HomeMy WebLinkAboutFORT COLLINS MONTESSORI SCHOOL - FDP200002 - CORRESPONDENCE - RESPONSE TO STAFF REVIEW COMMENTS1
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6689
970.224.6134 - fax
fcgov.com/developmentreview
April 01, 2020 April 16, 2020
David Kasprzak
TFG Design, LLC
138 E 4th Street, STE 1
Loveland, CO 80537
RE: Fort Collins Montessori School, FDP200002, Round Number 3
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Fort Collins Montessori School. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
your Development Review Coordinator, Brandy Bethurem Harras via phone at
970-416-2744 or via email at bbethuremharras@fcgov.com.
Comment Summary:
Department: Engineering Development Review
Contact: Spencer Smith, 970-221-6603, smsmith@fcgov.com
Topic: General
Comment Number: 11
03/25/2020: FOR FINAL APPROVAL – UPDATED:
I see that the previous Emergency Access Easement area(s) have been
labeled as Drainage Easements as well. I do see a couple of other apparent
adjustments to drainage easement linework to accommodate the storm pipes, but
I can't clearly identify if all drainage infrastructure is contained within drainage
easements from the utility plans alone. Until I have a revised plat, I cannot
confirm that this comment has been addressed completely.
A revised Plat is being provided.
TFG Response: A revised Plat is provided and should be considered an exhibit only. It reflects the latest
BDR comments but is waiting for reception numbers to be finalized.
03/03/2020: FOR FINAL APPROVAL:
Please add areas of additional drainage easement for storm pipes that extend
outside of the drainage easements that you currently show (see redlines).
Comment Number: 12
03/25/2020: FOR DCP – UPDATED:
2
A draft of the DA has been sent to our City Attorney's Office for review. I also
sent the applicant a base draft version of our DA so that the general language
could be reviewed while we await the City Attorney review. I will coordinate
directly once I receive comments or questions from our City Attorney.
Acknowledged.
03/03/2020: FOR DCP
The City will require a development agreement (DA) for this project. City staff is
currently preparing a draft of this agreement and will send it to you for review as
soon as it is complete. A DA information form will be sent with these comments
and will need to be completed and returned to the City as soon as possible.
You may also visit the Engineering Development Review website for additional
information: https://www.fcgov.com/engineering/devrev.php
Comment Number: 13
03/25/2020: FOR DCP – UPDATED:
Thank you for the cost estimate. I will be forwarding it on to our Chief Engineering Inspector
for review. If there are questions, I will have him contact the engineering consultant directly.
Cost estimated updated.
03/03/2020: FOR DCP
We will need an engineer's cost estimate for the project to be submitted to
Engineering for review by our inspections staff. This will allow us to determine
what level of permitting is required for the public improvements. Please refer to
the Engineering website listed in comment #12 for a template of the cost
estimate (under the Development Construction Permit (DCP) section).
Comment Number: 15
03/25/2020: FOR FINAL APPROVAL
Please add the City signature block to all plan sheets in the utility plan set.
Signature block added to all sheets.
Department: Stormwater Engineering
Contact: Matt Simpson, (970)416-2754, masimpson@fcgov.com
Topic: General
Comment Number: 20
03/30/2020: DEVELOPMENT AGREEMENT:
The City will be requiring a Development Agreement for final approval of this
project. The Development Agreement will include requirements for long-term
maintenance of the onsite storm drainage facilities. We will provide you with a
draft copy of the Development Agreement as soon as possible.
Acknowledged.
Comment Number: 21
03/30/2020: FOR FINAL APPROVAL - ESCROW:
For Final Approval of the project, the City **is requesting** an escrow for the Lot
Grading & Site Drainage Certifications. This escrow will be the minimum
amount of $3,000. **The $200 administrative fee is waived**.
The escrow is **requested** of this project because the City is not issuing the
Building Permit or Certificate of Occupancy. These are our standard
3
mechanisms to obtain the as-built Lot Grading and Site Drainage Certifications.
The escrow amount will be returned upon acceptance of the post-project Lot
Grading and Site Drainage Certifications.
**Our intent is to have a mechanism that provides assurance that the City will be
able to obtain these post-project certifications. If the Grading Escrow method is
not acceptable to the applicant, please suggest another mechanism that will
provide the assurance that these certifications will be completed. Please feel
free to contact us to discuss.**
Acknowledged.
Comment Number: 22
03/30/2020: FOR FINAL APPROVAL - FEES:
There will be stormwater development fees and review fees. These are based
on new impervious area and are typically due at the time of building permit.
However, since this project will not obtain the building permit through the City,
these fees need to be collected for final approval of the project.
Please contact the Development Review Coordinator, Brandy, for the fee amount.
Acknowledged.
Comment Number: 23
03/30/2020: FOR FINAL APPROVAL:
Please see the included redlines of the Utility Plans and Landscape Plans for
minor comments. These include:
-Minor labeling revisions.
-Check grades on stormwater rundown on Rain Garden 1.
-Check "Storm-5" pipe clearance from tree (due to alignment change).
-Update Landscape Plan with "Storm-5" pipe location.
-Add permanent erosion control to 2 storm rundowns (Rain Garden 1 and 3)
and at the outlet to "Storm-5".
-Update sidewalk chase detail to Fort Collins Stormwater Detail D-10:
https://citydocs.fcgov.com/index.php?
scope=doctype&dn=Utilities&dt=DETAIL+DRAWINGS&vid=189&q=stormwater&cmd=search
All minor comments have been addressed.
TFG Response: Storm-5 is shown on the landscape plans and plant material was adjusted for minimum
clearances.
Department: Water-Wastewater Engineering
Contact: Matt Simpson, (970)416-2754, masimpson@fcgov.com
Topic: General
Comment Number: 2
03/30/2020: FOR FINAL APPROVAL - UPDATED:
Please change the callout at the water service abandonment location to
"Contact FCLWD Inspector for abandonment requirements."
Note updated.
02/28/2020: FOR FINAL APPROVAL:
The water service to be abandoned on the east side of the site is connected to
a Fort Collins-Loveland Water District main. Please perform abandonment of
4
service per FCLWD standards and not Fort Collins standards. Update the plan
notes accordingly.
Department: Forestry
Contact: Nils Saha, , nsaha@fcgov.com
Topic: Landscape Plans
Comment Number: 8
3/31/2020: INFORMATION ONLY - UPDATED
Please see redlines.
03/02/2020: INFORMATION ONLY
Please see redlines for tree/utility separation conflicts and cleanup items.
TFG Response: Per follow up email correspondence, the tree/utility separation conflicts have been
resolved. The island tree in question was relocated to the northwest corner of the building, removing it
from the proximity of the new ‘diagonal’ storm pipe. Shrubs were adjust, as well.
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Site Plan
Comment Number: 1
03/30/2020: FOR FINAL APPROVAL-UNRESOLVED:
There are line over text issues that were not corrected. See redlines.
TFG Response: The parking count for the row of ‘11’ was corrected to remove line over text.
02/04/2020: FOR FINAL APPROVAL:
There are line over text issues. See redlines.
Department: Water Conservation
Contact: Eric Olson, 970-221-6704, eolson@fcgov.com
Topic: General
Comment Number: 1
03/23/2020: Please remove the Preliminary Stamp from the Irrigation Plans. The irrigation plans
must comply with the provisions outlined in Section 3.2.1(J) of the Land Use Code.
Direct questions concerning irrigation requirements to Eric Olson, at 221-6704 or eolson@fcgov.com
TFG Response: The Preliminary Stamp is removed and the irrigation plans comply with 3.2.1(J).
Department: Fort Collins Loveland Water District
Contact: Nate Ensley, ,
Topic: General
Comment Number: 3
03/24/2020: INFORMATION ONLY:
Coffey Engineering has addressed all of our concerns and we have no further
comments on the Civil Plans.
We are coordinating an easement dedication directly with their development team.
TFG Response: Understood, thank you.
5
Department: Environmental Services
Contact: Linda Hardin, , lhardin@fcgov.com
Topic: General
Comment Number: 2
03/31/2020: INFORMATIONAL:
Fine, airborne particulate matter (fugitive dust) generated by construction
related activities is considered a Criteria Air Pollutant and is regulated by
federal, state, and local government due to its impact on public health and
safety, and the environment. Per Section 12-153 of Municipal Code, the City’s
Dust Control Manual requires that specific dust control measures are utilized for
specific dust generating activities. Due to the proximity of the proposed
development to existing residential area we request that, though not required, a
Dust Control Plan be prepared and submitted to jkomes@fcgov.com for review.
Dust Control Plan guidance is available within the City’s Dust Prevention and
Control Manual at fcgov.com/dust; please contact Jason Komes at
jkomes@fcgov.com with questions.
TFG Response: Acknowledged.