TYPE OF PROJECT - The project is a Auto related center of business
appealing to the traveler.
PROJECT LOCATION - The project is located at the southeast corner
of Prospect Road and I - 25.
DESCRIPTION - The project will consist of five separate
businesses. Two of the buildings are Motels, one
is a Convenience Store, and two are restaurants.
The uses that will be dealing in Hazardous
Materials and the handling of emergency
situations relation to hazardous material
spilling or leakage. These land uses are the
Motels and the Convenience Store. The Motels
will have and need to address the Hazardous
material of Chlorine Gas and the Convenience
Store will have the Petroleum Fuel for autos.
The fuel sales operation will follow all State,
Local, and Federal Laws in the construction of
the facility, in the installation of tanks for
fuel storage, and the sales of such fuels to
individuals. The fuel retailer will make all
appropriate document filings and permit
applications with the City, State, and Poudre
Fire Authority at the Building Permit Stage. The
Retailer will allow and cooperate with the
Authority during the installation of the storage
tanks and associated controls for the
operation.
The site will provide for the storage of
approximately 25,500 gallons in four storage
tanks.
At this preliminary stage of the project the
owner / developer is in discussion with two
operators for the Site, one being Texaco and the
second being Convenience Plus. Both site users
have similar plans as to how fuel spillage is
handled. The following summarizes the two
approaches.
1. The Building adjacent to the door and the
Pump Island will be signed that master
shut-off valves are located inside of the
building.
2. The site drainage is so designed to
contain and release drainage at one point
at a curb break of 6" wide in a 6" high
curb.
3. On site within the building will be stored
sand or a block plate that will block the
site drainage release point in the case of
a spillage controlling the spill on site.
4. Fire Department Emergency numbers for the
site will be programmed into the phone
system for speed automatic dialing in case
of emergency.
5. The company will have a standardize
training program for employees as to how
to react to an emergency spillage
situation. This program outlines the
sequence and response required of the on
service employee in the case of an
emergency on site.
6. All employees will go through a training
session each year regarding emergency
site situations.
7. All trucks servicing the site with fuel
products are equipped with automatic shut-
off switching to avoid over flow and
nozzle separation.
L
The Motels have the potential of spilling
Chlorine which in quantity is a lethal chemical.
The two motels considering the site are national
chains and at this preliminary stage require
confidence as to their specific identity. At the
Final Submission the specific motel franchise
will be identified. Each of the two site users
are considering installing an interior pool but
this will not be finalized until their market
studies are completed. Each Motel Operator being
a part of a national chain has a corporate
emergency response plan for implementation in
case of emergencies situations of fire and
chemical spills. A summary of these plans is
included.
1. Hazardous Materials and Chemicals are
stored in a locked materials room and or
cabinet. The doors to such rooms are
marked with international symbol for
appropriate hazardous material.
2. Each Room is provided an emergency escape
route diagram permanently affixed.
Emergency escape route are noted by
diagram at each stairway and lobby
area. Emergency exiting signs both height
mounted at 90" A.F.F. and floor height.
3. Fire alarm panel is provided with the
building. Fire alarm horns are located on
each floor with strobe lights. Hearing
impaired rooms will have strobe lights.
4. in the case of an emergency spill of
Chlorine the staff will notify the Fire
Authority. and evacuate the building.
5. The Franchise has a published emergency
evacuation plan that each facility adheres
to.
6. The employees will all be trained as to
emergency evacuation and authority
notification.
7. Employees will attend refresher training
for emergency response at least once a
year.
B. Emergency response numbers will be
programmed into the building phone system.
9. Fire alarm panel will wired with dialer to
fire authority when panel responds.
10. Hazardous chemical monitor will be mounted
in chemical storage area and will signal
alarm panel when levels exceed acceptable
levels.
w
11. Fire alarm panel is equipped with manual
actuation station. Staff is to be trained
in the process of actuating the alarm
system in cases of an emergency. Staff is
to be trained to note location of
handicapped or faculty impaired guest in
case of such emergency.
The operators of the individual businesses will
file its hazardous material spill procedures to
the Fire Authority at the time of the Final
Submittal and at the time of Building Permit
application. We will provide any additional
information as requested by the Authority at the
time the Project is processed to a Final.