HomeMy WebLinkAboutDAKOTA RIDGE PUD THIRD FILING FINAL - 60 91L - CORRESPONDENCE - RESPONSE TO APPLICANTCommunity P➢< ng and Environmental Services
Planning Department
Citv of Fort Collins
December 20, 1994
CDL Partnership
C/o TST, Inc.
748 Whalers Way
Fort Collins, CO 80525
RE: Dakota Ridge PUD, Third Filing - Final,.#60-91L
Dear Sirs:
On December 12, 1994, the Planning and Zoning Board of the City of
Fort Collins .aiDoroved the above referenced project with the
following condition:
1. The Planning and Zoning Board approves this planned unit
development final plan upon the condition that the development
agreement, final utility plans, and final P.U.D., plans for
the planned unit development be negotiated between the
developer and City staff and executed by the developer prior
to the second monthly meeting (February 27, 1994), of the
Planning and Zoning Board following the meeting at which this
planned unit development final plan was conditionally
approved; or, if not so executed, that the developer, at said
subsequent monthly meeting, apply to the Board for an
extension of time. The Board shall not grant any such
extension of time unless it shall first find that there exists
with respect to said planned unit development final plan
----certain. specific unique and extraordinary circumstances which
require the granting of the extension in order -to -prevent -
exceptional and unique hardship upon the owner of developer of
such property and provided that such extension can be granted
without substantial detriment to the public good.
If the staff and the developer disagree over the provisions to
be included in the development agreement, the developer may
present such dispute to the Board for resolution if such
presentation is made at the next succeeding, or second
succeeding monthly meeting of the Board. The Board may table
any such decision, until both the staff and the developer have
had reasonable time to present sufficient information to the
Board to enable it to make its decision. (If the Board elects
to table the decision, it shall also extend the term of this
condition until the date such decision is made).
281 North College Avenue • P.O. Box 580 Fort Collins, CO 80522-0580 • (303) 221-6750
FAX (303) 221-6378 TDD (303) 224-6002
.•
If this condition is not met within the time established
herein• '(or as extended, as applicable), then the final
approval of this planned unit development shall become null
and void and of no effect. The date of final approval for
this planned unit development shall be deemed to be the date
that the condition is met, for purposes of determining the
vesting of rights. For purposes of calculating the running of
time for the filing of an appeal pursuant to Chapter 2,
Article•II, Division 3, of the City Code, the $@final decision@$
of the Board shall be deemed to have been made at the time of
this conditional approvals however, in the event .that a
dispute is presented to the Board for resolution regarding
provisions to be included in the development agreement, the.
running of time for the filing of an appeal of such '*final
decision@@ shall, be counted from the date of the Boardes
decision resolving such dispute.
2. That the updated Overall Drainage Plan for the •Pinecone
Overall Development Plan and the revised drainage report and
plan for the Third Filing be approved by the City Stormwater
Utility and that the developer obtain a necessary off -site
grading easement on the future City.park site from the Parks
and Recreation Department prior to the development agreement,
utility plans, and P.U.D. documents being recorded and
building permits being issued.
If you have any questions, please call our office at 221-6750.
Sin erely,
Steve Olt
City Planner
sO/gjd