HomeMy WebLinkAboutTRAFFIC OPERATIONS FACILITY PDP - 30 91E - CORRESPONDENCE - RESPONSE TO STAFF REVIEW COMMENTSMarch 26, 2002
Ted Shepard
Project Planner
281 North College Ave.
Fort Collins, CO 80522
RE: Traffic Operations Facility
Dear Ted Shepard,
The responses below address the comments raised by city staff.
Engineering:
Utility Sheet C2
58. City of Ft. Collins is referenced & a variance citation is listed.
Utility Sheet C5
61. The wall is removed.
Utility Sheet C5-grading
82. Refer to the interim grading plan.
Utility Sheet C7
62. Althougl
the information is provided on the profile, more spots have been
inserted.
65. The single grade break at the south extent of road improvements to Linden
has been modified to be 0.4 percent or less. The "especially large" grade
break at the north extent of improvements represents the connection
between curb & gutter improvements and dirt associated with the Railroad
ROW which will not be improved with the Project. This has been
discussed with City Staff previously.
66. Curves have been smoothed to the greatest extent practical.
Utility Sheet C7-Linden plan and profile
83. A Site visit reveals no obstructions to site distances.
84. Although this information is available on the plan view, it is now made
available for reviewers on the profile.
85. Barricades have been modified.
M
Utility Sheet C8-Linden Cross -sections
86. This design was requested by City Staff in prior comments, and was
inserted. Now the item is removed with the new set of comments.
87. True cross slopes are added.
Police Department:
39. The Cherry and Pear trees have been removed from the parking island. They
have been replaced with a canopy shade tree that has a higher branching
structure.
-The west side of the building will be lit by the streetlights along Linden Street.
The northern most door will not be built until phase 2 is constructed. There is no
timeline for the construction at this time. Security lighting may be added upon
construction.
-The evergreen trees have been moved away from this door.
Stormwater Utility:
Drainage
96. This was a cross over reflecting on interim conditions for Erosion Control
measures. This is now adjusted to ultimate build out, and has been
coordinated directly with Stormwater.
97. The 2-foot pan installed as part of the CDOT site (adjacent east), and is
actually not in conformance with the original approved master drainage
plan done for the Site (in fact, the storm sewer system which receives the
Project's drainage is also not in conformance). As a result, and per
discussions with Stormwater, new capacity calculations are completed and
included with the report.
98. This was a clerical error and has been changed.
100. Flow depth information for the Private Drive has been supplied and
coordinated directly with Stormwater.
Erosion/Sediment Control
99. A cut has been made in the silt fence.
Wastewater:
Easement
92. "Easements" are on their way, and will be supplied as separate documents.
General
43. All items are called out.
46. "Easements" are on their way, and will be delivered as separate
documents.
48. This note was on the most recent submittal, and will remain.
49. Details checked and modified as needed.
50. Acknowledged.
General Notes
91. Acknowledged.
Landscape Plan
90. Utility information has been updated. See landscape plans.
Utility Details
94. This item is included on a separate sheet.
Utility Plan
93. Water service realigned.
95. Distance between pit and reducer cited.
Sincerely,
7
achel Linder
Project Manager