HomeMy WebLinkAboutMOURNING SUBDIVISION 2ND REPLAT LOTS 1 AND 2 - 13 91A - CORRESPONDENCE - MEETING COMMUNICATIONJanuary 31, 1992
Project No: 1270-01-91
Mr. Steve Olt; Project Planner
City of Fort Collins Planning Department
281 North College Avenue
P.O. Box 580
Ft. Collins, Colorado 80522-0580
Re: Chili's Grill and Bar; Lot 2, Second Replat of Mourning Subdivision
Ft. Collins, Colorado
Dear Steve,
We have submitted revised Chili's Utility Plans to Kerrie Ashbeck for
distribution and review. The revised Utility Plans have been revised based
on input from several sources and decisions made at several meetings.
I have personally met with Dellenbach Chevrolet representatives on two (2)
occasions for their input on the project. My first occasion was on Monday,
January 7, 1992 to present the project to Dellenbach in concept. Present
at this meeting were:
Frank Vaught; Vaught -Frye Architects
Rick Ensdorf; City of Fort Collins Traffic Department
Brian Shear; Shear Engineering Corporation
Dick Dellenbach; Dellenbach Chevrolet
Mike,Dellenbach, Dellenbach Chevrolet
Steve Dellenbach; Dellenbach Chevrolet
Carole Arceneaux; Dellenbach Chevrolet
Buddy Forehand with Brinker International was unable to attend because of
weather conditions that day. However, this meeting followed a previous
meeting which Buddy Forehand (representing Chili's) had with Dellenbach
Chevrolet earlier. Dellenbach representatives had expressed concerns at
the earlier meeting with Mr. Forehand which were addressed for this
January 7 meeting. Of particular concern to Dellenbach representatives,
was the original proposal to delete. the Frontage Road _access in its
entirety. Subsequent discussions with Rick Ensdorf and Frank Vaught
resulted in the concept of maintaining a one way access (northbound)
through the Chili's site to Dellenbach Chevrolet. This concept was
acceptable to Rick Ensdorf and Dellenbach Chevrolet. This one way access
is represented in our Utility Plans.
In our January 7 meeting, Dellenbach representatives indicated further
.concerns, suggestions and requirements relative to the modified Chili's
proposal. Issues which were discussed included the following:
* Overall circulation
* One way northbound access in location of existing Frontage Road
* Southbound Right Turn lane,from.College Avenue
Based on our discussions and decisions made in the January 7 meeting, we
have revised the Chili's Utility Plans to reflect the input of everyone
involved.
4836 S. College, Suite 12 Fort Collins, CO 80525 (303)226-5334
PAGE 2
January 31, 1992
Project No: 1270-01-91
Re: Chili's Grill and Bar; Lot 2, Second Replat of Mourning Subdivision
I again met with the Dellenbach's on Wednesday, January 29, 1992 to
present our revised Utility Plans and to further discuss the common
east -west access drive and right turn lane from College. Dick and Mike
Dellenbach accompanied me in the field to visualize the design presented.
Decisions at this meeting require us to make one additional modification
to our plans. This would include moving the drive approach to Dellenbach's
Chevrolet site off of the east -west access drive west, to align with their
existing north -south travelway in front of (the east side) their building.
This revision was not made prior to resubmittal of the plans to the City.
Also discussed at this meeting was Dellenbach's preference to locate the
proposed right turn lane on College Avenue for a direct right turn onto
the east -west access drive. This location, though ideal in most respects,
presents a concern in my mind. The grade difference between the College
Avenue existing curb flowline and the inlet low point of the Chili's site
(currently the low point of the existing Frontage Road) is approximately
three feet (3'). I indicated to Dick and Mike Dellenbach that we would
further detail this area in cross section to see if the grade difference
would be workable.
On January 23, I received a copy of a letter from Vaught -Frye Architects
to Buddy Forehand dated January 17, 1992 indicating the revised project
schedule and City Staff requirements for project approval. I would discuss
each item individually at this time for update purposes only:
1. Utility Plans approved:
We have submitted detailed revised Utility Plans for routing and
further review. City and utility comments from our initial
submittal have been addressed.
2. Development agreement for improvements between Brinker International
and City agreed to in concept:
* No Response
3. Site/Landscape Plan approved by City Zoning Administrator:
* I have submitted a print of the Landscape Plan for the Chili's
site to you. If you have'nt seen it yet, ask Kerrie Ashbeck. We
submitted it when Utility Plans were submitted. The Landscape
Plan was prepared by Jim Sell Design. Should you require further
prints of the Landscape Plan, please request these from Jim Sell.
4. Planning and Zoning endorsement of the Plat:
* We had submitted 15 prints of the revised plat to you on January
8, 1992. There are currently only two (2) revisions to the plat
since we submitted it to you on the 8th;
* We have provided a 10'x10' utility easement in the vicinity
of the proposed water service. This was requested by the
Water and Sewer Department.
* We have represented a wider access easement on the
Dellenbach property. We did show 17' on the plat. We
currently show 25'.
* The latest revision to the plat is included in the Utility
Plans as submitted on January 30.
PAGE 3
January 31, 1992
Project No: 1270-01-91
Re: Chili's Grill and Bar; Lot 2, Second Replat of Mourning Subdivision
5. Dellenbach's approval and easement agreement:
I have asked the Dellenbach's to write you a letter indicating
their position to date on our Utility Plans and Plat as
presented. They understand that an easement would be required on
their site with the east -west access drive centered on the
property line since and half of the access drive located on their
property.
We have expended a tremendous amount of time, energy and cost to
appropriately address all of the issues and feel that there should not be
a reason why the plat can't go before the Planning Board on February 24,
1992. If there is anything you still need at this time, let me or Frank
Vaught know. There are still issues to resolve. I understand that. But not
related to plat endorsement by the Planning and Zoning Board.
If you have any questions or require additional information, please call
me. My number is (303) 226-533
Sincer
Shear Engineering Cor ion
Brian W. Shear, P.E.
BWS/so
cc: Buddy Forehand; Brinker International (Dallas)
Ken Hollifield; Vincent Architects (Dallas)
Dick Dellenbach; Dellenbach Chevrolet
Mike Dellenbach; Dellenbach Chevrolet
Russ Cates; Steele's Market, Inc.
Frank Vaught; Vaught -Frye Architects
Rick Ensdorf; City of Fort Collins Traffic Department
Kerrie Ashbeck; City of Fort Collins Planning Department
Jim Sell; Jim Sell Design