January 27, 1992
Robert K. Glover
2101 Lindenmeier Rd.
Fort Collins, CO 80524
Dear Robert,
City Staff has reviewed your re -submittal for the Blevins Court Lot
9 PUD and offers the following comments:
1. The City Water Utilities Department will install a 6-inch
water main in Blevins Ct. next spring (Spring of 1992). The
water service for lot 9 will be tapped to this main.
Coordinate with Mark Taylor at 221-6681 on the timing of your
water service. A building permit will not be granted until
this utility construction is completed.
2. A sanitary sewer main exists along the southern boundary of
this lot. A 15-foot utility easement must be provided north
of this existing sewer main, measured from the center line of
the main, 15 feet to the north. The sewer service for this
lot will be tapped to this sewer main. Please coordinate with
Kerrie Ashbeck at 221-6750 for information on how to record
that utility easement. Since the lot is already platted, you
would need to describe the easement and file a legal
description of it as a separate document. Please provide this
information to the Planning/Engineering Department and show
the easement on the site plan and utility plans.
3. A final planting list describing .the existing and proposed
species and sizes of -trees and shrubs should be shown -on -the
final site/landscape plan.
4. Off -site flows are a major concern with this project. This
type of in -fill project typically has potential to cut-off
flows that have been, routed to a vacant piece of land,
especially in older developments where City standards for
drainage control have not been met. The report is good for a
preliminary report but lacks the final detail needed for final
approval. Please see the redlined report and plans for
detailed comments and return them to Glen Schlueter with
revisions. If you have questions about the drainage report
please contact Glen at 221-6589.
5. An erosion control plan for construction should be submitted
with the final drainage plan.
281 North College Avenue • P.O. Box 580 Fort Collins, CO 80522-0580 • (303) 221-6750
w
6. Planning Staff has concerns about the amount of parking on the
site and feels that the amount of parking that seems to be
required, from the neighborhood perspective, is cramping the
site, setbacks, open landscaped areas, and landscaped buffers.
The parking situation seems to be a symptom of the density.
7. The grass-crete areas are a definite help in keeping the
amount of hard surface to a minimum, but Staff believes that
it would be difficult to enforce that area as overflow parking
given the proximity to the front doors. Maintenance would
likely be an on -going problem. Staff would recommend moving
the turfstone area to replace the three northern most parking
spaces on the east side of the property where they would be
less heavily used. Six spaces would more than meet the City
requirements for a duplex.
8. A motorcycle space is called out inthe notes but not on the
site plan. Staff would recommend that you provide a
motorcycle space so potential motorcycle owners don't take up
a regular size parking space. Perhaps north of the trash
enclosure would be a good location. City Code requires that
parking lots with 6 or more spaces provide motorcycle parking.
9. A handicapped space is also called out in the notes but not
shown on the site plan. By Code, handicapped spaces are not
required for parking lots with fewer than 15 spaces. If you
plan to design a space to meet.the dimensions of a H/C space
but don't plan to stripe it you would not have to indicate the
space as H/C. You could provide a note on the site plan
indicating that the space is sized as such.
10. Staff agrees that the fence needs to be broken up as you have
indicated, rather than having it a solid wall which would only
separate this use from the neighborhood rather than integrate
it. There has been some concern from the neighbors to the
south that the fence should continue across the south property
line to provide privacy both for the back yards of houses on
Prospect _and for the residents of lot 9 on- Blevins-Court—The
Planning Staff agrees that the south property line should be
a continuous fence from the southwest corner to the trash
enclosure. However, the other openings make sense.
10. Reflecting on the Planning and Zoning Board's and Prospect
Shields Neighborhood Group's concerns about the density of
this project, from a bedroom per lot perspective, the Planning
Staff recommends that you consider a maximum of 6 bedrooms on
this site. City parking requirements would be in the range of
4 to 6 spaces for most configurations of 6 bedrooms.
11. From a neighborhood compatibility point of view, the people
density of a . duplex is much more in line with the existing
character of the neighborhood. Planning Staff feels that, at
this time, they would be unable to recommend approval of a
tri-plex. The feeling is that a duplex would be more in line
with the existing density and level of human activity of
surrounding properties. The Planning and Zoning Board
expressed these concerns as well.
12. The site plan lists bicycle parking at 3 per unit, yet the
total is 7. Please correct this on the plan.
13. Indicate the location of the curb stop and meter pit for water
service on the grading, drainage, and utility plan.
14. Parkland fees are $625.00 per unit and street oversizing fees
are $584.00 per unit. These fees are collected at the time a
building permit is issued.
15. Columbine CableVision has requested that the building be
prewired for cable TV in a home run system with cable to their
standards. Please contact Dennis Greenwalt at CCV to discuss
this.
16. Light and Power had the same comments as on the previous plan
concerning service underground, development charges, and
coordination of the installation of the electric system with
Light and Power.
This concludes staff comments at this time. In order to stay'on
schedule for the February 24, 1992 Planning and Zoning Board
hearing, please note the following deadlines:
Plan revisions are due February 5, 1992 by 12:00 noon.
PMT's, colored renderings, 10 prints are due Feb. 18, 1992.
Final signed mylars and other documents are due Feb. 20, by
12:00 noon.
If you have any questions about these comments or would like to
schedule a time to meet to discuss them, please contact me at 221
6750.
— ----Sincerely,
Kirsten A. Whetstone
Project Planner
cc Kerrie Ashbeck
David Knox
Jeff Couch
Janet Meisel
Emily Smith- Prospect Shields Neighborhood Group