HomeMy WebLinkAboutMOUNTAINRIDGE FARM PUD, 1ST FILING FINAL - 18 92A - CORRESPONDENCE - STORMWATER-RELATED DOCUMENTS (2)Utility f vices
Stormwater
March 19, 1993
Mr. Steve Hair
Community Construction, Inc.
521 California Avenue
Bakersfield, California 93304
Re: Mountainridge PUD
Dear Steve:
/eV
Please find enclosed a copy of the report entitled "Analysis of the Mountainridge
P.U.D. Groundwater Study; Ramifications to the Regional Detention Facility and
the Mountainridge P.U.D. First Filing" by RED, Inc., dated March 5, 1993. This
report was prepared for the Stormwater Utility to help us evaluate what options
we have and what type of development could occur without adversely impacting our
regional drainage facilities.
I won't go into the details of the report, but some of the major points are:
- Lining the Pleasant Valley & Lake Canal appears to be beneficial in that
it will lower the groundwater table.
- The extent of lining needed to lower the groundwater table far enough to
allow construction of the regional drainage facilities and Mountainridge
First Filing is much greater than originally anticipated. Potentially,
lining from the north property line of Mountainridge to Harmony Road may
be necessary.
- Installation of a dewatering system would be difficult since there does
not appear to be a practical outfall location.
The information in this report confirms that we need to complete our Master Plan
update in order to determine, exactly what improvements we need to make,
particularly with respect to the Canal. Lining the Canal for the recommended
distance may not be the best alternative. We also want to look at realigning the
Canal, piping the Canal, and/or diverting some of the stormwater runoff into the
Canal in order to reduce the amount of onsite regional detention needed.
However, as I have previously told you, we do believe that there are options
available to you to allow the development of the First Filing prior to the
completion of the City's study. Based upon the recommendations in the report,
construction of the First Filing could proceed if the following conditions were
met:
- Proceed with lining the Canal at your expense. If our study shows that
lining the Canal is the preferred alternative for the construction of the
regional drainage facilities, there is the potential for partial
reimbursement from the Utility of the cost incurred to line the Canal. At
this point it can't be determined with any certainty how much the
reimbursement would be.
w
- Construct the First Filing with a "temporary" connection into the
existing storm sewer under Shields Street. This assumes that the
improvements to Shields Street will not be required when the First Filing
is built. Even though the existing storm sewer does not meet our
235 Mathews • P.O. Box 580 -• Fort Collins, CO 80522-0580 • (303) 221-6589
criteria, we would be willing to allow its use until the regional drainage
facilities are built.
- In conjunction with construction of the First Filing, the downstream
regional channel, (east of Shields Street), would have to be constructed.
As was originally anticipated, this would be eligible for partial
reimbursement under the Developer Repayment program.
- The waterline in the proposed Wabash Street alignment.would have to be
constructed based on the existing surface elevations. Until our study is
complete we do not know what elevation Wabash Road will have to be. There
is the potential that the waterline would have to be raised if Wabash is
raised, and this would be at the cost of the Developer. There is the
possibility, however, that the Water/Wastewater Utility may be able to,
grant a variance from .their depth criteria and that a future relocation
could be avoided. I suggest that you contact Mark Taylor at 303/221-6681
to discuss this in more -detail.
Revise the drainage report and utility plans to reflect these changes.
These items are, of course, only related to the drainage issues. There may be
other outstanding issues that must be resolved prior to final approval of the
First Filing. I suggest that you contact Ted Shepard or Mike Herzig at 303/221-
6750, to identify any other issues that must be addressed.
I hope that this clarifies for you what your options are for proceeding on with
the development of the First Filing. If you have any questions regarding the
report or this letter please call me at 303/221-6589.
Sincerely,
�
Susan L.�Duba Hayes, P.E.
Civil Engineer II
Attachment
cc: Peter Kast, GT Land (with attachment)
Stan Myers, RED, Inc.
Ted Shepard, --Planning'
Mike Herzig, Engineering