Planning Department
June 4, 1990
Mr. Merle Hayworth
Robb, Brenner, and Brelig, Inc.
125 South Howes
Suite 880
Fort Collins, CO. 80521
Dear Merle:
This letter is to serve as a follow up to our phone conversation of Friday,
June 1st regarding the Utility Services Center P.U.D.
The primary remaining issues relate to drainage and lighting. Drainage issues
are being coordinated by Susan Hayes of the City's Stormwater Utility and
with the engineering consulting firm.
The lighting issues, however, should be resolved by your firm and the client.
The Planning and Zoning Board will look for two issues to be resolved:
1. The P.U.D. should, wherever possible, keep lighting to a security minimum.
This includes the interior parking lot areas and along the perimeter.
2. There should be some evidence that the concerns about the overall utility
yard lighting have been relayed to the appropriate parities at the utility
departments. Please be prepared to indicate whether a letter has been sent,
or if a meeting has occurred with the affected parties.
The schedule for the June 25, 1990 Planning and Zoning Board meeting is as
follows.
Two sets of the latest plans should be received by Thursday, June 7, 1990..
P.M.T.'s, 10 prints, and colored renderings (if any major changes) are due
Monday, June 18, 1990.
Final documents, mylars, are due Thursday, June 21, 1990.
Planning and Zoning Board worksession is Friday, June 22, 1990.
Planning and Zoning Board formal public hearing is Monday, June 25, 1990.
If you have any questions, please do not hesitate to call our office.
Sincerely:
Ted Shepard
Project Planncr