DEVELOPMENT REVIEW 281 North College Avenue PO Box 580 Fort Collins, CO 80522 970.221.6750 fcgov.com/developmentreview
October 15, 2025
Michael Gornik
Polestar Gardens
850 S Overland Trail #15
Fort Collins, CO 80521
RE: Stenson Minor Subdivision, BDR250001, Round Number 2
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about any
comments, you may contact the individual commenter or direct your questions through the
Project Planner, Clark Mapes, at 970-221-6225 or cmapes@fcgov.com.
Comment Summary:
Department: Planning Services
Contact: Marissa Pomerleau, (970) 416-8082, mpomerleau@fcgov.com
Topic: General
Comment Number: 1
01/22/2025: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me know
and I can assist you and your team. Please include me in all email correspondence
with other reviewers and keep me informed of any phone conversations. Thank you!
(comment read)
Comment Number: 2
01/22/2025: SUBMITTAL:
As part of your re-submittal, a response to the comments provided in this letter and
a response to plan markups is required. The final letter is provided to you in
Microsoft Word format. Please use this letter to insert responses to each comment
for your submittal, using a different font color. Please use the markups to insert
responses to each comment on plans. Please do not flatten markup responses.
Provide a detailed response for any comment asking a question or requiring an
action. Any comment requesting a response or requiring action by you with a
response of noted, acknowledged etc. will be considered not addressed. You will
need to provide references to specific project plans, pages, reports, or
explanations of why comments have not been addressed [when applicable].
(all comments will be addressed)
Comment Number: 3
01/22/2025: SUBMITTAL:
Correct file naming is required as part of a complete submittal. The files included
in the Round 1 submittal did not follow these standards so please be sure to follow
them with your Round 2 submittal.
Please follow the Electronic Submittal Requirements and File Naming Standards
found here:
https://www.fcgov.com/developmentreview/files/electronic-submittal-requirements-
and-file-naming-standards_v1_8-1-19.pdf?1703783275
File names should have the corresponding number, followed by the file type prefix,
project information, and round number.
For example: 1_SITE PLAN_Project Name_FDP_Rd1.
A list of numbers and prefixes for each file can be found at the link above.
(pdf will be name accordingly)
Comment Number: 4
01/22/2025: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and
remove layers. Some of the files included in the Round 1 submittal did not follow
these standards so please be sure to follow them with your Round 2 submittal.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be
removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set, and
these must be removed prior to submittal as they can cause issues with the PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove
this feature, type "EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and
newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarticle
s/sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-AutoCAD.html
(Verified PDFSHX is set to 0)
Comment Number: 5
01/22/2025: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced
notice as possible.
(Resubmittal will be submitted as instructed)
Comment Number: 6
02/04/2025: INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the expiration
of your project.
(comment read)
Comment Number: 7
02/04/2025: INFORMATION:
ANY project that requires four or more rounds of review would be subject to an
additional fee of $3,000.00.
(comment read)
Comment Number: 8
02/04/2025: NOTICE:
A Development Review sign has be posted on the property. This sign will be
posted through the final decision and appeal process. A request for the removal of
signs will be made by your Development Review Coordinator at the appropriate time.
(comment read)
Comment Number: 9
10/08/2025: FOR RECORDING – PLAT:
The City's signature blocks still do not match. Please ensure that the Director's title
match in both the signature line and the approval statement above it.
(revised signature to match)
02/04/2025: FOR RECORDING – PLAT:
Could you please update the City signature blocks on the Plat? Instead of using
"this _______ day of ______A.D., 20____," could you opt for "on this day,
____________" for the date? This alternative format facilitates smoother date
input with digital signatures.
Additionally, kindly ensure there is sufficient space between the signature line and
the title line to accommodate the digital signature.
(City signatures have been changes accordingly)
Comment Number: 10
02/04/2025: FOR FINAL APPROVAL:
The Director shall issue a written decision to approve, approve with conditions, or
deny the development application based on compliance with the standards
referenced in Step 8 of the Common Development Review Procedures (Section
2.2.8).
The written decision shall be mailed to the applicant, to any person who provided
comments during the comment period and to the abutting property owners and
shall also be posted on the City's website at www.fcgov.com.
(comment read)
Comment Number: 11
02/04/2025: FOR FINAL APPROVAL:
If the project is approved by the Director, there is a two-week appeal period from
the date of the decision. The project is not able to be recorded until it is confirmed
there are no appeals.
(comment read)
Comment Number: 12
02/04/2025: FOR FINAL APPROVAL:
All "For Final Approval / For Approval" comments need to be addressed and
resolved prior to moving forward with the final documents and recording of this
project. I will provide a recording checklist and process information when we are
closer to this step.
(comment read)
Department: Engineering Development Review
Contact: Tim Dinger, tdinger@fcgov.com
Topic: General
Comment Number: 1
01/27/2025: FOR APPROVAL:
W. Elizabeth Street is classified as a 2-lane arterial by the City's Master Street
Plan. Therefore, you will need to dedicate a 42-foot 'half' right-of-way (ROW), and a
15-foot width utility easement on your property adjacent to the ROW. This means
an additional 12' of ROW must be dedicated by this plat. Please see LCUASS
Figure 7-3F for more information.
(plat shows 12’ ROW to be dedicated and 15’ UE)
Comment Number: 2
01/27/2025: FOR APPROVAL:
Please add the access easement for the walkway through the site to the plat, and
add "dedicated by separate document, reception #xxx" as a label. Fill in the
reception number when the easement is recorded with the Polestar Village project.
(recorded # added)
Comment Number: 3
01/27/2025: INFORMATION:
Since you are depicting the ditch company's easement on the plat, they will need
to review and most likely sign the plat. We have routed the plat to them for review,
but please reach out to them directly to ensure they have looked at the plat and
have provided any comments they might have.
(ditch easement added)
Department: Technical Services
Contact: Jeff County, 970-221-6588, jcounty@fcgov.com
Topic: Plat
Comment Number: 1
10/02/2025: FOR FINAL APPROVAL - UPDATED:
Please make changes as marked in the Technical Services (TS) markup PDF. If
changes are not made or you disagree with comments, please provide written
response of why corrections were not made. Please provide any responses on
redlined sheets and/or in response letter. If you have any specific questions about
the markups, please contact John Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
(See redlines for response comments)
02/04/2025: FOR FINAL APPROVAL:
Please make changes as marked in the Technical Services (TS) markup PDF. If
changes are not made or you disagree with comments, please provide written
response of why corrections were not made. Please provide any responses on
redlined sheets and/or in response letter. If you have any specific questions about
the markups, please contact John Von Nieda at 970-221-6565 or
jvonnieda@fcgov.com
(all comments addressed)