EROSION CONTROL STUDY
FOR THE
INECONE APARTMENTS P.U.D.
FORT COLLINS, COLORADO
1
i
VI. CONCLUSIONS
A. Compliance with Standards
All computations that have been completed within this report are. in
compliance with the City of Fort Collins Erosion Control Reference Manual
for Construction Sites and the Storm Drainage Design Criteria Manual. In
addition, all computations are in compliance with the Overall Drainage Study
for the Pinecone P.U.D. prepared by RBD, Inc. in June, 1992.
B. Drainage Concept
The proposed drainage concepts presented in this report and on the
construction plans adequately provide for the transmission of developed on -
site runoff to the interim regional channel section along the northerly
boundary of the project site.
The on -site detention pond will provide adequate storage requirements per
the projections of the SWMM computer model, with an additional 1 foot of
freeboard. An emergency overflow weir will also be constructed at the
northeast corner of the pond. Peak release rates from the pond are below
the maximums specified in the Overall Drainage Study for the Pinecone
P.U.D. In addition, the peak flow rate for the 100-year design storm in the
Fossil Creek Reservoir Inlet Ditch has not been projected to exceed 799 cfs.
The interim channel section along the northerly boundary of the site will be
improved to convey 100 cfs with additional capacity as freeboard. In
addition, the Apartment finished floor elevations as established by the
grading plan do allow for the future development of the Ultimate regional
channel section.
C. Erosion Control Concept
The proposed erosion control concepts presented in this report adequately
provide for the control of wind and rainfall erosion from the Pinecone
Apartments site. Throughout the construction of the proposed erosion
control implements, the City of Fort Collins performance standards will be
met. The proposed erosion control concepts presented in this report and
shown on the Erosion Control plan are in compliance with the City of Fort
Collins Erosion Control Criteria.
A
REFERENCES
1. Storm Drainage Design Criteeria and
nuary 19 Construction Standards by the City of Fort
Collins, Colorado, Revised
2. Erosion Control Refere 1 e Manual for Construction Sites by the City of Fort Collins,
Colorado, January 199
3, Foothills Basin (Basin G) Drainage Master Plan, Fort Collins, Colorado, by
Resource Consultants Inc. February 1981.
4. overall Drainage Study for the Pinecone P.U.D. Fort Collins, Colorado, by RBD,
Inc., June 4, 1992.
I, 7
FINAL DRAINAGE AND
EROSION CONTROL STUDY
FOR THE
PINECONE APARTMENTS P.U.D.
FORT COLLINS, COLORADO
November 30, 1992
Prepared for:
Client:
The W.W. Reynolds Companies
4909 Pearl East Circle, Suite 300
Boulder, Colorado 80301
Prepared by:
RBD, Inc. Engineering Consultants
2900 South College Avenue
Fort Collins, Colorado 80525
(303) 226-4955
Engineering Consultants
2900 South College Avenue
Fort Collins, Colorado 80525
303/226-4955
FAX:303/226-4971
November 30, 1992
Ms. Kathy Malers
City of Fort Collins
Utility Services Stormwater
235 Mathews
Fort Collins, Colorado 80522
RE: Final Drainage and Erosion Control Study
for the Pinecone Apartments P.U.D.
Dear Kathy:
We are pleased to submit to you, for your review and approval, this Final Drainage and
Erosion Control Study for the Pinecone Apartments P.U.D.. All computations within this
report have been completed in compliance with the City of Fort Collins Storm Drainage
Design Criteria.
We appreciate your time and consideration in reviewing this submittal. Please call if you
have any questions.
Respectfully,
RBD Inc. Engineering Consultants
Roger A. Curtiss, P.E.
Project Engineer
Other offices: Denver 303/453-5526 • Vail 303/476-6340 • Longinont 303/678-9584
TABLE OF CONTENTS
DESCRIPTION
PAGE
I. GENERAL LOCATION AND DESCRIPTION
1
A. LOCATION
1
B. DESCRIPTION OF PROPERTY
1
II. DRAINAGE BASINS
1
A. MAJOR BASIN DESCRIPTION
1
B. SUBBASIN DESCRIPTION
2
III. DRAINAGE DESIGN CRITERIA
2
A. REGULATIONS
2
B. DEVELOPMENT CRITERIA REFERENCE AND CONSTRAINTS
2
C. HYDROLOGICAL CRITERIA
2
D. HYDRAULIC CRITERIA
3
E. VARIANCES FROM CRITERIA
3
IV. DRAINAGE FACILITY DESIGN
3
A. GENERAL CONCEPT
3
B. SPECIFIC DETAILS
3
V. EROSION CONTROL
5
A. GENERAL CONCEPT
5
B. SPECIFIC DETAILS
5
VI. CONCLUSIONS
6
A. COMPLIANCE WITH STANDARDS
6
B. DRAINAGE CONCEPT
6
C. EROSION CONTROL CONCEPT
6
REFERENCES
7
APPENDIX
VICINITY MAP & PARTIAL SWMM SCHEMATIC
2
SITE HYDROLOGY
3
DETENTION POND
8
REVISIONS TO THE ORIGINAL SWMM MODEL
11
ORIGINAL SWMM MODEL INPUT DATA FILE
17
REVISED SWMM MODEL INPUT DATA FILE - 2 YEAR
22
REVISED SWMM MODEL INPUT DATA FILE - 100 YEAR
27
REVISED SWMM MODEL OUTPUT FILE -
32
2 YEAR (SUMMARY OUTPUT ONLY)
REVISED SWMM MODEL OUTPUT FILE
40
100 YEAR (COMPLETE OUTPUT)
DESIGN OF INLETS, STORM SEWER AND CHANNELS
76
RIPRAP DESIGN
89
EROSION CONTROL
92
CHARTS, TABLES AND FIGURES .
97
FINAL DRAINAGE AND
EROSION CONTROL STUDY
FOR THE
PINECONE APARTMENTS P.U.D.
FORT COLLINS, COLORADO
GENERAL LOCATION AND DESCRIPTION
A. Location
The Pinecone Apartments are a part of the Pinecone P.U.D., located east
of Timberline Road, 2000 feet north of Horsetooth Road and the proposed
High School site, south of the Colorado State University Agronomy
Research Center. Proposed Vermont Drive will border the project on the
south, and proposed Pinecone Circle will border the site on the east. The
site is shown on the excerpt of the Overall Drainage Study included in the
appendix. More particularly, the project can be described as situate in the
southwesterly portion of Section 29, Township 7 North, Range 68 West of
the Sixth P.M., City of Fort Collins, Larimer County, Colorado.
B. Description of Property
The Pinecone Apartment site contains approximately 12.7 acres of land,
more or less. A small portion in the southwest corner of the site will be used
as Commercial site. The existing site contains a small farmstead, with
several buildings surrounded by farm land to the south and east.
The Foothills Regional Channel runs through the northwest corner and along
the northerly boundary of the proposed site. The majority of the site slopes
towards the east at approximately 1%. Several irrigation lines and a storm
sewer pipe run through the north portion of the site.
II. DRAINAGE BASINS
A. Major Basin Description
The Pinecone Apartments and the Pinecone P.U.D. lie within Reach 2 of the
Foothills Basin (Basin G) Drainage Master Plan, by Resource Consultants
" Inc. dated February, 1981. This project is also contained within the Overall
Drainage Study for the Pinecone P.U.D., prepared by RBD, Inc. dated June
4, 1992. The Pinecone Apartment site is represented in the Foothills Basin
SWMM model as Basin 61. This basin is drained by conveyance element
210, which is also the on -site detention facility.
1
B. Sub -basin Description
The Pinecone site has been broken down into six sub -basins, 1, 2, 3, 4,
60,and 0-1. Subbasins 1,2,3 and 4 were originally modelled in Basin 61 of
the Master plan. Subbasin 0-1 was originally a part of Basin 62 of the
Master plan. The SWMM model has been corrected as a part of this report
to include this area as a part of Basin 61. Subbasin 60 was also originally
a part of Basin 61. The SWMM model was corrected to include this area as
a part of Basin 60 of the Master plan.
III. DRAINAGE DESIGN CRITERIA
A. Regulations
The City of Fort Collins Drainage Design Criteria is being used for the
subject site.
B. Development Criteria Reference and Constraints
The Overall Drainage Study for the Pinecone P.U.D., Fort Collins Colorado,
and the Preliminary Drainage Study for the Pinecone Apartments, Fort
Collins, Colorado., criteria and constraints are being utilized in this Final
Drainage Study. Drainage criteria not specified in the Overall Drainage Study
will be in accordance with the City of Fort Collins Storm Drainage Design
Criteria and Construction Standards Manual.
The Overall Drainage Study for the Pinecone P.U.D. recommends using on -
site detention and using multiple release rates of not more than 14 cfs for
the 2-year design storm, and 24 cfs for the 100-year design storm. It is also
a requirement from the Overall Drainage Study that the ultimate peak 100-
year flows in the Fossil Creek Reservoir inlet ditch not exceed 799 cfs.
C. Hydrological Criteria
The SWMM hydrological model was used in the Foothills Basin (Basin G)
Drainage Master Plan. The SWMM model analyzed the developed flows
within the basin with the ultimate developments in place. A copy of the
original SWMM computer model was obtained from the City of Fort Collins
Stormwater Utility, and was updated to include the final development criteria
used in the Pinecone Apartments project. A copy of the original input data
file as well as the revised input data files are included in the appendix of this
report.
E
The Rational Method for determining surface runoff was used for this project
site. The 2 year and 100 year storm event criteria, obtained by the City of
Fort Collins, was used in calculating runoff values, and for sizing drainage
structures. These calculations and criteria are included in the appendix of
this report.
D. Hydraulic Criteria
All hydraulic calculations within this report have been prepared in
accordance with the City of Fort Collins Drainage Criteria and are also
included in the appendix.
E. Variances from Criteria
No variances are being sought for the proposed project site.
IV. DRAINAGE FACILITY DESIGN
A. General Concept
All on -site developed runoff from subbasins 1, 2, 3, 4, and 0-1 will flow to
the east towards an on -site detention pond (Conveyance Element 210)
located at the easterly corner of the site. Detained flows from this pond will
be released to an interim regional channel section which flows from west to
east along the northerly boundary of this project. Developed flows from
subbasin 60 will not be detained and will sheet flow directly to the interim
regional channel section.
B. Specific Details
Subbasin 1 is essentially the westerly half of the Apartment project.
Developed flows from this subbasin will be directed towards the central
parking area, and directed easterly to a series of metal sidewalk culverts.
There flows will be directed easterly through subbasin 2 and on to the on -
site detention pond provided.
Berms will be constructed along the westerly edge of subbasin 1 to prevent
flows from overtopping Timberline road and entering the Apartment site from
the west.
Subbasin 2 is essentially the easterly portion of the Apartment complex site.
Flows from this basin will also be directed to the center parking are and
transported easterly on the surface along with developed flows from
subbasin 1 to the on -site detention pond.
3
Subbasin 3 contains the commercial convenience center, the northerly
portion of Vermont Drive, and the northwesterly portion of Pinecone Circle
up to the property limits. Developed flows from this subbasin will be by curb
and gutter to a future curb inlet to be located in Pinecone Circle. With this
development, Vermont Drive will only be built up past the second entry into
the Apartment Development. The remainder of Vermont Drive and Pinecone
Circle will be completed later.
Developed flows from Timberline Road south of Vermont Drive and the
south half of Vermont Drive will be routed through the proposed High School
site, south of Pinecone Apartments. Subbasin 0-1 represents the flows that
will be directed north and east to the Pinecone Apartments on -site detention
pond. The area from this subbasin has been subtracted from Basin 62 of
the SWMM model and included in the area of Basin 61. A complete
calculation breakdown of the additions and modifications done to the original
SWMM model can be found in the appendix.
Subbasin 60 includes the easterly half of Timberline Road north of Vermont
Drive and adjacent to this development, along with the area from the
apartment complex to the regional channel section. This area has been
added to the area of Basin 60 of the Master plan, and subtracted from the
area of Basin 61. Basin 60, per the Overall Drainage Plan was free release
to the Regional Channel.
The Regional Channel section used for this development was sized to
accommodate 100 cfs (calculations are included in the appendix). This is
the capacity of the downstream interim regional channel section recently
constructed. Ultimate flows in this channel when all development has
occurred are projected to be approximately 450 cfs for the 100-year storm
C event. The finished grading for the apartments accounts for the development
of this future ultimate regional channel section.
The on -site detention pond to be constructed for this site will contain
approximately 1.1 acre-ft of storage (up to elevation 4926.5), with an
additional 1 foot of freeboard. The required detention per the SWMM
computer model is 1.0 acre-ft. Detained release from this pond will be by a
multiple release structure, with a projected peak release for the 2-year
design storm of 4 cfs and a projected peak release for the 100-year design
storm of 21 cfs. This is below the maximum allowable release rates as
specified in the Overall Drainage Study for the Pinecone P.U.D. (projections
are from the SWMM computer model, included in the appendix).
Additionally, the pond will also contain irrigation storage water for the
proposed development, below the detention storage provided.
4
r.
V
EROSION CONTROL
A. General Concept
This development lies with the Moderate Rainfall Erodibility Zone and the
Moderate Wind Erodibility Zone per the City of Fort Collins zone maps. It is
anticipated that the initial overlot grading of the site will occur during the
c early part of 1993.
The Erosion Control Performance Standard (PS) for the site was computed
to be 78.1% per the City of Fort Collins Erosion Control Reference Manual
for Construction Sites. The Effectiveness (EEF) of the proposed erosion
control plan was calculated to be 79.3%. Therefore, the Erosion Control plan
as detailed in this report meets the City of Fort Collins requirements.
B. Specific Details
Before overlot grading, the permanent detention pond shown in subbasin
4 shall be initially constructed such that it will function as a sediment trap for
the improvements planned in subbasins 1, 2, 3, 4, and 0-1. The initial
detention pond, for sediment collection, must contain at least 0.92 acre-ft
of volume, an outlet pipe with a gravel filter, and an emergency spillway per
the detail shown in the construction plans. Once the temporary vegetative
seed and mulch, roadway asphalt and concrete have been installed, the
detention pond can be converted into a final pond.
After the overlot grading has been completed, all disturbed areas not in a
roadway or building pad, shall have temporary vegetative seed applied per
the specifications on the plans. After seeding, a hay or straw mulch shall be
applied over the seed at a rate of 2 tons/acre minimum and the mulch
should be adequately anchored, tacked, or crimped into the soil. After the
utilities have been installed, the roadways and parking areas should receive
the pavement structure. After installation of the curb inlets and metal
sidewalk culverts, they shall be filtered with a combination of concrete
blocks, 1/2" wire screen and course gravel, constructed according to the
details in the construction plans.
In the event that a portion of the road or parking lot pavements and utilities
will not be constructed for an extended period of time after overlot grading,
apply temporary vegetation seed and mulch to the pavement areas as
discussed above.
5