March 24, 1992
G.T. Land Colorado, Inc.
c/o of Eldon Ward, Cityscape Urban Design
3030 South College Avenue
Fort Collins, CO 80525
Dear Mr. Ward:
For your information, attached is a copy of the Staff's comments concerning
Pinecone Apartments presented before the Conceptual Review Team on March 23,
1992.
The comments are offered informally by Staff to assist you in. preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincerely,
Ted Shepard
Senior Planner.
TS/gjt
Attachment
cc: Tom Peterson, Planning Director
Kerrie Ashbeck, Civil Engineer
Transportation Department
Project Planner
File
281 North College Avenue P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 22"1-6750
CONCEPTUAL REVIEW STAFF COMMENTS
MEETING DATE: March 23, 1992
ITEM: Pinecone Apartments
APPLICANT: G.T. Land Colorado, Inc., c/o of Eldon Ward, Cityscape
Urban Design, 3030 South College Avenue, Suite 200, Fort Collins,
CO. 80525.
LAND USE DATA: Request for 195 apartments 13 acres located on the
northeast corner of Timberline Road and Vermont (extended), in the
Pinecone Farm Overall Development Plan. Request also includes a
convenience store with gasoline sales located immediately on the
corner. Other improvements include a recreation center, swimming
pool, covered parking, storm channel improvements, and bicycle/
pedestrian loop.
COMMENTS:
1. The City Light 'and Power Department has single phase.
electrical power in the immediate area. All normal
development charges will apply. Please coordinate with Light -
and Power on the location of the transformer.
2. Both water and sewer mains are available in the intersection
of Timberline and Vermont. These mains are available, with
extension, to serve the subject property. Please check for
adequate grades for use of the sewer line. If grades are not
adequate, then another main must be brought in.
3. The Poudre Fire Authority requires a minimum of 30 foot wide
access drive to serve a three story structure. This minimum
is to allow for outriggers to stabilize the ladder truck. A
three story structure, with dirt mounded around the first
.story, will not be considered a "garden level" apartment for
purposes of the Fire Code access requirement. This 30
requirement must be provided where the truck will serve the
structure.
4. Please check to verify that the water pressure in the area
will be adequate to serve the fire fighting capability. Also,
please coordinate with Poudre Fire Authority on the location
of the fire hydrants. It appears that this site may need two
hydrants to servethe site.
5. The Building Inspection Division has copies of the local
amendments to the 1988 U.B.C. regarding the number of handicap
accessible/adaptable units. The local requirement is that one
in seven units meet the handicap accessible/adaptable
requirements, and that these units be spread evenly across the
one and two bedroom units.
1
6. The Building Inspection Division advises that there are state
and federal codes pertaining to the number of handicap
accessible or adaptable units. These codes are not enforced
by the local municipality. For further information, please
contact Sharon Getz, Plans Examiner, Building Inspection
Division, 221-6760.
7. The Parks and Recreation Department reminds the applicant that
the Parkland Development Fee, as of 1992, is $625 per unit.
8. The intersection of Timberline and Vermont should align at 90
degrees to a depth of 100 feet. Similarly, the intersection
of Vermont and the second driveway should also align at 90
degrees.
9. Please check to make sure that the minimum sight distance is
provided at the intersection of Vermont and the convenience
store driveway.
10. Timberline Road needs to be designed off site to both the north
and south of the property. The design should be fora four
lane arterial, within the six lane arterial right-of-way.
This will tesult in a wider than normal parkway for
approximately 20 years. This interim condition was used to
design Timberline south of Horsetooth Road along the frontage
of the Fox Meadows Business Park. Please contact Mike Herzig
for further information on the design parameters.
11. If any sidewalks are located outside dedicated right-of-way,
then access easements must be provided.
12. A temporary cul-de-sac should be provided. for public turn-
around at the termination of Vermont, just past the second
driveway entrance..
13. Please check the setbacks from Vermont for the first parking
stall in the apartment parking lot. If the setbacks are not
as per Code, then 'a variance, based on traffic engineering
data, must be provided for review.
14. The Street Oversizing Fee for apartment units is $584 per
unit. The fee for the convenience store is $14,005 .per
developed acre.
15. The traffic impact analysis that is the basis for the new high
school should be expanded in scope to account for the two uses
proposed. Please have the traffic engineering consultant
check with Rick Ensdorff, Transportation Director, on the
scope of the study.
16. It is preferred that Timberline be improved at the same time
as the obligations for the new high school. If Pinecone
Apartments' obligation for Timberline improvements must be
financially secured for future construction, then cash is the
preferred security. A letter of credit will be accepted if
renewed annually with an increase to account for inflation.
17. The site is located in the Foothills Drainage Basin. The
Drainage Fee in this basin is $5,024 per acre subject to the
runoff coefficient and the amount of onsite detention.
18. The storm channel on the north is part of a regional
improvement identified in the basin master plan. If this
channel is improved as part of the. proposed development, then
Stormwater Utility will reimburse the developer for the design
and construction. Please be advised that reimbursement funds
are not budgeted for 1992 and will have to be budgeted for
1993 based on preliminary design estimates.
19. There may be a problem with a lack of downstream capacity
within this basin. As a result, it may be necessary to
oversize detention on the subject property on a temporary
basis. Design for Pinecone Apartments must be coordinated
with the City's project downstream.
20. If there are true garden level units, please be aware of the
high water line and potential flooding.
21. Staff applauds the extensive bicycle/pedestrian paths and the
perimeter loop. The paths will provide non -vehicular access
to the convenience store and the loop will provide a
recreational amenity. (Please keep in mind that the Poudre
River Trail is at the C.S.U. Nature Center, about 3/4 of a
mile to the northeast.)
22. Building 12 may need special buffering to mitigate the
proximity to.Timberline Road.
23. The architectural character of the convenience store, and the
gas canopy, should be of residential character and match the
Pinecone Apartments. Please refer to Neighborhood Convenience
Shopping Center: Design Guidelines, Policies, Criteria for
further information.