March 12, 2020
David Kasprzak .
TFG Design, LLC
138 E 4th St
STE 1
Fort Collins, CO
RE: Montessori Subdivision, BDR190017, Round Number 3
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Montessori Subdivision. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Brandy Bethurem Harras via phone at 970-416-2744 or
via email at bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras, 970-416-27449 bbethuremharras@fcgov.com
Topic: General
Comment Number: 1
11 /15/2019: INFORMATION:
I am your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team.
Please include me. in all email correspondence with other reviewers and keep
me informed of any phone conversations. Thank you!
Comment Number: 2
03/03/2020: INFORMATION:
As part of your resubmittal you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a
different font color. When replying to the comment letter please be detailed in
your responses, as all comments should be thoroughly addressed.
Provide reference to specific project plans or explanations of why comments
have not been addressed, when applicable.
Please avoid using acknowledged, noted, or other non -descriptive replies.
Department: Engineering Development Review
Contact: Spencer Smith, 970-221-6603, smsmith@fc4ov.com
Topic: General
Comment Number: 3
03/12/2020: INFORMATION ONLY:
See redlines for additional comments. REDLINES ADDRESSED
Comment Number: 4
03/12/2020: FOR APPROVAL
There need to be additional drainage easements for the storm sewer pipes that
run underneath the drive aisles/parking areas, etc. on site. EASEMENTS MODIFIED
Comment Number: 5
03/12/2020: FOR APPROVAL
The proposed off -site easement reception number needs to be filled in once that easement is recorded. I
DON'T BELIEVE THAT THIS IS RECORDED YET
Department: Stormwater Engineering
Contact: Matt Simpson, (970)416-2754, masimpson@fcgov.com
Topic: General
Comment Number: 2
03/02/2020: FOR FINAL APPROVAL:
The proposed storm pipes, that connect the detention ponds, need to be
completely inside of a drainage easement (20-ft min.) There appears to be 4
locations where the drainage easement appears to stop at the location where
the storm pipes cross the EA easement. Please confirm or revise so that
these storm pipes are completely in a drainage easement. See redlined Plat for more information.
Please revise the name of the 30-foot Utility Easement to be 'Utility and
Drainage Easement'. Thank you. EASEMENTS MODIFIED
02/04/2020: FOR FINAL APPROVAL:
The outlet storm pipe needs to be in a 20-foot drainage easement. The
'equalizer pipes' that connect the detention ponds need to be in a 20-foot drainage easement.
11/04/2019: FOR APPROVAL:
Drainage easements are required for all detention basins and stormwater
quality facilities. This includes the area encompassing the basin itself, side
slopes, the area of the 100-year water surface elevation and freeboard, all
appurtenances necessary for the ouff all, and operation and maintenance of the facility.
Department: Technical Services
Contact: Jeff County, 970-221-6588, (county@fcgov.com
Topic: Plat
Comment Number: 1
03/03/2020: FOR FINAL APPROVAL -UPDATED:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response letter. REDLINES
ADDRESSED