August 14, 1990
Gary Udall
Udall Architects
425 S. Cherry St., Suite 130
Denver, CO 80522
Dear Gary:
For your information, attached is a copy of the Staff's comments concerning
the Zeta Tau Alpha Sorority, which was presented before the Conceptual
Review Team on August 6, 1990.
The comments are offered informally by Staff to assist you in preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincerely.
.. C,f."
Kirsten Whetstone
Project Planner
KW/gjt
Attachment
xc: Tom Peterson, Director of Planning
Kerrie Ashbeck, Civil Engineer I
Project Planner
File
281 N. College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6750
CONCEPTUAL REVIEW STAFF COMMENTS
MEETING DATE: August 6, 1990
PROJECT: Zeta Tau Alpha Sorority
APPLICANT: Gary Udall, Udall Architects, 425 S. Cherry St., Suite 130,
Denver, CO 80522. 1-321-0111.
LAND USE DATA: A proposal to create a legal subdivided lot from a 30,000
square foot parcel, to construct a 10,000 sq. ft. sorority house for 50 sorority
sisters. The lot is located on the SE corner of Bluebell Ave and Baystone
Drive.
COMMENTS:
1. An overhead powerline
crosses the site and will have
to
be relocated before
development can occur. Relocation will be done
by
Light and Power.
There is single phase
power available at the site.
If
three phase power
will be required, it is
available at Birch and Shields
St.,
the developer pays
to get it to the site.
Otherwise, normal development
charges
apply.
2. Light and Power is requesting an 8' utility easement along Baystone,
Wagner, and Bluebell right of ways. These easements need to be shown on
the plat.
3. It will be important to coordinate timing of the installation of underground
utilities with removal of the overhead lines. It is possible that there will
c9Ve4c.6.t L, be utilities, other than electric, on the overhead poles which will also
have to be relocated. A utility coordination meeting would be advisable as
the project progresses.
4. There is existing water and sewer in Bluebell Ave which can be tapped
into. A grease trap located somewhere outside of the building will be
required for the commercial kitchen facilities. Mark Taylor at 221-6681
can assist you in sizing the trap.
5. Poudre Fire Authority will require the building to have an automatic
sprinkler system or fire separation walls. If the building will be three
stories, an automatic sprinkler system will be required, regardless. Please
contact Roger Frasco at 221-6570 for further information on fire code
requirements.
6. Sidewalks will have to be constructed on Baystone and Bluebell. The curb
cut on Wagner may have to be moved further north. Utility easements
along the right of ways and also along the southern property line, will
need to be dedicated on the plat.
7. Street oversizing fees of $5,252.00 per acre will be assessed.
Parking stalls can be 17' long when perpendicular to a curb, this will allow
for 24' aisles. Please check with the Parking lot standards for specific
information about parking and landscaping requirements. In particular the
plan should address screening of the parking lot from the neighboring
residential areas and from the adjacent right of ways. There is also a
requirement for 6% interior landscaping for a parking lot.
9. A storm drainage report will be required. On site detention would likely
be needed. The site is in the Canal Importation Basin. Please contact
Glen Schlueter at 221-6589 for further information on fees and
requirements. ftiby -Jb VAM1 (1�1 i VV'A-i->
10. The transportation department has two concerns, the first is access to the
site, and the second is that all parking needs be satisfied with on site
parking. The one way access at the south side is fine, but enforcement is
up to the owners. This access could also be two way if the site is
redesigned to accommodate it. On site parking must meet the needs of the
sorority. The City does not have specific requirements for parking. The
Transportation Director recommends that the applicant look at existing
sororities on this campus or other ZTA sororities on other campuses to
determine what the parking needs will be. Written documentation
explaining the parking situation will be required at the time of submittal.
11. Zoning on the site is R-H, high density residential. Sorority houses are a
use by right in this zone. The project will have to meet the zoning
requirements for the R-H zone, including parking and setback requirements.
An approved landscape plan will be required at submittal.
7 _tea
12. Building construction will have to be type 5 one hour for fire safety. It is
possible that fire sprinklers would alter the requirements somewhat. Please
refer to the amendments to the code, chapters 12 and 13 for further
explanation or contact the Building Inspection Department at 221-6760.
13. This site is in a fairly high crime area for Fort Collins. Anything that is
not tied down or made permanent, will disappear. This holds true during
construction as well as after completion. Exterior and grounds security
lighting would be highly recommended. Indoor bike storage/ security areas
would be a real asset. Security of the entrance and exits to the house
should be a real concern. Light and Power does provide a program for
outdoor security lighting. For more information about this contact Doug
Martine at Light and Power at 221-6700. Ken Kirchhoff with the Fort
Collins Police at 221-6833, will be able to assist you with further
information on crime prevention and security.
14. The next step in the review process is to submit the project as a Minor
Plat. Please see the attached information on this process.