September 18, 1992
Jim Gefroh
Gefroh-Hattman Architects
145 West Swallow Road
Fort Collins, CO. 80526
Dear Jim,
The staff met in an Interdepartmental Meeting this morning and
discussed your revised concept drawing for overland Hills West, RF
Site Plan Review. I would like to offer the following comments that
were expressed at this meeting:
1. I need to reiterate a comment from my letter to you addressed
August 20, 1992 in response to our staff Interdepartmental
Meeting of August 17th. Comment #28 read that "This request is
not ready to go to the Planning and Zoning Board on September
28th due to the lack of information on utilities, storm
drainacre and traffic impacts". These items were not addressed
as part of the original submittal on August 3rd (see comments
#6 & #9, Aug. 20th letter). They still have not been addressed
and we are 2 weeks into the review period for the October 19th
Board hearing. The idea of waiting until the September 30th
plan revision date is just not acceptable, since the original
submittal did not meet the City's requirements. If sufficient
information is provided by September 28th, then this item can
be considered for the November 16th Planning and Zoning Board
hearing.
2._---- A_ follow—up neighborhood -_meeting_ (to_ the_one-held-July 22nd-)
is required and should be scheduled to occur as soon as
possible. An expanded APO Notification list is necessary to
include the people that were present and involved in the first
meeting, most of them being in the Springfield Subdivision. A
map of the new notification area is available at Planning's
Development Review Center counter. Staff feels that it is
important for Kim Stuart to be present at this meeting, if at
all possible, to express his intentions for this property and
become more than a no -face out of town developer.
3. The submittal we have presently before us, though not a
complete submittal as defined in Section 29-116 of the City
Code, is being considered as a Preliminary Site Plan Review
only at this time. Request for consideration of a Final Plan
will have to be submitted and presented to the Board at a
later date.
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6750
4. The original Overland Hills West Site Plan submittal did not
identify what is to happen at the east end of the development,
between Overland Trail and the approved Overland Hills 1st &
• 2nd Filings and Barnes property. City Parks & Recreation
Department is interested in a bicycle/pedestrian trail
easement along the west side of Spring Creek, with some or all
of it conceivably on Overland Hills West.
5. There is still a question about the potential "single point of
access" to this development (homes outside of a 660 foot
distance) since Overland Trail is not planned to continue
north or south of this property with this request. No
secondary point of access is proposed. Have you discussed this
situation with Warren Jones of the Poudre Fire Authority yet?
Warren can be reached at 221-6570.. Presently, if this
development were to be approved, the single point of access
would occur at the intersection of West Horsetooth Road and
Platte Drive. Providing individual residential in-house
sprinkler systems is one solution to this concern (please
refer to comment #7 of the August 20th letter).
6. The open space must be identified on this plan and the status
defined in terms of ownership and maintenance. Please see
Section 29-116 (2)(9) of City Code, attached.
7. The City Stormwater Utility has concerns about this plan and
still 'has not received information sufficient to evaluate
drainage requirements. There may be floodplain mapping
requirements associated with Spring Creek for this request.
Please contact Kathy Malers at 221-6589 with your storm
drainage questions.
8. There was a statement related to farm animals on the original
plan submittal in August. You should be aware of Sections 29-
115 and 29-116 (10) of City Code indicating the need to
address this issue with an RF Site Plan Review. A copy of the
section is attached.
9. The lots on the upper tier of the cluster development plan
must be designed to be sympathetic to the area and comply with
Section 29-116 (4)(6) of City Code, attached.
10. Is consideration being given to local street connections from
this development to potential future development to the north
and south?
This completes staff review comments at this time. Additional
comments may be forthcoming as the various departments and
reviewing agencies continue to review this request. It is important
to have a complete set of documents to the City by September 28,
1992 to enable you to be on line for the November 16, 1992 Planning
and Zoning Board hearing. ,
Please contact me at 221-6750 if you have questions or concerns
related to these comments. I would like to schedule a meeting with
you as soon as possible, if necessary, to discuss these comments.
Ae�
y,
Project Planner
xc: Kerrie Ashbeck
Sherry Albertson -Clark
Advance Planning
Stormwater Utility
Transportation
Natural Resources
Parks & Recreation
Kim Stuart
Stewart and Associates
file/Project Planner