HomeMy WebLinkAboutHIGH TOP CULTIVATION FACILITY - BDR200006 - SUBMITTAL DOCUMENTS - ROUND 1 - TRAFFIC STUDY7200 South Alton Way, Suite C400, Centennial, CO 80112
303-740-9393 x Fax: 303-721-9019 x www.jrengineering.com
March 26, 2020
Martina Wilkinson
City of Fort Collins
Traffic Operations Department
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
RE: Traffic Letter – High Top Development
JR Engineering Project No. 39783.00
Dear Ms. Wilkinson:
This Traffic Letter has been prepared to provide a recommendation on whether a change-of-use permit
from the Colorado Department of Transportation (CDOT) is required for the conversion of a portion of
an existing building to a marijuana cultivation facility. The existing building is located at 6629 South
College Avenue in Fort Collins, and the project is referred to as the High Top Development. The scope
of this letter will be limited to changes proposed to the land use and site plan and the effects of these
changes on the anticipated trip generation.
The project is shown on the Kind Care of Colorado Lot 2 site plan. Lot 1 includes the existing Kind
Care marijuana dispensary. Lot 2 is specifically located within the northeastern corner of Section 14 of
Township 6 North, Range 69 West, 6th Principal Meridian, City of Fort Collins, County of Larimer, and
State of Colorado. The lot is located on the southwestern corner of the intersection of West Trilby Road
and South College Avenue (US 287). The lot is accessed by an existing right-in, right-out (RIRO)
located approximately 300 feet south of Trilby Road on the west side of US 287. A vicinity map is
shown in Appendix A.
JR Engineering understands that a full Traffic Impact Study is not required due to the changes to the
Kind Care of Colorado Lot 2 site plan, but that a Traffic Letter is required to address the change in trip
generation from the site compared to the existing conditions.
Trip Generation Summary
Trip generation has been calculated from the latest data contained within the Institute of
Transportation Engineers' (ITE) Trip Generation Manual, 10th Edition. Based on the updated site plan,
the site was studied as ITE Code 110 (General Light Industrial) with 10 employees. Based on the land
use and the guidelines within Volume 1 of the Trip Generation Manual, JR used the fitted curve
equation from the Trip Generation Manual for the weekday, AM peak hour, and PM peak hour trips
generated for the General Light Industrial (ITE 110) land use.
The project is expected to generate the approximate following number of trips at full build-out (10
employees):
Traffic Letter Page 2
High Top Development March 26, 2020
7200 South Alton Way, Suite C400, Centennial, CO 80112
303-740-9393 x Fax: 303-721-9019 x www.jrengineering.com
• 50 weekday daily trips
• 3 AM peak hour vehicle trips, split 2 (83%) entering and 1 (17%) exiting
• 1 PM peak hour vehicle trips, split 0 (22%) entering and 1 (78%) exiting
The trip generation reports are included in Appendix B. The reports show a summary of land use, trip
generation rates, and the total volume added to the adjacent streets. No adjustments were made for
internal capture trips or pass-by trips. The largest vehicular wheel base expected to use the access would
be a garbage truck from Ram Waste
Based on the data from current studies found in the Trip Generation Manual, 10th Edition, the volume of
traffic utilizing the access to the property will only increase by 15% based on peak hour volumes
calculated from the proposed average trips per day taken from the Hauser Architects 2017 site plans for
the marijuana dispensary. (10% of the proposed 196 daily trips was used as a conservative estimate for
peak hour volume). The traffic volumes for the site access are found in Table 1 below, as well as
Appendix C. Based on this number the impact to the existing traffic will not require additional
improvements to the roadway system and is expected to produce fewer trips than required for a change-
of-use permit.
Table 1. Site Access Traffic Volumes
Kind Care of Colorado Site Access Traffic
AM Peak Hour PM Peak Hour Daily Trips
Existing* Projected Increase Existing* Projected Increase Existing Projected Increase
Enter 10 12 25% 10 10 0% 98 123 26%
Exit 10 11 10% 10 11 10% 98 123 26%
Total 20 23 15% 20 21 5% 196 146 26%
*Existing traffic counts based on projected average daily trips per Hauser Architects 2017 site plans
Conclusion
This Traffic Letter has been prepare to determine the overall impact of the High Top Development on
existing traffic in the area and whether it requires a change-of-use permit from CDOT. Based on the
changes described herein to the anticipated trips generated, JR Engineering is of the opinion that the
findings and impacts stated to the existing roadway network are unnecessary to require a change of use
permit from the CDOT. If you have any questions or comments, please feel free to contact me at
efarney@jrengineering.com or 303-267-6183.
Sincerely,
JR Engineering, LLC
Eli Farney, PE, PTOE
Director of Public Works
Attachments: Appendix A: Vicinity Map
Appendix B: Trip Generation and Land Use Summary Reports
Appendix C: Site Traffic Map
7200 South Alton Way, Suite C400, Centennial, CO 80112
303-740-9393 Fax: 303-721-9019 www.jrengineering.com
APPENDIX A
VICINITY MAP
A Westrian Company
SITE
7200 South Alton Way, Suite C400, Centennial, CO 80112
303-740-9393 Fax: 303-721-9019 www.jrengineering.com
APPENDIX B
TRIP GENERATION AND LAND USE SUMMARY REPORTS
Trip Generation Summary
Open Date:
Analysis Date:
3/24/2020
Project: High Tops 3/24/2020
Alternative:
Alternative 1
Phase:
ITE Land Use * Enter Exit Total * Enter Exit Total * Enter Exit Total
Weekday Average Daily Trips
Weekday AM Peak Hour of
Adjacent Street Traffic
Weekday PM Peak Hour of
Adjacent Street Traffic
110 Marijuana Cultivation Warehouse
10 Employees
25 25 50 2 1 3 0 1 1
Unadjusted Volume 25 25 50 2 1 3 0 1 1
Internal Capture Trips 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0
25 25 50 2 1 3 0 1 1
Pass-By Trips
Volume Added to Adjacent Streets
Total Weekday Average Daily Trips Internal Capture = 0 Percent
Total Weekday AM Peak Hour of Adjacent Street Traffic Internal Capture = 0 Percent
Total Weekday PM Peak Hour of Adjacent Street Traffic Internal Capture = 0 Percent
TRIP GENERATION 10, TRAFFICWARE, LLC P. 1
Source: Institute of Transportation Engineers, Trip Generation Manual 10th Edition
* - Custom rate used for selected time period.
Detailed Land Use Data
Project:
Open Date:
High Tops Analysis Date:
3/23/2020
3/23/2020
For 10 Employees of Marijuana Cultivation Warehouse
( 110 ) General Light Industrial
Day / Period Rate
Avg
Rate
Min
Rate
Max
Dev
Std
Trips
Pass-By
Size
Avg
Enter Exit
% %
Eq.
Use
Trips Equation R2
Total
Weekday Average Daily Trips 50 0 3.05 1.53 23.5 1.64 80 50 50 True Ln(T) = 0.77 Ln(X) + 2.13 0.85
Source : Trip Generation Manual 10th Edition
Weekday AM Peak Hour of Adjacent Street Traffic 3 0 0.52 0.05 2.07 0.26 91 83 17 True T = 0.54(X) - 2.2 0.85
Source : Trip Generation Manual 10th Edition
Weekday PM Peak Hour of Adjacent Street Traffic 1 0 0.49 0.04 2.33 0.23 84 22 78 True T = 0.54(X) - 3.96 0.85
Source : Trip Generation Manual 10th Edition
TRIP GENERATION 10, TRAFFICWARE, LLC 1
Source: Institute of Transportation Engineers, Trip Generation Manual 10th Edition
7200 South Alton Way, Suite C400, Centennial, CO 80112
303-740-9393 Fax: 303-721-9019 www.jrengineering.com
APPENDIX C
SITE PLAN
A Westrian Company
HIGH TOP
SITE
X:\3970000.all\3978300\Word\Reports\Traffic\Drawings\High Tops TIS Figures.dwg, C-Site Map, 3/26/2020 12:47:57 PM, farneye