HomeMy WebLinkAboutFOSSIL CREEK ESTATES PUD PRELIMINARY - 50 92D - CORRESPONDENCE - STAFF'S PROJECT COMMENTSCommu,utyPlanning and Environmental services Planning Department City of Fort Collins September 27, 1993 Jim Sell Jim Sell Design 117 E. Mountain Ave. Fort Collins, CO 80524 Dear Jim, Staff has reviewed your submittal for Fossil Creek Estates PUD- Preliminary and offers the following comments: 1. US West will provide telephone service in accordance with the rates and tariffs on file with the Colorado Public Utilities Commission. The developer is responsible for provision of all trench, street crossings, and ditch crossings for telephone facilities within the subdivision, and the developer pays up front construction costs for facilities within the development.. 2. Any relocation of existing telephone facilities required by these plans will be paid for by the developer. 3. Review of these plans should not be construed as a commitment that telephone facilities sufficient to serve this project are presently available. 4, Telephone facilities generally occupy rear lot utility .easements, which must be located on terrain which permits trenching operations. US West would require rear lot easements on all lots. 5. A 15' by 30' easement' for three large telephone. equipment cabinets will be required in the general vicinity of the northeast corner of the development or in Tract A. 6. Shade trees on South Shields Street must to conform to tree/street light standards and separation requirements. 7. Please refer to comments on the utility plans and attached letter for Fort Collins -Loveland Water and South Fort Collins Sanitation District comments. The planshave been forwarded to the engineering consultant.. 8. 'Public Service company may want to install a gas feeder main in the 20' emergency access easement that straddles the common lot line between lots 7 and 8. The final plat needs to dedicate this as 1120' emergency access easement and utility easement". This gas feeder- main will also have to be 281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (303) 221-6750 y,. installed in a portion of the 15' wide space between west curb and west right-of-way line of S. Shields Street. Planting of trees in this space will have to be coordinated closely with PSC so that no trees are closer than 4' to any gas line, as you have noted on the plans. 9. Poudre Valley REA has an existing 12470 Volt, three-phase, overhead power line running east and west just south of the Section line in the North 1/2 of Section 10, Township 6 North, Range 69 West, County of Larimer. Any conflicts that may occur which result in a request to relocate this power line will be at the expense. of the property developer/owner. 10. Much of this project exceeds the 660' requirement, for a single point of access. Poudre Fire Authority has discussed this with the developer and the plan indicates an acceptable solution for the easterly half of the project. The western half, west of Cliffrose Court must be designated as a future phase with development conditioned on securing a full street access to the west. Include a note to this effect on the plans, it should be clear that completion of Phase 2 is not possible.until there is a connection to the west. 11. The street name "Bluestein Drive" already exists in Miramont PUD south of PACE. "Cliffrose" already exists in Paragon Point and "Yarrow" already exists in the Redwood/Conifer area. 12. The circle street must be designated as east and west for addressing purposes. 13. No phasing was shown on the site plan or utility plans. 14. The title should be changed, it says Preliminary and Final, and Phase 4? 15. No plat was submitted. A preliminary plat should be submitted with the revisions. 16. The width transitions on Fossil Creek Drive do not meet City standards. 17. An updated soils report needs to be submitted. Engineering and Stormwater have concerns about the high groundwater, unstable soils, suitability for development, presence of bedrock, expansive nature of the soils, and the need for engineered foundation and de -watering systems. There is also a .question of water quality for surface detention, given the presence of significant wetlands. Further soils investigation is required. The Aspen Ridge soils report needs to be expanded upon to include the entire area and the above concerns. If you have questions about what the City is looking for, please contact Mike Herzig at 221-6750. Additional Stormwater Utility comments will be forwarded to the engineering consultants. i8. Streets and intersections must meet City Street standards for intersections, curves, transitions,: grades, ramps etc. or.a formal variance, submitted by a licensed engineer, must be submitted and approved by the City, prior to the Planning and Zoning Board hearing. 19. Parkland fees are $779.00 per dwelling unit and are collected at the time of building permit issuance. 20. Natural Resources needs a statement regarding the expected impacts of this developmenton existing wetlands, including hydrologic and groundwater impacts. Natural Resources feels that some of the wetlands were not included on the wetlands mapping shown on the plans, in the vicinity of Lots 25-2'9. Otherwise, the wetlands mapping appears essentially.correct. Natural Resources will investigate further between preliminary and final stages of review. Please submit a written statement from the wetland consultant certifying that the wetlands mapping is correct. 21. A statement of intent, regarding mitigation for all wetland areas to be disturbed, needs to be submitted. Notes should'be included on the plans indicating what will be allowed to occur in the wetlands areas. Will these areas be placed in conservation easements? How will you guarantee to the City that these areas will remain undeveloped, if that is the intent? 22. The entrance road is shown on City Open Space. Further discussions need to occur with Natural Resources, Planning, and Parks and Recreation prior to the Planning and Zoning Board hearing. The City will have to approve off -setting mitigation measures for use of City property €h 4 .dedicated public right-of-way. This area will have to..be shown on the, plat and the City will have to sign the plans and plat. 23.. Please include fence and entry wall details for the Shields Street area. 24. Please verify that lots 68, 59, and 104 are truly solar oriented lots. It looks like they are right at 3.0 degrees. It looks like Lots 1, 35, and 58 are solar lots and.that Lot 30 could be, with some redrawing of lot lines. Lots 110, 34 and 32 are not solar lots by my calculations. It also appears that there are 130 lots total, so you would need to have a minimum of 84 solar lots. Staff highly recommends that you _provide at least the minimum number of solar lots. Given the open space areas throughout the site, it should be possible to reconfigure some lot lines to achieve south property lines along open space areas which would meet the definition. If this is not possible, a formal variance request must be submitted to the City, explaining your rational for the variance. 25. Will the pedestrian/equestrian trails be constructed with this development? Will the trail be located in, easements or tracts? Provide a detail of the trail, showing construction materials, widths, etc. Will the canal be in a separate tract or in easements on individual lots? Staff prefers the former. 26. Natural. Resources has some concerns about the trail through the wetland areas. It would be preferable if these trails were not improved (paved), unless the trails were to loop through the development (for example, along the rear lot lines of Lots 77 through 94). It is likely that any trails in the Open Space Area near this development, will not be paved and therefore it would be awkward to have a paved. trail end, unless there was some way to transition the paved section into a non -paved trail in the Open Space Area. But staff feels that paved trails should go somewhere or loop. Please discuss your trails concept with Parks and Recreation and Natural Resources. 27. Is Lot 87 missing on.the site plan? 28. A temporary cul-de-sac will be required at the "future connection" to the west,, if Lot 42 is to be constructed on with the first phase. Otherwise, there should be a note indicating that Lot 42 is part of Phase 2, and no. building permit can be issued prior to completion of the street connection. 29. Are you planning to dedicate the Wetland Area to the City by separate document, prior to the Planning and Zoning Board hearing of the final plans? Has Natural Resources agreed to this? If the wetlands areas are fully dedicated to the City prior to final, then the area can be taken out of the density calculations. If not, the area must be included in the gross density calculations. 30. If the project does not meet the minimum density of 3 DU/ac a formal variance request must 'be submitted. The variance request should mention the condition of annexation on the eastern half of the site which allowed a density of 1.5 DU/ac. 31. Please submit information on how grading of lots on significant slopes will be handled, water quality control of the run-off, and how erosion control will be handled. Notes should be placed on the plans addressing overlot grading and disturbance of sensitive areas. 32. Staff recommends a drought tolerant grass mix along Shields Street and for the sodded open space areas within the development. 33. It is possible that a variance to the density point chart will also be required. Technically, the project earns only the 20 points for being near the park/.open space area. Technically the contiguity points are for existing urban development. Scenic Knolls and the Open Space Area do not meet the definition. Also points for permanent open space are for off- site open space. Points for recreational use must meet the' definition of recreational space in the LDGS. Active open space is for the use of more than 3 families, and must be a parcel not less than 10,000 sq. ft. and not less than 50 linear feet at the smallest dimension. Public dedications may not contribute to the active open space area. Partial credit may be given to active open space which are for flood control or areas encumbered by flowage, floodway, or drainage easements (possibly the canal would fit in here, but it is not a tract) . It is very possible for single family homes to exceed the minimum energy code of the City of Fort Collins. I would suggest that you look into a 10% reduction (through insulation, high efficiency furnaces, etc.) and achieve your additional 10 points there. You need a minimum of 30 points for 3 DU/ac. 34. The Scenic Knolls Ditch Company will be signing off on the utility plans, so they should be included in any discussions about drainage, engineering, landscape treatment along the ditch, etc. This concludes staff comments at this time. In order to stay on schedule for, the October 25, 1993 Planning and Zoning Board hearing, please note the following deadlines: Plan revisions are due October 6, 1993 by 12:00 noon. PMTIs, colored renderings, and 10 prints are due October 18th. Final mylars and other documents are due October 22nd. Please be aware that if a development agreement and utility plans are required with this project, these documents and plans must be signed prior to the Planning and_Zoning Board Hearing. If not, a condition will be placed on the project giving you 60 days to finalize the plans and agreement, after which time, you must submit a request for an extension from the Planning and Zoning Board. If you have any questions about these comments or would like to schedule a time to meet to discuss them, please contact me at 221- 6750. Sincerely, Kirsten Whetstone Project Planner cc: Kerrie Ashbeck, City Engineering Kate Mailers, City Stormwater Utility. Shear Engineering Corp. Carter Ewing, applicant File �Gotiylxs-Low � o 7 w d 9TE� DIS't�`~G� M E M O SOUTH FORT COLLINS Sanitation District TO: Kirsten Whetstone City of Fort Collins Planning Department FROM: Mr. Terry Farrill, Systems Engineer r7 DATE: September 15, 1993 RE: FOSSIL CREEK ESTATES PUD - PRELIMINARY The Fort Collins -Loveland Water District and the South Fort Collins Sanitation District have reviewed the above mentioned project and submit the following comments: 1. The entire property will be required to petition into the South Fort Collins Sanitation District prior to the approval of the construction drawings. 2. The engineer should contact the Fort Collins - Loveland Water District regarding the installation and location of a pressure regulating valve. 3. A 12" water line will be required from Taft Hill Road to Shields Street. The Fort Collins -Loveland Water District and the South Fort Collins Sanitation District are willing and able to provide service provided all District requirements are satisfied. Please do not hesitate to contact me at 226-3104 if you have any questions or require additional information. xc: Michael DiTullio District Manager 4700 South College Avenue ...p Fort Collins, Colorado 80525 Telephone 226-3104 - 669-43219-432 FAX (303) 226-0186