urban design, inc.
BURNS RANCH AT QUAIL RIDGE
Tentative Schedule
Revised May 10, 1990
Outlined below
is a tentative schedule and description of the
steps needed to
complete Preliminary P&Z review of the Cluster
Plan.
Date
Activity
April 27
Review Alternative Concept Plans
May 3
Meet with key City (Planning and Engineering)
Staff
May 22
Submit Annexation Petition to the City
May 29
Attend Conceptual Review Meeting
June 5
City Council Resolution on Annexation
June 13
Review in progress site and landscape plans,
prepare required building elevations, and review
other requirements of the RF Zone.
June 25
P&Z Public Hearing on Annexation and Zoning
June 27
Attend Parks and Recreation Board Meeting, if
necessary.
July 2
Submit Cluster Plan to the City.
July 17
First Reading of Annexation and Zoning Ordinance
by City Council.
July 20
Receive City Staff Comments on Cluster Plan.
August 8
Submit revised Cluster Plan to the City.
August 20
Submit Rendered Plans, Reductions, and any Final
Signed Documents to City.
August 27
Planning and Zoning Board Public Hearing for
preliminary Cluster Plan approval.
September 18
Second reading of Annexation and Zoning Ordinance
by City Council.