HomeMy WebLinkAboutMOUNTAINRIDGE FARM PUD PRELIMINARY - 18 92 - CORRESPONDENCE - CORRESPONDENCE-CONCEPTUAL REVIEW (2)Developm Services
Planning Department
November 26, 1991
G.T. Land
c/o Eldon Ward, Cityscape Urban Design
3030 South College Avenue, Suite 200
Fort Collins, CO 80525
Dear Eldon:
For your information, attached is a copy of the Staff's comments concerning, 10
acres in the Mountain Ridge Farm, that was presented before the Conceptual Review
Team on November 25, 1991.
The comments are offered informally by Staff to assist you in preparing the
detailed components of the project application. Modifications and additions to
these comments may be made at the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in
the review process, please feel free to call me at 221-6750.
Sincerely,
Ted Shepard
Project Planner
TS/gjt
Attachment
cc: Tom Peterson, Planning Director
Kerrie Ashbeck, Civil Engineer
Project -Planner
File
281 North Cuile_e Avenue • 11.0. Box 580 • Fort Collins, CO 5052-0550 • (303) 221-6750
CONCEPTUAL REVIEW STAFF COMMENTS
MEETING DATE: November 25, 1991
ITEM: 10 acres in the Mountain Ridge Farm
APPLICANT: G.T. Land c/o Eldon Ward, Cityscape Urban Design, 3030
South College Avenue, Suite 200, Fort Collins, CO. 80525
LAND USE DATA: Proposal for 34 single family lots on 10 acres
within the Mountain Ridge Farm, east of Westfield Park, along
Seneca Street (extended), and west of the Pleasant Valley and Lake
Canal. .... _...... _..--._... -
COMMENTS:
1. Electrical power will be brought from the south along the east
side of Seneca Street. Please refer to the handout for a
detailed breakdown of the development charges (off -site
facilities, primary lines streetlighting), and building site
charges (secondary service fee for undergrounding service line
on -site within property boundaries). Please note that
additional charges may be applied for unusual conditions. For
further information regarding electrical distribution or fees,
please call Alan Rutz, Light and Power Department, 221-6700.
2. There is an existing 12 inch diameter water line in Seneca.
Off this main is an existing 8 inch diameter stub which runs
east. Since this stub does not appear to align with any of
the proposed cul-de-sac, it may not needed. If not needed, it
must be abandoned back to the main. In addition, a 12 inch,
water line will be required to placed in Troutman. The first
developer to build Troutman Parkway will be required .to
construct this line and be eligible for reimbursement from the
future, adjacent developers who will benefit.
3. The sewer line that will serve this project is located in
Shields Street. This line must be extended to. the project.
The developer will be eligible for repays from both the City
and adjacent developers for oversizing this line. For further
information regarding water and sewer issues and fees, please
contact Mark Taylor, Water and Wastewater Utility, 221-6681.
4. The Poudre Fire Authority will require a second point. of
access. This second point could either be from Horsetooth via
Seneca, or through Imperial Estates via Westfield Drive. The
extent of the improvement to Westfield could depend on the
timing of the construction of Westfield Park. For further
information, please contact Warren Jones, Poudre Fire
Authority, 221-6570.
5. The site is located in the McClelland -Mail Creek Drainage
Basin. The fee for this basin is $3,232 per gross acre
depending on the amount of impervious surface and the amount
of onsite detention.. The option is available to provide
onsite detention or directly convey flows, without detention,
into the proposed regional detention pond adjacent to the
east. This regional detention pond is master planned as a
basin -wide improvement.. It will be constructed in phases on
an "as needed" basis as development occurs. The City
Stormwater Utility knows the amount of volume that needs to be
detained in the regional pond. The exact size and shape,"
however, are not yet determined.
6. Please be aware that the Stormwater Utility has not budgeted
any funds in 1992 for repayment to the developer for regional
pond improvements. The earliest the Utility can make a
repayment is in 1993. This is not meant to discourage seeking
development approval, but only that funds for this pond cannot
be released according to City Code until 1993.
7. Please be aware that developed flows from Westfield Park must
be conveyed to the regional pond. These off site flows may be
substantial. Also, the developer of Phase Two of Westbrook
P.U.D. has made preliminary assumptions about draining to the
north. Westbrook needs a northern outfall across Troutman.
This drainage is the offsite condition that affects the
subject proposal.
8. Submittal requirements include a Drainage Report, Drainage and
Grading Plan, and Erosion Control Plan.
9. The design and construction of Westfield Park is approximately
one to three years away. The Parks and Recreation Department
would like to coordinate with the developer for location of an
irrigation line (and pump) from the Pleasant Valley and Lake
Canal to the park for raw water irrigation. Also, since park
restrooms will need access to the sewer line, coordination
with the developer will be necessary. Where park drainage
bisects the development, this.area could be improved with a
path to provide a connection to the Pleasant Valley and Lake
Canal. In addition to being a drainage easement, this area
should also be designated as "access easement".
10. The Parkland Development Fee is $625 per dwelling unit payable
at the time of building permit issuance. For further
information on the development of Westfield Park or fees,
please contact Craig Foreman, Parks and Recreation Department,
221-6640.
11. The primary issue for the City Transportation Department is
the timing of constructing Troutman Parkway. Troutman is a
collector street which is required to include 50 feet of
pavement on 68 feet of right-of-way. Please update the
existing traffic impact analysis for this area and address how
the proposed development fits into the phasing scheme for
Troutman improvements.
12. The alignment of Troutman is somewhat fixed with the existence
of a 54 inch diameter water line.
13. The Development Agreement will document the extent of public
improvements required by this development, as well as the off -
site improvements which are eligible for reimbursements by
either adjacent developers or the City.
14. Standard utility plans will be required. The Ditch Company
approval will be required on the plans. It is preferred that
intersections be aligned at 90 degrees. One of the
significant off -site improvements that must be addressed is
the ditch crossing on Troutman. The Street Oversizing Fee is
$584 per dwelling unit payable at the time of building permit
issuance.
15. The connection to Imperial Estates via Westfield Drive must be
negotiated in terms of participation with Parks and Recreation
and the property owner to the north. Also, the extent to
.which this connection is improved must also be discussed.
While many residents are aware that Westfield will connect to
Seneca, many may not. It may be advisable to inform the
neighborhood prior to construction that this connection will
be made.
16. The City Department of Natural Resources is concerned about
the wooded area northeast of the proposed project. This area
is considered sensitive, because of the valuable wildlife
habitat that it provides. It would seem logical to extend the
proposed bikepath through the proposed regional detention pond.
to this area. Also, please be aware that the ditch company
may need to preserve a service access parallel to the ditch.
17. Who will maintain the proposed entry feature? Will there be
a homeowners association?
18. Fencing along Troutman should be a design that does not
promote the "canyon effect".