Stripping, grubbing, subgrade preparation, and fill and
backfill placement should be accomplished under the continuous
observation of the geotechnical engineer. Field density tests
should be taken daily in the compacted subgrade, fill and backfill
under the direction of the geotechnical engineer.
Laboratory resistivity tests, pH, oxidation-reduction
potential and sulfide tests performed in the laboratory indicate
the subsoils at the site are noncorrosive, and protection of metal
utility pipe will not, in our opinion, be required.
Flexible Pavement
It is our opinion flexible pavement is suitable for the
proposed street construction at the site. A flexible pavement
alternate:should consist of asphalt concrete underlain by crushed
aggregate base course and subbase or asphalt concrete underlain by
plant mix bituminous base course. The design criteria described
below will be utilized in determining the pavement thicknesses at
the site. All soils data needed for pavement design has been
provided and is included in this report. When traffic data becomes
available, pavement sections for Graystone Court will be provided.
City of Fort Collins "Design Criteria and Standards for
Streets" dated July 1986 and AASHTO Guide for Design of
Pavement Structures 1986
18 kip ESAL - 36,500 based on an 18 kip EDLA of 5 for
residential streets
Resilient Modulus MR of 3775 psi based on an "R" value of 5
Reliability Factor - 70
Overall Deviation - .44
Initial Serviceability Index - 4.5
Terminal Serviceability Index - 2.0
Drainage Coefficient - 1
Qi.
f!
Terracon
20-Year Design Life
Structural Number - 2.24
Strength Coefficients:
Asphalt Concrete - 0.44
Plant Mix Bituminous Base Course - 0.34
Crushed Aggregate Base Course - 0.11
Select Subbase - 0.10
The following minimum pavement thicknesses are recommended for
Jewelstone, Rosestone and Jadestone Courts:
Asphalt Concrete 3"
Crushed Aggregate Base Course 8"
Total Pavement Thickness 11"
Asphalt Concrete 2"
Plant Mix Bituminous Base Course 4"
Total Pavement Thickness 6"
The select subbase should meet City of Fort Collins Class 1
specifications, and the crushed aggregate base course should meet
City of Fort Collins Class 5 or 6 specifications. The subgrade
below the proposed asphalt pavement should be prepared in
accordance with the recommendations discussed in the "Site Grading,
Excavation and Utilities" section of this report. Upon proper
preparation of the subgrade, the subbase and base course should be
placed and compacted between optimum moisture and two percent (2%)
wet of optimum moisture to at least ninety-five percent (95%) of
Standard Proctor Density ASTM D 698-78. (See Appendix C.)
It is recommended the asphalt concrete and/or plant mix
bituminous base course be placed in two (2) to three (3) inch
lifts. All plant mix bituminous base course and asphalt concrete
shall meet City of Fort Collins specifications and shall be placed
-7-
Terracon
in accordance with these specifications. All subbase material
shall have an "R" value between 50 and 69, the crushed aggregate
base course shall have an "R" value between 70 and 77, the plant
mix bituminous base course shall have an Rt value of 90 or greater,
and the asphalt concrete shall have an Rt value of 95 or greater.
The "R" value of the pavement materials used should be verified by
laboratory tests. Field density test results should be taken in
the aggregate base course, bituminous base course and asphalt
concrete under the direction of the geotechnical engineer.
Rigid Pavement
A feasible foundation alternate at the site would be rigid
pavement. Using the 18 kip equivalent daily load application
described above, a modulus of subgrade reaction of one hundred
(100) pounds per square inch per inch based on an "R" value of 5,
a design life of 20 years, and concrete designed with a modulus of
rupture of six hundred fifty (650) pounds per square inch, the
following minimum pavement thicknesses are recommended:
Jewelstone, Rosestone, and Jadestone Courts
Nonreinforced Concrete - 6"
Subgrade below proposed streets should be prepared in accordance
with the recommendations discussed in the "Site Grading, Excavation
and Utilities" section of this report. Concrete pavement should be
placed directly on the subgrade that has been uniformly and
properly prepared in accordance with the above recommendations.
All concrete used in the paving shall meet ASTM specifications, and
all aggregate shall conform to ASTM C 33 specifications. The
concrete should be designed with a minimum modulus of rupture of
six hundred fifty (650) pounds per square inch in twenty-eight (28)
days. It is recommended laboratory mix designs be performed to
-8-
I�
Terracon
determine the proper proportions of aggregates, cement and water
necessary to meet these requirements. It is essential the concrete
_ have a low water -cement ratio, an adequate cement factor, and
sufficient quantities of entrained air. Joints should be carefully
designed and constructed in accordance with City of Fort Collins
j "Design Criteria and Standards for Streets" specifications to
I� ensure good performance of the pavement. It is recommended all
concrete pavement be placed in accordance with City of Fort Collins
and/or Colorado Department of Transportation specifications. If
paving is done during cold weather, acceptable cold weather
procedures as outlined in the City of Fort Collins specifications
should be utilized. The concrete pavement should be properly cured
and protected in accordance with the above specifications.
Concrete injured by frost should be removed and replaced. It is
i recommended the pavement not be opened to traffic until a flexural
I� strength of 400 pounds per square inch is obtained or a minimum of
14 days after the concrete has been placed.
GENERAL COMMENTS
This report has been prepared for the exclusive use of our
client for specific application to the project discussed and has
been prepared in accordance with generally accepted geotechnical
engineering practices. No warranty, express or implied, is made.
This report has been prepared to aid in the evaluation of the
street grades and to assist the engineer in the design of this
project. In the event that any changes in the design of the street
1 grades or their locations are planned, the conclusions and
recommendations contained in this report will not be considered
valid unless said changes are reviewed and conclusions of this
report modified or approved in writing by Empire Laboratories,
Inc., the geotechnical engineer of record.
Terracon
Every effort was made to provide comprehensive site coverage
through careful locations of the test borings, while keeping the
site investigation economically viable. Variations in soil and
ground water conditions between test borings may be encountered
during construction. In order to permit correlation between the
reported subsurface conditions and the actual conditions
encountered during construction and to aid in carrying out the
plans and specifications as originally contemplated, it is
recommended that Empire Laboratories, Inc. be retained to perform
continuous construction review during the excavation and foundation
phases of the work. Empire Laboratories, Inc. assumes no
responsibility for compliance with the recommendations included in
this report unless they have been retained to perform adequate on -
site construction review during the course of construction.
I —10—
TEST BORING LOCATION PLAN
g5?-F4::7�I E � ► r:: nHA�5
i L4Co L 41
L45 Ld$
n1
L44 L4 or
IL43- L5� I
L5v L55 L5q L53 L52 L51
L 57
1 L5g LDS
L5�► �—� Ltcco
Lxo7
L&3
L 400 Loos
UoI
L�2
L78 w i
t„ L 77 L 70
L71
LSo, La L74o
L82 0.2
�v5E5-�arl6 c-� 05 L72
I
L86 4 L83 L74- L73 I
A �)
LJU/aL•� I'�Zar�i �u
A-2
EMPIRE LABORATORIES, INC. _
R
UN
REPORT
OF A
PAVEMENT DESIGN
FOR
STONE RIDGE VILLAGE P.U.D. PHASE II
FORT COLLINS, COLORADO
THE KAPLAN COMPANY
FORT COLLINS, COLORADO
PROJECT NO. 2093-5030
EMPIRE LABORATORIES, INC.
A DIVISION OF THE TERRACON COMPANIES INC.
301 NORTH HOWES STREET
FORT COLLINS, COLORADO 80521
TABLE OF CONTENTS
Table of Contents ................................. i
Letter of Transmittal .............................
Report ............................................ 1
Appendix A ........................................ A-1
Test Boring Location Plan A-2
Key to Boring Logs ........................... A-3
Log of Borings .................................. A-4
Appendix B........................................ B-1
Hveem Stabilometer Data ......................... B-2
Summary of Test Results ......................... B-3
AppendixC........................................ C-1
i
Empire Laboratories, Inc.
A Division of The Terracon Companies, Inc.
P.O. Box 503 • 301 No. Howes
Fort Collins, Colorado 80522
(303) 484-0359
FAX No. (303) 484-0454
February 26, 1993
The Kaplan Company, Inc.
1060 Sailors Reef
Fort Collins, Colorado 80525
Attention: Mr. Les Kaplan
Gentlemen:
We are pleased to submit our Report of a Pavement Design prepared
for the proposed streets for Phase II of Stone Ridge Village
located on Horsetooth Road in east Fort Collins, Colorado.
The accompanying report presents our findings in the subsurface and
our recommendations for pavement design based upon these findings.
Very truly yours,
EMPIRE LABORATORIES, INC. �' ` 75 `0' `
ALPv 8
'LPL 0 ��)
Neil R. errod
Senior Engineering Geologist
Reviewed by:
TER
S?„
ice•
P Hoag;
Chester C. Smith, P.E. - 1:6 o
0ZZ
Division Manager o 412r3
cic
cc: RBD, Inc. - Mr. Stan Meyers
Offices of The Terracon Companies, Inc. 1 i Geotechnical, Environmental and Materials Engineers
Arizona: Tucson ■ Colorado: Colorado Springs, Denver, Ft. Collins, Greeley, Longmont ■ Idaho: Boise
Illinois: Bloomington, Chicago, Rock Island ■ Iowa: Cedar Falls, Cedar Rapids, Davenport, Des Moines, Storm Lake
Kansas: Lenexa, Topeka. Wichita ■ Minnesota: St. Paul ■ Missouri: Kansas City ■ Nebraska: Lincoln, Omaha
Oklahoma: Oklahoma City, Tulsa ■ Texas: Dallas ■ Utah: Salt Lake City ■ Wyoming: Cheyenne
QUALITY ENGINEERING SINCE 1965
REPORT
OF A
PAVEMENT DESIGN
SCOPE
Terracon
This report presents the results of a pavement design prepared
for the proposed streets located in Stone Ridge Village Phase II in
east Fort Collins, Colorado. The scope of the project included
test borings and laboratory testing of samples obtained from these
borings.
The objectives of this study were to (1) determine the soil
and ground water conditions at the site, (2) develop criteria for
determining pavement design, and (3) make recommendations regarding
pavement types and thicknesses for the proposed streets to be
constructed at the site.
SITE EXPLORATION
The field exploration, carried out on February 19, 1993,
consisted of drilling, logging, and sampling four (4) test borings.
The test borings were located by Empire Laboratories, Inc. from
existing property pins using conventional chaining methods. The
locations of the test borings are shown on the Test Boring Location
Plan included in Appendix A of this report. Boring logs prepared
from field logs are shown in Appendix A. These logs show soils
encountered, location of sampling and ground water at the time of
the exploration.
The borings were advanced with a four -inch diameter,
continuous -type, power -flight auger drill. During the drilling
operations, a geotechnical engineer from Empire Laboratories, Inc.
was present and made continuous observations of the soils
encountered.
' -1-
Terracon
SITE LOCATION AND DESCRIPTION
The Phase II portion of the site is located directly north of
the Phase I portion of the project on Horsetooth Road in east Fort
Collins, Colorado. More particularly, the site is described as
Stone Ridge Village P.U.D., Phase II, situate in the Southeast 1/4
of Section 29, Township 7 North, Range 68 West of the Sixth P.M.,
City of Fort Collins, Larimer County, Colorado.
The site consists of fallow farmland which is sparsely
vegetated with grass and weeds. The majority of the site has been
stripped of topsoil. The area is relatively flat and has minor
drainage to the south-southeast. The Phase I portion of the
project is located to the south and west. Existing farmland is
located to the north and east.
LABORATORY TESTS
Samples from the test borings were subjected to testing in the
laboratory to provide a sound basis for evaluating the physical
properties of the soils encountered. Moisture contents, dry unit
weights, unconfined compressive strengths, laboratory resistivity,
pH, sulfides, oxidation-reduction potential, and the Atterberg
limits were determined. A summary of the tests results is included
in Appendix B. A Hveem stabilometer test was run to determine the
"R" value of representative subgrade material at the site, and a
curve showing this data is included in Appendix B.
SOIL AND GROUND WATER CONDITIONS
The soil profile at the site consists of strata of materials
j arranged in different combinations. In order of increasing depths,
l they are as follows:
no=
Terracon
(1) Silty Topsoil: The area tested is overlain by a six (6)
inch layer of silty topsoil. The topsoil has been
penetrated by root growth and organic matter and should
not be used as a bearing soil or as a fill and/or
backfill material.
(2) Lean Clay: A layer of brown lean clay underlies the
topsoil and extends to depths of four and one-half (4-
1/2) to six (6) feet below the surface. The clay is
moderately plastic, is moist and exhibits low subgrade
characteristics.
(3) Sandy Lean Clay: A layer of tan to red sandy lean clay
underlies the upper clay and extends to the sand with
gravel stratum below and/or the depths explored. The
lower clay contains varying amounts of sand, traces of
gravel, is moist and medium stiff.
(4) Sand with Gravel: This stratum was encountered in
( Borings 2 and 3 at depths of twelve (12) to thirteen (13)
feet below the surface and extends beyond the depths
explored. The sand contains varying amounts of fine to
medium gravel, is wet, medium dense and poorly graded.
(5) Ground Water: Six days after drilling, free ground water
was encountered at the site at depths of eleven (11) to
twelve and one-half (12-1/2) feet below the surface.
Water levels in this area are subject to change due to
seasonal variations and irrigation demands on and
adjacent to the site.
-3-
Terracon
RECOMMENDATIONS AND DISCUSSION
It is our understanding that Jewelstone, Rosestone and
Jadestone are residential streets ending in cul-de-sacs. Graystone
Court will extend through the project area to a future development
to the north. At the time of the site exploration, traffic data
for Graystone Court was not available. However, the other streets
are considered to be local residential streets. We further
understand that minor amounts of cut and fill are proposed, and an
underdrain system will be constructed in the Istreets below the
proposed sewer. The drainage system will connect to the existing
drainage system below Fieldstone Drive. The drainage system
should be properly designed and approved by the City of Fort
Collins.
Site Grading Excavation and Utilities
It is recommended the upper six (6) inches of topsoil
encountered at the site be stripped and stockpiled for reuse in
planted areas. The upper six (6) inches of the natural subgrade
below should be scarified and recompacted between optimum moisture
and two percent (2%) wet of optimum moisture to at least ninety-
five percent (95%) of Standard Proctor Density ASTM D 698-78. (See
Appendix C.)
All fill should consist of the on -site soils or imported
material having an "R" value greater than 5, and this material
should be approved by the geotechnical engineer. Fill placed at
the site should be placed in uniform six (6) to eight (8) inch
lifts and compacted between optimum moisture and two percent (2%)
wet of optimum moisture to at least ninety-five percent (95%) of
Standard Proctor Density ASTM D 698-78. The finished subgrade in
cut sections below streets should be scarified a minimum of six (6)
inches and recompacted between optimum moisture and two percent
-4-
r
L'
I`
� Terracon
t
(2%) wet of optimum moisture to at least ninety-five percent (95%)
li of Standard Proctor Density ASTM D 698-78. Finished subgrade below
all pavement should be placed a minimum of three (3) feet above
existing ground water, or the area should be dewatered to allow for
a minimum of three (3) feet between the ground water and the
I� pavement subgrade. In areas where subgrade compaction cannot be
met due to wet or unstable conditions, the subgrade should be
Ii stabilized by use of granular pit run or by geotextiles, lime, fly
ash, kiln dust or by other suitable means.
All excavations should be dug on safe and stable slopes. The
slope of the sides of the excavations should comply with local
codes or OSHA regulations. Where this is not practical, sheeting,
shoring and/or bracing of the excavation will be required. The
sheeting, shoring and bracing of the excavation should be done to
prevent sliding or caving of the excavation walls and to protect
construction workers and adjacent structures. The side slopes of
the excavation or sheeting, shoring or bracing should be maintained
under safe conditions until completion of backfilling. In
addition, heavy construction equipment should be kept a safe
distance from the edge of the excavation.
Where utilities are excavated below ground water, dewatering
will be needed during placement of pipe and backfilling for proper
construction. All piping should be adequately bedded for proper
load distribution. Backfill placed in utility trenches in open and
planted areas should be compacted in uniform lifts between optimum
moisture and two percent (2%) wet of optimum moisture to at least
ninety percent (90%) of Standard Proctor Density ASTM D 698-78 the
full depth of the trench. Backfill placed in utility trenches
under roadways and paved areas should be compacted between optimum
moisture and two percent (2%) wet of optimum moisture to at least
ninety-five percent (95%) of Standard Proctor Density ASTM D 698-
78.