September 19, 2025
Katherine Herr
426 E OAK ST
Fort Collins, CO 805242950
RE: ADU at 426 E Oak Street, BDR250018, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of ADU at 426 E Oak Street. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Marissa Pomerleau via phone at (970) 416-8082 or via
email at mpomerleau@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Marissa Pomerleau mpomerleau@fcgov.com (970) 416-8082
Topic: General
Comment Number: 1
09/16/2025: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email
correspondence with other reviewers and keep me informed of any phone
conversations. Thank you! Acknowledged.
Comment Number: 2
09/16/2025: SUBMITTAL:
As part of your submittal, a response to the comments provided in this letter and
a response to plan markups is required. The final letter is provided to you in
Microsoft Word format. Please use this letter to insert responses to each
comment for your submittal, using a different font color. Please use the markups
to insert responses to each comment on plans. Please do not flatten markup responses.
2
Provide a detailed response for any comment asking a question or requiring an
action. Any comment requesting a response or requiring action by you with a
response of noted, acknowledged etc. will be considered not addressed. You
will need to provide references to specific project plans, pages, reports, or
explanations of why comments have not been addressed [when applicable]. Acknowledged.
Comment Number: 3
09/16/2025: SUBMITTAL:
Correct file naming is required as part of a complete submittal. Please follow
the Electronic Submittal Requirements and File Naming Standards found here:
https://www.fcgov.com/developmentreview/files/electronic-submittal-requiremen
ts-and-file-naming-standards_v1_8-1-19.pdf?1703783275
File names should have the corresponding number, followed by the file type
prefix, project information, and round number.
For example: 1_SITE PLAN_Project Name_FDP_Rd1.
A list of numbers and prefixes for each file can be found at the link above. Acknowledged.
Comment Number: 4
09/16/2025: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be removed
from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set, and these
must be removed prior to submittal as they can cause issues with the PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove
this feature, type "EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and
newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarticles/
sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-AutoCAD.html Acknowledged.
Comment Number: 5
09/16/2025: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced
notice as possible. Acknowledged.
Comment Number: 6
09/16/2025: INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the expiration of your project.
Comment Number: 7
09/16/2025: INFORMATION:
ANY project that requires four or more rounds of review would be subject to an
additional fee of $3,000.00. Acknowledged.
Comment Number: 8
09/16/2025: NOTICE:
A Development Review sign will be posted on the property. This sign will be posted through
the final decision and appeal process. A request for the removal of signs will be made by your
Development Review Coordinator at the appropriate time. Acknowledged.
3
Comment Number: 9
09/16/2025: FOR RECORDING – PLAT AND PLANNING SET:
Could you please update the City signature blocks on the Plat and Planning
Set? Instead of using "this _______ day of ______A.D., 20____," could you opt
for "on this day, ____________" for the date? This alternative format facilitates
smoother date input with digital signatures. They read as you’ve noted. See G0.00.
Please update the Signature Line, from "Director" to CDNS Director or
Designee OR Director of Community Development and Neighborhood Services
or Designee. Changed – see G0.00.
Comment Number: 10
09/16/2025: FOR APPROVAL:
All "For Final Approval / For Approval" comments need to be addressed and
resolved prior to moving forward with the final documents and recording of this
project. I will provide a recording checklist and process information when we
are closer to this step. Acknowledged.
Comment Number: 11
FOR APPROVAL:
The Director shall issue a written decision to approve, approve with conditions,
or deny the development application based on compliance with the standards
referenced in Step 8 of the Common Development Review Procedures (Section 6.3.8).
The written decision shall be mailed to the applicant, to any person who provided comments
during the comment period and to the abutting property owners and shall also be posted on
the City's website at fcgov.com/developmentreview/proposals Acknowledged.
Comment Number: 12
09/16/2025: FOR APPROVAL:
Once the decision has been finalized by the Director, there is a two-week
appeal period from the date of the signed decision. The project is not able to be
recorded until it is confirmed there are no appeals. Acknowledged.
Department: Planning Services
Contact: Arlo Schumann aschumann@fcgov.com 970-221-6599
Topic: General
Comment Number: 1
09/16/2025: For Recording: Make sure any code references in the plan set are
referencing current LUC sections. Code sections have been checked using linked code sections at
https://www.fcgov.com/planning-development-services/luc. One change was made in the land use table on G0.00 because some
numbering had changed.
Department: Engineering Development Review
Contact: Shawn Mellinger smellinger@fcgov.com
Topic: General
Comment Number: 1
09/10/2025: FOR APPROVAL:
Due to Riverside Ave being a 4-lane arterial, a total of 15ft in utility easements
4
along that frontage needs to be dedicated. Please revise the plat to add an
additional 6 ft along the . Plat has been revised. See plat. The ADU has been moved 2’ west and 1.5’
south in order to have the roof eave clear this newly required wider easement. That change is reflected in all applicable views of
the model.
Comment Number: 2
09/10/2025: FOR APPROVAL:
The utility and site plans show parking spaces, but the vehicle access from the
alley is not clearly depicted. Please show the existing or proposed access
route from the alley to the parking on all proposed depictions. This has been updated in the Revit model
and now shows in all applicable views. The 18’ width of the parking spaces has been extended to connect to the alley.
Comment Number: 3
09/16/2025: FOR APPROVAL:
The submitted Utility Plan is not standard. Given what is being proposed, a
standardized Utility Plan signed by a licensed Civil Engineer will not be
required. Since it is not signed or sealed by a licensed engineer, it should
instead be labeled as a Site Plan to avoid confusion with official engineering
documents. Drawing title has been changed. See C2.01.
Comment Number: 4
09/10/2025: FOR APPROVAL:
Please address all redlines on the utility plans and plat. Corrections have been made. See C2.01 and
the plat.
Department: Historic Preservation
Contact: Jim Bertolini jbertolini@fcgov.com 970-416-4250
Topic: General
Comment Number: 1
09/16/2025: INFORMATION - CODE REQUIREMENTS WHEN A CITY
LANDMARK IS ON THE PROPERTY:
If the property in question is a City Landmark, or a contributing building in a
Landmark District, then all exterior modifications and infill construction on the
site must meet the City’s adopted Standards for the treatment of historic
properties (Municipal Code 14, Article IV). In this case, because the property is
protected by ordinance, Preservation staff or the Historic Preservation
Commission are decision-makers on exterior alterations. Acknowledged.
Comment Number: 2
FOR BUILDING PERMIT – PLAN OF PROTECTION:
A plan of protection for all nearby historic resources is required to be submitted
to Historic Preservation. This plan will need to detail the particular
considerations and protective measures that will be employed to prevent
short-term and long-term material damage and avoidable impact to identified
historic resources within the 200-foot area of adjacency from demolition, new
construction, and operational activities, as well as any additional requirements
for rehabilitation, long-term stabilization and interpretation of historic resources.
Once at the permitting stage, this Plan would cover equipment and material
staging to ensure protection of the historic house and lime kiln on the site, and
ensure adequate communication channels between the project foreperson and
5
City Preservation staff. The plan of protection was submitted as part of the initial BDR submittal. Also,
the fencing referenced in that plan is graphically shown on drawing 2/C2.01 labeled Construction Logistics Plan.
Comment Number: 3
09/16/2025: FOR APPROVAL – HISTORIC PRESERVATION COMMISSION -
WAIVED (citations and process corrected 9/17/2025):
The applicant is required to seek an approval from the HPC for projects on City
Landmarks. The approval addresses compliance of the development with
Chapter 14, Article IV of the Municipal Code. Staff has the discretion to waive
that requirement and provide staff approval. The HPC meets every third
Wednesday of the month.
The HPC already approved this design (and preferred it) in late 2023. Staff will
confirm details are generally matching to that Certificate of Appropriateness
already issued by the HPC at that time and assuming no concerns, will re-issue
the same with the updated plans. Acknowledged.
Department: Traffic Operation
Contact: Steve Gilchrist sgilchrist@fcgov.com 970-224-6175
Topic: General
Comment Number: 1
09/11/2025: INFORMATION: The requirement of a Transportation Impact
Study was waived within the Conceptual Review process. Acknowledged.
Department: Stormwater Engineering – Erosion Control
Contact: Andrew Crecca acrecca@fcgov.com
Topic: Erosion Control
Comment Number: 1
08/28/2025: INFORMATION:
Based upon the submitted materials it has been determined that this project;
will disturb less than 10,000 sq. ft., is not proposed to be in a sensitive area,
has no steep slopes (greater than 3H:1V) within or adjacent to the project, and
is not part of a larger common development that will or is under construction.
Therefore, Erosion Control Material submittal is not needed. Acknowledged. If this project
substantially changes in size or design where the above criteria now apply,
erosion control materials should be submitted. Although the project at this time
requires no erosion control material submittal, the project still must be swept
and maintained to prevent dirt, saw cuttings, concrete wash, trash & debris,
landscape materials and other pollutants from the potential of leaving the site
and entering the storm sewer at all times during the project in accordance with
City Code §26-498. If complaints are received or site observation of the project
seems not to prevent the pollutants from being discharged, The City may
require the project to install erosion and sediment control measures. Nearby
inlets that may be impacted by the pollutants, in particular dirt, should be
protected as a good preventative practice and individual lots should be
protected from material escaping onto the sidewalk through the use of straw
wattles or silt fence. If at building permit issuance any issues arise, please email
6
erosion@fcgov.com to help facilitate getting these permits signed off. Acknowledged.
Department: Stormwater Engineering – Water Utilities
Contact: Dan Mogen dmogen@fcgov.com 970-305-5989
Topic: General
Comment Number: 1
09/15/2025: FOR APPROVAL:
Please see redlines. I encourage you to reach out with any questions or to
review potential revisions, and I’d be happy to set up a meeting or conference
call to do so. Acknowledged.
Comment Number: 2
09/15/2025: FOR APPROVAL:
Please remove AutoCAD SHX comments from all PDF plans.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the
PDF file. The default setting is "1" ("on") in AutoCAD. To change the setting
and remove this feature, type "EPDFSHX" in the command line and enter "0".
Read this article at Autodesk.com for more tips on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarticles/
sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-AutoCAD.html Acknowledged.
Comment Number: 3
09/15/2025: FOR RECORDING:
Please provide stamped, signed and dated copies of the drainage memo and
grading plan. Acknowledged.
Comment Number: 4
09/17/2025: FOR APPROVAL:
The drainage memo and grading plan document the changes in impervious as
well as the existing and proposed grading and drainage for the site. Please
remove similar documentation from the "utility plans." The duplicative table has been removed and the
drawings titles and annotations have been modified so they do not reference pervious / impervious. The areas have been updat ed
to reflect the move of the ADU 2’ west and 1.5’ south in order to have the roof eave clear the 15’ easement newly required as noted
in the Engineering Development Review above .
Department: Water-Wastewater Engineering
Contact: Dan Mogen dmogen@fcgov.com 970-305-5989
Topic: General
Comment Number: 1
09/04/2025: INFORMATION:
There is a sewer main in Oak Street in addition to the sewer main in Riverside
Avenue. Neither main is directly adjacent to this property. The main in Oak
extends west from the alley south of 414. It is likely service to 426 connects to a
manhole at this location; however, that has not been confirmed. As indicated in
7
the response letter, it is not necessarily consequential at this time since service
will be extended from the existing residence. Acknowledged.
Comment Number: 2
09/04/2025: INFORMATION:
Water/Wastewater Fees are estimated to be $1984 for the extension of
services to the ADU (2025 rates). This will update monthly billing to duplex
rates for service of the two dwelling units. These fees are paid with building
permit, and a covenant agreement will also be required at this time to allow
service to both dwelling units (agreement states separate services will be
required if the property were to subdivide in the future, and a copy of the
agreement template has been emailed).
Please contact me or Utility Fees with any questions. (970) 416 -4252 or
UtilityFees@fcgov.com. Acknowledged.
Department: Light And Power
Contact: Luke Unruh lunruh@fcgov.com 970-416-2724
Topic: General
Comment Number: 1
09/16/2025: INFORMATION:
The ADU would be required to be individually metered and will require its own
service. Electric capacity fees, development fees, building site charges and any
system modification charges necessary to feed the site will apply to this development.
The meter location will need to be coordinated with Light and Power. Please
refer to Section 8 of the Electric Service Standards for additional requirements
for metering. A link has been provided below.
https://www.fcgov.com/utilities/img/site_specific/uploads/ElectricServiceStanda
rds_FINAL_18November2016_Amendment.pdf Acknowledged.
Comment Number: 2
09/16/2025: INFORMATION:
The meter location and connection point shown will work for L&P. L&P will install
the service if there is a clear path without trees or tree roots in the way of the trench.
If L&P deems the service to difficult to install the owner will need to install the service. Acknowledged.
Comment Number: 3
09/16/2025: INFORMATION:
You may contact Luke Unruh with project engineering if you have questions.
lunruh@fcgov.com. You may reference Light & Power’s Electric Service Standards
at: https://www.fcgov.com/utilities/img/site_specific/uploads/electricservicestandar
ds.pdf?1645038437
You may reference our policies, development charge processes, and use our
fee estimator at http://www.fcgov.com/utilities/business/builders-and-developers Acknowledged.
Department: Environmental Planning
Contact: Kristie Raymond kraymond@fcgov.com
Topic: General
Comment Number: 1
8
08/26/2025: No comments. Acknowledged.
Department: Forestry
Contact: Freddie Haberecht fhaberecht@fcgov.com
Topic: General
Comment Number: 1
09/17/2025: FOR INFORMATION
Please to the best of your ability preserve the existing trees on site. Trees add
significant property value and are not easily replaced. Please reach out to
forestry (fhaberecht@fcgov.com) if you would like more information or any
advice on how to best preserve the existing trees on site. Acknowledged.
Department: Park Planning
Contact: Missy Nelson mnelson@fcgov.com
Topic: General
Comment Number: 1
09/13/2025:
INFORMATION:
Thank you for adding comment regarding irrigation to plans.
Both Park Planning & Development (PPD) and Parks Operations and
Maintenance (Parks O&M) comments will be provided by Missy Nelson |
mnelson@fcgov.com | 970.416.8077
Comment Number: 2
09/13/2025: FOR SUBMITTAL:
PLEASE ACCURATELY SHOW PROPERTY LINE IN RELATION TO THE
SIDEWALK AND THE STREET TREES SO CONNECTION FROM PRIVATE
SIDEWALK TO PUBLIC SIDEWALK CAN BE DETERMINED.
CONTRACTOR WILL NEED TO MEET WITH PARKS DEPARTMENT STAFF
TO CONFIRM LOCATION OF SIDEWALK AND PARKS' IRRIGATION WILL
NEED TO BE SLEEVED & REPAIRED. Sidewalk lines sourced from cad of the Tri Peaks ISP have been
added to the site plan on A1.00. Street trees have been located using Google Earth and Street View between the curb and the
sidewalk. Contractor will meet with Parks Department Staff re: irrigation.
Department: PFA
Contact: Marcus Glasgow marcus.glasgow@poudre-fire.org 970-416-2869
Topic: General
Comment Number: 1
09/15/2025: N/A per the direction of the Fire Marshal. Acknowledged.
Department: Internal Services
9
Contact: Russell Hovland rhovland@fcgov.com 970-416-2341
Topic: Building Insp Plan Review
Comment Number: 1
A permit is required for single family house (ADU) construction and shall
comply with adopted codes as amended. Current adopted codes are:
• 2021 International Residential Code (IRC) with local amendments
• Colorado Plumbing Code (currently 2021 IPC) with local amendments
• 2023 National Electrical Code (NEC) as amended by the State of Colorado
• Projects shall comply with the current adopted building codes, local
amendments and structural design criteria can be found here:
https://www.fcgov.com/building/codes Acknowledged.
• New 2024 buildings codes will be adopted in early 2026.
• Please read the residential permit application submittal checklist for complete requirements.
• Snow Live Load: Ground Snow Load 35 PSF.
• Frost Depth: 30 inches.
• Wind Loads: Risk Category II (most structures):
• 140mph (Ultimate) exposure B or Front Range Gust Map published by The
Structural Engineer's Association of Colorado
• Seismic Design: Category B.
• Climate Zone: Zone 5
• Energy Code: 2021 IECC residential chapter Acknowledged.
INFORMATIONAL ITEMS:
• 5ft setback required from property line or provide fire rated walls & openings
for non-fire sprinkled houses per chap 3 of the IRC. 3ft setback is required for
fire sprinkled houses. Acknowledged.
• Fire separation of 10ft between dwellings is required. Acknowledged.
• Bedroom egress windows (emergency escape openings) required in all bedrooms. Acknowledged.
• For buildings using electric heat, heat pump equipment is required. Acknowledged.
• A passing building air tightness (blower door) test is required for certificate of occupancy. Acknowledged.
• For projects located in Metro Districts, there are special additional code requirements for
new buildings. Please contact the plan review team to obtain the requirements for each district.
Acknowledged.
• New IRC code amendment R320 requires dwellings with habitable space on the 1st floor must
provide a visitable bathroom and path to such. Acknowledged.
• The roof must be provided with solar-ready zones at outlined in IRC appendix RB. Acknowledged.
• Energy code requires short hot water supply lines by showing plumbing compactness. Acknowledged.
Note this project will be factory built modular construction and as such will be permitted through both the State of Colorado Division
of Housing for the factory built components, and through Fort Collins for the site built components. An OC letter will be pr ovided as
DOH requires.
Department: Technical Services
Contact: Jeff County jcounty@fcgov.com 970-221-6588
Topic: Plat
Comment Number: 1
09/10/2025: FOR FINAL APPROVAL:
Please make changes as marked in the Technical Services (TS) markup PDF. Changes have been made.
10
See updated plat.
If changes are not made or you disagree with comments, please provide written
response of why corrections were not made. Please provide any responses on
redlined sheets and/or in response letter. If you have any specific questions
about the markups, please contact John Von Nieda at 970 -221-6565 or
jvonnieda@fcgov.com
Topic: Site Plan
Comment Number: 2
09/10/2025: FOR FINAL APPROVAL:
Please revise the legal description as marked. See markups. The legal description has been updated.
See G0.00.
Department: Outside Agencies
Contact: Donna George, Xcel Energy
Topic: General
Comment Number: 1
09/11/2025: INFORMATION:
See attached letter. Attached letter has been reviewed.
Department: Water Conservation
Contact: Emma Pett epett@fcgov.com
Topic: General
Comment Number: 1
09/04/2025: INFORMATION:
Rebates are available for Fort Collins Utilities customers for water and energy
conservation measure such as efficient toilets, low water landscaping and more. Acknowledged.