HomeMy WebLinkAbout1605 Peterson Place Carriage House - FDP200023 - Correspondence SUBMITTAL DOCUMENTS - ROUND 1 - 10/19/2020Community Development and
Neighborhood Services
281 North College Avenue
PO Box 530
Fort Collins, CO 80522
970.2 t.67 0
970-224.6134 fax
fcgovcom
January 10, 2019
Shannon Corrough
Re: 1605 Peterson Place SingleFamily
Description of project: This is a request to build a singlefamily detached house at 1605
Peterson Place (parcel #9724210003). Access is taken from Peterson PI to the east and
Peterson, St to the west. The proposed project is within the Low Density MixedUse
Neighborhood (LMN) zone district and is subject to Administrative (Type 1) review,
Please see the following summary of comments regarding the project request referenced
above. The comments offered informally by staff during the Conceptual Review will assist you
in preparing the detailed components of the project application. Modifications and additions
to these comments may be made at the time of formal review of this project. If you have any
questions regarding these comments or the next steps in the review process, you may contact
the individual commenter or direct your questions through: the Development Review Coordinator,
Todd Sullivan at 970-221-6695 or tsu1livan(a)fcQov.c m .
Comment Summary:
Planning Services
Contact: Clay Frickey, 9702246045, efrickey@Lcgov.com
Clay is no longer in Planning. Todd is checking to see who the Planner dill be going forward.
1. For the purposes of this development, we're considering Peterson St to be an alley rather
than a typical public street. This is important as certain standards like our garage door
standards change based on this determination.
2. For your formal development application, you will need to submit a site plan showing the
location of any existing structure on the lot, the location of the carriage house, and location
of parking. You'll also need to include tables describing the size of structures, the amount
of parking provided, and size of the site. I can provide you an example of what your site
plan should look like with the final comment letter.
3. Since your lot is 75 feet wide, you will need to provide at least one offstreet parking
space for the new house. The new structure will provide two new parking spots.
4. The maximum building height in this zone district is 2.5 stories. The new structure %AdR be one story.
5. Will you be replatting your lot as part of this project? If so, you will need to provide a
subdivision plat as part of your formal submittal to the City. N/A
6. Please also provide architectural elevations of the new house as part of your formal
submittal. This will be included with the survey.
7. The following setbacks will apply to your new house:
From Peterson St. 8 feet
Side lot line 5 feet.
These setbacks have been accounted for in the design and placement of the new structure.
8. The proposed development project is subject to a Type 1 review and public hearing, the
decision maker for Type 1 hearings is an Administrative Hearing Officer. The applicant
for this development request is not required to hold a neighborhood meeting for a Type 1
hearing, but if you would like to have one to notify your neighbors of the proposal, please
let me know and I can help you in setting a date, time and location for a meeting.
Neighborhood Meetings are a great way to get public feedback and avoid potential
hiccups that may occur later in the review process. I have spoken personally with a few of my neighbors
but the structure (other than the initial noise which I have made them aware of) will not effect their
properties. I will not be pursuing a Neighborhood meeting at this time.
9. Please see the Development Review Guide at www.fcgov.com/drg. This online guide
features a color coded flowchart with comprehensive, easy to read information on each
step in the process. This guide includes links to just about every resource you need
during development review.
10. This development proposal will be subject to all applicable standards of the Fort Collins
Land Use Code (LUC), including Article 3 General Development Standards. The entire
LUC is available for your review on the web at
http://wwvv.(,,olgggdp-.Qomiff.collins/landuse/be,ain.htm. I was unable to pull this information up
on the internet. Please make me aware if there is anything significant I may need to know.
11. If this proposal is unable to satisfy any of the requirements set forth in the LUC, a
Modification of Standard Request will need to be submitted with your formal development
proposal. Please see Section 2.8.2 of the LUC for more information on criteria to apply
for a Modification of Standard.
12. Please see the Submittal Requirements and Checklist at:
ht.to://www.f M -,viewli /aoocations.ohn
mov,com/develool entr(
13. The request will be subject to the Development Review Fee Schedule that is available in
the Community Development and Neighborhood Services office. The fees are due at the
time of submittal of the required documents for the appropriate development review
process by City staff and affected outside reviewing agencies. Also, the required
Transportation Development Review Fee must be paid at time of submittal.
14. When you are ready to submit your formal plans, please make an appointment with
your Development Review Coordinator, Todd Sullivan at 970-221-6695 or Lsuiltvan@fcgov.com.
Department: Historical Preservation
Contact: Cassandra Burrigarner, 9704162990, cburgS@Mg.r j§k99y.0m
Cassandra is no longer vft the City of Fort Collins. Please reach out to Todd if you have any
questions.
1. This property is a potentially eligible resource. At the conceptual review stage, the
applicant is responsible for ordering (through historic preservation staff) thirdparty
surveys by an independent contractor of any parcels on or adjacent to the development
2
site that may be eligible for Fort Collins Landmark status. This step will provide your
team with accurate, predictable, and official information regarding which abutting
parcels, if any, will need to be considered in terms of the site plan and architecture of
new construction. As soon as you have confidence that you will proceed with an
application, you will need to pay for the survey of 1605 Peterson Street so that we can
get the results of the survey as soon as possible. This is a mandatory requirement as
long as the project goes forward. I have conducted a survey of the entire property and will
submit that with all documents.
2. If the property is eligible, the proposed accessory dwelling unit will need to be
compatible with the existing dwelling on the parcel. If the property is not eligible, staff will
need to identify a reasonable approach to getting information about nearby resources if
we think there are some potentially eligible resources inside the 200 foot boundary. If
Historic Preservation staff determines that survey is necessary for one or more parcels
associated with this development, completed determinations of eligibility for these
properties, which are based on the thirdparty surveys, are now required as part of the
presubmittal process for development proposals. Historic Preservation staff cannot sign
off on our presubmittal requirements until these survey results are complete and fees are
paid. The applicant is responsible for the fees associated with those surveys and should
contact Historic Preservation staff before submitting a PDP application to begin the
survey process and remit payment. I was told in an email dated 6/11120 that this project
does not require historical preservation review after changes made to codes as of April 2019.
Please contact me asap at cbumgarner@fcgov.com to request a staff evaluation
regarding this presubmittal requirement.
Department: Engineering Development Review
Contact: Spencer Smith, 9702216603, smsmithBiggowcom
1. Please contact Spencer Smith (smsmith@fcgov.com or (970)2216603) if you have
further questions regarding these conceptual engineering comments or requirements.
2. Typically, development or redevelopment is required to construct adjacent street
frontage improvements to current City standards. This would include asphalt, curb and
gutter, sidewalk, parkway, etc. In this case, it may not make sense to construct sidewalk
for example, when there is no adjacent sidewalk to connect to. Engineering staff likes to
look at these kinds of projects on a casebycase basis to determine what should be
required of an applicant. I am going to discuss this project at our Transportation
Coordination meeting coming up on Monday, 1/14. 1 will be able to provide more
information on Engineering requirements after that meeting. The new structure will be accessed
from the west side of my property (Peterson Street), there are no curbs, gutters or sidewalks,
on that street.
3. As with the street frontage improvements mentioned in the previous comment, a project
is typically responsible for dedicating any rightofway (ROW) and easements that are
necessary or required by the Co. Most easements to be dedicated need to be public
easements dedicated to the City. This shall include the standard utility easements that
are to be provided behind the ROW (15 foot along an arterial, 8 foot along an alley, and
9 foot along all other street classifications). Based on existing ROW/easements, this
project would need to dedicate 10 1/2 feet of road ROW along the Peterson Pl. frontage,
as well as a 9foot utility easement (per the City standard Residential Local roadway
3
0
section). As long as Poludre Fire Authority and the rest of the City departments are okay
with the existing 16 foot alley ROW along the west side of this property, Engineering
would not likely ask for any additional ROW for the alley (the 16 feet falls within City alley
ROW width standards). The City may still require that the standard 8 foot wide alley
utility easement be dedicated with this project, however. Information on the dedication
process can be found at: htgL/jwww.fc vxom/en ineerin dgv v.ph
I am aware that I will have to submit an easement and right-of-way dedication to the city regarding
the area off of Peterson Street. l plan to do so while this project is being reviewed by the City for
approval.
4. All public sidewalk, driveways and ramps, existing or proposed, adjacent or within the
site, need to meetADA standards. If they currently do not, they will need to be
reconstructed so that they do meet current ADA standards as a part of this project.
Engineering staff will conduct a site visit to determine the extent of pedestrian facilities
that would need to be brought up to current ADA standards. This site inspection would
occur after the initial project submittal so that this information can be provided with the
first round of staff review comments.
5. All necessary permitting will be required of any proposed worklimprovements, within the
public ROW, prior to construction. At this time, ll am not aware of any work or improvements that will
happen in the ROW,
6. Larimer County Road Impact Fees and Transportation Expansion Fees are due at the
time of building permit. Please contact Kyle Lambrecht at (970)2216566 if you have
any questions
7. The City's Transportation Development Review Fee (TDRF) is due at the time of
submittal. For additional information on these fees, please see:
hftp://www.fcgov,com/engineering/devreview.php
8. Any damaged curb, gutter and sidewalk existing prior to construction, as well as streets,
sidewalks, curbs and gutters, destroyed, damaged or removed due to construction of
this project, shall be replaced or restored to City of Fort Collins standards at the
Developer's expense prior to the acceptance of completed improvements and/or prior
to the issuance of the first Certificate of Occupancy.
9. Any public improvements must be designed and built in accordance with the Larimer
County Urban! Area Street Standards (LCUASS). They are available online at:
lifto�://www,larimer.org/engi,neerfna/GMARdStds/UrbanSt. htm
10. A utility coordination meeting on this site is suggested. Utility coordination meetings, if
requested, are typically scheduled after the preliminary submittal of the project, but can
be scheduled prior to submittal upon request. Please provide a site plan with a
preliminary utility layout for routing with the meeting notice. If you are interested in having
a utility coordination meeting, please contact the development review engineer for
scheduling. I am available to have a utility meeting (if necessary) after submittal. At this time,
my grading and drainage engineer (Scott, Nesbitt, PE) has been in touch with Dan Mogen, E1, CFN4
regarding the utility plan proposal we wN be submitting. After submittal, l will complete a Declaration of
Covenants Agreement regarding utility service conditions.
11. All fences, barriers, posts or other encroachments within the public ROW are only
permitted upon approval of an encroachment permit. Applications for encroachment
permits shall be made to the Engineering Department for review and approval prior to
installation. Encroachment items shall not be shown on the site plan as they may not be
approved, need to be modified or moved, or if the permit is revoked then the site/
4
M
landscape plan is in noncompliance, l have no plans to have any fencing, barriers or
encroachment items within the ROW in this project.
12. The development/site cannot use the ROW for any Low Impact Development to treat the
site's storm runoff. N/A
13. With regards to construction of this site, the public ROW shall not be used for staging or
storage of materials or equipment associated with the Development, nor shall it be used
for parking by any contractors, subcontractors, or other personnel working for or hired by
the Developer to construct the Development. The Developer will need to find a
location(s) on private property to accommodate any necessary staging and/or parking
needs associated with the completion of the Development. Information on the
location(s) of these areas will be required to be provided to the City as a part of the
Development Construction Permit application. Ail materials, staging, equipment and subcontractors
will be within my private property boundaries on the west side of the property and will not obstruct the ROW.
Department: Traffic Operations
Contact: Martina Wilkinson, 9702216887, mwilkinson(c)fcgov.com
1. The anticipated change in traffic volume is not expected to meet the threshold of
requiring a Traffic Impact Study. Based on Chapter 4 of the Larimer County Urban Area
Street Standards (LCUASS), the Traffic Impact Study is waived. N/A
2. Work with the Engineering Department on any required improvements to roadway
frontages.
Department: WaterWastewater Engineering
Contact: Shane Boyle, 9702216339, sboyleMcmuom
1. Water and Sewer Service (site specific comment):.
There are existing 8inch water and sewer mains in Peterson Place. The new house will
be required to install separate service connections at the main and cannot be served
from the same service lines as the existing house. I will, be submitting a utility plan with my documents.
2. Water conservation (standard comment):
The water conservation standards for landscape and irrigation will apply. Information on
these requirements can be found at hftp://www.fcgov.com/standards
3. Fees (standard comment):
Development fees and water rights will be due at building permit. These fees are to be
paid at the time each building permit is issued. Information on fees can be found at:
hftp:/Iwww.fegov.com/utilities/business/buildersanddevelopers/plantnvestmentdevelo
pmentfees or contact our Utility Fee and Rate Specialists at (970) 4164252 for
questions on fees.
Department: Stormwater Engineering
Contact: Shane Boyle, 9702216339, sbovie@fcoov.com
1. Master plan and criteria compliance (site specific comment):
5
The design of this site must conform to the drainage basin design of the Spring Creek
Master Drainage Plan as well the Fort Collins Stormwater Criteria Manual.
2. Documentation requirements (site specific comment):
If there is an increase in imperviousness greater than 1,000 square feet a drainage
report, erosion control report and construction plans are required and they must be
prepared by a Professional Engineer registered in the State of Colorado. The drainage
report must address the fourstep process for selecting structural BMPs. If the increase
in impervious area is greater than 350 square feet and less than 1,000 square feet, a
drainage letter along with a grading and erosion control plan should be sufficient to
document the existing and proposed drainage patterns. A grading plan is required if the
increase in imperviousness is less than 350 square feet. I will be submitting a drainage letter and
and a grading and erosion control plan with my documents. This has been prepared by a licensed
Engineer, Scott Nesbitt, PE. All additional sections of this comment will be addressed as well.
3. Stormwater outfall (site specific comment):
The stormwater outfall options for this site appear to be the adjacent rightsofway.
Drainage into streets and alleys in this area can be problematic, causing damage to
downstream and neighboring properties. As part of any development on this property, a
drainage analysis will need to be completed by a Civil Engineer addressing any
additional drainage created by the development and showing how conveyance of site
drainage is conveyed to an adequate public facility without impacting downstream
properties.
4. Imperviousness documentation (standard comment):
It is important to document the existing impervious area since drainage requirements
and fees are based on new impervious area. An exhibit showing the existing and
proposed impervious areas with a table summarizing the areas is required prior to the
time fees are calculated for each building permit.
5. Detention requirements (standard comment):
When improvements are proposed to an existing developed site and there is an
increase in impervious area greater than 1000 square feet, onsite detention is required
with a 2year historic release rate for water quantity. Parking lot detention for water
quantity is allowed as long as it is not deeper than one foot. If there is less than 1000 but
more than 350 square feet of new impervious area, a site grading plan is required along
with the impervious area documentation.
6. Detention drain times (standard comment):
Per Colorado Revised Statute §3792602 (8) that became effective August 5, 2015,
criteria regarding detention drain time will apply to this project. As part of the drainage
design, the engineer will be required to show compliance with this statute using a
standard spreadsheet (available on request) that will need to be included in the
drainage report. Upon completion of the project, the engineer will also be required to
upload the approved spreadsheet onto the Statewide Compliance Portal. This will
apply to any volume based stormwater storage, including extended detention basins.
7. Standard water quality requirements (standard comment):
6
0
When improvements are proposed to an existing developed site and there is an
increase in impervious area greater than 1000 square feet, fifty percent of the site runoff
is required to be treated using the standard water quality treatment as described in the
Fort Collins Stormwater Manual, Volume Best Management Practices (BMPs).
(hftp-//www.fcgov.com/ufilities/business/buildersanddevelopersldevelolpmentformsgui
delinesregulations/stormwatercriteria) Extended detention is the usual method
selected for water quality treatment; however the use of any of the BMiPs, is encouraged.
8. LID requirements, (standard comment):
When improvements are proposed to an existing developed site and there is an
increase in impervious area greater than 1000 square feet, low Impact Development
(LID) requirements are required on all new or redeveloping property which includes sites
required to be brought into compliance with the Land: Use Code. These require a higher
degree of water quality treatment with one of the two following options:
1. 50% of the newly added or modified impervious area must be treated by LID
techniques and 25% of new paved areas must be pervious.
2. 75% of all newly added or modified impervious area must be treated by LID
techniques.
9. Erosion control requirements (standard comment):
The erosion control report requirements are in Section 1.3.3, Volume 3, Chapter 7 of the
Fort Collins Stormwater Criteria Manual. If you need clarification concerning this section,
please contact the Erosion Control Inspector, Jesse Schlarn at 2246015 or
jschlam@fcgov.com.
10. Fees (standard comment):
The 2019 city wide Stormwater development fee (PIF) is $8,217/acre for new
impervious area over 350 square feet and there is a $1,045/acre of site review fee. No
fee is charged for existing impervious area. These fees are to be paid at the time each
building permit is issued. Information on fees can be found at:
http://www.fcgov.comluftlifies/business/buildersanddevelopers/p[antnvestmentdevelo
pmentfees or contact our Utility Fee and Rate Specialists at (970) 4164252 for
questions on fees. There is also an erosion control escrow required before the
Development Construction permit is issued. The amount of the escrow is determined by
the design engineer, and is based on the site disturbance area, cost of the measures, or
a minimum amount in accordance with the Fort Collins Stormwater Manual.
Monthly fees hil, ://www.fcoo,v.com/mtilitiesibusiness/rates
Department: Electric Engineering
Contact: Tyler Siegmund, 9704162772, jaie �mun_ o�v&Am
1. Light and Power currently feeds the existing home with electric service coming from
Peterson Place. Light and Power has, electric facilities, along Peterson St as well that
can provide electric service to the new residence. I spoke with Tyler Siegmund on a phone
call dated 6125/20 regarding the requirements listed below. ll am looking to add to the existing transformer
on Peterson Street. I was made aware of fees and the different arnps required. I plan to add
7
200 amps, as to accommodate future solar panels on my roof. I was made aware that if we trench
from the meter to the transformer, I would not incur an additional fee but would have to backfill. I am
prepared to meet all requirements and pay all fees related to these steps.
2. Electric capacity fees, development fees, building site charges and any system
modification charges necessary to feed the site will apply to this development. Please
contact me or visit the following website for an estimate of charges and fees related to
this project.
hftp://www.fcgov.com/utlifies/business/buildersanddevelopers/planfinvestmentdevelo
pmentfees
3. Depending on loading on the existing single phase transformer along Peterson St and
the requested electric service size for this new residence, the transformer may have to
be upsized to accommodate the new service load. The owner/developer is responsible
for any modifications needed to our system to feed the new residence. Please contact
me if you would like to discuss Light and Power fees for this project.
4. The new residence will need to be individually metered.
5. Meter location will need to be coordinated with Light and Power. Please how proposed
meter location on the utility plans for the next submittal. A utility plan will be submitted with
my documentation.
6. Please contact Tyler Siegmund with Light & Power Engineering if you have any
questions at 970.416.2772. Please reference our policies, construction practices,
development charge processes, electric service standards, and use our fee estimator at
hftp://wvvw,fcoov.com/i)tilifies/busingss/buildeLsanddeve oIle r.s
Department: Fire Authority
Contact: Andrew Rosen, 9704162599, aro,sen@poudreflm.or
1. 2018 IFC CODE ADOPTION
Poudre Fire Authority and the City of Fort Collins (Town of Timnath, Larimer County) are
in the process of adopting the 2018 International Fire Code. Code adoption is
anticipated in early 2019. Building plan reviews shall be subject to the adopted version
of the fire code in place at the time of plan review submittal and permit application. I have been in touch
with Jim Lynxwiler over the last few months with, our last email exchange on 10/7120.
�11111111111105yd
>A hydrant producing 1 000gpm at 20psi residual pressure is required within 400ft of all
residences. The hydrant at Parker St is approximately 520ft from the Carriage house
since access will be taken from Peterson St therefore requiring a new hydrant to be
installed. In email discussion with Jim Lynxwiler on 1017/20, it was determined that the fire hydrant
on Prospect Road and Peterson Street (270 feet from the location of the proposed new structure) would
be sufficient in an Operational emergency per the PFA and will not require I install a hydrant south of
Prospect Road. This exception will negate the need for me to install a fire suppression system within
the new structure as long as the new structure can be addressed and accessed off of Peterson Street.
I was made aware during a meeting on 9/25120 by Todd Sullivan that CIS/City will allow me to address
off of Peterson Street.
>Should this not be possible, this out of compliance condition may be mitigated if the
proposed residence is designed with an approved residential fire sprinkler system. This
would require approval of the Fire Marshal.
9
0
3. ACCESS
Access is required to within 150ft of all portions of the exterior perimeter of the
proposed Carriage House. This can be measured from Peterson Place and Peterson
St since they are both unclassified streets. No further action required on this.
4. ADDRESSING/WAYFINDING
To assist with prompt emergency response the proposed carriage house should be a
separate address through GIS. Should this not be possible, a unit designator such as
Unit B can be used. Should this be a Peterson Place address, the full address including
street name should be clearly visible from Peterson St. This has been approved through GIS
per Todd Sullivan on 9/25/20.
5. SOLAR ARRAYS
Commercial rooftop structures and ground mounted solar arrays require a separate plan
review and permit from the Poudre Fire Authority. Please call Plan Review Technician
Kerry Koppes at 9704164241 with Solar Array questions. Refer to 2018 lFC 1204 for
access, pathway, and marking details. I will address this in the future when solar panels are installed.
We are preparing the electrical and orienting the roof in our design for installation in the future.
Department: Environmental Planning
Contact: Stephanie Blochoyfiak, 9704164290, sbiocho"ak@Lcgov.com
1. City of Fort Collins Land Use Code [Section 3.2.1 (E)(3)], requires that to the extent
reasonably feasible, all plans be designed to incorporate water conservation materials
and techniques. This includes use of lowwateruse plants and grasses in landscaping
or relandscaping and reducing bluegrass lawns as much as possible. Native plants and
wildlifefriendly (ex: pollinators, butterflies, songbirds) landscaping and maintenance are
also encouraged. Please refer to the Fort Collins Native Plants document available
online and published by the City of Fort Collins Natural Areas Department for guidance
on native plants is: http://www.fcgov.com/naturalareas/pdf/nabveplants20l3.pdf. Also
see the City of Fort Collins Plant List' hftps://www.fcgov.com/forestL)L/plaDLE§Lpg I will incorporate
water conservation materials and techniques in the landscape design. I plan to use lower water use
plants and grasses within the design.
2. If trees may be impacted then a review of trees shall be conducted with Ralph Zentz,
Senior Urban Forester (9702216302 or rzentz@fcgov.com) to determine the status of
existing trees and any mitigation requirements that could result from the proposed
development. LUC Section 3.2.1 (C) requires developments to submit a landscape and
tree protection plan, and if receiving water service from the City, an irrigation plan, that:
"...(4) protects significant trees, natural systems, and habitat, and (5) enhances the
pedestrian environment. " Note that a significant tree is defined as one having DBH
(Diameter at Breast Height) of six inches or more. No trees will be impacted due to this project.
3. In regard to outdoor lighting, especially LED light fixtures, cooler color temperatures are
harsher at night and cause more disruption to circadian (biological) rhythms for both
humans and wildlife. Warmer color temperature (warm white, 3000K or less) for any
LED light fixtures is preferred. Please also consider fixtures with motionsensing or
dimming capabilities, so that light levels can be adjusted as needed. Site light sources
shall be fully shielded and downdirectional to minimize uplight, light spillage and glare
[see LUC 3.2.4(D)(3)]. Thank you in advance for supporting City of Fort Collins Night
Sky Objectives. For further information regarding health effects please see,
9
httg://darksky,qLq/amarer)ortaffirmshumanhealthimpart afr �mted/ I plan to follow these guidelines both
outside and inside the structure.
4,. Our city has an established identity as a forwardthinking community that cares about the
quality of life it offers its residents now and generations from now. Thus, the City of Fort
Collins has many sustainability programs and goals that may benefit this project. Of
particular interest may be:
1) ClimateWise Program: http-,I/fcgov.com/climatewise, contact
climatewise@fcgov.com or Kelsey Doan at KDoan@fcgov.com, 9704162410
2) Zero Waste Plan and the Waste Reduction and Recycling Assistance Program
(WRAP): http://fcgov.com/recycling/Wrap.php, contact Jonathon Nagel at 9704162701
orjnagel@fcgov.com
3) Utilities Building Energy Scoring:
hftps:l/www.fcgov.com/utilities/business/buildingenergyscoring , contact Kirk Longstein
at 9704164325 or klongstein@fcgov.com
4) Solar Rebate Program: www.fcgov.com/Solar, contact Rhonda Gatzke at
9704162312 or rgatzke@fcgov.com
5) Integrated Design Assistance Program: hftp-.//fcgov.comlidap, contact Gary
Schroeder at 9702246003 or gschroeder@fcgov.com
6) Nature in the City Program: hftp://fcgov.com/natureinthecity, contact Justin Scharton at
9702216213 or jscharton@fcgov.com
7) Bike Share Program: http-./Ifcgov.com/bikeshare, contact Stacy Sebeczek at Bike
Fort Collins at stacy@bikefortcollins.org or 9704815577
Department: Forestry
Contact: Molly Roche, 2246161992, mrocheCdfqg2v.corn
1/10/2019: BY FIRST ROUND PDP:
If there will be any impact to existing trees, please schedule an onsite meeting with City
Forestry to obtain tree inventory and mitigation information. Existing significant trees
should be retained to the extent reasonably feasible. I am not aware of any significant trees that
will be impacted due to the building of this structure.
Department: Technical Services
Contact: Jeff County, 9702216588, 1ggmnVAJg_qQ_v.om
1. As of January 1, 2015 all development plans are required to be on the NAVD88 vertical
datum. Please make your consultants aware of this, prior to any surveying and/or design
work. Please contact our office for up to date Benchmark Statement format and City
Vertical Control Network information.
2. If submitting a replat for this property/project, addresses are not acceptable in the
Subdivision Plat title/name. Numbers in numeral form may not begin the tifle/name.
Please contact our office with any questions,
10