24' EMERGENCY ACCESS EASEMENTDRAINAGE EASEMENTSTORM LINE A(SEE SHEET C3.10)STORM LINE E(SEE SHEET C3.12)PRECISION TECHNOLOGY LLC 12/09/2020U200151" = 30'1" = N/APRECISION TECHNOLOGY NORTH 12/8/2020 2:49:18 PMC:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\CP\C5.00 - DRAINAGE PLAN.DWGC5.00 - DRAINAGE PLAN SME NKS C5.0024DRAINAGE PLAN030'60'SCALE: 1" = 30'15'PREPARED FOR:JOB NUMBERSHEET NUMBERSHEETSOFDATE SUBMITTED:VERTICAL:HORIZONTAL:SCALEPR E L IM IN AR Y P L AN SNOT FO R CON S T RUC T IO N PROJ. MGR:DRAWING NAME:PATH:DESIGNER:DATE:TIME: The engineer preparing these plans will not be responsible for, or liable for, unauthorized changes to or uses of these plans. All changes to the plans must be in writing and must be approved by the preparer of these plans. NO.BY DATE CAUTIONREVISIONS:CIVIL ENGINEERING & CONSULTINGUNITED CIVILDesign Group19 OLD TOWN SQUARE #238FORT COLLINS, CO 80524(970) 530-4044www.unitedcivil.com13X.XXX.XXXX.XXBASIN DESIGNATIONBASIN AREA (ACRE)5 - YR RUNOFF COEFF.100 - YR RUNOFF COEFF.DESIGN POINTFLOW DIRECTIONDPD1LEGEND1.EXISTING UNDERGROUND AND OVERHEAD PUBLIC AND PRIVATEUTILITIES AS SHOWN ARE INDICATED ACCORDING TO THE BESTINFORMATION AVAILABLE TO THE ENGINEER.2.VEGETATIVE SWALES, BIOSWALES, AND THE BIORETENTION PONDSSHALL BE MAINTAINED BY THE PROPERTY OWNER AND FOLLOWAPPLICABLE STANDARD OPERATING PROCEDURES AS SHOWN INDEVELOPMENT AGREEMENT.3.SEE GRADING PLANS (SHEET C4.00) FOR MORE DETAIL ON PONDAND SITE GRADING.NOTESCHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:APPROVED:DRAINAGE SUMMARYPOND SUMMARYLOW IMPACT DEVELOPMENT TREATMENT SUMMARYBioretention PondLID WQCV REQUIRED3,058 CFLID WQCV PROVIDED3,458 CFBOTTOM OF POND ELEVATION4,908.00LID WQCV WATER SURFACE ELEVATION4,909.00100-YEAR WATER SURFACE ELEVATION4,910.00TOP OF POND ELEVATION4,910.64Proposed BasinsBasinArea%IC2C100Q2Q100(acre)(cfs)(cfs)A10.242%0.250.310.160.71A20.1085%0.851.000.251.04A30.1686%0.861.000.401.62A40.1090%0.951.000.281.01A50.082%0.250.310.050.23A60.5283%0.841.001.155.14A1.10.1090%0.951.000.271.00A1.20.0690%0.951.000.160.58A1.30.4790%0.951.001.264.63A1.40.4590%0.951.001.214.43A1.50.4690%0.951.001.234.53A1.60.5090%0.951.001.344.93A Total3.2480%0.851.005.1621.10B10.5729%0.460.580.522.37B1.10.0890%0.951.000.210.78B1.20.1590%0.951.000.401.47B1.30.1090%0.951.000.281.01B1.40.0690%0.951.000.150.57B1.50.0690%0.951.000.170.63B Total1.0256%0.680.841.746.82C10.1024%0.420.530.120.53D10.1032%0.550.690.140.63E10.092%0.250.310.060.28E20.3077%0.780.980.662.88E Total0.3959%0.660.820.733.17Proposed Total4.8571%0.780.987.9032.32BasinProposedImperviousArea (sf)LID TreatmentArea Treated(sf)% of SiteTreated (%)A1213Bioretention Pond2130%A23,904Bioretention Pond3,9043%A36,117Bioretention Pond6,1174%A43,990Bioretention Pond3,9903%A573Bioretention Pond730%A618,576Bioretention Pond18,57612%A1.13,951Bioretention Pond3,9513%A1.22,276Bioretention Pond2,2762%A1.318,234Bioretention Pond18,23412%A1.417,468Bioretention Pond17,46812%A1.517,868Bioretention Pond17,86812%A1.619,432Bioretention Pond19,43213%A Total112,103Bioretention Pond112,10375%B17,323None00%B1.13,059None00%B1.25,778None00%B1.33,986None00%B1.42,236None00%B1.52,480None00%B Total24,862None00%C11,037None00%D11,800None00%E179None00%E29,880None00%E Total9,959None00%Total Site149,411112,10375% LOT 2HARMONY TECHNOLOGY PARKFIFTH FILINGLOT 1HARMONY TECHNOLOGY PARKFOURTH FILINGPORTION OF LOT 2HARMONY TECHNOLOGY PARKSECOND FILINGTRACT AHARMONY TECHNOLOGY PARKSIXTH FILINGLOT 1HARMONY TECHNOLOGY PARKFIFTH FILINGPRECISION DRIVE9' UTILITY EASEMENT64' ROW30' UTILITY & DRAINAGE EASEMENT45' UTILITY & DRAINAGEEASEMENTEXISTING STORM SEWERLOT LINELOT LINELOT LINELOT LINEEXISTING STORM SEWEREXISTING BIORETENTION PONDOFFSITE EMERGENCYACCESS EASEMENTEXISTING 24' EMERGENCYACCESS EASEMENTPRECISION TECHNOLOGY LLC 12/09/2020U200151" = 30'1" = N/APRECISION TECHNOLOGY NORTH 12/9/2020 7:40:25 AMC:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\ET\EC PLANS.DWGEC PLANS SME NKS EC 13 INITIAL EROSION CONTROL PLAN030'60'SCALE: 1" = 30'15'PREPARED FOR:JOB NUMBERSHEET NUMBERSHEETSOFDATE SUBMITTED:VERTICAL:HORIZONTAL:SCALEPRELIMINARYP L AN SNOT FOR CONSTRUCTIONPROJ. MGR:DRAWING NAME:PATH:DESIGNER:DATE:TIME: The engineer preparing these plans will not be responsible for, or liable for, unauthorized changes to or uses of these plans. All changes to the plans must be in writing and must be approved by the preparer of these plans. NO.BY DATE CAUTIONREVISIONS:CIVIL ENGINEERING & CONSULTINGUNITED CIVILDesign Group19 OLD TOWN SQUARE #238FORT COLLINS, CO 80524(970) 530-4044www.unitedcivil.com1SWALE FLOWLINEWALLINLET PROTECTIONROCK SOCKSEDIMENT CONTROL LOGCONCRETE WASHOUT AREAEROSION CONTROLBLANKETSILT FENCEVEHICLE TRACKINGCONTROLSLOPE PROTECTIONPROPOSED MAJORCONTOURPROPOSED MINORCONTOURPROPOSED BUILDING PADLEGENDNOTES1.EXISTING UNDERGROUND AND OVERHEAD PUBLIC AND PRIVATEUTILITIES AS SHOWN ARE INDICATED ACCORDING TO THE BESTINFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOESNOT GUARANTEE THE ACCURACY OF SUCH INFORMATION.EXISTING UTILITY MAINS AND SERVICES MAY NOT BE STRAIGHTLINES OR AS INDICATED ON THESE DRAWINGS. THE CONTRACTORSHALL BE RESPONSIBLE TO CALL ALL UTILITY COMPANIES (PUBLICAND PRIVATE) PRIOR TO ANY CONSTRUCTION TO VERIFY EXACTUTILITY LOCATIONS.2.THE CONTRACTOR SHALL PROTECT ALL EXISTING FEATURES THATARE NOT TO BE REMOVED ADJACENT TO THE CONSTRUCTIONAREA INCLUDING, BUT NOT LIMITED TO, PAVEMENT, PRIVATEFENCES, ABOVE GROUND OR UNDERGROUND UTILITIES,STRUCTURES, AND UNDERGROUND FOUNDATIONS. THECONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE THATSHOULD OCCUR TO ANY ON-SITE, OFF-SITE, PUBLIC OR PRIVATEFACILITY OR FEATURE AS A RESULT OF THE CONSTRUCTIONPROCESS FOR THIS PROJECT.3.ALL DISTURBED AREAS NOT PAVED SHALL BE REVEGETATED PERTHE LANDSCAPE PLANS.EROSION CONTROL PRACTICES, SITEPROTECTION, AND REVEGETATION METHODS SHALL FOLLOW CITYREGULATIONS.4.CONTRACTOR SHALL COORDINATE ALL CONSTRUCTION ITEMSIMPACTING ADJACENT PROPERTIES WITH THE PROPERTY OWNERSPRIOR TO BEGINNING ANY CONSTRUCTION ACTIVITIES.CONTRACTOR SHALL NOTE THAT LOTS 1 AND 2 OF HARMONYTECHNOLOGY PARK FIFTH FILING ARE BOTH OWNED BY PRECISIONTECHNOLOGY LLC.5.REFER TO SHEETS C4.10-C4.11 FOR DETAILED GRADING PLANS.6.IN ADDITION TO THE EROSION CONTROL MEASURES SHOWN ONTHIS DRAWING, THE CONTRACTOR SHALL COMPLETE,COORDINATE WITH, AND UPDATE AS REQUIRED, THESTORMWATER MANAGEMENT PLAN (SWMP) FOR THIS PROJECT.7.ANY AREAS USED FOR STOCKPILING AND/OR STAGING SHOULDALSO HAVE SEDIMENT AND EROSION CONTROL MEASURES ASNECESSARY. THESE AREAS SHOULD BE LOCATED AT LEAST 100'AWAY FROM DRAINAGE WAYS. THE SWMP SHOULD BE UPDATEDTO SHOW THESE AREAS AND SEDIMENT AND EROSION CONTROLITEMS. THE ITEMS MAY INCLUDE BUT ARE NOT LIMITED TOVEHICLE TRACKING CONTROL, SILT FENCE, CONSTRUCTIONFENCE, CONCRETE WASHOUT, AND SEDIMENT TRAP.8.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ONSEEDING/PLANTING, REVEGETATION, EROSION FABRIC/BLANKETS,IRRIGATION, HARDSCAPE AND OTHER TEMPORARY ANDPERMANENT SITE STABILIZATION METHODS.9.STREET SWEEPING SHALL BE PERFORMED AS NEEDED AND/OR ATTHE DIRECTION OF THE CITY ENGINEERING INSPECTOR.10.CONTRACTOR TO TERRACE SLOPES USING A "TRACKED" VEHICLE,RUN PERPENDICULAR TO SLOPE TO INHIBIT RILL/GULLEY EROSION,CONTRACTOR MAY USE OTHER WINDROW-TYPE METHODS ASAPPROVED BY ENGINEER. TYPICAL ALL SLOPES, REPEAT ASNECESSARY UNTIL LANDSCAPING IS INSTALLED.11.REFER TO SHEET C0.02 FOR ADDITIONAL EROSION CONTROLNOTES.EXISTING MAJOR CONTOUREXISTING MINOR CONTOUREXISTING PROPERTY BOUNDARYRIGHT OF WAYCHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:APPROVED:EROSION CONTROL NOTESPROJECT:PRECISION TECHNOLOGYBEST MANAGEMENT PRACTICE ITEM:PRESERVE EXISTING VEGETATIONSILT FENCEVEHICLE TRACKING CONTROLSTAGING AREAS (if applicable)CONSTRUCTION FENCE (if applicable)ROCK SOCKSCONCRETE WASHOUT AREA(if applicable)TEMPORARY SEEDINGINLET PROTECTION (EXIST. & PROP.)1.COLUMNS SHOWN BELOW FOR TEMPORARY EROSION CONTROL ITEMS REPRESENT PHASE OFCONSTRUCTION INCREMENTS, NOT SPECIFIC TIME DURATIONS.2.CONTRACTOR IS RESPONSIBLE FOR REGULAR MAINTENANCE OF ALL BMPs.MOBILIZATIONDEMOLITIONUTILITYINSTALLATIONBUILDINGCONSTRUCTIONSITE GRADING& PAVINGFINAL LANDSCAPING& STABILIZATIONPHASE OF CONSTRUCTIONEROSION CONTROL SEQUENCINGEROSION CONTROL NOTES1.TOTAL DISTURBED AREA = 214,788 SF (4.93 ACRES).2.THE SITE WILL BE LANDSCAPED TO FINAL STABILIZATION. SEE FINALLANDSCAPE PLAN FOR DETAILS.3.REFER TO SHEET C0.02 FOR STANDARD EROSION AND SEDIMENTCONTROL CONSTRUCTION PLAN NOTES.4.EROSION CONTROL PRACTICES, SITE PROTECTION, ANDREVEGETATION METHODS SHALL FOLLOW CITY REGULATIONS.5.ANY AREAS USED FOR STOCKPILING AND/OR STAGING SHOULD ALSOHAVE SEDIMENT AND EROSION CONTROL MEASURES AS NECESSARY.THESE AREAS SHOULD BE LOCATED AT LEAST 100' AWAY FROMDRAINAGE WAYS. THE ITEMS MAY INCLUDE BUT ARE NOT LIMITED TOVEHICLE TRACKING CONTROL, SILT FENCE, CONSTRUCTION FENCE,CONCRETE WASHOUT, AND SEDIMENT TRAP.6.SOIL AMENDMENTS SHALL BE INCORPORATED IN ALL LANDSCAPEAREAS TO A DEPTH OF 6" AT A RATE OF 3 CUBIC YARDS PER 1000SQUARE FEET OF AREA -OR- 4" OF LOOSE TOPSOIL IMPORTED ONTOTHE SITE OVER 4" OF LOOSENED SUBGRADE SOILS. REFER TO CITYOF FORT COLLINS CODE SECTIONS 12-130 THROUGH 12-132.7.TEMPORARY SEEDING SHALL BE UTILIZED IN THE EVENT THAT AGRADED AREA IS EXPOSED LONGER THAN 30 DAYS. THE SITE SHALLBE SEEDED WITH THE APPROPRIATE SEED MIX AND INSTALLATIONMETHOD AS SPECIFIED ON THE APPROVED LANDSACPE PLANS.8.A COMMERCIAL FERTILIZER WITH THE FOLLOWING SPECS SHALL BEUSED:INGREDIENT% AVAILABLEBY WEIGHTAPPLICATIONRATE INLBS/ACRENITROGEN1365POTASSIUM1680POTASSIUMM120 RDRDRDRDRDRDRDRDRDOVFRDGFFE=4916.50LOT 2HARMONY TECHNOLOGY PARKFIFTH FILINGLOT 1HARMONY TECHNOLOGY PARKFOURTH FILINGPORTION OF LOT 2HARMONY TECHNOLOGY PARKSECOND FILINGTRACT AHARMONY TECHNOLOGY PARKSIXTH FILINGLOT 1HARMONY TECHNOLOGY PARKFIFTH FILINGPRECISION DRIVE9' UTILITY EASEMENT64' ROW30' UTILITY & DRAINAGE EASEMENT45' UTILITY & DRAINAGEEASEMENTEXISTING STORM SEWERLOT LINELOT LINELOT LINELOT LINEEXISTING STORM SEWERBIORETENTION POND DRAINAGE SWALE1.5' SPILL C&G1.5' CATCH C&G1.5' SPILL C&GCURB CUTCURB CUTTRENCH DRAINEXISTING BIORETENTION PONDPROPOSED BUILDIINGFFE = 4916.50EXPOSE FFE AS SHOWN FOR LOADING DOCK(SEE NOTE 5)DRAINAGE EASEMENT24' EMERGENCYACCESS EASEMENT24' EMERGENCY ACCESS EASEMENTDRAINAGE EASEMENTDRAINAGE EASEMENTOFFSITE EMERGENCYACCESS EASEMENTEXISTING 24' EMERGENCYACCESS EASEMENTCURB CUT20' UTILITY EASEMENT24' EMERGENCY ACCESS EASEMENTDRAINAGE EASEMENTCURB CUTPRECISION TECHNOLOGY LLC 12/09/2020U200151" = 30'1" = N/APRECISION TECHNOLOGY NORTH 12/9/2020 7:40:36 AMC:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\ET\EC PLANS.DWGEC PLANS SME NKS EC 23INTERIM EROSION CONTROL PLAN030'60'SCALE: 1" = 30'15'PREPARED FOR:JOB NUMBERSHEET NUMBERSHEETSOFDATE SUBMITTED:VERTICAL:HORIZONTAL:SCALEPR E L IM IN AR Y P L AN SNOT FO R CON S T RUC T IO N PROJ. MGR:DRAWING NAME:PATH:DESIGNER:DATE:TIME: The engineer preparing these plans will not be responsible for, or liable for, unauthorized changes to or uses of these plans. All changes to the plans must be in writing and must be approved by the preparer of these plans. NO.BY DATE CAUTIONREVISIONS:CIVIL ENGINEERING & CONSULTINGUNITED CIVILDesign Group19 OLD TOWN SQUARE #238FORT COLLINS, CO 80524(970) 530-4044www.unitedcivil.com2SWALE FLOWLINEWALLINLET PROTECTIONROCK SOCKSEDIMENT CONTROL LOGCONCRETE WASHOUT AREAEROSION CONTROLBLANKETSILT FENCEVEHICLE TRACKINGCONTROLSLOPE PROTECTIONPROPOSED MAJORCONTOURPROPOSED MINORCONTOURPROPOSED BUILDING PADLEGENDNOTES1.EXISTING UNDERGROUND AND OVERHEAD PUBLIC AND PRIVATEUTILITIES AS SHOWN ARE INDICATED ACCORDING TO THE BESTINFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOESNOT GUARANTEE THE ACCURACY OF SUCH INFORMATION.EXISTING UTILITY MAINS AND SERVICES MAY NOT BE STRAIGHTLINES OR AS INDICATED ON THESE DRAWINGS. THE CONTRACTORSHALL BE RESPONSIBLE TO CALL ALL UTILITY COMPANIES (PUBLICAND PRIVATE) PRIOR TO ANY CONSTRUCTION TO VERIFY EXACTUTILITY LOCATIONS.2.THE CONTRACTOR SHALL PROTECT ALL EXISTING FEATURES THATARE NOT TO BE REMOVED ADJACENT TO THE CONSTRUCTIONAREA INCLUDING, BUT NOT LIMITED TO, PAVEMENT, PRIVATEFENCES, ABOVE GROUND OR UNDERGROUND UTILITIES,STRUCTURES, AND UNDERGROUND FOUNDATIONS. THECONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE THATSHOULD OCCUR TO ANY ON-SITE, OFF-SITE, PUBLIC OR PRIVATEFACILITY OR FEATURE AS A RESULT OF THE CONSTRUCTIONPROCESS FOR THIS PROJECT.3.ALL DISTURBED AREAS NOT PAVED SHALL BE REVEGETATED PERTHE LANDSCAPE PLANS.EROSION CONTROL PRACTICES, SITEPROTECTION, AND REVEGETATION METHODS SHALL FOLLOW CITYREGULATIONS.4.CONTRACTOR SHALL COORDINATE ALL CONSTRUCTION ITEMSIMPACTING ADJACENT PROPERTIES WITH THE PROPERTY OWNERSPRIOR TO BEGINNING ANY CONSTRUCTION ACTIVITIES.CONTRACTOR SHALL NOTE THAT LOTS 1 AND 2 OF HARMONYTECHNOLOGY PARK FIFTH FILING ARE BOTH OWNED BY PRECISIONTECHNOLOGY LLC.5.REFER TO SHEETS C4.10-C4.11 FOR DETAILED GRADING PLANS.6.IN ADDITION TO THE EROSION CONTROL MEASURES SHOWN ONTHIS DRAWING, THE CONTRACTOR SHALL COMPLETE,COORDINATE WITH, AND UPDATE AS REQUIRED, THESTORMWATER MANAGEMENT PLAN (SWMP) FOR THIS PROJECT.7.ANY AREAS USED FOR STOCKPILING AND/OR STAGING SHOULDALSO HAVE SEDIMENT AND EROSION CONTROL MEASURES ASNECESSARY. THESE AREAS SHOULD BE LOCATED AT LEAST 100'AWAY FROM DRAINAGE WAYS. THE SWMP SHOULD BE UPDATEDTO SHOW THESE AREAS AND SEDIMENT AND EROSION CONTROLITEMS. THE ITEMS MAY INCLUDE BUT ARE NOT LIMITED TOVEHICLE TRACKING CONTROL, SILT FENCE, CONSTRUCTIONFENCE, CONCRETE WASHOUT, AND SEDIMENT TRAP.8.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ONSEEDING/PLANTING, REVEGETATION, EROSION FABRIC/BLANKETS,IRRIGATION, HARDSCAPE AND OTHER TEMPORARY ANDPERMANENT SITE STABILIZATION METHODS.9.STREET SWEEPING SHALL BE PERFORMED AS NEEDED AND/OR ATTHE DIRECTION OF THE CITY ENGINEERING INSPECTOR.10.CONTRACTOR TO TERRACE SLOPES USING A "TRACKED" VEHICLE,RUN PERPENDICULAR TO SLOPE TO INHIBIT RILL/GULLEY EROSION,CONTRACTOR MAY USE OTHER WINDROW-TYPE METHODS ASAPPROVED BY ENGINEER. TYPICAL ALL SLOPES, REPEAT ASNECESSARY UNTIL LANDSCAPING IS INSTALLED.11.REFER TO SHEET C0.02 FOR ADDITIONAL EROSION CONTROLNOTES.EXISTING MAJOR CONTOUREXISTING MINOR CONTOUREXISTING PROPERTY BOUNDARYRIGHT OF WAYCHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:APPROVED:PROJECT:PRECISION TECHNOLOGYBEST MANAGEMENT PRACTICE ITEM:PRESERVE EXISTING VEGETATIONSILT FENCEVEHICLE TRACKING CONTROLSTAGING AREAS (if applicable)CONSTRUCTION FENCE (if applicable)ROCK SOCKSCONCRETE WASHOUT AREA(if applicable)TEMPORARY SEEDINGINLET PROTECTION (EXIST. & PROP.)1.COLUMNS SHOWN BELOW FOR TEMPORARY EROSION CONTROL ITEMS REPRESENT PHASE OFCONSTRUCTION INCREMENTS, NOT SPECIFIC TIME DURATIONS.2.CONTRACTOR IS RESPONSIBLE FOR REGULAR MAINTENANCE OF ALL BMPs.MOBILIZATIONDEMOLITIONUTILITYINSTALLATIONBUILDINGCONSTRUCTIONSITE GRADING& PAVINGFINAL LANDSCAPING& STABILIZATIONPHASE OF CONSTRUCTIONEROSION CONTROL SEQUENCINGEROSION CONTROL NOTES1.TOTAL DISTURBED AREA = 214,788 SF (4.93 ACRES).2.THE SITE WILL BE LANDSCAPED TO FINAL STABILIZATION. SEE FINALLANDSCAPE PLAN FOR DETAILS.3.REFER TO SHEET C0.02 FOR STANDARD EROSION AND SEDIMENTCONTROL CONSTRUCTION PLAN NOTES.4.EROSION CONTROL PRACTICES, SITE PROTECTION, ANDREVEGETATION METHODS SHALL FOLLOW CITY REGULATIONS.5.ANY AREAS USED FOR STOCKPILING AND/OR STAGING SHOULD ALSOHAVE SEDIMENT AND EROSION CONTROL MEASURES AS NECESSARY.THESE AREAS SHOULD BE LOCATED AT LEAST 100' AWAY FROMDRAINAGE WAYS. THE ITEMS MAY INCLUDE BUT ARE NOT LIMITED TOVEHICLE TRACKING CONTROL, SILT FENCE, CONSTRUCTION FENCE,CONCRETE WASHOUT, AND SEDIMENT TRAP.6.SOIL AMENDMENTS SHALL BE INCORPORATED IN ALL LANDSCAPEAREAS TO A DEPTH OF 6" AT A RATE OF 3 CUBIC YARDS PER 1000SQUARE FEET OF AREA -OR- 4" OF LOOSE TOPSOIL IMPORTED ONTOTHE SITE OVER 4" OF LOOSENED SUBGRADE SOILS. REFER TO CITYOF FORT COLLINS CODE SECTIONS 12-130 THROUGH 12-132.7.TEMPORARY SEEDING SHALL BE UTILIZED IN THE EVENT THAT AGRADED AREA IS EXPOSED LONGER THAN 30 DAYS. THE SITE SHALLBE SEEDED WITH THE APPROPRIATE SEED MIX AND INSTALLATIONMETHOD AS SPECIFIED ON THE APPROVED LANDSACPE PLANS.8.A COMMERCIAL FERTILIZER WITH THE FOLLOWING SPECS SHALL BEUSED:INGREDIENT% AVAILABLEBY WEIGHTAPPLICATIONRATE INLBS/ACRENITROGEN1365POTASSIUM1680POTASSIUMM120 RDRDRDRDRDRDRDRDRDOVFRDGFFE=4916.50LOT 2HARMONY TECHNOLOGY PARKFIFTH FILINGLOT 1HARMONY TECHNOLOGY PARKFOURTH FILINGPORTION OF LOT 2HARMONY TECHNOLOGY PARKSECOND FILINGTRACT AHARMONY TECHNOLOGY PARKSIXTH FILINGLOT 1HARMONY TECHNOLOGY PARKFIFTH FILINGPRECISION DRIVE9' UTILITY EASEMENT64' ROW30' UTILITY & DRAINAGE EASEMENT45' UTILITY & DRAINAGEEASEMENTEXISTING STORM SEWERLOT LINELOT LINELOT LINELOT LINEEXISTING STORM SEWERBIORETENTION POND DRAINAGE SWALE1.5' SPILL C&G1.5' CATCH C&G1.5' SPILL C&GCURB CUTCURB CUTTRENCH DRAINEXISTING BIORETENTION PONDPROPOSED BUILDIINGFFE = 4916.50EXPOSE FFE AS SHOWN FOR LOADING DOCK(SEE NOTE 5)DRAINAGE EASEMENT24' EMERGENCYACCESS EASEMENT24' EMERGENCY ACCESS EASEMENTDRAINAGE EASEMENTDRAINAGE EASEMENTOFFSITE EMERGENCYACCESS EASEMENTEXISTING 24' EMERGENCYACCESS EASEMENTCURB CUT20' UTILITY EASEMENT24' EMERGENCY ACCESS EASEMENTDRAINAGE EASEMENTCRUSHER FINES TRAIL TO CONNECT TO EXISTINGTRAIL AT TIME OF PROJECT CONSTRUCTIONCURB CUTPRECISION TECHNOLOGY LLC 12/09/2020U200151" = 30'1" = N/APRECISION TECHNOLOGY NORTH 12/9/2020 7:40:48 AMC:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\ET\EC PLANS.DWGEC PLANS SME NKS EC 33FINAL EROSION CONTROL PLAN030'60'SCALE: 1" = 30'15'PREPARED FOR:JOB NUMBERSHEET NUMBERSHEETSOFDATE SUBMITTED:VERTICAL:HORIZONTAL:SCALEPRELIMINARYPLANSNOT FOR CONSTRUCTIONPROJ. MGR:DRAWING NAME:PATH:DESIGNER:DATE:TIME: The engineer preparing these plans will not be responsible for, or liable for, unauthorized changes to or uses of these plans. All changes to the plans must be in writing and must be approved by the preparer of these plans. NO.BY DATE CAUTIONREVISIONS:CIVIL ENGINEERING & CONSULTINGUNITED CIVILDesign Group19 OLD TOWN SQUARE #238FORT COLLINS, CO 80524(970) 530-4044www.unitedcivil.com3SWALE FLOWLINEWALLINLET PROTECTIONROCK SOCKSEDIMENT CONTROL LOGCONCRETE WASHOUT AREAEROSION CONTROLBLANKETSILT FENCEVEHICLE TRACKINGCONTROLSLOPE PROTECTIONPROPOSED MAJORCONTOURPROPOSED MINORCONTOURPROPOSED BUILDING PADLEGENDNOTES1.EXISTING UNDERGROUND AND OVERHEAD PUBLIC AND PRIVATEUTILITIES AS SHOWN ARE INDICATED ACCORDING TO THE BESTINFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOESNOT GUARANTEE THE ACCURACY OF SUCH INFORMATION.EXISTING UTILITY MAINS AND SERVICES MAY NOT BE STRAIGHTLINES OR AS INDICATED ON THESE DRAWINGS. THE CONTRACTORSHALL BE RESPONSIBLE TO CALL ALL UTILITY COMPANIES (PUBLICAND PRIVATE) PRIOR TO ANY CONSTRUCTION TO VERIFY EXACTUTILITY LOCATIONS.2.THE CONTRACTOR SHALL PROTECT ALL EXISTING FEATURES THATARE NOT TO BE REMOVED ADJACENT TO THE CONSTRUCTIONAREA INCLUDING, BUT NOT LIMITED TO, PAVEMENT, PRIVATEFENCES, ABOVE GROUND OR UNDERGROUND UTILITIES,STRUCTURES, AND UNDERGROUND FOUNDATIONS. THECONTRACTOR SHALL BE RESPONSIBLE FOR ANY DAMAGE THATSHOULD OCCUR TO ANY ON-SITE, OFF-SITE, PUBLIC OR PRIVATEFACILITY OR FEATURE AS A RESULT OF THE CONSTRUCTIONPROCESS FOR THIS PROJECT.3.ALL DISTURBED AREAS NOT PAVED SHALL BE REVEGETATED PERTHE LANDSCAPE PLANS.EROSION CONTROL PRACTICES, SITEPROTECTION, AND REVEGETATION METHODS SHALL FOLLOW CITYREGULATIONS.4.CONTRACTOR SHALL COORDINATE ALL CONSTRUCTION ITEMSIMPACTING ADJACENT PROPERTIES WITH THE PROPERTY OWNERSPRIOR TO BEGINNING ANY CONSTRUCTION ACTIVITIES.CONTRACTOR SHALL NOTE THAT LOTS 1 AND 2 OF HARMONYTECHNOLOGY PARK FIFTH FILING ARE BOTH OWNED BY PRECISIONTECHNOLOGY LLC.5.REFER TO SHEETS C4.10-C4.11 FOR DETAILED GRADING PLANS.6.IN ADDITION TO THE EROSION CONTROL MEASURES SHOWN ONTHIS DRAWING, THE CONTRACTOR SHALL COMPLETE,COORDINATE WITH, AND UPDATE AS REQUIRED, THESTORMWATER MANAGEMENT PLAN (SWMP) FOR THIS PROJECT.7.ANY AREAS USED FOR STOCKPILING AND/OR STAGING SHOULDALSO HAVE SEDIMENT AND EROSION CONTROL MEASURES ASNECESSARY. THESE AREAS SHOULD BE LOCATED AT LEAST 100'AWAY FROM DRAINAGE WAYS. THE SWMP SHOULD BE UPDATEDTO SHOW THESE AREAS AND SEDIMENT AND EROSION CONTROLITEMS. THE ITEMS MAY INCLUDE BUT ARE NOT LIMITED TOVEHICLE TRACKING CONTROL, SILT FENCE, CONSTRUCTIONFENCE, CONCRETE WASHOUT, AND SEDIMENT TRAP.8.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ONSEEDING/PLANTING, REVEGETATION, EROSION FABRIC/BLANKETS,IRRIGATION, HARDSCAPE AND OTHER TEMPORARY ANDPERMANENT SITE STABILIZATION METHODS.9.STREET SWEEPING SHALL BE PERFORMED AS NEEDED AND/OR ATTHE DIRECTION OF THE CITY ENGINEERING INSPECTOR.10.CONTRACTOR TO TERRACE SLOPES USING A "TRACKED" VEHICLE,RUN PERPENDICULAR TO SLOPE TO INHIBIT RILL/GULLEY EROSION,CONTRACTOR MAY USE OTHER WINDROW-TYPE METHODS ASAPPROVED BY ENGINEER. TYPICAL ALL SLOPES, REPEAT ASNECESSARY UNTIL LANDSCAPING IS INSTALLED.11.REFER TO SHEET C0.02 FOR ADDITIONAL EROSION CONTROLNOTES.EXISTING MAJOR CONTOUREXISTING MINOR CONTOUREXISTING PROPERTY BOUNDARYRIGHT OF WAYCHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:APPROVED:PROJECT:PRECISION TECHNOLOGYBEST MANAGEMENT PRACTICE ITEM:PRESERVE EXISTING VEGETATIONSILT FENCEVEHICLE TRACKING CONTROLSTAGING AREAS (if applicable)CONSTRUCTION FENCE (if applicable)ROCK SOCKSCONCRETE WASHOUT AREA(if applicable)TEMPORARY SEEDINGINLET PROTECTION (EXIST. & PROP.)1.COLUMNS SHOWN BELOW FOR TEMPORARY EROSION CONTROL ITEMS REPRESENT PHASE OFCONSTRUCTION INCREMENTS, NOT SPECIFIC TIME DURATIONS.2.CONTRACTOR IS RESPONSIBLE FOR REGULAR MAINTENANCE OF ALL BMPs.MOBILIZATIONDEMOLITIONUTILITYINSTALLATIONBUILDINGCONSTRUCTIONSITE GRADING& PAVINGFINAL LANDSCAPING& STABILIZATIONPHASE OF CONSTRUCTIONEROSION CONTROL SEQUENCINGEROSION CONTROL NOTES1.TOTAL DISTURBED AREA = 214,788 SF (4.93 ACRES).2.THE SITE WILL BE LANDSCAPED TO FINAL STABILIZATION. SEE FINALLANDSCAPE PLAN FOR DETAILS.3.REFER TO SHEET C0.02 FOR STANDARD EROSION AND SEDIMENTCONTROL CONSTRUCTION PLAN NOTES.4.EROSION CONTROL PRACTICES, SITE PROTECTION, ANDREVEGETATION METHODS SHALL FOLLOW CITY REGULATIONS.5.ANY AREAS USED FOR STOCKPILING AND/OR STAGING SHOULD ALSOHAVE SEDIMENT AND EROSION CONTROL MEASURES AS NECESSARY.THESE AREAS SHOULD BE LOCATED AT LEAST 100' AWAY FROMDRAINAGE WAYS. THE ITEMS MAY INCLUDE BUT ARE NOT LIMITED TOVEHICLE TRACKING CONTROL, SILT FENCE, CONSTRUCTION FENCE,CONCRETE WASHOUT, AND SEDIMENT TRAP.6.SOIL AMENDMENTS SHALL BE INCORPORATED IN ALL LANDSCAPEAREAS TO A DEPTH OF 6" AT A RATE OF 3 CUBIC YARDS PER 1000SQUARE FEET OF AREA -OR- 4" OF LOOSE TOPSOIL IMPORTED ONTOTHE SITE OVER 4" OF LOOSENED SUBGRADE SOILS. REFER TO CITYOF FORT COLLINS CODE SECTIONS 12-130 THROUGH 12-132.7.TEMPORARY SEEDING SHALL BE UTILIZED IN THE EVENT THAT AGRADED AREA IS EXPOSED LONGER THAN 30 DAYS. THE SITE SHALLBE SEEDED WITH THE APPROPRIATE SEED MIX AND INSTALLATIONMETHOD AS SPECIFIED ON THE APPROVED LANDSACPE PLANS.8.A COMMERCIAL FERTILIZER WITH THE FOLLOWING SPECS SHALL BEUSED:INGREDIENT% AVAILABLEBY WEIGHTAPPLICATIONRATE INLBS/ACRENITROGEN1365POTASSIUM1680POTASSIUMM120 PRECISION TECHNOLOGY LLC 12/09/2020U200151" = N/A1" = N/APRECISION TECHNOLOGY 12/8/2020 2:50:11 PMC:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\CP\C6.00 - CONSTRUCTION DETAILS.DWGC6.00 - CONSTRUCTION DETAILS SME NKS C6.0924CONSTRUCTION DETAILS PREPARED FOR:JOB NUMBERSHEET NUMBERSHEETSOFDATE SUBMITTED:VERTICAL:HORIZONTAL:SCALEPRELIMINARYP L AN SNOT FOR CONSTRUCTIONPROJ. MGR:DRAWING NAME:PATH:DESIGNER:DATE:TIME: The engineer preparing these plans will not be responsible for, or liable for, unauthorized changes to or uses of these plans. All changes to the plans must be in writing and must be approved by the preparer of these plans. NO.BY DATE CAUTIONREVISIONS:CIVIL ENGINEERING & CONSULTINGUNITED CIVILDesign Group19 OLD TOWN SQUARE #238FORT COLLINS, CO 80524(970) 530-4044www.unitedcivil.com23CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:APPROVED:APPROVED:DATE:DRAWN BY:12/27/00NBJF L O WAPPROVED:DATE:DRAWN BY:NBJ11-29-2000APPROVED:DATE:DRAWN BY:01/03/01NBJSEDIMENT CONTROL LOG INSTALLATION DETAILNOT TO SCALE2C6.09ROCK SOCK DETAILNOT TO SCALE1C6.09 PRECISION TECHNOLOGY LLC 12/09/2020U200151" = N/A1" = N/APRECISION TECHNOLOGY 12/8/2020 2:50:15 PMC:\UNITED CIVIL DROPBOX\PROJECTS\U20015 - PRCS PRECISION TECH II\CADD\CP\C6.00 - CONSTRUCTION DETAILS.DWGC6.00 - CONSTRUCTION DETAILS SME NKS C6.1024CONSTRUCTION DETAILS PREPARED FOR:JOB NUMBERSHEET NUMBERSHEETSOFDATE SUBMITTED:VERTICAL:HORIZONTAL:SCALEPRELIMINARYPLANSNOT FOR CONSTRUCTIONPROJ. MGR:DRAWING NAME:PATH:DESIGNER:DATE:TIME: The engineer preparing these plans will not be responsible for, or liable for, unauthorized changes to or uses of these plans. All changes to the plans must be in writing and must be approved by the preparer of these plans. NO.BY DATE CAUTIONREVISIONS:CIVIL ENGINEERING & CONSULTINGUNITED CIVILDesign Group19 OLD TOWN SQUARE #238FORT COLLINS, CO 80524(970) 530-4044www.unitedcivil.com24CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:CHECKED BY:APPROVED:CWAVEHICLE CONTROL TRACKING PADNOT TO SCALECONCRETE WASHOUT AREANOT TO SCALE1C6.102C6.10VTCSURFACE ROUGHENINGNOT TO SCALE3C6.10DANDY CURB BAGTMOVERFLOWGAPCURB ANDGUTTER INLETCURBFILTERLOW PROFILE WITHGUTTER FOR SAFETYAND CURB APPEALLIFTINGSTRAPSSTORM SEWERGRATE COMPLETELYCOVERED BYHI-FLOW FABRICDANDY BAGVELCROCLOSURELIFT STRAPSUSED FOR EASYMOVEMENT ANDINSPECTION OFUNITSTORMSEWERGRATEDANDY BAGRSTORMSEWERGRATERDANDY CURBTMMANHOLECURB OPENINGWITHOUT GRATECURB FILTEROVERFLOWGAPAGGREGATEPOUCHINLET FILTER DETAILSNOT TO SCALESTABILIZED STAGING AREA DETAILNOT TO SCALECOMBINATION INLET FILTER - DP1TYPE R INLET FILTER - DP2AREA INLET FILTER - DP3NOTES:1.INLET FILTERS SHALL BE DANDY PRODUCTS AS SHOWN OR APPROVED EQUAL. PLAN VIEWREFERS TO DANDY PRODUCTS AS "DP-#" AS DESIGNATED ON THIS DETAIL.4C6.105C6.10 A PPENDIX C C ONTRACTOR I NSERTS (P ERMIT ,I NSPECTION R EPORTS , ETC .)