May 15, 2020
Brad Schlagbaum
Wells Fargo NA
9780 S MEddian Blvd
Englewood, CO 80112
RE: Wells Fargo Parking Lot & ATMs, MJA190003, Round Number 3
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Wells Fargo Parking Lot & ATMs. If you have questions
about any comments, you may contact the individual commenter or direct your questions
through your Development Review Coordinator, Tenae Beane via phone at 970-224-6119
or via email at tbeane@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Meaghan Overton, 970-416-2283, moverton a()fcgov.com
Comment Number: 19
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6689
970.224.6134 - fax
fcgov. com/developmentre view
Comment Originated: 03/02/2020
03102/2020: FOR FINAL PLAN: Please add the standard site plan notes. I can
provide these if needed. In particular, note that signage must be approved by
separate sign permit. The plan set cover or index sheet may also need to be
updated to meet City standards (for example, there is no signature block). I will
provide more details about required elements.
Acknowledged.
Comment Number: 22
Comment Originated: 05/12/2020
05/12/2020: READY FOR HEARING: Planning is ready for hearing. Thank you
for addressing comments from the last round of review.
Department: Engineering Development Review
Contact: Morgan Stroud, 970-416-4344, mstroud(a)fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 12/17/2019
05/08/2020: For Final Approval - Updated:
The legal descriptions provided meet our requirements. However, a current
surveyor with King Surveyors will need to prepare and stamp the legal exhibits
before it is recorded. The next step in this process is for the applicant team to
execute the deed template that was provided in the 2nd round redlines, this
template can also be found at this address:
https://www.fcgov.com/engineering/pdf/GeneralDeed.doc?l568214756 . After
this step is complete, we can calculate recording fees and get the document
recorded.
Updated legal exhibits signed by a current King Surveyors employee.
12/17/2019: For Final Approval:
Please continue to work with me and Technical Services to get the utility
easements dedicated.
Comment Number: 3
Comment Originated: 12/17/2019
12/17/2019: Development Construction Permit:
This project will require a Development Construction Permit "DCP" before
construction can begin. For the application, cost and quantity estimates, and
more information about this permit please follow this link:
hfti)s://www.fcqov.com/engineering/devrev.php
Acknowledged.
Comment Number: 4 Comment Originated: 12/17/2019
12/17/2019: Development Agreement:
This project will require a Development Agreement. Once all contributing
departments have their comments resolved, I will be able to put a draft together.
I have provided the "Information for Development Agreement' form in our
redlines. Please fill this out and return it back to me.
Acknowledged.
Comment Number: 5 Comment Originated: 05/13/2020
05/13/2020: For Final Approval:
If the 30 inch diameter Green Ash tree adjacent to the alleyway is going to be
removed with this project, please show a continuous curb and gutter along the
alleyway. Previously we allowed for a gap in the curb and gutter to allow for less
disturbance to the tree.
Acknowledged.
Department: Stormwater Engineering
Contact: Claudia Quezada, (970)416-2494, cc uezadaMcQov.com
Topic: Floodplain
Comment Number: 24
Comment Originated: 05/08/2020
05/08/2020: FOR FINAL PLAN:
Since both ATMs are shown out of the 100-year floodplain, can remove:
-Note #4 under "floodplain notes" (pg. 5 of site plan, "Proposed Plan")
-BFE and RFPE elevations (pg. 6 of site plan, "ATM Details").
Note removed.
Contact: Matt Simpson, (970)416-2754, masimpson &fcaov.com
Topic: General
Comment Number: 17 Comment Originated: 12/17/2019
05/11/2020: FOR FINAL PLAN:
r.
Thank you for providing this profile.
Please meet with us before Final Plan to discuss design of the 36-inch dry well.
Coffey Engineering met with CFC Stormwater meet on 6/19/2020 to discuss dry well design.
12/17/2019: FOR FINAL PLAN:
Please show a pipe profile through the dry well — include 1 pipe upstream and
downstream of the drywell. Provide confirmation that the pipe hydraulics
through this section will work. What flow rate and design frequency is this pipe
designed for?
Comment Number: 19
Comment Originated: 12/17/2019
05/11/2020: FOR INFORMATION:
Please contact us for an estimate of development fees and PIFs.
Acknowledged.
12/17/2019: FOR INFORMATION:
If this project does not require a building permit (I am unclear if ATM machines
will require a building permit), please note that stormwater PIF's (and water fees
for irrigation) will need to be paid prior to us signing mylars on this project. If
there is to be a building permit, then the fees will be paid at the time of building
permit
Acknowledged.
Comment Number: 21 Comment Originated: 03/09/2020
05/11/2020: STORMWATER IS READY FOR HEARING.
03/09/2020: STORMWATER IS READY FOR HEARING.
Department: Water -Wastewater Engineering
Contact: Matt Simpson, (970)416-2754, masimpson(&fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 12/18/2019
05/11/2020: FOR INFORMATION:
Please contact us for an estimate of development fees and PIFs
Acknowledged.
12118/2019: FOR INFORMATION:
If this project does not require a building permit (I am unclear if ATM machines
will require a building permit), please note that water fees for irrigation(and
stormwater fees) will need to be paid prior to us signing mylars on this project.
If there is to be a building permit, then the fees will be paid at the time of
building permit
Comment Number: 2 Comment Originated: 03/09/2020
03/09/2020: READY FOR HEARING.
Department: Light And Power
Contact: Austin Kreager, 970-224-6152, akreaaer(a)fc4ov.com
Topic: General
Comment Number: 13 Comment Originated: 05/12/2020
05/12/2020: FOR HEARING:
The new transformer location is still located within a public utility easement
along right of way. This is not preferable, but if this is the only location that will
work, we can consider it. Please make changes to your landscape plan to
3
reflect the transformer location. The transformer must have a 3 foot clearance
from any bushes that could interfere with the maintenance of the transformer.
Landscape Plans updated with transformer location.
Contact: Cody Snowdon, 970-416-2306, csnowdon(a).fc4ov.com
Topic: General
Comment Number: 2
03/10/2020:
12/16/2019 FOR HEARING:
Comment Originated: 12/16/2019
Please show the primary and secondary routing of the electric line on the Utility
Plans to show adequate separation from other utilities. The primary line feeding
the proposed transformer will come from the existing oval located west of the
existing alley.
Acknowledged.
Comment Number: 3 Comment Originated: 12/16/2019
03/10/2020:
12/16/2019 FOR HEARING:
The electric service to the site will need to be metered separately with an
address associated with that meter. Meter location will need to be coordinated
with Light and Power. Please show proposed meter location on the utility plan.
Reference Section 8 of our Electdc Service Standards for electric metering
standards. A link has been provided below.
https://www.fcgov.com/utilitiesAmg/site_specific/uploads/ElectricServiceStanda
rds_FI NAL_18November2016_Amendment.pdf
Acknowledged.
Comment Number: 5
Comment Originated: 12/16/2019
03/10/2020:
12/16/2019 FOR INFORMATION:
There is an existing 400W HPS floodlight on the North side of the property. If
this light is to be removed please contact Light & Power to have this structure
removed prior to any demolition.
Acknowledged.
Comment Number: 7 Comment Originated: 12/16/2019
03/10/2020:
12/16/2019 FOR INFORMATION:
Service to the building is considered a commercial service; therefore, the
service is required to be installed, owned and maintained by the property
owner.
Acknowledged.
Comment Number: 8 Comment Originated: 12/16/2019
03/10/2020: FOR FINAL:
Thank you for submitting a one -line diagram. Please submit a C-1 form that
matches the one -line diagram.
12/16/2019 FOR FINAL:
4
A commercial service information form (C-1 form) and a one -line diagram for all
commercial meters will need to be completed and submitted to Light & Power
Engineering for review prior to Final Plan. A link to the C-1 form is below:
http://zeus.fcgov.com/utils-procedures/files/EngWikiMikiPdfs/C/C-1 Form.pdf
Acknowledged.
Comment Number: 9 Comment Originated: 12/16/2019
12/16/2019 FOR INFORMATION:
Electric capacity fees, development fees, building site charges and any system
modification charges necessary to feed the site will apply to this development.
Please contact me or visit the following website for an estimate of charges and
fees related to this project:
http://www.fcgov.com/utilities/businesslbuilders-and-developers/plant-investmen
t-development-fees
Acknowledged.
Comment Number: 10 Comment Originated: 12/16/2019
12/16/2019 FOR INFORMATION:
Light & Power will require AutoCAD files of the Site Plan, Utility Plans, and
Landscape Plans prior to the Entitlement Process approval.
Acknowledged.
Comment Number: 11 Comment Originated: 12/16/2019
12/16/2019 FOR INFORMATION:
Please reference our policies, construction practices, development charge
processes, electric services standards, and fee estimator at :
http://www.fcaov.com/uti l ities/busi ness/bu i lders-and-developers.
Acknowledged
Department: Forestry
Contact: Molly Roche, 224-616-1992, mrochecDfcgov.com
Topic: General
Comment Number: 14
Comment Originated: 05/13/2020
5/13/2020: FOR FINAL APPROVAL
Due to the placement of the storm sewer main within the critical root zone of
tree #1, the overall health of the tree canopy, and considering the future
presence of EAB in Fort Collins, City Forestry recommends removing and
mitigating this tree. Mitigation in the form of placing mitigation trees on -site or
providing a payment in lieu are acceptable.
Acknowledged.
Comment Number: 15
Comment Originated: 05/13/2020
5/13/2020: FOR FINAL APPROVAL
Texas Red Oak and Shumard Oak are very similar species (nearly identical).
Forestry recommend replacing one of these species with another type of
canopy shade tree such as Choice City Elm, Chinkapin Oak, or Hackberry.
Acknowledged.
Comment Number: 16 Comment Originated: 05/13/2020
5/13/2020: FOR FINAL APPROVAL
Please place the Street Tree Permit Note on sheet LS 2.
Acknowledged.
Comment Number: 17
Comment Originated: 05/13/2020
5113/2020: FOR FINAL APPROVAL
Redlines are provided to the Development Review Coordinator. Please review
and update the following items on the site/landscape plan:
- Label mitigation trees on the plans, next to the tree symbols, and in the plant
list
- Show Tree #1 to be removed with a X over the symbol
- Update the tree inventory and mitigation table to show Tree #1 to be
removed.
- Update information below tree inventory and mitigation table:
o UPDATE INFORMATION IN THIS BOX:
o TREES TO BE REMOVED: 1
o TREES TO BE PRESERVED AND PROTECTED: 6
o MITIGATION REQUIRED: 3
Acknowledged.
Department: Environmental Planning
Contact: Stephanie Blochowiak, 970-416-4290, sblochowiak(a)fcgov.com
Topic: General
Comment Number: 1
12/17/2019: No comments.
Department: PFA
Comment Originated: 12/17/2019
Contact: Jim Lynxwiler, 970-416.2869, llynxwiler(a)poudre-fire.org
Topic: General
Comment Number: 1 Comment Originated: 12/16/2019
12/16/2019: Poudre Fire Authority has no comment.
Department: Technical Services
Contact: Jeff County, 970-221.6588, icunty(a)fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 12/13/2019
05/08/2020: INFORMATION ONLY:
Unless required during MJA, a complete review of all plans will be done at FDP.
03/09/2020: INFORMATION ONLY:
Unless required during MJA, a complete review of all plans will be done at FDP.
12/13/2019: INFORMATION ONLY:
Unless required during PDP, a complete review of all plans will be done at
FDP.