Loading...
HomeMy WebLinkAboutFIRE STATION NO 10 MINOR SUBDIVISION - 35 90 - SUBMITTAL DOCUMENTS - ROUND 1 - GEOTECHNICAL (SOILS) REPORTr •_ - The sump should be a minimum of eighteen (18) inches in diameter and three (3) feet deep. A minimum of one (1) foot of clean, graded gravel meeting the above specifications should be placed adjacent to the bottom and sides of the sump. The sump should be provided with a pump designed to discharge all flow to the sump. Water from the sump should be disposed of by suitable means well beyond the foundation of the building. Due to the swelling pressures exerted by the materials at subgrade at the upper level, it is our opinion that the only positive solution for construction of the slab at the upper level where movement will not occur is a structural floor with a void beneath it. However, the cost of this type of system may be prohibitive. It is our opinion that, with certain precautions and knowing that some risk is involved, a floating floor slab may be a reasonable alternative. If the owner is willing to assume the risk of future slab movement and related structural damage, the following recommendations may reduce slab movement and its adverse effects. Subgrade below slabs on grade at the upper level should be prepared in accordance with the recommendations discussed in the "Site Grading, Excavation and Utilities" section of this report. If the subgrade below slabs on grade at the upper level is allowed to dry below the required moisture, the subgrade should be rescarified and recompacted to two percent (2%) wet of optimum moisture to the required density just prior to placement of underslab gravel and concrete. Slabs on grade should be underlain by a minimum of four (4) inches of clean, graded gravel or crushed rock devoid of fines. Slabs surrounded by perimeter drains should be underlain by a minimum of eight (8) inches of clean, graded gravel or crushed rock devoid of fines. Garage slabs should be designed for the imposed loadings and be reinforced with wire mesh running .through the control joints. A floor drain system should be designed for the garage slab to prevent the accumulation of water from snow melt, wash water or other sources. The floor drain should empty into a storm sewer, a sump and pump or other suitable drain outlet: In addition, slabs on grade should be designed and constructed structurally independent of bearing members. -7- To minimize and control shrinkage cracks which may develop in slabs on grade, we suggest that control joints be placed every fifteen (15) to twenty (20) feet and that the total area contained within these joints be no greater than four hundred (400) square feet. In addition, if building construction is done during winter months, it is recommended that the slab on grade not be poured until the building has been enclosed and heat is available within the building area so that slab -on -grade concrete is not placed on frozen ground. This will also aid in proper curing of the slab concrete. We further recommend that nonbearing partitions placed on floor slabs at the upper level be provided with a slip joint (either top or bottom). Slip joints reduce pressure applied by heaving floor slabs and thus minimize damage to the portion of the structure above. It is emphasized that if the subsoils are kept dry, movement of slabs on grade should be minimal. However, if moisture is permitted to reach the subsoils below the slabs, heaving will probably occur. Parking and Driveway Areas The required total thickness for the pavement structure is dependent primarily upon the foundation soil or subgrade and upon traffic conditions. Based on the soil conditions encountered at the site and the type and volume of traffic assuming a fire truck having a maximum gross weight of 64,000 pounds and using a group index of 13 as the criterion for pavement design, the following minimum pavement thicknesses should be provided for the pavement structure: Passenger Car Parking Asphalt Concrete 21" Crushed Aggregate Base Course 8" Total Pavement Thickness 10" Asphalt Concrete 2" Plant Mix Bituminous•Base Course 3" Total Pavement Thickness 5" -8- Driveways and Truck Parking Areas Asphalt Concrete 4" Crushed Aggregate Base Course 8" Select Subbase 10" Total Pavement Thickness 22" Asphalt Concrete 2" Plant Mix Bituminous Base Course 8" Total Pavement Thickness 10" Subgrade below proposed paved areas should be prepared in accordance with the recommendations discussed in the "Site Grading, Excavation and Utilities'-' section. The surface of the subgrade should be hard, uniform, smooth, and true to grade. To prevent the growth of weeds, it is suggested that all subgrade under parking areas be treated with a soil sterilant. The select subbase should meet City of Fort Collins Class 1 specifications. The base course overlying the subgrade should consist of a hard, durable, crushed rock or stone and filler and should have a minimum "R" value of 80. The composite base course material should be free from vegetable matter and lumps or balls of clay and should meet the City of Fort Collins Class 5 or 6 Aggregate Base Course. The base course should be placed on the subgrade at or near optimum moisture and compacted to at least ninety-five percent (95%) of Standard Proctor Density ASTM D 698-78. (See Appendix C.) It is important , that the base course be shaped to grade so that proper drainage of the parking area is obtained. All asphalt concrete shall meet City of Fort Collins specifications and shall be placed in accordance with these specifications. A reasonable pavement alternate would be nonreinforced concrete pavement. Using a modulus of subgrade reaction of one hundred (100) pounds per square inch per inch, a design life of twenty (20) years, and concrete with a modulus of rupture of six hundred (600) pounds per square inch, the following minimum pavement thicknesses are recommended: -9- Passenger Car Parking Nonreinforced Concrete - 5" Driveways_ and Truck Parking Areas Nonreinforced Concrete - 7" Subgrade below the proposed pavement should be prepared in accordance with the recommendations discussed in the "Site Grading, Excavation and Utilities" section of this report. Concrete used in the pavement should meet ASTM specifications,, and aggregate should conform to ASTM C-33 specifications.. Concrete should be designed with a minimum modulus of rupture of six hundred (600) pounds per square inch in twenty-eight (28) days. It is suggested that a minimum cement content of six (6) sacks be used for this .mix, It" is, further recommended that laboratory mix designs be done to determine the proper proportions of aggregate, cement, and water to meet this requirement. It is essential that the concrete mix have a low water -cement ratio, an adequate cement factor, and sufficient quantities of entrained air. It is recommended that the subgrade be in a moist condition at the time the concrete is placed. The pavement surface should be free of depressions in which water may stand. Catch basins and manhole castings should be separated from the pavement with expansion joint material. The jointing plan should be prepared by the contractor and/or architect and approved by the geotechnical engineer prior to pavement. Longitudinal and transverse joint spacing should be at regular ten (10) to thirteen (13) foot intervals. Longitudinal and transverse contraction joints should have a depth approximately equivalent to one-fourth (1/4) the pavement thickness. The joints should be cut within twenty-four (24) hours of pouring. Expansion joints should be full -depth and should only be used to isolate fixed objects abutting or within the pavement area. Joint openings wider than one-fourth (1/4) inch should be cleaned and sealed before opening to traffic. A uniform, gritty final surface texture should be provided. Curing should be obtained with uniform coverage with white membrane curing 'compound or by seven-day coverage with white polyethylene or waterproof paper. The completed pavement should -10- be closed to automobile traffic for three (3) days and to truck traffic for seven (7) days. If paving is done during cold weather, cold weather procedures should be used. The concrete should be protected from freezing temperatures until it is at least ten (10) days old. GENERAL RECOMMENDATIONS 0 Laboratory test results indicate that water soluble sulfates in the soil are negligible, and a Type 1-11 cement may be used in concrete exposed to subsoils. Slabs on grade subjected to de-icing chemicals should be composed of a more durable concrete with low water -cement ratios and higher air contents. (2) Finished grade should be sloped away from the structure on all sides to give positive drainage. Ten percent (10%) for the first ten (10) feet away from the structure is the suggested slope. (3) Backfill placed around the interior and exterior perimeter of the structure should be mechanically compacted in. uniform lifts. Puddling should not be permitted as a method of compaction. Interior backfill and exterior backfill below paved areas should be compacted to a minimum of ninety-five percent (95%) of Standard Proctor Density ASTM D 698-M (See Appendix C. ) Exterior backfill below planted areas should be compacted to a minimum of ninety percent (90%) of Standard Proctor Density ASTM D 698-78. (4) Plumbing and utility trenches underlying slabs and paved areas should be backfilled with an approved material compacted to at least ninety-five percent (95%) of Standard Proctor Density ASTM D 698-78. Puddling should not be permitted as a method of compaction. (5) Gutters and downspouts should be designed to carry roof runoff water well beyond the backfill area. -11- (6) Underground sprinkling systems should be designed such that piping is placed a minimum of five (5) feet outside the backfill of the structure. Heads should be designed so that irrigation water is not sprayed onto the foundation walls. These recommendations should be taken into account in the landscape planning. (7) Plumbing under slabs should be eliminated wherever possible since plumbing failures are quite frequently the source of free water which may cause slab heave. (8) Footing and/or grade beams sizes should be proportioned to equalize the unit loads applied to the soil and thus minimize differential settlements. (9) It is recommended that compaction requirements specified herein be verified in the field with density tests performed under the direction of the geotechnical engineer. (10) It is recommended that a registered professional engineer design the substructure and that he take into account the findings and recommendations of this report. GENERAL COMMENTS This report has been prepared to aid in the evaluation of the property and to assist the architect and/or engineer in the design of this project. In the event that any changes. in the design of the structure or its location are planned, the conclusions and recommendations contained in this report will not be considered valid unless said changes are reviewed and conclusions of this report modified or approved in writing by Empire Laboratories, Inc., the geotechnical engineer of record. Every effort was made 'to provide comprehensive site coverage through careful Locations of the test borings, while keeping the site -12- investigation economically viable. Variations in soil and ground water conditions between test borings may be encountered during construction. In order to permit correlation between the reported subsurface conditions and the actual conditions encountered during construction and to aid in carrying out the plans and specifications as originally contemplated, it is recommended that Empire Laboratories, Inc. be retained to perform continuous construction review during the excavation and foundation phases of the work. Empire Laboratories, Inc. assumes no responsibility for compliance with the recommendations included in this report unless they have been retained to perform adequate on -site construction review during the course of construction. -13 a ti TEST BORING LOCATION PLAN -f HOEMUNI✓ 94A17 MLr PA.RIC.I" 140-1 PKwbw-v I' 3d A-2 EMPIRE LABORATORIES, INC. i f:. 1., KEY TO BORING LOGS TOPSOIL �•, • . GRAVEL ® FILL •�`; SAND & GRAVEL SILT ft �* SILTY SAND & GRAVEL CLAYEY SILT oop 0 COBBLES SANDY SILT I' Lai � SAND, GRAVEL &COBBLES ® CLAY ® WEATHERED BEDROCK / SILTY CLAY PH SILTSTONE BEDROCK SANDY CLAY CLAYSTONE BEDROCK SAND r 1 SANDSTONE BEDROCK /.'. SILTY SAND ® LIMESTONE CLAYEY SAND jiid. � GRANITE SANDY SILTY CLAY ❑ ' SHELBY TUBE SAMPLE STANDARD PENETRATION DRIVE SAMPLER CJ WATER TABLE 24 hrs. AFTER DRILLING C HOLE CAVED T 5/12 Indicates that 5 blows of a 140 pound hammer falling 30 inches was required to penetrate 12 inches. A-3 nna ti loo 95 90 85 LOG OF MIMNGS T.B.11.__= Ntl__bonnet, bolt at fire. hydrant; Elevation: 100.0' A-4 EMPIRE LABORATORIES, INC: 100 P2 90 85 LOG Of BORINGS No, 4 N.-S AA rim ram EWA !Flo P� IW"A via 80 - - EMPIRE LAIOMTOIRIES, INC. No Text .49 .49 .48 .48 G .47 Q .47 .46 .46 .45 45 SWELL - CONSOLIDATION TEST PRO. 8338 DEPTH: 3.0 IMMI MOISTURE: 15.8 =Nor moo �C�III�C�C�K� 0.25 0.5 1.0 5 10 APPLIED PRESSURE - TSF 0.1 0.25 0.5 1.0 5 10 APPLIED PRESSURE - TSF _ EHPIRE LABORATORIES INC. B-2 CONSOLIDATION TEST PRO. 8338 Mmmllllllm BORING NO.: 4 DEPTH: 7.0 mmollillim--- DRY DENSITY: 95.5 PCF MOISTURE: 22o6k. - - MERIMMIllimmoollill MEM111111hommmillill mmollillimmoollill, moollillimmmillill • 0.1 4.0 J 3 2.0 UI 0.25 0.5 1.0 5 10 APPLIED PRESSURE TSF C! J0.1 0.25 0.5 1.0 5 10 APPLIED PRESSURE - TSF EMPIRE LABORRTORIES INC. B-3 Ah o� w N CIJMW N cm N N N N N N N Ol In cm O M co 1" lD f� to In 0.02 x� x cc soO _x nN� L U ar 'o$ «K � -0 t a O r QE�t N7 J :3 J H W x D y W F- LL O o 2� 0 > O - Q �: 3 N N to �= M a Ln 00 O . . �LL Cl C CDO� M to N V' n t g In 1� In Ln CT . M 0.--4 � .--� 1p N Cl Ln N 00 M kO LA t., usL p c N In 00 . p — O O. O 00 N In Ln tO 'cY N .--1 1p O 1� N O O! N Ol lO G In .41 1� In M to �r M 00 O1 00 n M 1" to N N «-1 •--4 •--4 4 N V- '4 4 .- 4 N .- 4 r-I 4 N N .--4 O O O LO 0 0 0 O. In O O O O O O O a 4 In QO 01 L-n .--1 M 4 00 On Lr;O � M st 00 O1 .--4 p 1 LC) 1 O 1 O 1 O . 1 O 1 O 1 Ln 1 O 1 O 1 O 1 O 1 Co 1 O 1 O 1 O 1 Co 1 O O . M . sr 1� N . O N CM 00 4 N M 9 N 4 c rp Z .� N M m qS C. O C N N N N N N N N lqw N OO to cm r\ d d to to d ey Qx o c QO M .y Sx V J U IL ■ C S N e Ch u • 6 � Sv ► M =Ex J M y W ir n i y _ i W i U. s O a «.. ��x cc i CQ G }} S co N yam- «1 b� e r O In n pe L► tp d r=� O ° d O1 CDO� 14 L 117 4 1� O Ln d O M 11') .N4 4 N .� .-i N cmM «4 N cm N CM In O • O . O . O . In Cl • O • O Cl • O O O ri 4 d to CO M .-4 N In .4 N to .--4 1 1 In 1 O 1 O I O 1 O 1 O 1 O 1 O t O 1 O 1 O O O M Z In t0 B-5 No Text APPENDIX C. Suggested Minimum Specifications for Placement of Compacted Earth Fill and/or Backfilis GENERAL The geotechnical engineer shall be the owner's, architect's, engineer's or contractor's representative to observe placement of compacted fill and/or backfill on the project. The geotechnical engineer or his representative shall approve all earth materials prior to their use, the method of placement and the degree of compaction. MATERIALS Soils used for all compacted fill and backfill shall be approved by the geotechnical engineer or his representative prior to their use. Fill material shall be free from organic matter, frozen material and other unsuitable substance and shall not contain rocks or lumps having a diameter greater than six (6) inches. SUBGRADE PREPARATION All topsoil, vegetation, trees, brush, timber, debris, rubbish and all other unsuitable material shall be removed to a depth satisfactory to the geotechnical engineer or his representative. The material shall be disposed of by suitable means prior to beginning preparation of the subgrade. The subgrade shall be scarified a minimum depth of six (6) inches, moisture conditioned as necessary and. compacted in a suitable manner prior to placement of fill material. Fill shall not be placed until approval by the geotechnical engineer or , his representative; and in no case, shall fill material be placed on frozen or unstable ground. Subgrade which is not stable may require the use of imported granular material, geotex.tiles or other methods for stabilization as approved by the geotechnical engineer. FILL PLACEMENT Fill material shall not be placed during unfavorable weather conditions. Material proposed for use as fill shall be approved by the geotechnical engineer or his representative prior to use. Proposed import material shall be approved, by the geotechnical engineer or his representative prior to hauling to the project site. Fill material shall be C-2 uniformly mixed such as to preclude the formation of lenses of material differing from the surrounding material. All clods shall be broken into small pieces. The contractor shall construct the fill in approximately horizontal lifts extending the entire length of the fill. The thickness of the layers before compaction shall not be greater than eight (8) inches. Fill being placed on slopes or hillsides shall be benched into the existing slope. A minimum two (2) foot horizontal bench shall be cut into the existing excavated slope for each four (4) feet vertical of fill, or each lift should be benched slightly into the existing grade. MOISTURE CONTROL Prior to and during compaction operations, the .fill material being placed shall be maintained within the range of optimum moisture specified. A general recommendation is to maintain the fill material within two percent (2%) plus or minus of optimum moisture so _that proper compaction to the specified .density may be obtained with a minimal effort. In building pad and paved areas, material exhibiting swelling potential shall be maintained between optimum moisture and two percent (2%) wet of optimum moisture content. The moisture content of the fill material shall be maintained uniform throughout the fill. The contractor may be. required to add necessary moisture to the fill material and to uniformly mix the water with the fill material if, in the opinion of the geotechnical engineer, it is not possible to obtain uniform moisture content by adding water on. the fill surface. If, in the opinion of the geotechnical engineer, the material proposed for use in the compacted fill is too wet to permit adequate compaction, it shall . be dried in an acceptable manner prior to placement and compaction. Uniform mixing may require discing, blading or other methods approved by the geotechnical engineer or his representative. Adjustments of moisture content shall be made on the basis of determinations of moisture content by field. tests as construction progresses. COMPACTION The contractor shall furnish and operate the necessary types and kinds of equipment to perform the operations required to obtain the specified compaction. This equipment may include approved tamping rollers, rubber tired rollers, smooth wheeled rollers and vibratory rollers. If a sheepsfoot roller is used, it shall be provided with cleaner bars so attached as to prevent the accumulation of material between the tamper feet. Fill areas which are not accessible to full-sized construction equipment shall be placed in maximum four (4) inch lifts and compacted with power tampers to the specified density. C-3 Empire Laboratories, Inc. GEOTECHNICAL ENGINEERING 5 MATERIALS TESTING February 9, 1990 Architectural Resource Group 205 South Meldrum Fort Collins, Colorado 80521 Attention: Mr. Larry Trampe Gentlemen: CORPORATEOFFICE P.O. Box 503 a 361 Na Howes Fort Collins, Colorado 80522 (303)484-0359 FAX No. (303) 484-0454 We are pleased to submit our Report of a Geotechnical Investigation prepared for the proposed Fire Station No. 10 to be located in south Fort Collins, Colorado.. Based upon our findings in the subsurface, it is our opinion the site is suitable for the proposed construction, providing the design criteria and recommendations set forth in this report are met. The accompanying report presents our findings in the subsurface and our recommendations based upon these findings. Very truly yours, EMPIRE LABORATORIES, INC. Ron L. Lindburg Staff Engineer Reviewed by: Aa Chester C. Smith, P.E. President cic a ER C. �rF OF nr:1i4:111a scold OMces - P.O. Box 16859 P.O. Box 1135 P.O. Box 1744 P.O. Box 5659 Colorado Springs, CO 80935 Longmont CO 80502 Greeley, CO 80632 Cheyenne, WY 82003 (719) 597-2116 (303) 776.3921 (303) 351-0460 (307) 632-9224 Member of Consulting Engineers Council Compaction should meet the minimum percentages of maximum density as set forth in the project specifications or the recommendations of the report. The contract specifications supercede the recommendations given in this report. MOISTURE DENSITY RELATIONSHIP DETERMINATION Samples of representative fill materials to be placed shall be furnished by the contractor to the geotechnical engineer for determination of maximum density and optimum moisture or relative density. Sufficient laboratory moisture density or relative density curves will be made to determine the optimum moisture content and maximum density for the various soils placed as fill. Tests for this determination will be made using the appropriate method conforming to the requirements of ASTM D 698 (Standard Proctor), ASTM D 1557 (Modified Proctor) or ASTM D 4253, D 4254 (Relative Density). The materials used for _fill shall be classified In accordance with ASTM D 2487 in order to permit correlation between the moisture density relationship data and the material being placed and compacted. Copies of the results of these tests will be furnished to the client and others as directed by the client. These test results shall be the basis of control for all compaction effort. FIELD DENSITY AND MOISTURE TESTS The In -place density and moisture content, of compacted fill will be determined by the geotechnical engineer or his representative in accordance with ASTM D 1.556 (sand cone method) or ASTM D 2922, D 3011 (nuclear methods). Material not meeting the required compaction and/or moisture specifications shall be recompacted and/or moisture conditioned until the required percent compaction and/or moisture content Is obtained. Sufficient compaction tests shall be made and submitted to support the geotechnical engineer's or his representative's recommendations. The results of density tests will -also be furnished to the client and others as directed. C-4 REPORT OF A GEOTECHNICAL INVESTIGATION SCOPE This report presents the results of a geotechnical evaluation prepared for the proposed Fire Station No. 10 to be located at the intersection of Vermont Drive and Timberline Road in south Fort Collins, Colorado. The investigation included test borings and laboratory testing of samples obtained from these borings. The objectives of this study were to (1) evaluate the subsurface conditions at the site relative to the proposed construction, (2) make recommendations regarding the design of the substructure, (3) recommend certain precautions which should be taken because of adverse soil and/or ground water conditions, and (4) make recommendations regarding pavement types and thicknesses for the proposed driveways and parking areas to be constructed at the site. SITE. EXPLORATION The field exploration, carried out on January 31, 1990, consisted of drilling, logging, and sampling six (6) test borings. The test borings were located by Empire Laboratories, Inc. from existing curb lines using conventional chaining methods. The locations of the test borings are shown on the Test Boring Location Plan included in Appendix A of this report. Boring logs prepared from the field logs are shown in Appendix A. These logs show soils encountered, location of sampling, and ground water at the time of the exploration. The borings were advanced with a four -inch diameter, continuous - type, power -flight auger drill. During the drilling operations, a geotechnical engineer from Empire Laboratories, Inc. was present and made continuous observations of the soils encountered. -1- SITE LOCATION AND DESCRIPTION The proposed site is located at the southwest corner of the intersection of Vermont Drive and Timberline Road in south Fort. Collins, Colorado. More particularly, the site is described as a tract of land situate situate in the East 1 /2 of Section 30, Township 7 North, Range 68 West of the Sixth P.M., Larimer County, Colorado.. The site consists of a relatively flat tract of land vegetated with dense, low grass and weeds. The site exhibits generally poor surface drainage characteristics. The property is bordered to the north by Vermont Drive, to the east by Timberline Road and to the south by vacant land. An entrance road to the Timberline Tech Center borders the property to west. LABORATORY TESTS AND EVALUATION Samples obtained from the test borings were subjected to testing in the laboratory to provide a sound basis for evaluating the physical properties of the soils encountered.: Moisture contents, dry unit weights, unconfined compressive strengths, water soluble sulfates, swelling potentials, and the Atterberg limits were determined. A summary of the test results is included in Appendix Be Swell -consolidation characteristics were also determined, and curves showing this data are included in Appendix B. SOIL AND GROUND WATER CONDITIONS The soil profile at the site consists of strata of materials arranged in different combinations. In order of increasing depths, they are as follows: (1) Silty Topsoil: A six (6) inch layer of silty topsoil was encountered at the surface of the borings drilled at the site. The topsoil has been penetrated by root growth and organic -2- matter and should not be used as a bearing soil nor as a fill and/or backfill material. (2) Silty Clay: A layer of brown silty clay was encountered below the topsoil and extends to the sandy silty clay below. The silty clay is plastic and exhibits moderate bearing characteristics. The damp upper portion of the clay stratum exhibits moderate to high swell potential; while the moist portions of the stratum exhibit slight swell potential. Upon loading of the clay stratum, consolidation occurs. (3) Sandy Silty Clay; This stratum was encountered at a depth of seven (7) to eight and one-half (8-1/2) feet below the surface and extends to the silty sand and gravel below or to the depths explored. The sandy silty clay is plastic and exhibits low to moderate bearing characteristics in its moist in situ condition. When wetted, the clay stratum exhibits slight swell potential. (4) Silty Sand and Gravel: The silty sand and gravel stratum was encountered at a depth of twelve (12) to fourteen (14) feet in Borings 3 and 4. The sand and gravel is poorly graded and has generally moderate bearing characteristics. (5) Ground Water: Free ground water was encountered at depth of twelve and one-half (12=1 /2). to thirteen and one-half (13-1 /2) feet below the surface in Borings 1, 2, 3 and 4 twenty-four hours after drilling the site. Ground water levels in this area are subject to change due to seasonal variations and irrigation demands on and/or adjacent to the site. RECOMMENDATIONS AND DISCUSSION It is our understanding that a single -story, masonry structure with slab -on -grade and full basement construction is proposed for the site. -3- Site Grading, Excavation and Utilities Specifications pertaining to site grading are included below and in Appendix C of this report. It is recommended that the upper six (6) inches of topsoil below building, filled and paved areas be stripped and stockpiled for reuse in planted areas. The upper six (6) inches of subgrade below should be scarified and recompacted two percent (2%) wet of optimum moisture to at least ninety-five percent (95%) of Standard Proctor Density ASTM D 698-78. (See Appendix C.) Additional fill should consist of the on -.site soils or imported material, approved by the geotechnical engineer. Fill should be placed in uniform six (6) to eight (8) inch lifts and mechanically compacted between optimum moisture to two percent (2%) wet of optimum moisture to at least ninety-five percent (95%) of Standard Proctor Density ASTM D 698-78. All excavations should be dug on safe and stable slopes. It is suggested that excavated slopes be on minimum grades of 1-1/2:1 or flatter. The slope of the sides of the excavations should comply with local codes or OSHA regulations. Where this is not practical, sheeting, shoring and/or bracing of the excavation will be required. The sheeting, shoring and bracing of the excavation should be done to prevent sliding or caving of the excavation walls and to protect construction workers and adjacent structures. The side slopes of the excavation or sheeting, shoring or bracing should be maintained under safe conditions until completion of backfilling. In addition, heavy construction equipment should be kept a safe distance from the edge of the excavation. Backfill placed in utility trenches in open and planted areas should be compacted in uniform Lifts at optimum moisture to at least ninety percent (90%) of Standard Proctor Density ASTM D 698-78 the full depth of the trench. The upper four (4) feet of Backfill placed in utility trenches under building and paved areas should be compacted at or near optimum moisture to at least ninety-five percent (95%) of Standard Proctor Density ASTM D 698-78, and the lower portion of these trenches should be compacted to at least ninety percent (90%) of -4- Standard Proctor Density ASTM D 698-78. Addition of moisture to and/or drying of the subsoils may be needed for proper compaction. Stripping, grubbing, subgrade preparation, and fill and backfill placement should be accomplished under continuous observation of the. geotechnical engineer. Field density tests should be taken daily in the compacted subgrade, fill, and backfill under the direction of the. geotechnical engineer. Fnt In`iat inn In view of the loads transmitted by the proposed construction and the soil conditions encountered at the site, it is recommended that the structure be supported by conventional -type spread footings and/or grade beams. All footings and/or grade beams should be founded on the original, undisturbed soil. All exterior footings should be placed a minimum of thirty (30) inches below finished grade for frost protection.. The identification and undisturbed nature of the soil should be verified by the geotechnical engineer prior to placement of any foundation concrete. Footings and/or grade beams founded at the upper levels may be designed for a maximum allowable bearing capacity of three thousand (3000) pounds per square foot (dead load plus maximum Five load). To counteract swelling pressures which will develop if the subsoils become Wetted, all footings and/or grade beams at the upper level should be designed for a minimum dead load of one thousand (1000) pounds per square foot. Footings and/or grade beams founded at the basement level may be designed for a maximum allowable bearing capacity of one thousand two hundred fifty (1.250) pounds per square foot (dead load plus maximum live load). The predicted settlement under the above maximum loadings, as determined by laboratory consolidation tests, should be less than three -fourths (3/4) inch, generally considered to be within acceptable tolerances. -5- Basement, Dewatering System_ and Slabs on Grade In view of the depth to ground water and/or bedrock encountered at the site, it is our opinion the proposed basement construction is feasible, provided the finished basement slab is placed a minimum of three (3) feet above existing ground water or at elevation 88.5 or above. If the finished basement slab is placed within three (3) feet of existing ground water or below elevation 88.5; then it is recommended that a complete dewatering system is designed and constructed for the structure. The dewatering system should contain a four (4) inch diameter perforated pipe, underslab gravel, a sump and pump, or other suitable drain outlet. The perforated pipe should be placed around the entire perimeter of the lower basement area. All piping in the perimeter trench should be surrounded by clean, graded gravel from three -fourths (3/4) inch to the #4 sieve in accordance with ASTM C 33-78, Size No. 67. The gravel should extend from at least three (3) inches below the bottom of the pipe to a minimum of two (2) feet above the pipe, the full width of the trench. To minimize the cost of gravel backfill, it is suggested that the excavation be limited to the area necessary for construction; however, the trench should be a minimum of twelve (12) inches wide. The top of the gravel backfill adjacent to foundation walls sho.uld be covered with an untreated building paper to help minimize clogging of the medium with earth backfill. To minimize the potential for surface water to enter the system, it is recommended that a clay backfill be placed over the system and compacted at or near optimum moisture to at least ninety percent (90%) of Standard Proctor Density ASTM D 698-78. (See Appendix C.) We recommend that the drainage pipe be placed at least one (1 ) foot below the finished slab and have a minimum grade of one -eighth (1/8) inch per foot. All lower level slabs surrounded by perimeter drains should be underlain by a minimum of eight (8) inches of clean, graded gravel or crushed rock devoid of fines. The drainage system should empty into a sewer unde.rdrain should one adequately sized to accept the anticipated flows exist at the site, or the water from the drain should empty into a sump provided in the lower basement area. -6-