January 27, 2020
Cathy Mathis
TB Group
Berthoud, CO 80513
RE: Lofts at Timberline, PDP190019, Round Number 2
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Lofts at Timberline. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Todd Sullivan via phone at 970-221-6695 or via email at tsullivan@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Pete Wray, 970-221-6754, pwray@fcgov.com
Topic: General
Comment Number: 7
01/24/2020: INFORMATION ONLY:
Ready for Hearing.
Department: Engineering Development Review
Contact: Morgan Stroud, 970-416-4344, mstroud@fcgov.com
Topic: General
Comment Number: 3
01/24/2020: FOR HEARING:
The work being proposed in the shared drive aisle between this project and the
properties to the east appears to have large impacts to the access for these
properties since it is the only access to them. Please provide us information on
conversations with the neighbors about access to their properties while this project is being constructed.
Response. The applicant serves on the Timberline Center Board. The Board has already been in contact
with all adjacent owners/businesses about the project. The project will be phased to avoid disruption to
their businesses. Construction coordination is not an element of approval by the City, but we appreciate
the comment.
2
Comment Number: 2
12/10/2019: FOR HEARING:
Please see my redlines for minor comments.
Fire truck turning template. This is simply an exhibit provided to fulfill a request from PFA. There is no path
of vehicular travel planned over the sidewalk in this area. It is simply overlapping linework from the turning
template.
Sheet 9. There is no standard to require storm pipe to cross public right of way perpendicular. The design
will remain as presented.
Department: Stormwater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
Comment Number: 2
12/09/2019: FOR HEARING - UNRESOLVED:
The City suggests a meeting with Stormwater Staff to discuss the LID design
and potential modifications that may help in the design's efficiency and grading.
Comment Number: 3
12/09/2019: It is unclear in the report how the sub-basins are being modified
with all of them being reduced in size. Please compare the entire sub-basins to
ensure compliance with the original drainage report.
Additional exhibits have been included in the drainage memo to clarify the basin changes.
Comment Number: 4
12/09/2019: The City's Criteria Manual states porous pavers at a 40%
impervious ratio. Please revise all the calculations to reflect this.
Updated.
Comment Number: 5
01/27/2020: FOR HEARING:
The LID requirement looks to be at 33% and not at the required 50%. We do
flex some on this if it is near the 50%, but 33 percent is too low.
We are happy to meet again to discuss option.
The only option that will come close to satisfying the requirement is to add a raingarden at the east side of
the project. This LID feature has been included.
Comment Number: 6
01/27/2020: FOR HEARING:
I did check within our department and the City does not want the water line stub
to be a public main since it is not serving more than one customer and serving
just this development. The City will be looking for this to be a private fire line
and the water service line to connect to the main in the public street to the east.
3
The waterline configuration has been changed to address this comment. The 8-inch waterline will be
abandoned at the main. A separate fire and service line will be installed from the main.
Department: Water-Wastewater Engineering
Contact: Wes Lamarque, 970-416-2418, wlamarque@fcgov.com
Topic: General
Comment Number: 1
12/09/2019: The 2-inch water service and fire line are being proposed to
connect to a public dead end main. The City is requesting this dead end main
become a private fire line and a 2-inch water service line be connected to the
main in the private drive to the east. Please revise.
Addressed.
Comment Number: 2
12/09/2019: Please clarify what the existing valve and meter pit is located near
the southeast part of the building. The City does not have any record of this.
This line will need to be abandoned if it is not being used for this development.
The plans call for this to be abandoned.
Comment Number: 3
12/09/2019: Please label the 8-inch sewer stub that will become the building's service line as "private".
See comment responses above.
Comment Number: 4
12/09/2019: A minimum of 4 feet clearance is required from the meter pit to
any shrubs and 10 feet to any trees.
Acknowledged.
Department: Light And Power
Contact: Austin Kreager, 970-224-6152, akreager@fcgov.com
Topic: General
Comment Number: 1
12/10/2019: INFORMATION:
It is my understanding from your comment letter that the intention is to bring in
power from the northwest corner of the site to feed the new building. Please
show a proposed transformer location for your next submittal.
Comment Number: 2
12/10/2019: INFORMATION:
Contact Light and Power Engineering to coordinate the transformer and electric
meter locations, please show the locations on the utility plans.
Comment Number: 3
4
12/10/2019: INFORMATION:
Light and Power would like to remind you that all of our facilities must have a ten
foot clearance away from all water, wastewater, and storm sewer facilities. We
also require a three foot clearance away from all other utilities with the exception of communication lines.
Comment Number: 4
12/10/2019: FOR FINAL REVIEW:
Please provide a one line diagram and a C-1 form to Light and Power Engineering.
The C-1 form can be found at: http://zeus.fcgov.com/utils-procedures/files/EngWiki/WikiPdfs/C/C-1Form.pdf
Comment Number: 5
12/10/2019: INFORMATION:
You may contact Austin Kreager, project engineering if you have questions.
(970) 224-6152. You may reference Light & Power’s Electric Service Standards at
http://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStandar
ds_FINAL_18November2016_Amendment.pdf
You may reference our policies, development charge processes, and use our fee estimator at
http://www.fcgov.com/utilities/business/builders-and-developers.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, jlynxwiler@poudre-fire.org
Topic: General
Comment Number: 7
01/22/2020: FOR FINAL PLAN:
FIRE LANE SIGNAGE - Fire lane sign locations should be indicated on future
plan sets (eg. Horizontal Control and Signage). Refer to LCUASS detail #1418
& #1419 for sign type, placement, and spacing. Appropriate directional arrows
required on all signs. Posting of additional fire lane signage may be determined at time of final inspection.
Fire lane signage has been added to the signing and striping plans.
Comment Number: 8
01/22/2020: FOR FINAL PLAN:
FIRE DEPARTMENT CONNECTION - Location of the fire line and riser room is
no issue however per code, Fire Department Connections shall be located on
the street side of buildings, fully visible and recognizable from the street or
nearest point of fire department vehicle access.
Acknowledged.
Comment Number: 9
01/22/2020: FOR FINAL PLAN:
TURNING TEMPLATE - Thank you for providing the Turning Exhibit in the Utility
Plans. Our ladder truck dimensions are somewhat different than the ones used
for this study. Please update the exhibit with current fire truck dimensions
(provided in project's Redlines folder). As I don't believe an updated exhibit will
fail to guarantee truck access, I don't feel this item is required for hearing.
Template has been updated.
5
Comment Number: 10
01/22/2020: FOR FINAL PLAN:
ADDRESS POSTING - Prior comments regarding address posting should be
reflected in the plans and elevations.
This will be provided at Final.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcgov.com
Topic: General
Comment Number: 1
12/10/2019: FOR INFORMATION
The Traffic Impact Memorandum submitted indicates that the anticipated
vehicular trip generation is lower overall on a daily basis than what was
originally anticipated and approved with the overall development plan. Since
the infrastructure was constructed assuming the higher trip generation, it is
concluded that this proposal is within the previously approved parameters. The
TIS conclusions are accepted and no further traffic review is needed.
Comment Number: 2
12/10/2019: FOR INFORMATION
Thank you for aligning the driveways with those on the other side of the street,
and providing sidewalks around and throughout the project.
Department: Stormwater Erosion Control
Contact: Basil Hamdan, 970-222-1801, bhamdan@fcgov.com
Topic: Erosion Control
Comment Number: 1
12/04/2019: FOR INFORMATION ONLY:
The construction activities associated with this site's development will exceed
the 1 acre threshold, therefore Erosion Control Plan, Report and Escrow
calculations will be required at FDP level submittal.
This development will also be subject to the State's Stormwater Discharge permit requirements.
The erosion control requirements are located in the Stormwater Design Criteria
in Chapter 2 Section 6.0, a copy of the requirements can be found at:www.fcgov.com/erosion
Department: Environmental Services
Contact: Jonathon Nagel, 970-416-2701, jnagel@fcgov.com
Topic: General
Comment Number: 2
11/27/2019: INFORMATION ONLY: The Community Recycling Ordinance (No.
109 2016) requires that all new business and multifamily complexes subscribe
to recycling service that is at minimum 1/3 of their overall service capacity (total
bin capacity x number of weekly pickups, include both trash and recycling when
calculating overall service capacity). In general recycling containers must be at
least 50% the size of proposed trash containers to meet this requirement.
6
Please make sure proposed containers meet this requirement and that
adequate space is provided in all enclosures.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: General
Comment Number: 2
01/24/2020: INFORMATION ONLY:
Unless required during PDP, a complete review of all plans will be done at FDP.
Topic: Plat
Comment Number: 1
01/24/2020: FOR FINAL PLAN -UPDATED:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response letter.
Acknowledged.