HomeMy WebLinkAboutReports - Drainage - 10/01/2025Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 1 of 31 PREPARED FOR: Hartford Homes, LLC 4801 Goodman St. Timnath, CO 80547 PREPARED BY: Galloway & Company, Inc. 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 Contact: James Prelog, PE DATE: July 16th, 2025 Revised: October 1st, 2025 BLOOM COMMERCIAL Fort Collins, CO FINAL DRAINAGE REPORT Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 2 of 31 ENGINEER’S STATEMENT “I hereby attest that this report for the final drainage design for the Bloom Commercial was prepared by me or under my direct supervision, in accordance with the provisions of the Fort Collins Stormwater Criteria Manual. I understand that the City of Fort Collins does not and will not assume liability for drainage facilities designed by others.” Herman Feissner, P.E. 0038066 Date For and on behalf of Galloway & Company, Inc. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 3 of 31 I. Introduction ................................................................................................................................................ 4 General Location .............................................................................................................................. 4 Existing/Pre-Project Site Info ........................................................................................................... 4 II. Master Drainage Basin .............................................................................................................................. 5 Overall Basin Description ................................................................................................................. 5 Existing Drainage Facilities .............................................................................................................. 5 Floodplain ......................................................................................................................................... 6 III. Project Description ................................................................................................................................... 7 Existing Conditions ........................................................................................................................... 7 Proposed Conditions ........................................................................................................................ 7 IV. Proposed Drainage Facilities ................................................................................................................... 8 General Concept .............................................................................................................................. 8 Proposed Drainage Basins .............................................................................................................. 9 Detention Pond .............................................................................................................................. 10 Low Impact Development and Water Quality ................................................................................ 11 V. Drainage Design Criteria ........................................................................................................................ 12 Directly Connected Impervious Area (DCIA) ................................................................................. 12 Development Criteria Reference and Constraints ......................................................................... 13 Hydrological Criteria ....................................................................................................................... 13 Hydraulic Criteria ............................................................................................................................ 14 VI. EROSION AND SEDIMENT CONTROL MEASURES .................................................................... 16 Construction Material & Equipment ............................................................................................... 16 Maintenance ................................................................................................................................... 16 VII. Conclusions .......................................................................................................................................... 18 Compliance with Standards ........................................................................................................... 18 Variances ....................................................................................................................................... 18 Summary of Concepts .................................................................................................................... 18 VIII. References .......................................................................................................................................... 19 Appendices: A. Exhibits and Figures B. Excerpts from Reference Materials C. Hydrologic Computations D. Hydraulic Computations E. SWMM Model F. Drainage Maps TABLE OF CONTENTS Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 4 of 31 I. Introduction General Location The proposed Bloom Commercial project site (Site or commercial site) is in the southern region of Bloom. More specifically it is located directly south of Donella Drive and north of East Mulberry Street, just west of I-25, to the east of the Mosaic Subdivision in Fort Collins, Colorado. The overall Bloom development is bordered to the north by East Vine Drive; to the east by the Imu-Tek Animal Health Clinic and undeveloped land; to the south by East Mulberry Street; and to the west by East Ridge Second Filing (i.e., Mosaic Subdivision). The Bloom Commercial site is located in the Northwest Quarter of Section 9, Township 7 N., Range 66 W. of the 6th P.M., City of Fort Collins, County of Larimer, State of Colorado. A vicinity map is included in Appendix A for reference. This report follows a previous report by Galloway & Company, Inc. (GAL), “Final Drainage Report Bloom Filing 1” dated November 2022. Two amendments to the November 2022 report have been filed: - June 2023: “Bloom Filing 1 Amendment – Drainage Modifications”; - January 2025: “Bloom Filing 1 Amendment – Drainage Modifications”. Existing/Pre-Project Site Info The commercial site consists of the area of the overall site that is south of Donella Drive. In the pre- project conditions the land was undeveloped and overlot graded. Pre-project grades across the site vary from 0.5 to 3.0 percent. The commercial site generally drains from north to south. The project site is located within the Cooper Slough/Boxelder Basin and the Cooper Slough channel is located just to the east of the project site. The Lake Canal also cuts across the southwest corner of the overall Bloom site. SWMM basin I from the November 2022 work is not a part of this current work. This basin is located southwest of the Lake Canal. According to the Natural Resources Conservation (NRCS) Web Soil Survey, the commercial site consists of a mix of soil types and Hydrologic Soil Groups (HSG) including: - Ascalon Sandy Loam (17), HSG ‘B’ - Garrett Loam (83%), HSG ‘B’ The soil map generated by the Web Soil Survey can be found in Appendix A. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 5 of 31 II. Master Drainage Basin Overall Basin Description The overall Bloom project site is located in the lower portion of the Cooper Slough Watershed. The master plan for this drainage basin was updated in May of 2021. This report is titled “City of Fort Collins Upper Cooper Slough Basin Selected Plan of Improvements” prepared by Icon Engineering, Inc. (Master Plan). The Cooper Slough drainage basin resides in northeast Fort Collins and unincorporated Larimer County, Colorado. The Master Plan describes it as a long and slender watershed, flowing from north to south, comprising 28 square miles which are tributary to Box Elder Creek and the Cache la Poudre River. The watershed begins at the confluence with Box Elder Creek, which is about one-half mile south of Mulberry Street and slightly west of I-25, and proceeds north for 20 miles to Larimer County Road 80 at a location northwest of the Town of Wellington. The basin has a maximum width of 3.9 miles at a location just south of Wellington. Predominant land uses are characterized by farmland and open space, with development occurring mainly in the southern portion of the watershed, near northeast Fort Collins. The Cooper Slough watershed is divided into upper and lower portions by the Larimer & Weld Canal. The project site is located in the lower portion of the watershed. The Master Plan discusses improvements to the Cooper Slough and Lake Canals including culverts installed in Vine Drive and Mulberry Street (i.e., Highway 14), but these improvements lie outside of the boundaries of this project and therefore are not a part of this project. There will be no changes to the Cooper Slough or Lake Canal as part of this project. The proposed development to the southeast of the project site, Peakview, has included a portion of a box culvert that will eventually divert water from the Lake Canal to the Cooper Slough. The box culvert will be designed, constructed, plugged, and buried until future Master Plan culvert improvements are constructed. Relevant excerpts from the Master Plan are included in Appendix B. Existing Drainage Facilities A historic/existing conditions basin map was developed with the November 2022 report, reference Appendix B, for an excerpt from the report. SWMM was used to determine the existing runoff and the 2- year and 100-year runoff values from the models are included in the basin description below. According to the Master Plan, future development within the area of the site is to “Limit the release (both peak discharge and volume) associated with future development within the Upper Cooper Slough Basin to the 100-year existing condition release rates into the lower Cooper Slough area.” Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 6 of 31 Basin H-3 was established in the November 2022 report and includes the Bloom Commercial site. Basin H-3 (±162 acres, Q2 = 8.7 cfs, Q100 = 52.0 cfs) is associated with the western portion of the site. Runoff currently sheet flows south into the Lake Canal. Floodplain The Cooper Slough runs along the eastern boundary of the overall Bloom project site. According to the Federal Emergency Management Agency (FEMA) Flood Insurance Rate Map Panels 982 (FIRM Number 08069C0982F) effective date December 19, 2006 and Panel 984 (FIRM Number 08069C0984H) effective date May 2, 2012 included in Appendix A, a portion of the site lies within Zone AE of the Cooper Slough, an area subject to inundation by the 1% annual chance 100-yr flood. In Zone AE, the base flood elevations (BFEs) have been determined. A LOMR (FEMA Case No.: 17-08-1354P) became effective February 21, 2019. The LOMR was submitted as a part of a restudy of the Boxelder and Cooper Slough prepared for the Boxelder Stormwater Authority by Ayres Associates. The effective 100-yr floodplain encroaches on a significant portion of the commercial site south of Donella Drive. No development activities are planned to encroach on the effective floodway. All elevations provided are in reference to the NAVD 1988, with Cooper Slough effective 100-yr floodplain water surface elevations ranging between 4930.5 ft and 4960.2 ft adjacent to the overall Bloom project site. The development shall follow floodplain regulations stated in Chapter 10 of the City Code. All structures shall have the elevation of the lowest floor above regulatory flood protection elevations. It is anticipated that no work shall commence within the floodway. A floodplain use permit was submitted to the City of Fort Collins in conjunction with the November 2022 report. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 7 of 31 III. Project Description The Bloom Commercial development encompasses ±35.6 acres and will include the development of higher density residential land uses, commercial use, and associated streets, utilities, and open space. The project site is bordered to the east by Greenfields Court; to the west by existing industrial development; to the north by Donella Drive; and to the south by the Lake Canal and Frontage Road. This report summarizes the drainage facilities for the commercial site including proposed storm drain improvements, Low Impact Development (LID) Best Management Practices (BMPs), Water Quality (i.e., Extended Detention Basin (EDB), and stormwater quantity detention. Existing Conditions The existing project site is ±35.6 acres of undeveloped ground. Existing grades of the Site generally slope from 0.5 to 3.0 percent. Proposed Conditions The proposed Bloom Commercial site will include the development of higher density residential land uses, commercial buildings, associated streets, utilities, and open space. The commercial site drains to the west, southwest, and southeast to (3)-three detention ponds (i.e., G1, H (existing) and J). These (3)- three detention ponds will eventually outfall into the Cooper Slough. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 8 of 31 IV. Proposed Drainage Facilities General Concept Runoff from the developed site will generally be conveyed via overland flow and curb and gutter to a proposed storm drain system that will convey the minor and major event stormwater runoff to on-site detention ponds. There are three (3)-detention ponds proposed within the commercial site to provide water quality (e.g., associated with the remaining 25% of newly added impervious area) and quantity detention. - Pond G1 (proposed) will outfall into proposed Storm A that ties into the existing Cooper Slough Outfall (designed and constructed w/Bloom Filing 1). - Pond H (existing) ties into the existing Cooper Clough outfall. Existing detentions ponds E and G are also included in the commercial site SWMM because they contribute to the total release rate into the Cooper Slough. - Pond J (proposed) will outfall into proposed Storm A that ties into the existing Cooper Slough Outfall (designed and constructed w/Bloom Filing 1). Per GAL’s November 2022 FDR and subsequent June 2023 and January 2025 Bloom Filing 1 Amendment documents, the total allowable release into the Cooper Slough is ±44.4 cfs (i.e., ±222 acres * 0.2 cfs/acre – per accepted variance). The total release from detention ponds A, B, C, and D is ±23.7 cfs; therefore, the allowable remaining release from ponds E (existing), G (existing), G1 (proposed with the commercial site), H (existing), and J (proposed with the commercial site) is ±20.7 cfs. Detention ponds G1, H, and J were analyzed herein using EPA SWMM 5.2. This current work proposes a revision to the above based on a refinement to the SWMM model and area that was not previously included in the allowable release rate calculations. First, the in-series routing of existing detention ponds A and B was re-evaluated running SWMM using Dynamic Wave (DW) routing instead of Kinematic Wave routing. The total release from detention ponds A, B, C, and D is ±22.7 cfs (i.e., ±1.0 cfs reduction from the above). Second, a ±13.65-acre area within the Site area was not included in the original release rate calculations. Therefore, we are proposing an increase of ±2.7 cfs to the accepted variance (see above), ±44.4 cfs, for a total allowable release rate of ±47.1 cfs. The proposed release rate attributable to the Bloom Commercial site and Filing 4 (i.e., ±13.3 cfs), which is inclusive of Pond E, is ±24.4 cfs. A summary of the pond volumes and release rates from the SWMM model is included in Appendix C. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 9 of 31 The commercial site has been divided into three (3)-three larger SWMM basins G1, H, and J. These larger basins were further divided into twenty-nine (29) smaller basins for the purposes of Rational Method calculations. Water Quality will be provided on-site through Low Impact Development (LID) practices located within each of the future tracts/lots and Water Quality Capture (WQCV) within the proposed/existing detention ponds. The City of Fort Collins, per section 2.3.7 Low Impact Development (FCSCM), requires implementation of LID systems following one of the following options: 1) 50% of the newly added or modified impervious area must be treated by LID techniques and 25% of new paved areas must be pervious; or 2) 75% of all newly added or modified impervious area must be treated by LID techniques. There are no off-site (i.e., outside the larger Bloom development project site boundaries) basins impacting the project site. There are no proposed improvements to the Cooper Slough associated with the development of the commercial site. A floodplain permit is to be submitted prior to any work being done within the floodplain. Proposed Drainage Basins Basin G1 Basin G1 encompasses areas of both Bloom Filing 3 and Bloom Commercial. The total area of G1 is approximately 32 acres (i.e., ±33.4 acres in Rational Method and ±32.0 acres in SWMM). We acknowledge there are minor discrepancies between the Rational Method and SWMM basin areas. Our intent is to resolve them as the project moves forward. Specific to the work herein, areas are relative to the SWMM areas. Approximately 21.0 acres of basin G1 are within the Filing 3 site, and approximately 11.0 acres are within the commercial site. This basin includes areas for commercial businesses, associated infrastructure, and open space. In a separate submittal for Tract A, LID design details will be added in support of treating 75% of the newly added impervious area with an LID technique (e.g., ±0.15 ac-ft for a volume-based LID, refer to Appendix C for an example Sand Filter (SF) sizing calculation). The Extended Detention Basin (i.e., ±0.25 ac-ft) within Pond G1 is sized to provide Water Quality Capture Volume (WQCV) for newly added impervious area within Tract A at an assumed developed imperviousness of 80% G1, adjacent Right-of-Way as well as basins associated with Filings 3 and 4 that are not tributary to each Site’s respective WQCV. The estimated WQCV was added to the estimated quantity volume. LID requirements for Filing 3 have been met within Filing 3. Filing 4 met both the WQCV and LID requirements with on-site infrastructure. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 10 of 31 Basin H Basin H comprises approximately 10.7 acres. This area will be developed in the future as commercial. Our intent is for the future developer to meet the CoFC LID requirements locally. The remaining 25% of the newly added impervious area will be treated in an EDB within Pond H (existing). Basin J Basin J comprises approximately 6.9 acres. This area will be developed in the future as higher-density residential (e.g., townhomes). Our intent is for the future developer to meet the CoFC LID requirements locally. The remaining 25% of the newly added impervious area will be treated in an EDB within Pond J (proposed). Detention Pond Each pond will provide volume for quality (i.e., EDB) and quantity. The Final Drainage Report Bloom Filing 1 (November 2022, GAL) presented the release rate methodology for the overall Bloom development that was approved and subsequently revised herein. Two follow-up memorandums by GAL in June 2023 and January 2025, revised the layout of Pond G by splitting it into two detention ponds (i.e., Pond G and Pond G1) and revised the total release rate into the Cooper Slough from detention ponds A, B, C, and D from ±21.9 cfs to ±23.7 cfs, respectively. Per this current work, see above section General Concept for more detail, GAL is proposing to revise allowable release rate into the Cooper Slough to ±24.4 cfs. Ponds G1, H, and J will provide WQCV locally (i.e., EDB). The table below lists the release rates and volumes associated with each detention pond. Refer to Appendices D and E for additional detail regarding the development of the proposed detention pond volumes. Detention Pond (s) 100-year Volume Required (per SWMM)1 Allowable Release Rate Proposed Release Rate (From SWMM Model) E and G EXISTING ±24.4 cfs2 ±13.3 cfs ±24.4** cfs G1 ±6.9 ac-ft / 299,529 ft3 ±10.0 cfs H ±3.3 ac-ft / 142,128 ft3 ±0.6 cfs J ±1.8 ac-ft / 79,523 ft3 ±0.5 cfs 1 Estimated WQCV added to estimated 100-year quantity volume per FCSCM 2 Per updated allowable release rate described herein Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 11 of 31 Low Impact Development and Water Quality The ODP has determined that water quality and detention will be required for the development of the Site. Required Water Quality Capture Volume (WQCV) was calculated using equation 7-1 and Equation 7-2 from FCSCM. The following table is the anticipated amount of the newly added impervious area and a breakdown of the total area treated by an LID or an EDB feature. Basin SWMM Basin Area SWMM % IMP. Preliminary LID and WQCV Area Estimates ft2 acres Newly Added Imp. Area (NAIA), ft2 75% of NAIA for LID, ft2 25% of NAIA for WQCV, ft2 G Site specific LID and WQCV addressed w/Filing 4 (F4), area shown (see right) is tributary to Pond G1 and associated with peripheral F4 basins and RoW. 36,464.1 G1 (total) 1395559.3 32.0 72.5% 1011780.5 758835.4 252945.1 G1 (local) 480048.2 11.0 80.0% 384038.6 288028.9 96009.6 H 464232.3 10.7 80.0% 371385.9 278539.4 92846.5 I 279160.8 6.4 80.0% 223328.6 167496.5 55832.2 J 300263.9 6.9 80.0% 240211.1 180158.3 60052.8 Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 12 of 31 V. Drainage Design Criteria Directly Connected Impervious Area (DCIA) Each step of the Four-Step process is listed below and includes a brief narrative describing the implementation strategy. Step 1 - Employ runoff reduction practices The newly added impervious area associated with developed runoff from the G1 (local), H, and J series of basins will drain to a local LID facility such as a Sand Filter (SF) or ADS StormTech system prior to entering the local on-site detention facilities. Our intent is to provide quantity detention and additive Water Quality Capture Volume (WQCV) for each basin and its estimated future imperviousness. Basin specific LID facilities will be designed at the time of tract development. However, Appendix C includes sample calculations for a Sand Filter (SF) in G1 (local). The SF design encourages settling of sediments, filtering, and infiltration. The Mile High Flood District (MHFD) defines the facility as an “engineered, depressed landscape area designed to capture and filter or infiltrate the Water Quality Capture Volume (WQCV).” Step 2 - Implement BMPs that provide a Water Quality Capture Volume (WQCV) The developed runoff from the G1, H, and J basins will drain into an Extended Detention Basin (EDB) sized for 25% of the newly added imperviousness within the respective tributary area. The MHFD defines an EDB as “An engineered basin with an outlet structure designed to slowly release urban runoff over an extended time period to provide water quality benefits and control peak flows for frequently occurring storm events. The basins are sometimes called "dry ponds" because they are designed not to have a significant permanent pool of water remaining between storm runoff events. Outlet structures for extended detention basins are sized to control more frequently occurring storm events.” Step 3 - Stabilize drainageways Measures have be implemented to protect the Cooper Slough from the on-site detention pond outflows. Step 4 - Implement site specific and other source control BMPS Site specific considerations such as material storage and other site operations are addressed in the Stormwater Management Plan (SWMP). Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 13 of 31 Development Criteria Reference and Constraints The project must release at historic rates for each drainage basin, however due to the site being located on flat, farmland it has been determined that 0.2 cfs/acre would be a more appropriate release into the Cooper Slough. The overall Bloom Commercial site will release into the Cooper Slough at a rate of ±24.4 cfs Hydrological Criteria For urban catchments that are not complex and are generally 160 acres or less in size, it is acceptable that the design storm runoff be analyzed using the Rational Method. The Rational Method is often used when only the peak flow rate or total volume of runoff is needed (e.g., storm sewer sizing or simple detention basin sizing). The Rational Method was used to estimate the peak flow at each design point. For preliminary design, no routing (i.e., time attenuation) calculations were completed; this work will occur at Final Design. When a total flow is reported within this preliminary drainage report, assume it is simply a summation of all upstream flows. The Rational Method is based on the Rational Formula: Q = CiA Where: Q = the maximum rate of runoff, cfs C = a runoff coefficient that can be interpreted as ratio between the runoff volume from an area and the average rate of rainfall depth over a given duration for that area i = average intensity of rainfall in in/hr for a duration equal to the Time of Concentration (Tc) A = area, acres The one-hour rainfall Intensity-Duration-Frequency tables for use with the Rational Method of runoff analysis are provided in Table 3.4-1 and Figure 3.4-1 (refer to Appendix B). The 2-year and 100-year storm events are the basis for the preliminary drainage system design. The 2- year storm is considered the minor storm event. It has a fifty percent probability of exceedance during any given year. The 100-year storm is considered the major storm event. It has a one percent probability of exceedance during any given year. The 2-year drainage system, at a minimum, must be designed to transport runoff from the 2-year recurrence interval storm event with minimal disruption to the urban environment. The 100-year drainage system, as a minimum, must be designed to convey runoff from the 100-year recurrence interval flood to minimize life hazards and health, damage to structures, and interruption to traffic and services. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 14 of 31 The preliminary detention requirements were estimated with EPA SWMM 5.2. The SWMM input parameters for each basin reference Table 4.1-1 of the FCSDCM. Hydraulic Criteria Street Capacity Analysis The maximum encroachment criteria (see below) for gutter flow within the respective street sections and during the minor storm (Q2) event was used to establish the street capacity. The maximum pavement encroachment standards presented below in Table ST-2. For example, the minor storm flows within local streets cannot overtop the curb (dmax=0.5’) or the crown of the street. During the major storm event (Q100), the street capacities were estimated based on the maximum street encroachment standards presented below in Table ST-3. Table ST-2 - Pavement Encroachment Standards for the Minor Storm Street Classification Maximum Encroachment Local No curb overtopping. Flow may spread to crown of street. Collector No curb overtopping. Flow spread must leave at least one lane free of water. Table ST-3 - Street Inundation Standards for the Major (i.e., 100-Year) Storm Street Classification Maximum Depth and Inundated Area Local and Collector The depth of water must not exceed the bottom of the gutter at the median to allow operation of emergency vehicles, the depth of water over the gutter flow line shall not exceed twelve-(12) inches, and the flow must be contained within the right-of-way or easements paralleling the right-of- way. The most restrictive of the three criteria shall govern. Table ST-4 – Allowable Cross-Street Flow Street Classification Initial Storm Flow Major (100-Year) Storm Flow Local 6 inches of depth in cross pan. 18 inches of depth above gutter flow line. Collector Where cross pans allowed, depth of flow should not exceed 6 inches. 12 inches of depth above gutter flow line. The street capacity calculations are embedded within the MHFD-Inlet_v6.00 spreadsheet. Refer to Appendix D for street capacity calculations. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 15 of 31 Inlet Capacity Analysis CDOT Type ‘R’ inlets are proposed throughout the project for removing excess developed runoff from the Right-of-Way. The minor and major storm event inlet capacities were estimated with MHFD-Inlet_v6.00. The street section geometry and storm event encroachment limits (i.e., street classification) established the maximum allowable ponding depth. We determined the inlet length using the rational method flows at the respective design point and the maximum allowable ponding depth. Appendix D includes capacity calculations for proposed Type ‘R’ curb inlets and (1)-one Type 13 combination inlet. Storm Drain Capacity Analysis The storm drain system hydraulic analysis was completed using Bentley StormCAD V8i. This software routes flows through each system by looking at the longest upstream tc at the manhole, calculating the intensity and multiplying it by the upstream CA. Detailed output for each storm drain system analysis is included in Appendix D. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 16 of 31 VI. EROSION AND SEDIMENT CONTROL MEASURES A General Permit for Stormwater Discharge Associated with Construction Activities issued by the Colorado Department of Public Health and Environment (CDPHE), Water Quality Control Division (WQCD), will be acquired for the site. A Stormwater Management Plan (SWMP) should be prepared to identify the Stormwater Control Measures (SCMs) which, when implemented, will meet the requirements of said General Permit. Below is a summary of SWMP requirements which may be implemented on-site. The following temporary SCMs may be installed and maintained to control on-site erosion and prevent sediment from traveling off-site during construction: • Silt Fence (SF) – a woven synthetic fabric that filters runoff. The silt fence is a temporary barrier that is placed at the base of a disturbed area. • Vehicle Tracking Control (VTC) – a stabilized stone pad located at points of ingress and egress on a construction site. The stone pad is designed to reduce the amount of mud transported onto public roads by construction traffic. • Straw Wattles (SW) – wattles act as a sediment filter. They are a temporary BMP and require proper installation and maintenance to ensure their performance. • Inlet protection (IP) – Inlet protection will be used on all existing and proposed storm inlets to help prevent debris from entering the storm sewer system. Inlet protection generally consists of straw wattles or block and gravel filters. Construction Material & Equipment The contractor shall store all construction materials and equipment and shall provide maintenance and fueling of equipment in confined areas on-site from which runoff will be contained and filtered. Maintenance The temporary SCMs will be inspected by the contractor at a minimum of once every two weeks and after each significant storm event. The property owner will be responsible for routine and non-routine maintenance of the temporary BMPs. Routine maintenance includes: • Remove sediment from the bottom of the temporary sediment basin when accumulated sediment occupies about 20% of the design volume or when sediment accumulation results in poor drainage. • Lawn mowing-maintain height of grass depending on aesthetic requirements. • Debris and litter removal-remove debris and litter to minimize outlet clogging and improve aesthetics as necessary. • Inspection of the facility-inspect the facility annually to ensure that it functions as initially intended. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 17 of 31 • Cleaning and repair of BMP’s is required when sediment has built up or the BMP is not working properly. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 18 of 31 VII. Conclusions Compliance with Standards The design presented in this drainage report for Bloom Commercial development has been prepared in accordance with the design standards and guidelines presented in the Fort Collins Stormwater Criteria Manual. Variances There are no variances requests associated with the current work. Summary of Concepts The proposed storm drainage improvements should provide adequate protection for the developed site. The proposed drainage system for the site should not negatively impact the existing downstream storm drainage system. Bloom Commercial Final Drainage Report Galloway & Company, Inc. Page 19 of 31 VIII. References 1. Urban Storm Drainage Criteria Manual, Urban Drainage and Flood Control District, January 2016 (with current revisions). 2. Fort Collins Stormwater Criteria Manual (Addendum to the Urban Drainage Storm Drainage Criteria Manuals Volumes 1, 2, and 3), prepared by City of Fort Collins, Revised December 2018 3. Soil Map – Larimer County Area, Colorado as available through the Natural Resources Conservation Service National Cooperative Soil Survey web site via Web Soil Survey 2.0. 4. Flood Insurance Rate Map – Larimer County, Colorado and Incorporated Areas Community Panel No. 08069C0982F, Effective December 19, 2006 and 08069C0984H, Effective May 2, 2012. 5. City of Fort Collins Upper Cooper Slough Basin Selected Plan of Improvements, Icon Engineering, Inc., May 2021. 6. Final Drainage Report for Peakview, United Civil Design Group, December 21, 2020. 7. Master Drainage Report for Mulberry, Galloway & Company, Inc., August 8, 2021 8. Preliminary Drainage and Erosion Control Report for Bloom Filing Three Fort Collins, Colorado, Aspen Engineering, June 14, 2023 9. Final Drainage and Erosion Control Report Bloom Multi Family Fort Collins, Colorado, CivilWorx, LLC, June 25, 2024 Bloom Commercial Preliminary Drainage Report Galloway & Company, Inc. APPENDIX A Exhibits and Figures 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 • GallowayUS.com BLOOM COMMERCIAL VICINITY MAP NOT TO SCALE Hydrologic Soil Group—Larimer County Area, Colorado (HFH073 | Bloom Commercial) Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 7/13/2025 Page 1 of 4 44 9 2 2 0 0 44 9 2 3 0 0 44 9 2 4 0 0 44 9 2 5 0 0 44 9 2 6 0 0 44 9 2 7 0 0 44 9 2 8 0 0 44 9 2 9 0 0 44 9 3 0 0 0 44 9 3 1 0 0 44 9 2 2 0 0 44 9 2 3 0 0 44 9 2 4 0 0 44 9 2 5 0 0 44 9 2 6 0 0 44 9 2 7 0 0 44 9 2 8 0 0 44 9 2 9 0 0 44 9 3 0 0 0 44 9 3 1 0 0 498200 498300 498400 498500 498600 498700 498800 498200 498300 498400 498500 498600 498700 498800 40° 35' 22'' N 10 5 ° 1 ' 1 9 ' ' W 40° 35' 22'' N 10 5 ° 0 ' 4 7 ' ' W 40° 34' 49'' N 10 5 ° 1 ' 1 9 ' ' W 40° 34' 49'' N 10 5 ° 0 ' 4 7 ' ' W N Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 13N WGS84 0 200 400 800 1200 Feet 0 50 100 200 300 Meters Map Scale: 1:4,880 if printed on A portrait (8.5" x 11") sheet. Soil Map may not be valid at this scale. MAP LEGEND MAP INFORMATION Area of Interest (AOI) Area of Interest (AOI) Soils Soil Rating Polygons A A/D B B/D C C/D D Not rated or not available Soil Rating Lines A A/D B B/D C C/D D Not rated or not available Soil Rating Points A A/D B B/D C C/D D Not rated or not available Water Features Streams and Canals Transportation Rails Interstate Highways US Routes Major Roads Local Roads Background Aerial Photography The soil surveys that comprise your AOI were mapped at 1:24,000. Warning: Soil Map may not be valid at this scale. Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale. Please rely on the bar scale on each map sheet for map measurements. Source of Map: Natural Resources Conservation Service Web Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857) Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required. This product is generated from the USDA-NRCS certified data as of the version date(s) listed below. Soil Survey Area: Larimer County Area, Colorado Survey Area Data: Version 19, Aug 29, 2024 Soil map units are labeled (as space allows) for map scales 1:50,000 or larger. Date(s) aerial images were photographed: Jul 2, 2021—Aug 25, 2021 The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident. Hydrologic Soil Group—Larimer County Area, Colorado (HFH073 | Bloom Commercial) Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 7/13/2025 Page 2 of 4 Hydrologic Soil Group Map unit symbol Map unit name Rating Acres in AOI Percent of AOI 7 Ascalon sandy loam, 0 to 3 percent slopes B 25.1 28.8% 35 Fort Collins loam, 0 to 3 percent slopes C 0.0 0.0% 40 Garrett loam, 0 to 1 percent slopes B 59.4 68.2% 73 Nunn clay loam, 0 to 1 percent slopes C 0.0 0.0% 76 Nunn clay loam, wet, 1 to 3 percent slopes C 1.8 2.1% 94 Satanta loam, 0 to 1 percent slopes C 0.7 0.8% Totals for Area of Interest 87.1 100.0% Hydrologic Soil Group—Larimer County Area, Colorado HFH073 | Bloom Commercial Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 7/13/2025 Page 3 of 4 Description Hydrologic soil groups are based on estimates of runoff potential. Soils are assigned to one of four groups according to the rate of water infiltration when the soils are not protected by vegetation, are thoroughly wet, and receive precipitation from long-duration storms. The soils in the United States are assigned to four groups (A, B, C, and D) and three dual classes (A/D, B/D, and C/D). The groups are defined as follows: Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist mainly of deep, well drained to excessively drained sands or gravelly sands. These soils have a high rate of water transmission. Group B. Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of moderately deep or deep, moderately well drained or well drained soils that have moderately fine texture to moderately coarse texture. These soils have a moderate rate of water transmission. Group C. Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission. Group D. Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink-swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission. If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in group D are assigned to dual classes. Rating Options Aggregation Method: Dominant Condition Component Percent Cutoff: None Specified Tie-break Rule: Higher Hydrologic Soil Group—Larimer County Area, Colorado HFH073 | Bloom Commercial Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 7/13/2025 Page 4 of 4 National Flood Hazard Layer FIRMette 0 500 1,000 1,500 2,000250 Feet Ü SEE FIS REPORT FOR DETAILED LEGEND AND INDEX MAP FOR FIRM PANEL LAYOUT SPECIAL FLOOD HAZARD AREAS Without Base Flood Elevation (BFE) Zone A, V, A99 With BFE or Depth Zone AE, AO, AH, VE, AR Regulatory Floodway 0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mile Zone X Future Conditions 1% Annual Chance Flood Hazard Zone X Area with Reduced Flood Risk due to Levee. See Notes.Zone X Area with Flood Risk due to Levee Zone D NO SCREEN Area of Minimal Flood Hazard Zone X Area of Undetermined Flood Hazard Zone D Channel, Culvert, or Storm Sewer Levee, Dike, or Floodwall Cross Sections with 1% Annual Chance 17.5 Water Surface Elevation Coastal Transect Coastal Transect Baseline Profile Baseline Hydrographic Feature Base Flood Elevation Line (BFE) Effective LOMRs Limit of Study Jurisdiction Boundary Digital Data Available No Digital Data Available Unmapped This map complies with FEMA's standards for the use of digital flood maps if it is not void as described below. The basemap shown complies with FEMA's basemap accuracy standards The flood hazard information is derived directly from the authoritative NFHL web services provided by FEMA. This map was exported on 7/13/2025 at 4:08 PM and does not reflect changes or amendments subsequent to this date and time. The NFHL and effective information may change or become superseded by new data over time. This map image is void if the one or more of the following map elements do not appear: basemap imagery, flood zone labels, legend, scale bar, map creation date, community identifiers, FIRM panel number, and FIRM effective date. Map images for unmapped and unmodernized areas cannot be used for regulatory purposes. Legend OTHER AREAS OF FLOOD HAZARD OTHER AREAS GENERAL STRUCTURES OTHER FEATURES MAP PANELS 8 B 20.2 The pin displayed on the map is an approximate point selected by the user and does not represent an authoritative property location. 1:6,000 105°1'21"W 40°35'12"N 105°0'43"W 40°34'45"N Basemap Imagery Source: USGS National Map 2023 4,514 752.3 HFH073 | Bloom Commercial This map is a user generated static output from the City of Fort Collins FCMaps Internet mapping site and is for reference only. Data layers that appear on this map may or may not be accurate, current, or otherwise reliable. City of Fort Collins - GIS 572.0 1: WGS_1984_Web_Mercator_Auxiliary_Sphere Feet572.00286.00 Notes Legend 3,430 Street Names FEMA Floodplain FEMA High Risk - Floodway FEMA High Risk - 100 Year FEMA Moderate Risk - 100 / 500 Year City Floodplains City High Risk - Floodway City High Risk - 100 Year City Moderate Risk - 100 Year City Limits Bloom Commercial Preliminary Drainage Report APPENDIX B Excerpts from Reference Materials ANHEUSER BUSCH (AB) PLANT Sod Farm Diversion Q diverted = 752 cfs Proposed Sod Farm Pond S = 164 AF Max WSE = 5033.2 ft Berm along southern end at 5037.0 ft Sod Farm Pond Outlet Pipe into No. 8 Outlet Ditch 36" RCP with a 33.6" Orifice Q = 54 cfs Mountain Vista Diversion From No8 Outlet Ditch Q = 2 5 0 c f s Q = 8 9 c f s Assume Full Development of AB Lands with 100yr -> 2yr Detention (On-Site) Mountain Vista Diversion May Be Conveyed In Open Channel or Pipe through Montava Development Proposed C&S/ Crumb Detention Pond (426) S = 193 AF WSE = 4987.0 ft Qin = 903 cfs New AB Pond Outfall Overflow Flume Discharges into Cooper Slough Q = 304 cfs Existing AB 425 Pond Outlet Remains Connected to L&W Canal Q = 385 cfs Existing AB Pond 425 S = 47 AF Max WSE = 4983.5 Qin = 732 cfs Remove Existing Flow Spill At CSRR Provide Open Channel to Convey Flows on West Side of RR Combined Outlow From C&S/ Crumb and L&W Canal Spill Q = 639 cfs Proposed E. Vine Dr. Culverts (3) 8' x 4' RCBC Q = 678 cfs Proposed E. Mulberry St. Culverts (2) 6' x 11' RCBC Q = 1050 cfs COOPER SLOUGH Canal Spill to Dry Creek Q = 0 cfs Canal Spill Q = 421 cfs Q = 7 7 8 c f s Q = 3 5 7 c f s Q = 2 2 9 c f s Q = 3 3 9 c f s Q = 1 0 0 2 c f s Q = 3 7 4 c f s NO . 8 O U T L E T D I T C H LARIME R & W E L D C A N A L CO L O R A D O & S O U T H E R N R A I L R O A D BOXELDER WATERSHED DRY CREEK WATERSHED COOPER SLOUGH WATERSHED BLACK HOLLOW OUTFALL CHANNEL IMPROVEMENTS FROM 2006 MASTER PLAN NOT INCLUDED IN 2021 UPDATE Q = 2 5 0 c f s N. Poudre Reservoir No. 6 Add 8-inch Iron Sill Plate to Spillway Q = 547 cfs S = 679 AF Max WSE = 5163.2' Proposed (2) 6'x11' RCBC to Lake Canal SH-14 Proposed Channel to Box Elder Creek Channel and Bank Improvements along Cooper Slough Pond A S = 82 AF Max WSE = 5019.6 ft Qout = 778 cfs Montava Swale Q = 778 cfs Q = 1 4 9 c f s Overflow Pond S = 20.3 AF WSE = 4980.2 ft Qin = 112 cfs Proposed C&S/ Crumb Outfalls: 42" RCP to AB Pond = 102 cfs 3ft x 13.5ft RCBC to AB Pond (3ft above Pond inv) = 331 cfs Spill to Overflow Pond = 112cfs Overflow Pond Outfall into L&W Canal 48" RCP with a 44.4" Orifice Qout = 103 cfs Proposed (3) 3'x15' RCBC under Lake Canal Proposed Channel Proposed culverts for local drainage MONTAVA DEVELOPMENT MT VISTA AND TIMBERLINE ROAD MIXED-USED DEVELOPMENT WATER'S EDGE DEVELOPMENT COUNTRY CLUB RESERVE DEVELOPMENT Existing 24-in Culvert Capaity = 21cfs Culvert Crossing (3) 10'X3' RCBC Q = 888cfs Proposed Channel Formalize Spill from Lake Canal E VINE DR IN T E R S T A T E 2 5 S B E MULBERRY ST GI D D I N G S R D TU R N B E R R Y R D RICHARDS LAKE RD MOUNTAIN VISTA DR E LIN C O L N A V E S TIMB E R L I N E R D COUNTRY CLUB RD E COUNTY ROAD 48 §¨¦25 §¨¦25 Cooper Slough Selected Plan (2021) Figure 3: Selected Plan Projects $ 0 0.5 Miles Legend swale Overflow_Pond Pond_A C&S_Pond AB_Pond CRUMB_OUTLET Sod Farm Pond Proposed_Channel Proposed Culvert Montava Dev Boundary Waters Edge Dev Boundary Cooper Slough Basin Boundary MtVista ! ! ! ! !Anheuser Busch Property 5265 Ronald Reagan Blvd., Suite 210 Johnstown, CO 80534 970.800.3300 GallowayUS.com Memorandum HFH22 - Memorandum F1 Amendment.docx Page 1 of 2 To:Wes Lamarque, PE City of Fort Collins From:Matthew Pepin, PE Galloway, Inc. Date:06/20/2023 Re:Bloom Filing 1 Amendment - Drainage Modifications To Mr. Lamarque, Bloom Filing 1 required revisions that would include a modified pond, an added pond, and modifications to associated storm infrastructure. This memorandum is to help provide information on the changes from the approved Bloom F1 Final Drainage Report for the stated Amendment. Pond Modification / Addition Pond G was initially approved to provide 9.5 ac-ft of volume and release at a rate of 17.6 cfs. This pond is being split into two separate ponds to allow for increased development within the piece of land where Pond G initially was planned. Pond G will now be reduced to a volume of 4.8 ac-ft and releasing at 13.5 cfs. A second pond, Pond G1, will be located on the western part of the site. Pond G1 will provide 5.1 ac-ft of volume and release at 4.4 cfs. This would increase the amount of total flow existing both ponds from the original by 0.2 cfs. In order to maintain a maximum of 22.3 cfs releasing into the southern part of the Cooper Slough outfall, Pond I’s flow will be restricted from 0.35 cfs to 0.15 cfs. Storm Infrastructure The associated basin that were tributary to the effected modification storm infrastructure are labeled as A-G1, A-G2,…A-G6. Inlet calculations were added for these basins as well. An updated StormCAD output for the effected storm lines has been included a part of this memo. Tailwater conditions were set based on the 100-year WSEL for the major storm event and a free outfall condition in the minor event. Note: there is HGL surcharging from SD Inlet L1.5 and SD Inlet L1. The HGL at this location is .27 higher than the RIM at the MH of SD MH L1.4. This equates to 3.24 inches and would remain within the ROW, not impacting the lots. Storm Infrastructure incorporating Bloom F2 In order to take into account LID’s within Bloom F2, there is another modification to the storm pipe infrastructure. A concern of too much flow entering the LID in the major storm events would cause damage needed to be mitigated. To prevent this from happening, a manhole would split flow from outfalling into the LID and by passing downstream to outfall into the EDB (Pond E). This flow split would have flow entering into the LID at a maximum of 15.5 cfs in the major storm event. The flow split is achieved by having the smaller 15” pipe sit lower than the larger pipe, restricting flow for the minor event to only pass through the 15” pipe. The flow rate allowing for all flow in the minor storm event to enter the LID at a flow rate of 12.02 cfs. Bloom Filing 1 06/20/2023 HFH22 - Memorandum F1 Amendment.docx Galloway & Company, Inc.Page 2 of 2 CONCLUSION The modifications to the site will not change the overall design intent that was originally approved with Bloom F1 Drainage Report. Sincerely, GALLOWAY Matthew Pepin, PE Civil Project Engineer MatthewPepin@Gallowayus.com 01/02/2024 5265 Ronald Reagan Blvd., Suite 210 Johnstown, CO 80534 970.800.3300 • GallowayUS.com Memorandum HFH22 - Memorandum F1 Amendment v2.docx Page 1 of 1 To: Wes Lamarque, PE City of Fort Collins From: Matthew Pepin, PE Galloway, Inc. Date: 01/31/2025 Re: Bloom Filing 1 Amendment - Drainage Modifications To Mr. Lamarque, Bloom Filing 1 required revisions that would include modifying Pond D outlet structure design. This memorandum is to help provide information on the changes from the approved Bloom F1 Final Drainage Report for the stated Amendment. Pond D Outlet Structure Modification Pond D was initially approved to release at a rate of 0.76 cfs. Upon completing the pond certification for the pond, it was determined that the pond would not drain in 120-hours per Colorado State Statute. Pond D’s release rate was modified to increase to 2.55 cfs to allow it to fully drain within the 120-hours. This increase would provide a total increase of 1.78 cfs into the upper portion of Cooper Slough. The approved Cooper Slough release rate initially was 21.91 cfs and the revised release rate is 23.69 cfs. To compensate for the increase on the upper portion of the Cooper Slough, the existing interim Pond G1 (which will be modified in its future condition) and the future commercial site proposed pond located within Basin H will restrict its release to equalize the total site to a maximum of 0.2 cfs per acre as outlined in the approved Final Drainage Report and City of Fort Collins Storm Drainage Criteria. These design modifications will occur at a later date. To allow for the change of flow, the restrictor plate will be raised to be approximately 0.3’ above the structure bottom. CONCLUSION The modifications to Pond D will not change the overall design intent that was originally approved with Bloom F1 Drainage Report and will allow for the pond to fully drain the stormwater stored within the pond within 120 hours. Sincerely, GALLOWAY Matthew Pepin, PE Sr. Civil Project Engineer MatthewPepin@Gallowayus.com H1 H4 H3 H2 CooperSlough LakeCanal O1 CityofFortCollins Mulberry - Existing Conditions SWMM 5.1 Page 1 SHARED STORM 1 - PROFILE STA: 9+50 TO STA 18+50 4910 4915 4920 4925 4930 4935 4940 4945 4950 4910 4915 4920 4925 4930 4935 4940 4945 4950 9+5010+0010+5011+0011+5012+0012+5013+0013+5014+0014+5015+0015+5016+0016+5017+0017+5018+0018+50 MH D P 1 - 2 ST A : 1 3 + 1 9 . 9 1 RI M 4 9 2 9 . 7 ± IN V . I N 4 9 2 4 . 0 3 ( N ) IN V . I N 4 9 2 2 . 0 1 ( W ) IN V . O U T 4 9 2 1 . 9 1 ( E ) FE S D P 1 - 1 ST A : 1 0 + 0 0 . 0 0 RI M 4 9 2 3 . 6 ± IN V . I N 4 9 2 1 . 2 7 ( W ) ST U B D P 1 - 3 ST A : 1 7 + 7 6 . 4 8 RI M 4 9 2 5 . 3 ± IN V . O U T 4 9 2 2 . 9 4 ( E ) PROPOSED GRADE EXISTING GROUND 456.6 LF 30" RCP @ 0.20% 319.9 LF 30" RCP @ 0.20% 5'(W) x 8'(L) TYPE L RIPRAP 100-YR HGL ST A R T B O X C U L V E R T ST A : 1 0 + 0 1 . 5 5 IN V . O U T 4 9 2 2 . 6 9 ( E ) IN V . O U T 4 9 2 2 . 6 9 ( W ) 137.3 LF 4'X12' BOX CULVERT @ 0.20% EN D B O X C U L V E R T ST A : 9 + 9 5 . 5 1 IN V . I N 4 9 2 2 . 4 1 ( W ) 9+7510+00 11+00 12+00 13+0014+0015+0016+0017+0018+00 FRON T A G E R O A D LOT 2 MULBERRY ST (CO HWY 14) FR O N T A G E R O A D GR E E N F I E L D S D R I V E STA: 9+75.00 N: 4440.56 E: 4688.12 START ALIGNMENT STUB DP 1-3 STA 9+99.20 N: 4469.56 E: 3887.42 FES DP 1-1 STA 9+84.18 N: 4442.19 E: 4663.17 319.9 LF 30" STORM 456.6 LF 30" STORM MH DP 1-2 STA 10+00.00 N: 4463.10 E: 4343.94 DP STORM 1 (SEE THIS SHEET) STA: 18+00.00 N: 4469.89 E: 3863.90 END ALIGNMENT GD STORM 1 (SEE SHEET C4.11) GD STORM 1-3 (SEE SHEET C4.11) FR STORM 1 (SEE SHEET C4.13) WQ STORM 1 (SEE SHEET C4.13) DP STORM 1 (SEE SHEET C4.13) 137.3 LF 4'X12' BOX CULVERT START BOX CULVERT STA 10+01.55 N: 4471.61 E: 3906.00 END BOX CULVERT STA 9+95.51 N: 4463.39 E: 4043.05 PROPOSED BOX CULVERT (SEE SHEET C7.10 FOR MORE INFO) 9+75 10+00 10+50 MH DP 1-2 STA 10+00.00 N: 4463.10 E: 4343.94 21.6 LF 12" STORM OUTLET DP 1-2.1 STA 10+21.62 N: 4484.71 E: 4344.28 FRO N T A G E R O A D STA: 9+75.00 N: 4438.10 E: 4343.55 START ALIGNMENT STA: 10+50.00 N: 4513.09 E: 4344.74 END ALIGNMENT MU L B E R R Y S T ( C O H W Y 1 4 ) DP STORM 1 - PROFILE STA: 9+50 TO STA 11+00 4910 4915 4920 4925 4930 4935 4940 4945 4950 4910 4915 4920 4925 4930 4935 4940 4945 4950 9+50 10+00 10+50 11+00 OU T L E T D P 1 - 2 . 1 ST A : 1 0 + 2 1 . 6 2 IN V . O U T 4 9 2 4 . 4 6 ( S ) MH D P 1 - 2 ST A : 1 0 + 0 0 . 0 0 IN V . I N 4 9 2 4 . 0 3 ( N ) IN V . I N 4 9 2 2 . 0 1 ( W ) IN V . O U T 4 9 2 1 . 9 1 ( E ) PROPOSED GRADE EXISTING GROUND 100-YR HGL 21.6 LF 12" RCP @ 2.00% VA L L E Y 1 4 L L C 12 / 2 1 / 2 0 2 0 U18024 1" = 50' 1" = 5' PE A K V I E W P L D NO R T H 12 / 2 3 / 2 0 2 0 11 : 0 6 : 5 3 A M C: \ U N I T E D C I V I L D R O P B O X \ P R O J E C T S \ U 1 8 0 2 4 - P E A K V I E W \ C A D D \ C P \ C 4 . 1 0 - S T O R M P L A N & P R O F I L E S . D W G C4 . 1 0 - S T O R M P L A N & P R O F I L E S SM E JR S C4.10 67 ST O R M P L A N & P R O F I L E 0 50'100' SCALE: 1" = 50' 25' PR E P A R E D F O R : JOB NUMBER SHEET NUMBER SHEETSOF DA T E S U B M I T T E D : VERTICAL: HORIZONTAL: SCALE PRE L I M I N A R Y PLA N S NOT F O R C O N S T R U C T I O N PR O J . M G R : DR A W I N G N A M E : PA T H : DE S I G N E R : DA T E : TI M E : Th e e n g i n e e r p r e p a r i n g t h e s e p l a n s w i l l n o t b e r e s p o n s i b l e f o r , o r l i a b l e f o r , u n a u t h o r i z e d ch a n g e s t o o r u s e s o f t h e s e p l a n s . A l l c h a n g e s t o t h e p l a n s m u s t b e i n w r i t i n g a n d m u s t be a p p r o v e d b y t h e p r e p a r e r o f t h e s e p l a n s . NO . BY DA T E CAUTION RE V I S I O N S : CIVIL ENGINEERING & CONSULTING UNITED CIVIL Design Group 19 OLD TOWN SQUARE #238 FORT COLLINS, CO 80524 (970) 530-4044 www.unitedcivil.com 19 CABLE TV LINE ELECTRIC LINE FIBER OPTIC LINE GAS LINE G GAS METER IRRIGATION LINE SANITARY MANHOLE SANITARY MAIN SANITARY SERVICE FLARED END SECTION STORM INLET STORM MANHOLE STORM OUTLET STRUCTURE STORM PIPE RIP RAP TELEPHONE LINE FIRE HYDRANT FIRELINE WATER FITTINGS WATER MAIN WATER SERVICE WATER METER THRUST BLOCK GATE VALVE FIBER, GAS, ELECTRIC, OR TELEPHONE PEDESTAL LEGEND N KEYMAP 1.THE CONTRACTOR IS RESPONSIBLE FOR VERIFYING THE FIELD CONDITIONS ARE AS SHOWN IN THE DRAWINGS. IF THE CONTRACTOR FINDS DISCREPANCIES THE CONTRACTOR SHALL CONTACT THE ENGINEER. 2.EXISTING UNDERGROUND AND OVERHEAD PUBLIC AND PRIVATE UTILITIES AS SHOWN ARE INDICATED ACCORDING TO THE BEST INFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOES NOT GUARANTEE THE ACCURACY OF SUCH INFORMATION. EXISTING UTILITY MAINS AND SERVICES MAY NOT BE STRAIGHT LINES OR AS INDICATED ON THESE DRAWINGS. THE CONTRACTOR SHALL BE RESPONSIBLE TO CALL ALL UTILITY COMPANIES (PUBLIC AND PRIVATE) PRIOR TO ANY CONSTRUCTION TO VERIFY EXACT UTILITY LOCATION. 3.THE CONTRACTOR SHALL COORDINATE ALL CONSTRUCTION ITEMS IMPACTING ADJACENT PROPERTIES WITH THE PROPERTY OWNERS PRIOR TO BEGINNING ANY CONSTRUCTION ACTIVITIES. 4.STORM SEWER SHALL BE CONSTRUCTED IN ACCORDANCE WITH CITY OF FORT COLLINS SPECIFICATIONS AND DETAILS. SEE ADDITIONAL NOTES ON SHEET C0.03. 5.STORM SEWER MAINS SHOWN ON THESE DRAWINGS AS HIGH DENSITY POLYETHYLENE (HDPE) SHALL BE WATERTIGHT ADS-N12 OR APPROVED EQUAL. 6.ALL PIPE LENGTHS ARE FROM CENTER TO CENTER OF ADJACENT STRUCTURES. DESIGN LENGTH OF THE PIPE INCLUDES THE LAYING LENGTH OF FLARED END SECTIONS. NOTES CHECKED BY: CHECKED BY: CHECKED BY: APPROVED: CITY OF GREELEY REVIEWED BY:___________________________________________ LARIMER COUNTY ENGINEERING DATE LARIMER COUNTY APPROVAL BLOCK NORTH G DE L O Z I E R R O A D LOT 10 LOT 7 LOT 9 LOT 8 LOT 7 LOT 10 LOT 9 LOT 8 BLOCK 28 BLOCK 30 E27 E6 E11 E24 E10 E7 E5 E22 E23 E9 E16 E14 E12 E12.1 E11.1 E24.1 E25.1 E15 E17 acres 0.68 0.85 0.63 acres E5 0.72 0.90 1.07 acres OS4 0.46 0.57 0.29 acres E7 0.74 0.92 1.03 acres E9 0.72 0.90 1.07 acres E10 0.74 0.93 1.03 acres E11 0.55 0.68 0.40 acres E12 0.79 0.99 0.44 acres E14 0.65 0.81 0.30 acres OS3 0.33 0.41 0.85 acres E15 0.82 1.00 0.57 acres OS6 0.60 0.75 0.43 acres E17 0.65 0.81 0.59 acres OS7 0.60 0.75 0.41 acres E22 0.76 0.96 0.99 acres E23 0.77 0.96 0.99 acres E24 0.54 0.67 0.73 acres E24.1 0.67 0.84 0.36 acres E27 0.69 0.86 0.33 acres FUT-G 0.90 1.00 40.3 acres OS5 0.79 0.99 0.15 acres E15.1 0.80 1.0 1.15 acres E26.1 0.80 1.00 0.72 acres E14.1 0.80 1.00 1.3 acres E12.1 0.94 1.00 0.21 acres E25.1 0.62 0.78 0.19 STAMP H: H a r t f o r d H o m e s C O F o r t C o l l i n s H F H 2 2 M u l b e r r y 0 C I V 3 C D F D P F 1 h f h 0 2 2 c 1 0 0 d r a i n a g e d w g Ma t t h e w P e p i n 7/ 1 2 2 0 2 2 Init.#Issue / DescriptionDate FI N A L D E V E L O P M E N T P L A N S BL O O M F I L I N G O N E FO R T C O L L I N S C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT GallowayUS.com 5265 Ronald Reagan Blvd., Suite 210 Johnstown, CO 80534 970.800.3300 PR E LIM IN A R Y NO T FO R B ID D IN G NO T FO R C O N S T R U C TIO N Date: Drawn By: Project No: Checked By: 06.01.2022 HFH000022 MA T C H L I N E S E E S H E E T C1 0 4 MATCHLINE-SEE SHEET C10.1 MATCHLINE-SEE SHEET C10.8 DESIGN POINT DETENTION POND BASIN BOUNDARY i.e., MHFD-Detention_v4.03 and/or SWMM) SUB-BASIN BOUNDARY (i.e., Rational Method) OVERLAND FLOW DIRECTION I.E., LANDSCAPING) DIRECT FLOW DIRECTION I.E., PAVEMENT, CURB AND GUTTER) BASIN ID 2-YR RUNOFF COEFFICIENT BASIN AREA ACRES) acres A1 0.05 0.35 2.50 A APPROXIMATE DETENTION POND OVERFLOW PATH 100-YR RUNOFF COEFFICIENT FEMA CROSS SECTION IRRIGATION POND LIMITS KEYMAP Know what's before you dig.SCALE: 1"=50' 0 205010 JKD JEP DRAINAGE PLAN C10.2 NOTES: 1.PORTIONS OF THIS PROPERTY ARE LOCATED IN THE FEMA-REGULATED, 100-YEAR COOPER SLOUGH FLOODPLAIN/FLOODWAY AND MUST COMPLY WITH THE SAFETY REGULATIONS OF CHAPTER 10 OF CITY MUNICIPAL CODE. 2.THE DEVELOPER SHALL OBTAIN A FLOODPLAIN USE PERMIT FROM THE CITY OF FORT COLLINS AND PAY ALL APPLICABLE FLOODPLAIN USE PERMIT FEES PRIOR TO COMMENCING ANY CONSTRUCTION ACTIVITY (BUILDING OF STRUCTURES, GRADING, FILL, DETENTION PONDS, BIKE PATHS, PARKING LOTS, UTILITIES, LANDSCAPED AREAS, FLOOD CONTROL CHANNELS, ETC.) WITHIN THE COOPER SLOUGH FLOODPLAIN LIMITS--. STORAGE OF EQUIPMENT AND MATERIALS (TEMPORARY OR PERMANENT) IS NOT ALLOWED IN THE FLOODWAY. ALL ACTIVITIES WITHIN THE FLOODPLAIN ARE SUBJECT TO THE REQUIREMENTS OF CHAPTER 10 OF THE FORT COLLINS MUNICIPAL CODE. 3.CRITICAL FACILITIES ARE PROHIBITED IN THE 100-YEAR FLOODPLAIN. CRITICAL FACILITIES INCLUDE ESSENTIAL SERVICES, AT-RISK POPULATION, HAZARDOUS MATERIALS, AND GOVERNMENT FACILITIES. 4.CONSTRUCTION OF NEW STRUCTURES, HARD SURFACE PATHS, WALKWAYS, DRIVEWAYS, WALLS, AND PARKING AREAS IS PROHIBITED IN THE FLOODWAY UNLESS NO-RISE CONDITIONS ARE MET. ANY CONSTRUCTION ACTIVITIES IN THE REGULATORY FLOODWAY MUST ALSO INCLUDE A NO-RISE CERTIFICATION PREPARED BY A PROFESSIONAL ENGINEER LICENSED IN COLORADO. AN APPROVED FEMA ELEVATION CERTIFICATE COMPLETED BY A LICENSED SURVEYOR OR CIVIL ENGINEER SHOWING THAT THE BUILDING IS CONSTRUCTED TO THE REQUIRED ELEVATION IS REQUIRED POST-CONSTRUCTION PRIOR TO A CERTIFICATE OF OCCUPANCY (CO) BEING ISSUED. PLEASE NOTE: IF ANY PART OF THE BUILDING IS WITHIN THE FLOODPLAIN BOUNDARY, THEN THE ENTIRE STRUCTURE IS CONSIDERED IN THE FLOODPLAIN AND THE ENTIRE BUILDING ENVELOPE MUST MEET THE REQUIREMENTS OF ELEVATING TO THE RFPE. 5.ALL BASE FLOOD ELEVATIONS ARE BASED ON NAVD 1988 DATUM. E17 acres E17 0.65 0.81 0.59 acres 0.60 0.75 0.41 acres FUT-G 0.90 1.00 40.3 acres G1 0.79 0.99 1.15 acres G2 0.79 0.99 1.15 STAMP H: H a r t f o r d H o m e s C O F o r t C o l l i n s H F H 2 2 M u l b e r r y 0 C I V 3 C D F D P F 1 h f h 0 2 2 c 1 0 0 d r a i n a g e d w g Ma t t h e w P e p i n 7/ 1 2 2 0 2 2 Init.#Issue / DescriptionDate FI N A L D E V E L O P M E N T P L A N S BL O O M F I L I N G O N E FO R T C O L L I N S C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT GallowayUS.com 5265 Ronald Reagan Blvd., Suite 210 Johnstown, CO 80534 970.800.3300 PR E LIM IN A R Y NO T FO R B ID D IN G NO T FO R C O N S T R U C TIO N Date: Drawn By: Project No: Checked By: 06.01.2022 HFH000022 MA T C H L I N E S E E S H E E T C1 0 9 MATCHLINE-SEE SHEET C10.2 MATCHLINE-SEE SHEET C10.10 DESIGN POINT DETENTION POND BASIN BOUNDARY i.e., MHFD-Detention_v4.03 and/or SWMM) SUB-BASIN BOUNDARY (i.e., Rational Method) OVERLAND FLOW DIRECTION I.E., LANDSCAPING) DIRECT FLOW DIRECTION I.E., PAVEMENT, CURB AND GUTTER) BASIN ID 2-YR RUNOFF COEFFICIENT BASIN AREA ACRES) acres A1 0.05 0.35 2.50 A APPROXIMATE DETENTION POND OVERFLOW PATH 100-YR RUNOFF COEFFICIENT FEMA CROSS SECTION IRRIGATION POND LIMITS KEYMAP Know what's before you dig.SCALE: 1"=50' 0 205010 JKD JEP DRAINAGE PLAN C10.8 NOTES: 1.PORTIONS OF THIS PROPERTY ARE LOCATED IN THE FEMA-REGULATED, 100-YEAR COOPER SLOUGH FLOODPLAIN/FLOODWAY AND MUST COMPLY WITH THE SAFETY REGULATIONS OF CHAPTER 10 OF CITY MUNICIPAL CODE. 2.THE DEVELOPER SHALL OBTAIN A FLOODPLAIN USE PERMIT FROM THE CITY OF FORT COLLINS AND PAY ALL APPLICABLE FLOODPLAIN USE PERMIT FEES PRIOR TO COMMENCING ANY CONSTRUCTION ACTIVITY (BUILDING OF STRUCTURES, GRADING, FILL, DETENTION PONDS, BIKE PATHS, PARKING LOTS, UTILITIES, LANDSCAPED AREAS, FLOOD CONTROL CHANNELS, ETC.) WITHIN THE COOPER SLOUGH FLOODPLAIN LIMITS--. STORAGE OF EQUIPMENT AND MATERIALS (TEMPORARY OR PERMANENT) IS NOT ALLOWED IN THE FLOODWAY. ALL ACTIVITIES WITHIN THE FLOODPLAIN ARE SUBJECT TO THE REQUIREMENTS OF CHAPTER 10 OF THE FORT COLLINS MUNICIPAL CODE. 3.CRITICAL FACILITIES ARE PROHIBITED IN THE 100-YEAR FLOODPLAIN. CRITICAL FACILITIES INCLUDE ESSENTIAL SERVICES, AT-RISK POPULATION, HAZARDOUS MATERIALS, AND GOVERNMENT FACILITIES. 4.CONSTRUCTION OF NEW STRUCTURES, HARD SURFACE PATHS, WALKWAYS, DRIVEWAYS, WALLS, AND PARKING AREAS IS PROHIBITED IN THE FLOODWAY UNLESS NO-RISE CONDITIONS ARE MET. ANY CONSTRUCTION ACTIVITIES IN THE REGULATORY FLOODWAY MUST ALSO INCLUDE A NO-RISE CERTIFICATION PREPARED BY A PROFESSIONAL ENGINEER LICENSED IN COLORADO. AN APPROVED FEMA ELEVATION CERTIFICATE COMPLETED BY A LICENSED SURVEYOR OR CIVIL ENGINEER SHOWING THAT THE BUILDING IS CONSTRUCTED TO THE REQUIRED ELEVATION IS REQUIRED POST-CONSTRUCTION PRIOR TO A CERTIFICATE OF OCCUPANCY (CO) BEING ISSUED. PLEASE NOTE: IF ANY PART OF THE BUILDING IS WITHIN THE FLOODPLAIN BOUNDARY, THEN THE ENTIRE STRUCTURE IS CONSIDERED IN THE FLOODPLAIN AND THE ENTIRE BUILDING ENVELOPE MUST MEET THE REQUIREMENTS OF ELEVATING TO THE RFPE. 5.ALL BASE FLOOD ELEVATIONS ARE BASED ON NAVD 1988 DATUM. G3 G4 G1 G2 acres FUT-H 0.80 1.00 33.3 acres G4 0.81 1.00 1.16 acres G3 0.81 1.00 1.18 acres FUT-G 0.90 1.00 40.3 STAMP H: H a r t f o r d H o m e s C O F o r t C o l l i n s H F H 2 2 M u l b e r r y 0 C I V 3 C D F D P F 1 h f h 0 2 2 c 1 0 0 d r a i n a g e d w g Ma t t h e w P e p i n 7/ 1 2 2 0 2 2 Init.#Issue / DescriptionDate FI N A L D E V E L O P M E N T P L A N S BL O O M F I L I N G O N E FO R T C O L L I N S C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT GallowayUS.com 5265 Ronald Reagan Blvd., Suite 210 Johnstown, CO 80534 970.800.3300 PR E LIM IN A R Y NO T FO R B ID D IN G NO T FO R C O N S T R U C TIO N Date: Drawn By: Project No: Checked By: 06.01.2022 HFH000022 MA T C H L I N E S E E S H E E T C1 0 1 1 MATCHLINE-SEE SHEET C10.8 MATCHLINE-SEE SHEET C10.12 DESIGN POINT DETENTION POND BASIN BOUNDARY i.e., MHFD-Detention_v4.03 and/or SWMM) SUB-BASIN BOUNDARY (i.e., Rational Method) OVERLAND FLOW DIRECTION I.E., LANDSCAPING) DIRECT FLOW DIRECTION I.E., PAVEMENT, CURB AND GUTTER) BASIN ID 2-YR RUNOFF COEFFICIENT BASIN AREA ACRES) acres A1 0.05 0.35 2.50 A APPROXIMATE DETENTION POND OVERFLOW PATH 100-YR RUNOFF COEFFICIENT FEMA CROSS SECTION IRRIGATION POND LIMITS KEYMAP Know what's before you dig. SCALE: 1"=50' 0 205010 JKD JEP DRAINAGE PLAN C10.10 NOTES: 1.PORTIONS OF THIS PROPERTY ARE LOCATED IN THE FEMA-REGULATED, 100-YEAR COOPER SLOUGH FLOODPLAIN/FLOODWAY AND MUST COMPLY WITH THE SAFETY REGULATIONS OF CHAPTER 10 OF CITY MUNICIPAL CODE. 2.THE DEVELOPER SHALL OBTAIN A FLOODPLAIN USE PERMIT FROM THE CITY OF FORT COLLINS AND PAY ALL APPLICABLE FLOODPLAIN USE PERMIT FEES PRIOR TO COMMENCING ANY CONSTRUCTION ACTIVITY (BUILDING OF STRUCTURES, GRADING, FILL, DETENTION PONDS, BIKE PATHS, PARKING LOTS, UTILITIES, LANDSCAPED AREAS, FLOOD CONTROL CHANNELS, ETC.) WITHIN THE COOPER SLOUGH FLOODPLAIN LIMITS--. STORAGE OF EQUIPMENT AND MATERIALS (TEMPORARY OR PERMANENT) IS NOT ALLOWED IN THE FLOODWAY. ALL ACTIVITIES WITHIN THE FLOODPLAIN ARE SUBJECT TO THE REQUIREMENTS OF CHAPTER 10 OF THE FORT COLLINS MUNICIPAL CODE. 3.CRITICAL FACILITIES ARE PROHIBITED IN THE 100-YEAR FLOODPLAIN. CRITICAL FACILITIES INCLUDE ESSENTIAL SERVICES, AT-RISK POPULATION, HAZARDOUS MATERIALS, AND GOVERNMENT FACILITIES. 4.CONSTRUCTION OF NEW STRUCTURES, HARD SURFACE PATHS, WALKWAYS, DRIVEWAYS, WALLS, AND PARKING AREAS IS PROHIBITED IN THE FLOODWAY UNLESS NO-RISE CONDITIONS ARE MET. ANY CONSTRUCTION ACTIVITIES IN THE REGULATORY FLOODWAY MUST ALSO INCLUDE A NO-RISE CERTIFICATION PREPARED BY A PROFESSIONAL ENGINEER LICENSED IN COLORADO. AN APPROVED FEMA ELEVATION CERTIFICATE COMPLETED BY A LICENSED SURVEYOR OR CIVIL ENGINEER SHOWING THAT THE BUILDING IS CONSTRUCTED TO THE REQUIRED ELEVATION IS REQUIRED POST-CONSTRUCTION PRIOR TO A CERTIFICATE OF OCCUPANCY (CO) BEING ISSUED. PLEASE NOTE: IF ANY PART OF THE BUILDING IS WITHIN THE FLOODPLAIN BOUNDARY, THEN THE ENTIRE STRUCTURE IS CONSIDERED IN THE FLOODPLAIN AND THE ENTIRE BUILDING ENVELOPE MUST MEET THE REQUIREMENTS OF ELEVATING TO THE RFPE. 5.ALL BASE FLOOD ELEVATIONS ARE BASED ON NAVD 1988 DATUM. CITY OF GREELEY Final Drainage and Erosion Control Report for Bloom Filing Three Fort Collins, Colorado March 12, 2025 41 42 39 35 36 37 38 39 40 40 40 40 37 38 38 39 39 39 39 41 41 42 42 40 40 39 40 39 39 39 40 40 40 41 40 40 41 41 42 42 41 41 42 40 40 39 39 41 41 41 41 40 37 38 39 39 40 37 38 39 41 38 39 39 39 38 38 39 3935 35 40 34 34 36 36 37 37 38 38 39 39 34 40 38 39 41 41 40 40 41 41 41 41 40 40 39 35 34 36 37 38 39 40 373839 3839 36373839 373839 38 39 3938 37 40 40 41 41 41 40 41 40 38 39 40 40 40 41 41 41 41 40 40 40 40 41 41 42 41 42 42 40 40 40 41 41 41 42 42 42 42 4142 42 41 42 42 42 40 40 40 41 40 39 41 42 43 44 41 41 41 4142 42 41 41 40 40 41 41 42 42 42 42 40 41 42 43 44 42 42 42 43 43 44 44 42 42 42 41 42 41 41 42 43 45 45 42 43 43 44 44 42 43 44 44 44 44 44 45 4242 4243 43 43 43 44 46 45 45 43 44 46 46 46 46 45 46 46 46 43 45 45 45 45 43 44 46 46 46 46 47 47 47 46 43 43 43 41 42 44 44 45 44 46 47 45 44 46 47 47 47 42 41 41 41 42 43 40 41 41 41 41 42 42 43 43 41 41 41 41 41 41 44 44 42 42 42 42 41 46 43 40 40 37 37 38 38 39 39 41 42 43 44 45 35 32 33 34 36 30 35 29 31 32 33 34 36 30 29 31 36 36 40 44 37 38 39 41 42 43 45 40 36 37 38 39 373839 38 35 40 38 37 37 38 39 40 41 42 43 36 44 46 44 45 46 46 45 45 46 37 47 CO CO CO CO UP UP UP UP UP UP UP UP UP UP UP UP UP UP 21 0.43 0.72 2 0.85 0.77 3 3 0.41 0.80 11 11 0.77 0.76 12 12 0.52 0.76 6 6 0.93 0.73 4 4 1.02 0.89 8 7 0.55 0.44 9 16 17 17 0.39 0.76 5 0.38 0.59 10 10 0.72 0.75 18 18 0.70 0.84 19 19 0.37 0.84 20 20 0.55 0.83 21 21 0.67 0.84 22 22 0.47 0.88 23 23 1.39 0.39 24 24 0.21 0.51 25 25 0.34 0.66 26 26 0.13 0.61 28 28 0.19 0.66 27 27 0.24 0.61 29 29 0.18 0.58 30 30 0.03 0.67 31 31 0.21 0.58 32 32 0.11 0.87 33 33 0.29 0.57 34 34 0.40 0.61 35 35 0.18 0.55 36 36 0.17 0.54 37 37 0.11 0.30 38 38 0.18 0.48 39 39 0.29 0.63 40 40 0.16 0.61 EX PROPERTY BOUNDARY/ ROW EX PROPERTY BOUNDARY/ ROW EX PROPERTY BOUNDARY/ ROW EX PROPERTY BOUNDARY/ ROW EX PROPERTY BOUNDARY/ ROW E.H.BARKER ET.AL. (PARCEL NO. 8708400002) BUILDING 1 BUILDING 2 BUILDING 3 BUILDING 4 BUILDING 5 BUILDING 6 BUILDING 7BUILDING 8 POOL BUILDING 9 COMMUNITY BUILDING BUILDING 10 BUILDING 11 BUILDING 12 BUILDING 13 BUILDING 14 BUILDING 15 PRIVATE DRIVE BARK PARK PROPOSED RAIN GARDEN BODE BOULEVARD ANGELA AVENUE INTERNATIONAL BLVD. DONELLA DRIVE AR I A W A Y AR I A W A Y DE L O Z I E R R D . DE L O Z I E R R D . EX PROPERTY BOUNDARY/ ROW EXISTING REGIONAL POND G (BY OTHERS) EXISTING REGIONAL POND E (BY OTHERS)(TO THE NORTH OF THIS MAP) 1 5 8 0.20 0.60 7 13 0.50 0.81 13 14 0.21 0.47 14 15 0.54 0.83 15 EXISTING REGIONAL POND G1 (BY OTHERS)(TO THE SOUTH OF THIS MAP) 16 0.17 0.59 9 0.24 0.34 9a 13a 15a 16a 17a 3a 4a 5a SHEET No: PR O J E C T / L O C A T I O N : DR A W I N G : OF CHECKED BY: DESIGNED BY: DRAWN BY: DE S C R I P T I O N O F R E V I S I O N : DA T E : RE V I S E D B Y : AP P R O V E D B Y : RE V . # 1 2 3 4 5 6 7 project no: date: BL O O M F I L I N G T H R E E FO R T C O L L I N S , C O L O R A D O DR A I N A G E E X H I B I T C-013 13 32 MARCH 12, 2025 801-004 JRG JRG JRG ASPEN 0' SCALE: 1" = 60' 60'120' LEGEND EXISTING CONTOURS NEW INTERMEDIATE CONTOURS39 40 NEW INDEX CONTOURS PROPOSED FLOWLINE EX RIGHT-OF-WAY/ PROPERTY BOUNDARY PROPOSED DRAINAGE BASIN BOUNDARY LINE PROPOSED STORM PIPE EXISTING STORM PIPE & MANHOLE RD PROPOSED ROOF DRAIN AND STORM PIPE 1.PROPOSED ELEVATIONS SHOWN ARE RELATIVE TO A DATUM OF 4900 FEET, AND ARE BASED ON THE BENCHMARKS DESCRIBED ON SHEET C-001. 2.THE DRAINAGE BASINS SHOWN ON THIS EXHIBIT WILL BE ULTIMATELY CONVEYED TO OFFSITE REGIONAL DETENTION PONDS, LOCATED NORTHEAST AND SOUTH OF THE BLOOM SITE, AND WITHIN THE MASTERPLAN DEVELOPMENT AREA. THE MASTERPLAN PONDS WILL PROVIDE WATER QUALITY AND DETENTION FOR THE DEVELOPED CONDITION OF THE BLOOM SITE. THE MAJORITY OF THE DEVELOPED SITE RUNOFF FROM THE ATTRIBUTING BASINS IS CONVEYED TO THE PROPOSED RAIN GARDEN, LOCATED NEAR THE SOUTHERN PROPERTY BOUNDARY, WHILE THE REMAINING SITE AREA RUNOFF IS CONVEYED TO STORM SYSTEMS, WHICH CONVEY RUNOFF DIRECTLY TO THE OFFSITE REGIONAL PONDS. 3.DRAINAGE DESIGN FOR THE PROPOSED SITE IS IN ACCORDANCE WITH THE MATERPLAN DEVELOPMENT, BY OTHERS. 4.PLEASE REFER TO THE RATIONAL METHOD CALCULATIONS FOR FINAL BASIN ROUTED FLOW CALCULATIONS. 5.12" OF CDOT CLASS 'A' BEDDING MATERIAL SHALL BE PLACED UNDER ALL RIPRAP SHOWN. 6.ROOF DRAINS FROM THE PROPOSED BUILDINGS ARE ANTICIPATED TO DISCHARGE OVERLAND TO NEARBY SWALES, INLETS, OR CURB AND GUTTER. 7.RUNOFF FROM THE SITE WILL DRAIN TO LOW POINTS AND PASS THROUGH CURB CUTS, SIDEWALK CHASES, SWALES, AND STORM SEWER PIPES, WHICH ULTIMATELY DISCHARGE TO THE PROPOSED ONSITE RAIN GARDEN, AND OFFSITE REGIONAL DETENTION PONDS. PERMANENT GEOTEXTILE FABRIC AND GRASS LINED DRAINAGE CHANNELS WILL ENHANCE EROSION CONTROL WITHIN THE SITE LIMITS. SITE BMP'S WILL BE IMPLEMENTED TO REDUCE SEDIMENT TRANSPORT OFFSITE, AND WILL BE SHOWN IN THE FINAL EROSION CONTROL PLAN/EXHIBIT. 8.ALL PROPOSED STORM DRAINAGE PIPES AND STRUCTURES (OUTSIDE OF PLATTED ROW) WILL BE PRIVATELY OWNED AND MAINTAINED BY THE OWNER. ALL EXISTING STORM SEWER WITHIN PUBLIC ROW, WILL BE OWNED AND MAINTAINED BY THE CITY OF FORT COLLINS. NOTES: PROPOSED DRAINAGE BASIN SUMMARY TABLE: PROPOSED DRAINAGE BASIN ID ACRES / 'C' VALUE PROPOSED DRAINAGE DESIGN POINT DRAINAGE FLOW DIRECTION DRAINAGE SWALE 0.720.43 1 PROPOSED LID SUMMARY TABLE: 4025 Automation Way, Ste B2 | Fort Collins, CO 80525 | 970-698-6046 |www.civilworxeng.com Final Drainage and Erosion Control Report Bloom Multi Family Fort Collins, CO Prepared for: Hartford Acquisitions, LLC 4801 Goodman Road Timnath, CO 80547 June 25, 2024 City of Fort Collins Approved Plans Approved by: Date: Bloom Commercial Preliminary Drainage Report APPENDIX C Hydrologic Calculations Tributary Area tc | 2-Year tc | 100-Year Q2 Q100 Sub-basin (acres)(min)(min)(cfs)(cfs) G1 18.45 0.80 1.00 17.8 17.7 25.5 111.0 G1.1 1.56 0.95 1.00 16.5 16.5 2.7 9.7 G1.2 1.36 0.95 1.00 17.2 17.2 2.3 8.3 G1.3 2.29 0.95 1.00 17.8 17.8 3.7 13.7 G1.4 0.23 0.95 1.00 5.0 5.0 0.6 2.3 G1.5 0.25 0.95 1.00 5.0 5.0 0.7 2.5 G1.6 0.39 0.95 1.00 5.1 5.0 1.0 3.8 G1.7 0.56 0.63 0.79 11.9 8.9 0.7 3.6 G1.8 2.06 0.83 1.00 7.3 5.0 4.3 20.5 G1.9 2.44 0.46 0.58 5.7 5.0 3.1 14.0 G1.10 1.00 0.85 1.00 5.0 5.0 2.4 9.9 G1.11 0.61 0.87 1.00 5.0 5.0 1.5 6.1 G1.12 0.61 0.95 1.00 5.0 5.0 1.6 6.0 G1.13 0.69 0.94 1.00 5.0 5.0 1.8 6.8 G1.14 0.32 0.75 0.94 6.1 5.0 0.6 3.0 G1.15 0.38 0.73 0.91 8.4 6.0 0.7 3.3 G1.16 0.12 0.70 0.87 5.0 5.0 0.2 1.0 G1.17 0.12 0.71 0.89 5.0 5.0 0.2 1.0 H 6.16 0.91 1.00 9.3 7.5 12.9 54.4 H1 0.61 0.80 1.00 11.6 8.8 1.0 5.0 H2 0.55 0.81 1.00 5.6 5.0 1.2 5.5 H3 0.61 0.85 1.00 5.3 5.0 1.5 6.1 H4 1.01 0.83 1.00 6.1 5.0 2.3 10.1 H5 0.35 0.62 0.78 5.0 5.0 0.6 2.7 H6 0.36 0.63 0.78 7.1 5.9 0.6 2.7 H7 5.31 0.72 0.89 9.7 6.7 8.5 43.6 H8 3.09 0.39 0.49 12.7 12.7 2.5 10.7 J 6.85 0.82 1.00 11.8 9.3 11.7 55.0 J1 0.80 0.68 0.85 12.8 11.4 1.1 5.0 BASIN SUMMARY TABLE C2 C100 Subdivision:Mulberry Project Name: Bloom Commerical Location:CO, Fort Collins Project No.: Calculated By: DSH Checked By: HHF INPUT User Input Date: 9/30/25 OUTPUT Calculated Value Single-Family Alley-Loaded SF Duplex/AttachedMulti-Family 95%5%100% G1 18.45 95 8.15 42 15 3.41 3 95 6.89 35 0.80 G1.1 1.56 95 1.56 95 15 0.00 0 95 0.00 0 0.95 G1.2 1.36 95 1.36 95 15 0.00 0 95 0.00 0 0.95 G1.3 2.29 95 2.29 95 15 0.00 0 95 0.00 0 0.95 G1.4 0.23 95 0.23 95 15 0.00 0 95 0.00 0 0.95 G1.5 0.25 95 0.25 95 15 0.00 0 95 0.00 0 0.95 G1.6 0.39 95 0.39 95 15 0.00 0 95 0.00 0 0.95 G1.7 0.56 95 0.34 57 15 0.22 6 95 0.00 0 0.63 G1.8 2.06 95 1.35 62 15 0.31 2 95 0.40 18 0.83 G1.9 2.44 95 0.00 0 15 1.55 10 100 0.89 37 0.46 G1.10 1.00 95 0.80 76 15 0.13 2 95 0.07 7 0.85 G1.11 0.61 95 0.46 71 15 0.06 1 95 0.09 15 0.87 G1.12 0.61 95 0.33 52 15 0.00 0 95 0.27 43 0.95 G1.13 0.69 95 0.24 33 15 0.01 0 95 0.44 61 0.94 G1.14 0.32 95 0.24 71 15 0.08 4 95 0.00 0 0.75 G1.15 0.38 95 0.28 69 15 0.10 4 95 0.00 0 0.73 G1.16 0.12 95 0.08 65 15 0.04 5 95 0.00 0 0.70 G1.17 0.12 95 0.08 67 15 0.04 4 95 0.00 0 0.71 H 6.16 95 3.76 58 15 0.30 1 95 2.09 32 0.91 H1 0.61 95 0.49 77 15 0.12 3 95 0.00 0 0.80 H2 0.55 95 0.46 79 15 0.09 3 95 0.00 0 0.81 H3 0.61 95 0.54 83 15 0.08 2 95 0.00 0 0.85 H4 1.01 95 0.86 81 15 0.15 2 95 0.00 0 0.83 H5 0.35 95 0.21 56 15 0.14 6 95 0.00 0 0.62 H6 0.36 95 0.21 56 15 0.15 6 95 0.00 0 0.63 H7 5.31 95 3.75 67 15 1.56 4 95 0.00 0 0.72 H8 3.09 95 0.44 14 15 2.15 10 95 0.49 15 0.39 J 6.85 95 4.80 67 15 1.11 2 95 0.94 13 0.82 J1 0.80 95 0.53 63 15 0.27 5 95 0.00 0 0.68 COMPOSITE RUNOFF COEFFICIENTS HFH73 Area (ac)Basin ID Total Area (ac)Runoff Coefficient Area Weighted C2Runoff Coefficient Area (ac) Roofs, Ponds Runoff Coefficient Area (ac)Area Weighted Asphalt + Concrete Walks Lawns, Sandy Soil Area Weighted 9/30/2025 Subdivision:Mulberry Project Name: Bloom Commerical Location:CO, Fort Collins Project No.: Calculated By: DSH Checked By: HF Date: 8/3/21 1 2 3 4 5 6 7 8 9 10 13 15 16 17 18 19 20 21 22 23 24 BASIN D.A. Hydrologic C2 C5 C100 L S Ti | 2-Year Ti | 100-Year L S Cv VEL. Tt COMP. Tc | 2-Year COMP. Tc | 100-Year TOTAL Urbanized Tc Tc | 2-Year Tc | 100-Year ID (AC) Soils Group Cf=1.00 Cf=1.00 Cf=1.25 (FT) (%) (MIN) (MIN) (FT) (%) (FPS) (MIN) (MIN) (MIN)LENGTH(FT)(MIN) (MIN) (MIN) G1 18.45 B 0.80 0.80 1.00 200 1.00 7.9 2.6 1200 1.00 20 1.3 15.1 23.0 17.7 1400 17.8 17.8 17.7 G1.1 1.56 B 0.95 0.95 1.00 55 1.00 2.1 1.4 1110 1.00 20 1.2 16.0 18.1 17.4 1165 16.5 16.5 16.5 G1.2 1.36 B 0.95 0.95 1.00 200 1.00 4.0 2.6 1100 1.00 20 1.1 16.3 20.2 18.9 1300 17.2 17.2 17.2 G1.3 2.29 B 0.95 0.95 1.00 200 2.00 3.1 2.1 1200 0.75 20 1.1 18.5 21.7 20.6 1400 17.8 17.8 17.8 G1.4 0.23 B 0.95 0.95 1.00 50 2.00 1.6 1.0 120 2.00 20 2.9 0.7 2.3 1.7 170 10.9 5.0 5.0 G1.5 0.25 B 0.95 0.95 1.00 50 2.00 1.6 1.0 120 2.00 20 3.3 0.6 2.2 1.7 170 10.9 5.0 5.0 G1.6 0.39 B 0.95 0.95 1.00 130 1.30 2.9 2.0 320 0.20 20 2.5 2.2 5.1 4.1 450 12.5 5.1 5.0 G1.7 0.56 B 0.63 0.63 0.79 75 0.50 9.6 6.4 270 1.60 20 1.8 2.5 12.1 8.9 345 11.9 11.9 8.9 G1.8 2.06 B 0.83 0.83 1.00 170 3.90 4.2 1.5 360 2.60 20 1.9 3.1 7.3 4.7 530 12.9 7.3 5.0 G1.9 2.44 B 0.46 0.46 0.58 20 1.90 4.3 3.5 210 1.50 20 2.5 1.4 5.7 4.9 230 11.3 5.7 5.0 G1.10 1.00 B 0.85 0.85 1.00 50 4.20 2.1 0.8 165 4.00 20 4.0 0.7 2.8 1.5 215 11.2 5.0 5.0 G1.11 0.61 B 0.87 0.87 1.00 130 2.20 3.7 1.6 50 0.20 20 2.8 0.3 4.0 1.9 180 11.0 5.0 5.0 G1.12 0.61 B 0.95 0.95 1.00 80 1.20 2.4 1.6 40 5.50 20 3.5 0.2 2.5 1.8 120 10.7 5.0 5.0 G1.13 0.69 B 0.94 0.94 1.00 40 1.20 1.8 1.1 230 0.70 20 2.4 1.6 3.4 2.7 270 11.5 5.0 5.0 G1.14 0.32 B 0.75 0.75 0.94 40 1.20 3.9 1.8 230 0.70 20 1.7 2.2 6.1 4.0 270 11.5 6.1 5.0 G1.15 0.38 B 0.73 0.73 0.91 40 0.70 4.9 2.5 280 1.70 20 1.3 3.5 8.4 6.0 320 11.8 8.4 6.0 G1.16 0.12 B 0.70 0.70 0.87 20 1.70 2.8 1.6 60 0.20 20 6.8 0.1 3.0 1.7 80 10.4 5.0 5.0 G1.17 0.12 B 0.71 0.71 0.89 20 1.70 2.7 1.5 60 0.20 20 6.8 0.1 2.9 1.6 80 10.4 5.0 5.0 H 6.16 B 0.91 0.91 1.00 180 2.00 3.8 2.0 280 0.40 20 0.8 5.5 9.3 7.5 460 12.6 9.3 7.5 H1 0.61 B 0.80 0.80 1.00 100 2.40 4.2 1.4 340 1.60 20 0.8 7.4 11.6 8.8 440 12.4 11.6 8.8 H2 0.55 B 0.81 0.81 1.00 30 3.70 1.9 0.7 390 1.00 20 1.8 3.7 5.6 4.4 420 12.3 5.6 5.0 H3 0.61 B 0.85 0.85 1.00 40 1.00 3.0 1.2 350 1.00 20 2.5 2.3 5.3 3.5 390 12.2 5.3 5.0 H4 1.01 B 0.83 0.83 1.00 50 1.00 3.6 1.3 370 1.00 20 2.4 2.5 6.1 3.9 420 12.3 6.1 5.0 H5 0.35 B 0.62 0.62 0.78 25 2.00 3.6 2.4 210 0.40 20 3.4 1.0 4.6 3.4 235 11.3 5.0 5.0 H6 0.36 B 0.63 0.63 0.78 25 2.00 3.5 2.4 210 0.40 20 1.0 3.6 7.1 5.9 235 11.3 7.1 5.9 H7 5.31 B 0.72 0.72 0.89 150 2.50 6.5 3.5 340 0.50 20 1.7 3.2 9.7 6.7 490 12.7 9.7 6.7 H8 3.09 B 0.39 0.39 0.49 110 0.70 15.6 13.5 370 0.40 20 1.0 6.2 21.8 19.7 480 12.7 12.7 12.7 J 6.85 B 0.82 0.82 1.00 50 0.90 3.8 1.4 450 1.20 20 0.9 8.0 11.8 9.3 500 12.8 11.8 9.3 J1 0.80 B 0.68 0.68 0.85 50 0.90 5.8 3.5 450 1.20 20 0.9 8.0 13.7 11.4 500 12.8 12.8 11.4 NOTES: Ti = (1.87*(1.1 - CCf)*(L)^0.5)/((S)^0.33), S in %Cv Tt=L/60V 2.5 Velocity V=Cv*S^0.5, S in ft/ft 5 Tc Check = 10+L/180 7 For urbanized basins a minimum Tc of 5.0 minutes is required.10 For non-urbanized basins a minimum Tc of 10.0 minutes is required 15 20 STANDARD FORM SF-2 TIME OF CONCENTRATION SUB-BASIN Tc CHECK HFH73 FINALINITIAL/OVERLAND (Ti) TRAVEL TIME (URBANIZED BASINS)(Tt) Paved Areas and Shallow Paved Swales DATA Type of Land Surface Heavy Meadow Tillage/Field Short Pasture and Lawns Nearly Bare Ground Grassed Waterway Page 1 of 1 7/14/2025 Project Name: Bloom Commerical Subdivision:Mulberry Project No.:HFH73 Location:CO, Fort Collins Calculated By: DSH Design Storm:Checked By: HF Date: TRAVEL TIME STREET De s i g n P o i n t Ba s i n I D Ar e a ( A c ) Ru n o f f C o e f f . | C 2 Tc | 2 - Y e a r ( m i n ) C* A ( A c ) I ( i n / h r ) Q ( c f s ) Tc ( m i n ) C* A ( A c ) I ( i n / h r ) Q ( c f s ) Sl o p e ( % ) St r e e t F l o w ( c f s ) De s i g n F l o w ( c f s ) Sl o p e ( % ) Pi p e S i z e ( i n c h e s ) Le n g t h ( f t ) Ve l o c i t y ( f p s ) Tt ( m i n ) REMARKS G1 G1 18.45 0.80 17.8 14.80 1.73 25.5 G1.1 G1.1 1.56 0.95 16.5 1.48 1.79 2.7 G1.2 G1.2 1.36 0.95 17.2 1.29 1.75 2.3 G1.3 G1.3 2.29 0.95 17.8 2.17 1.73 3.7 G1.4 G1.4 0.23 0.95 5.0 0.22 2.85 0.6 17.8 2.40 1.73 4.1 G1.5 G1.5 0.25 0.95 5.0 0.23 2.85 0.7 17.8 18.17 1.73 31.4 G1.6 G1.6 0.39 0.95 5.1 0.37 2.84 1.0 G1.7 G1.7 0.56 0.63 11.9 0.35 2.08 0.7 G1.8 G1.8 2.06 0.83 7.3 1.70 2.55 4.3 G1.9 G1.9 2.44 0.46 5.7 1.13 2.76 3.1 17.8 27.04 1.73 46.7 G1.10 G1.10 1.00 0.85 5.0 0.85 2.85 2.4 7.3 2.55 2.55 6.5 G1.11 G1.11 0.61 0.87 5.0 0.54 2.85 1.5 11.9 2.79 2.08 5.8 G1.12 G1.12 0.61 0.95 5.0 0.58 2.85 1.6 G1.13 G1.13 0.69 0.94 5.0 0.65 2.85 1.8 G1.14 G1.14 0.32 0.75 6.1 0.24 2.71 0.6 G1.15 G1.15 0.38 0.73 8.4 0.28 2.41 0.7 G1.16 G1.16 0.12 0.70 5.0 0.08 2.85 0.2 G1.17 G1.17 0.12 0.71 5.0 0.08 2.85 0.2 H H 6.16 0.91 9.3 5.61 2.30 12.9 H1 H1 0.61 0.80 11.6 0.49 2.10 1.0 H2 H2 0.55 0.81 5.6 0.45 2.77 1.2 H3 H3 0.61 0.85 5.3 0.52 2.81 1.5 H4 H4 1.01 0.83 6.1 0.84 2.71 2.3 H5 H5 0.35 0.62 5.0 0.22 2.85 0.6 H6 H6 0.36 0.63 7.1 0.22 2.58 0.6 H7 H7 5.31 0.72 9.7 3.80 2.24 8.5 H8 H8 3.09 0.39 12.7 1.21 2.03 2.5 6.2 13.36 2.70 36.1 J J 6.85 0.82 11.8 5.62 2.09 11.7 J1 J1 0.80 0.68 12.8 0.54 2.02 1.1 12.8 6.17 2.02 12.5 DIRECT RUNOFF TOTAL RUNOFF STREET PIPE STANDARD FORM SF-3 STORM DRAINAGE SYSTEM DESIGN (RATIONAL METHOD PROCEDURE) 2-Year 8/3/21 Page 1 of 1 7/14/2025 STANDARD FORM SF-3 STORM DRAINAGE SYSTEM DESIGN (RATIONAL METHOD PROCEDURE) Project Name: Bloom Commerical Subdivision:Mulberry Project No.:HFH73 Location:CO, Fort Collins Calculated By: DSH Design Storm: Checked By: HF Date: TRAVEL TIME STREET De s i g n P o i n t Ba s i n I D Ar e a ( A c ) Ru n o f f C o e f f . | C 10 0 Tc | 1 0 0 - Y e a r ( m i n ) C* A ( A c ) I ( i n / h r ) Q ( c f s ) Tc ( m i n ) C* A ( A c ) I ( i n / h r ) Q ( c f s ) Sl o p e ( % ) St r e e t F l o w ( c f s ) De s i g n F l o w ( c f s ) Sl o p e ( % ) Pi p e S i z e ( i n c h e s ) Le n g t h ( f t ) Ve l o c i t y ( f p s ) Tt ( m i n ) REMARKS G1 G1 18.45 1.00 17.7 18.45 6.02 111.0 G1.1 G1.1 1.56 1.00 16.5 1.56 6.25 9.7 G1.2 G1.2 1.36 1.00 17.2 1.36 6.11 8.3 G1.3 G1.3 2.29 1.00 17.8 2.29 6.01 13.7 G1.4 G1.4 0.23 1.00 5.0 0.23 9.95 2.3 17.8 2.52 6.01 15.2 G1.5 G1.5 0.25 1.00 5.0 0.25 9.95 2.5 17.7 22.00 6.02 132.4 G1.6 G1.6 0.39 1.00 5.0 0.39 9.95 3.8 G1.7 G1.7 0.56 0.79 8.9 0.44 8.22 3.6 G1.8 G1.8 2.06 1.00 5.0 2.06 9.95 20.5 G1.9 G1.9 2.44 0.58 5.0 1.41 9.95 14.0 17.8 32.19 6.01 193.4 G1.10 G1.10 1.00 1.00 5.0 1.00 9.95 9.9 5.0 3.06 9.95 30.4 G1.11 G1.11 0.61 1.00 5.0 0.61 9.95 6.1 8.9 3.20 8.22 26.3 G1.12 G1.12 0.61 1.00 5.0 0.61 9.95 6.0 G1.13 G1.13 0.69 1.00 5.0 0.69 9.95 6.8 G1.14 G1.14 0.32 0.94 5.0 0.30 9.95 3.0 G1.15 G1.15 0.38 0.91 6.0 0.35 9.51 3.3 G1.16 G1.16 0.12 0.87 5.0 0.10 9.95 1.0 G1.17 G1.17 0.12 0.89 5.0 0.11 9.95 1.0 H H 6.16 1.00 7.5 6.16 8.83 54.4 H1 H1 0.61 1.00 8.8 0.61 8.24 5.0 H2 H2 0.55 1.00 5.0 0.55 9.95 5.5 H3 H3 0.61 1.00 5.0 0.61 9.95 6.1 H4 H4 1.01 1.00 5.0 1.01 9.95 10.1 H5 H5 0.35 0.78 5.0 0.27 9.95 2.7 H6 H6 0.36 0.78 5.9 0.28 9.54 2.7 H7 H7 5.31 0.89 6.7 4.75 9.18 43.6 H8 H8 3.09 0.49 12.7 1.52 7.08 10.7 6.2 15.76 9.43 148.7 J J 6.85 1.00 9.3 6.85 8.02 55.0 J1 J1 0.80 0.85 11.4 0.68 7.38 5.0 11.4 7.53 7.38 55.6 PIPE 100-Year DIRECT RUNOFF TOTAL RUNOFF STREET 6/2/21 Page 1 of 1 7/14/2025 Bloom Commercial Preliminary Drainage Report APPENDIX D Hydraulic Calculations Bloom Commercial Final Drainage Report Street and Inlet Capacity Calculations ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.7 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =13.5 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 6.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 18.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 16.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.318 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.7 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =6.0 6.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.0 6.0 cfs Interception with Clogging Qwa =5.4 5.4 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 9.8 cfs Interception with Clogging Qoa =8.8 8.8 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.1 7.1 cfs Interception with Clogging Qma =6.4 6.4 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.4 5.4 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =18.7 18.7 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.33 0.33 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.4 5.4 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =0.7 3.6 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.7 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.8 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =15.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.016 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =50.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.005 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =50.0 50.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 12.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =3.00 3.00 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.87 1.87 inches Water Depth at Gutter Flowline (y + a)d =4.87 4.87 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =48.0 48.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.156 0.156 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =68.8 168.8 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =66.8 166.8 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.104 0.036 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.8 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT/Denver 13 Combination Local Depression (additional to continuous gutter depression 'a' from above)alocal =2.00 2.00 inches Number of Unit Inlets (Grate or Curb Opening)No =4 4 Water Depth at Flowline (outside of local depression)Ponding Depth =4.9 8.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =3.00 3.00 feet Width of a Unit Grate Wo =1.73 1.73 feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =0.43 0.43 Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =0.50 0.50 Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =3.30 3.30 Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =0.60 0.60 Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =3.00 3.00 feet Height of Vertical Curb Opening in Inches Hvert =6.50 6.50 inches Height of Curb Orifice Throat in Inches Hthroat =5.25 5.25 inches Angle of Throat Theta =0.00 0.00 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.70 3.70 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.66 0.66 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.88 1.88 Clogging Factor for Multiple Units Clog =0.24 0.24 Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =4.6 15.4 cfs Interception with Clogging Qwa =3.5 11.8 cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =28.1 35.7 cfs Interception with Clogging Qoa =21.5 27.3 cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =10.6 21.8 cfs Interception with Clogging Qma =8.1 16.7 cfs Resulting Grate Capacity (assumes clogged condition)QGrate =3.5 11.8 cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.25 1.25 Clogging Factor for Multiple Units Clog =0.05 0.05 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =3.1 15.4 cfs Interception with Clogging Qwa =3.0 14.6 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =21.0 25.4 cfs Interception with Clogging Qoa =19.9 24.1 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.0 17.0 cfs Interception with Clogging Qma =6.6 16.1 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =3.0 14.6 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =12.00 12.00 feet Resultant Street Flow Spread (based on street geometry from above)T =50.0 102.1 ft. >T-Crown Resultant Flow Depth at Street Crown dCROWN =0.0 3.1 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =0.43 0.69 ft Depth for Curb Opening Weir Equation dCurb =0.24 0.50 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =0.46 0.75 Curb Opening Performance Reduction Factor for Long Inlets RFCurb =N/A N/A Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =0.46 0.75 MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.3 21.6 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =4.3 20.5 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.8 9/29/2025, 11:00 AM Location:DP G1.10 Grate:CDOT Type C w/Close Mesh Grate Number of Grates:1 Length:3.00 ft 3.00 ft Width:3.00 ft 3.00 ft Number of Sides:4 Open Area:9.00 sq ft w/Adjustment:6.30 sq ft Open area ratio:0.70 Clogging factor:50% n:35% Weir Length, L 12.00 ft Open Area, A 9.00 sq ft Stage, ∆d 0.15 ft Weir Calculation:Orifice Calculation: Qw = ⅔nCdL(2g)1/2H3/2 Qo = ⅔nCdBL(2gH)1/2 Cd 0.79 *per MHFD Cd 0.79 *per MHFD Qw = nCwLH3/2 Qo =nC0BL(2gH)1/2 Cw 2.06 *per MHFD C0 0.64 *per MHFD Water Depth, d Elevation QW-INLET QO-INLET Inflow QW-INLET QO-INLET Inflow ft ft cfs cfs cfs cfs cfs cfs 0.00 4936.75 0.00 0.00 0.00 0.00 0.00 0.00 0.15 4936.90 0.77 5.16 0.77 0.38 6.27 0.38 0.30 4937.05 2.19 7.29 2.19 1.07 8.86 1.07 0.45 4937.20 4.02 8.93 4.02 1.96 10.85 1.96 0.60 4937.35 6.19 10.31 6.19 3.02 12.53 3.02 0.75 4937.50 8.65 11.53 8.65 4.21 14.01 4.21 0.90 4937.65 11.37 12.63 11.37 5.54 15.35 5.54 1.05 4937.80 14.32 13.64 13.64 6.98 16.58 6.98 1.20 4937.95 17.50 14.58 14.58 8.53 17.72 8.53 1.35 4938.10 20.88 15.47 15.47 10.18 18.80 10.18 1.50 4938.25 24.46 16.31 16.31 11.92 19.81 11.92 w/Flow Coefficient, Cd w/Coefficients Cw and Co 0.0 5.0 10.0 15.0 20.0 25.0 30.0 0.00 1.00 In l e t C a p a c i t y , c f s Depth of Flow, ft Qw-INLET Qo-INLET Inflow Input Type of Grate 24" Dome Head (ft) 1.33 Properties Orifice Flow Area (in)265.19 Orifice Flow Area (ft)1.83 Weir Flow Perimeter (in)71.47 Weir Flow Perimeter (ft)5.96 Solution Capacity (cfs)10.16 Capacity (gpm)4558.31 REV 2.1.21 Nyloplast Inlet Capacity Table DISCLAIMER: SAFETY FACTORS ARE NOT INCLUDED IN THESE CALCULATIONS. ACTUAL CALCULATIONS SHOULD BE CARRIED OUT AND VERIFIED BY THE DESIGN ENGINEER TAKING INTO ACCOUNT ALL LOCAL CONDITIONS. NYLOPLAST RECOMMENDS USING A MINIMUM SAFETY FACTOR OF 1.25 FOR PAVED AREAS AND 2.0 FOR TURF AREAS. ADS/NYLOPLAST IS NOT RESPONSIBLE FOR MISUSE OF THIS TOOL. ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.13 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =16.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 7.2 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 23.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 21.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.248 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.13 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =6.1 7.2 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.1 8.9 cfs Interception with Clogging Qwa =5.5 8.0 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 10.6 cfs Interception with Clogging Qoa =8.8 9.6 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.2 9.0 cfs Interception with Clogging Qma =6.5 8.1 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.5 8.0 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =19.0 23.7 ft. >T-Crown Resultant Flow Depth at Street Crown dCROWN =0.0 1.1 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.34 0.43 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.5 8.0 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =1.8 6.8 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.13 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.14 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =16.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 7.2 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 23.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 21.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.248 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.14 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =6.0 7.2 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.0 8.9 cfs Interception with Clogging Qwa =5.4 8.0 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 10.6 cfs Interception with Clogging Qoa =8.8 9.6 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.1 9.0 cfs Interception with Clogging Qma =6.4 8.1 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.4 8.0 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =18.7 23.7 ft. >T-Crown Resultant Flow Depth at Street Crown dCROWN =0.0 1.1 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.33 0.43 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.4 8.0 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =0.6 3.0 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.14 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.15 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =13.5 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 6.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 18.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 16.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.318 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.15 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =6.0 6.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.0 6.0 cfs Interception with Clogging Qwa =5.4 5.4 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 9.8 cfs Interception with Clogging Qoa =8.8 8.8 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.1 7.1 cfs Interception with Clogging Qma =6.4 6.4 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.4 5.4 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =18.7 18.7 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.33 0.33 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.4 5.4 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =0.7 3.3 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.15 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.16 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =16.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =2.8 3.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =5.2 6.2 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =3.2 4.2 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.876 0.807 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.16 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =2.8 3.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =0.5 0.7 cfs Interception with Clogging Qwa =0.4 0.6 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =6.8 7.1 cfs Interception with Clogging Qoa =6.1 6.4 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =1.6 2.1 cfs Interception with Clogging Qma =1.5 1.9 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =0.4 0.6 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =5.2 6.2 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.06 0.08 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =0.91 0.93 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =0.4 0.6 cfs WARNING: Inlet Capacity < Q Peak for Major Storm Q PEAK REQUIRED =0.2 1.0 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.16 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP G1.17 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =16.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =2.8 3.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =5.2 6.2 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =3.2 4.2 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.876 0.807 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.17 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =2.8 3.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =0.5 0.7 cfs Interception with Clogging Qwa =0.4 0.6 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =6.8 7.1 cfs Interception with Clogging Qoa =6.1 6.4 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =1.6 2.1 cfs Interception with Clogging Qma =1.5 1.9 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =0.4 0.6 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =5.2 6.2 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.06 0.08 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =0.91 0.93 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =0.4 0.6 cfs WARNING: Inlet Capacity < Q Peak for Major Storm Q PEAK REQUIRED =0.2 1.0 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP G1.17 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP H5 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =16.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.250 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 6.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 18.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 16.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.318 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP H5 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type =CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =6.0 6.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.0 6.0 cfs Interception with Clogging Qwa =5.4 5.4 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 9.8 cfs Interception with Clogging Qoa =8.8 8.8 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.1 7.1 cfs Interception with Clogging Qma =6.4 6.4 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.4 5.4 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =18.7 18.7 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.33 0.33 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.4 5.4 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =0.6 2.7 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP H5 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP H6 Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =16.0 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W =2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 6.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a)d =6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d =0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 18.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 16.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.318 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor)Q =SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V =0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d =0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R =SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied)d =inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP H6 9/29/2025, 11:00 AM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening)No =1 1 Water Depth at Flowline (outside of local depression)Ponding Depth =6.0 6.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =N/A N/A Clogging Factor for Multiple Units Clog =N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef =1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.0 6.0 cfs Interception with Clogging Qwa =5.4 5.4 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 9.8 cfs Interception with Clogging Qoa =8.8 8.8 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.1 7.1 cfs Interception with Clogging Qma =6.4 6.4 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.4 5.4 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L =5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above)T =18.7 18.7 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.33 0.33 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.4 5.4 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =0.6 2.7 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP H6 9/29/2025, 11:00 AM ALLOWABLE CAPACITY FOR ONE-HALF OF STREET (Minor & Major Storm) (Based on Regulated Criteria for Maximum Allowable Flow Depth and Spread) Project:HFH073 | Bloom Commercial Inlet ID:DP J Gutter Geometry: Maximum Allowable Width for Spread Behind Curb TBACK =13.5 ft Side Slope Behind Curb (leave blank for no conveyance credit behind curb)SBACK =0.020 ft/ft Warning 01 Manning's Roughness Behind Curb (typically between 0.012 and 0.020)nBACK =0.025 Height of Curb at Gutter Flow Line HCURB =6.00 inches Distance from Curb Face to Street Crown TCROWN =19.0 ft Gutter Width W = 2.00 ft Street Transverse Slope SX =0.020 ft/ft Gutter Cross Slope (typically 2 inches over 24 inches or 0.083 ft/ft)SW =0.083 ft/ft Street Longitudinal Slope - Enter 0 for sump condition SO =0.000 ft/ft Manning's Roughness for Street Section (typically between 0.012 and 0.020)nSTREET =0.016 Minor Storm Major Storm Max. Allowable Spread for Minor & Major Storm TMAX =19.0 19.0 ft Max. Allowable Depth at Gutter Flowline for Minor & Major Storm dMAX =6.0 6.0 inches Check boxes are not applicable in SUMP conditions Maximum Capacity for 1/2 Street based On Allowable Spread Minor Storm Major Storm Water Depth without Gutter Depression (T * Sx * 12)y =4.56 4.56 inches Vertical Depth between Gutter Lip and Gutter Flowline (W * Sw * 12)dC =2.0 2.0 inches Gutter Depression (dC - (W * Sx * 12))a =1.51 1.51 inches Water Depth at Gutter Flowline (y + a) d = 6.07 6.07 inches Allowable Spread for Discharge outside the Gutter Section (T - W)TX =17.0 17.0 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.313 0.313 Discharge outside the Gutter Section, carried in Section TX QX =0.0 0.0 cfs Discharge within the Gutter Section (QT - QX - QBACK)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Maximum Flow Based On Allowable Spread QT =SUMP SUMP cfs Flow Velocity within the Gutter Section V = 0.0 0.0 fps V*d Product: Flow Velocity times Gutter Flowline Depth V*d = 0.0 0.0 Maximum Capacity for 1/2 Street based on Allowable Depth Minor Storm Major Storm Theoretical Water Spread TTH =18.7 18.7 ft Theoretical Spread for Discharge outside the Gutter Section (T - W)TX TH =16.7 16.7 ft Gutter Flow to Design Flow Ratio by FHWA HEC-22 method (Eq. 7-7)EO =0.318 0.318 Theoretical Discharge outside the Gutter Section, carried in Section TX TH QX TH =0.0 0.0 cfs Actual Discharge outside the Gutter Section, (limited by distance TCROWN)QX =0.0 0.0 cfs Discharge within the Gutter Section (Qd - QX)QW =0.0 0.0 cfs Discharge Behind the Curb (e.g., sidewalk, driveways, & lawns)QBACK =0.0 0.0 cfs Total Discharge for Major & Minor Storm (Pre-Safety Factor) Q = SUMP SUMP cfs Average Flow Velocity Within the Gutter Section V = 0.0 0.0 fps V*d Product: Flow Velocity Times Gutter Flowline Depth V*d = 0.0 0.0 Slope-Based Safety Factor for Minor/Major Storm depth reduction, d > 6"R = SUMP SUMP Max Flow based on Allowable Depth (Safety Factor Applied)Qd =SUMP SUMP cfs Resultant Flow Depth at Gutter Flowline (Safety Factor Applied) d = inches Resultant Flow Depth at Street Crown (Safety Factor Applied)dCROWN =inches MINOR STORM Allowable Capacity is not applicable to Sump Condition Minor Storm Major Storm MAJOR STORM Allowable Capacity is not applicable to Sump Condition Qallow =SUMP SUMP cfs Warning 01: Manning's n-value does not meet the USDCM recommended design range. MHFD-Inlet, Version 6.00 (August 2025) HFH073_MHFD-Inlet_v6.00.xlsm, DP J 9/30/2025, 1:08 PM INLET IN A SUMP OR SAG LOCATION MHFD-Inlet, Version 6.00 (August 2025) Design Information (Input)MINOR MAJOR Type of Inlet Type = CDOT Type R Curb Opening Local Depression (additional to continuous gutter depression 'a' from above)alocal =3.00 3.00 inches Number of Unit Inlets (Grate or Curb Opening) No = 1 1 Water Depth at Flowline (outside of local depression) Ponding Depth = 6.0 6.0 inches Grate Information MINOR MAJOR Length of a Unit Grate Lo (G) =N/A N/A feet Width of a Unit Grate Wo =N/A N/A feet Open Area Ratio for a Grate (typical values 0.15-0.90)Aratio =N/A N/A Clogging Factor for a Single Grate (typical value 0.50 - 0.70)Cf (G) =N/A N/A Grate Weir Coefficient (typical value 2.15 - 3.60)Cw (G) =N/A N/A Grate Orifice Coefficient (typical value 0.60 - 0.80)Co (G) =N/A N/A Curb Opening Information MINOR MAJOR Length of a Unit Curb Opening Lo (C) =5.00 5.00 feet Height of Vertical Curb Opening in Inches Hvert =6.00 6.00 inches Height of Curb Orifice Throat in Inches Hthroat =6.00 6.00 inches Angle of Throat Theta =63.40 63.40 degrees Side Width for Depression Pan (typically the gutter width of 2 feet)Wp =2.00 2.00 feet Clogging Factor for a Single Curb Opening (typical value 0.10)Cf (C) =0.10 0.10 Curb Opening Weir Coefficient (typical value 2.3-3.7)Cw (C) =3.60 3.60 Curb Opening Orifice Coefficient (typical value 0.60 - 0.70)Co (C) =0.67 0.67 Grate Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef = N/A N/A Clogging Factor for Multiple Units Clog = N/A N/A Grate Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =N/A N/A cfs Interception with Clogging Qwa =N/A N/A cfs Grate Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =N/A N/A cfs Interception with Clogging Qoa =N/A N/A cfs Grate Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =N/A N/A cfs Interception with Clogging Qma =N/A N/A cfs Resulting Grate Capacity (assumes clogged condition)QGrate =N/A N/A cfs Curb Opening Flow Analysis (Calculated)MINOR MAJOR Clogging Coefficient for Multiple Units Coef = 1.00 1.00 Clogging Factor for Multiple Units Clog =0.10 0.10 Curb Capacity as a Weir (based on MHFD - CSU 2010 Study)MINOR MAJOR Interception without Clogging Qwi =6.0 6.0 cfs Interception with Clogging Qwa =5.4 5.4 cfs Curb Capacity as an Orifice (based on MHFD - CSU 2010 Study) MINOR MAJOR Interception without Clogging Qoi =9.8 9.8 cfs Interception with Clogging Qoa =8.8 8.8 cfs Curb Opening Capacity as Mixed Flow MINOR MAJOR Interception without Clogging Qmi =7.1 7.1 cfs Interception with Clogging Qma =6.4 6.4 cfs Resulting Curb Opening Capacity (assumes clogged condition)QCurb =5.4 5.4 cfs Resultant Street Conditions MINOR MAJOR Total Inlet Length L = 5.00 5.00 feet Resultant Street Flow Spread (based on street geometry from above) T = 18.7 18.7 ft Resultant Flow Depth at Street Crown dCROWN =0.0 0.0 inches Low Head Performance Reduction (Calculated)MINOR MAJOR Depth for Grate Midwidth dGrate =N/A N/A ft Depth for Curb Opening Weir Equation dCurb =0.33 0.33 ft Grated Inlet Performance Reduction Factor for Long Inlets RFGrate =N/A N/A Curb Opening Performance Reduction Factor for Long Inlets RFCurb =1.00 1.00 Combination Inlet Performance Reduction Factor for Long Inlets RFCombination =N/A N/A MINOR MAJOR Total Inlet Interception Capacity (assumes clogged condition)Qa =5.4 5.4 cfs Inlet Capacity IS GOOD for Minor and Major Storms (>Q Peak)Q PEAK REQUIRED =1.1 5.0 cfs H-VertH-Curb W Lo (C) Lo (G) Wo WP Override Depths HFH073_MHFD-Inlet_v6.00.xlsm, DP J 9/30/2025, 1:08 PM DP J1 | 5' Wide Curb Chase Project Description DischargeSolve For Input Data ft4,930.65Headwater Elevation ft4,930.15Crest Elevation ft4,930.15Tailwater Elevation ft^(1/2)/s2.85Weir Coefficient ft5.0Crest Length 2Number Of Contractions Results cfs4.9Discharge ft0.50Headwater Height Above Crest ft0.00Tailwater Height Above Crest ft²2.5Flow Area ft/s1.97Velocity ft6.0Wetted Perimeter ft5.00Top Width Page 1 of 127 Siemon Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 9/30/2025 FlowMaster [10.03.00.03] Bentley Systems, Inc. Haestad Methods Solution CenterHFH073_FlowMaster.fm8 Bloom Commercial Final Drainage Report StormCAD Output FlexTable: Conduit Table Start Node Invert (Start) (ft) Stop Node Invert (Stop) (ft) Length (User Defined) (ft) Slope (Calculated) (ft/ft) Section Type Diameter (in) Manning's n Flow (cfs) Velocity (ft/s) Upstream Structure Hydraulic Grade Line (In) (ft) Hydraulic Grade Line (In) (ft) Energy Grade Line (In) (ft) Hydraulic Grade Line (Out) (ft) Downstream Structure Hydraulic Grade Line (Out) (ft) Energy Grade Line (Out) (ft) SD OUTLET A6.1 4,927.02 SDMH A6 4,926.59 34.4 0.012 Circle 24 0.013 11.9 3.79 4,929.73 4,929.64 4,929.86 4,929.54 4,929.45 4,929.77 SDMH A4 4,925.76 SDMH A3 4,924.82 385.8 0.002 Circle 24 0.013 11.9 3.79 4,928.23 4,928.18 4,928.40 4,927.11 4,927.00 4,927.33 SDMH A5 4,926.49 SDMH A4 4,925.76 300.6 0.002 Circle 24 0.013 11.9 3.79 4,929.21 4,929.15 4,929.37 4,928.32 4,928.23 4,928.54 SDMH A6 4,926.59 SDMH A5 4,926.49 39.3 0.002 Circle 24 0.013 11.9 3.79 4,929.45 4,929.41 4,929.63 4,929.30 4,929.19 4,929.52 SDMH A3 4,924.82 SDMH A2 4,924.47 141.2 0.002 Circle 24 0.013 11.9 3.79 4,927.02 4,926.95 4,927.18 4,926.56 4,926.45 4,926.79 SDMH A2 4,924.27 EXISTING SD INLET A1 4,924.07 111.1 0.002 Circle 24 0.013 12.4 3.95 4,926.45 4,926.40 4,926.65 4,926.07 (N/A)4,926.31 SD OUTLET A2.1 4,924.58 SDMH A2 4,924.47 27.0 0.004 Circle 18 0.013 0.5 0.30 4,926.70 4,926.70 4,926.70 4,926.70 4,926.45 4,926.70 SDMH B3 4,927.98 SD INLET B2 4,927.81 87.6 0.002 Circle 42 0.013 18.8 1.96 4,935.15 4,935.10 4,935.16 4,935.07 4,934.98 4,935.13 SDMH B4 4,928.58 SDMH B3 4,927.98 297.9 0.002 Circle 36 0.013 19.9 2.82 4,935.46 4,935.40 4,935.52 4,935.13 4,935.11 4,935.26 SDMH B7 4,930.03 SDMH B6 4,929.62 101.9 0.004 Circle 24 0.013 0.0 0.00 4,936.03 4,936.03 4,936.03 4,936.03 4,936.03 4,936.03 SDMH B8 4,930.40 SDMH B7 4,930.23 42.5 0.004 Circle 24 0.013 0.0 0.00 4,935.60 4,936.03 4,936.03 4,936.03 4,936.03 4,936.03 SD INLET B2 4,927.81 STORM FES B1 4,927.56 125.4 0.002 Circle 42 0.013 22.7 2.36 4,935.02 4,934.96 4,935.05 4,934.90 (N/A)4,934.99 SDMH B5.1 4,929.64 SDMH B5 4,929.19 111.8 0.004 Circle 24 0.013 2.0 0.63 4,935.69 4,935.69 4,935.70 4,935.68 4,935.60 4,935.69 SDMH B5 4,928.99 SDMH B4 4,928.78 105.5 0.002 Circle 36 0.013 12.9 1.82 4,935.63 4,935.59 4,935.65 4,935.56 4,935.42 4,935.61 SDMH B6 4,929.42 SDMH B5 4,929.19 115.7 0.002 Circle 24 0.013 11.5 3.67 4,936.03 4,935.86 4,936.07 4,935.56 4,935.60 4,935.77 SD INLET B6.1 4,929.65 SDMH B6 4,929.62 14.0 0.002 Circle 24 0.013 8.7 2.77 4,935.59 4,936.05 4,936.17 4,936.03 4,936.03 4,936.28 SD INLET B6.1A 4,929.72 SDMH B6 4,929.62 24.0 0.004 Circle 24 0.013 3.3 1.05 4,935.59 4,936.03 4,936.05 4,936.03 4,936.03 4,936.24 SD INLET B5.2 4,929.95 SDMH B5.1 4,929.84 29.0 0.004 Circle 24 0.013 1.0 0.33 4,935.58 4,935.70 4,935.70 4,935.70 4,935.69 4,935.70 SD INLET B5.1-1 4,929.87 SDMH B5.1 4,929.84 9.0 0.004 Circle 24 0.013 1.1 0.34 4,935.58 4,935.70 4,935.70 4,935.70 4,935.69 4,935.70 SD INLET B4.1A 4,928.90 SDMH B4 4,928.78 29.0 0.004 Circle 24 0.013 6.9 2.20 4,935.56 4,935.57 4,935.64 4,935.54 4,935.42 4,935.62 SD INLET B4.1 4,928.82 SDMH B4 4,928.78 9.0 0.004 Circle 24 0.013 2.9 0.91 4,935.56 4,935.58 4,935.59 4,935.58 4,935.42 4,935.59 SD INLET B6.2 4,931.29 SD INLET B6.1 4,931.15 69.1 0.002 Circle 18 0.013 6.1 3.46 4,934.60 4,935.82 4,936.01 4,935.59 4,935.59 4,936.24 SDMH C2.1 4,928.72 SDMH C2 4,928.36 89.4 0.004 Circle 18 0.013 5.3 3.00 4,932.78 4,932.66 4,932.80 4,932.43 4,931.41 4,932.57 SDMH C2 4,928.16 STORM FES C1 4,928.07 46.6 0.002 Circle 36 0.013 59.5 8.42 4,931.41 4,931.19 4,932.29 4,930.56 (N/A)4,931.96 SDMH C3 4,928.49 SDMH C2 4,928.36 66.1 0.002 Circle 30 0.013 54.9 11.18 4,932.92 4,932.53 4,934.47 4,931.35 4,931.41 4,933.29 SD INLET C2.1-1 4,928.95 SDMH C2.1 4,928.92 9.0 0.004 Circle 18 0.013 2.7 1.53 4,932.92 4,932.90 4,932.94 4,932.90 4,932.69 4,932.93 SD INLET C2.2 4,929.03 SDMH C2.1 4,928.92 29.0 0.004 Circle 18 0.013 2.7 1.55 4,932.93 4,932.91 4,932.95 4,932.89 4,932.69 4,932.93 SDMH D3 4,925.47 SDMH D2 4,925.41 30.0 0.002 Circle 24 0.013 5.1 1.61 4,928.36 4,928.35 4,928.39 4,928.33 4,928.20 4,928.37 SDMH D2 4,925.41 SD FES D1 4,925.32 43.5 0.002 Circle 24 0.013 10.0 3.19 4,928.20 4,928.17 4,928.32 4,928.08 (N/A)4,928.24 SD FES F1 4,924.70 SD FES F2 4,924.42 137.4 0.002 Circle 24 0.013 0.0 0.00 (N/A)4,924.70 4,924.70 4,924.42 (N/A)4,924.42 SD INLET G2 4,928.52 SD FES G1 4,928.04 118.5 0.004 Circle 36 0.013 28.3 4.01 4,935.27 4,935.21 4,935.46 4,935.00 (N/A)4,935.25 SD INLET G3 4,929.92 SD INLET G2 4,928.72 301.4 0.004 Circle 36 0.013 20.7 2.92 4,935.70 4,935.73 4,935.86 4,935.44 4,935.26 4,935.57 HFH073_StomCAD.stsw StormCAD [24.00.03.23] 9/30/2025 Page 1 of 1 Know what's before you dig. PGS JEP UTILITY PLAN 38 C5.1 - - - - - - - - - - - - - - H: \ H \ H a r t f o r d H o m e s \ C O F o r t C o l l i n s H F H 7 3 - B l o o m C o m m e r c i a l \ 0 C I V \ 3 - C D \ F D P \ H F H 0 7 3 _ C 5 . 0 - U t i l i t y P l a n F D P . d w g - Lu k e K e r n s - 10 / 1 / 2 0 2 5 BL O O M F I L I N G N I N E FI N A L D E V E L O P M E N T P L A N FO R T C O L L I N S , C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 GallowayUS.com NOT F O R CON S T R U C T I O N #Date Issue / Description Init. Project No: Drawn By: Checked By: Date: HFH000073.20 10/01/2025 Sheet of 68 REVIEW DOES NOT CONSTITUTE "APPROVAL" OF PLANS. DESIGN ENGINEER IS RESPONSIBLE FOR ACCURACY AND COMPLETENESS OF DESIGN. GENERAL MANAGER REVIEWED BY: DATE EAST LARIMER COUNTY WATER DISTRICT UTILITY PLAN REVIEW Know what's before you dig. PGS JEP UTILITY PLAN 39 C5.2 - - - - - - - - - - - - - - H: \ H \ H a r t f o r d H o m e s \ C O F o r t C o l l i n s H F H 7 3 - B l o o m C o m m e r c i a l \ 0 C I V \ 3 - C D \ F D P \ H F H 0 7 3 _ C 5 . 0 - U t i l i t y P l a n F D P . d w g - Lu k e K e r n s - 10 / 1 / 2 0 2 5 BL O O M F I L I N G N I N E FI N A L D E V E L O P M E N T P L A N FO R T C O L L I N S , C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 GallowayUS.com NOT F O R CON S T R U C T I O N #Date Issue / Description Init. Project No: Drawn By: Checked By: Date: HFH000073.20 10/01/2025 Sheet of 68 REVIEW DOES NOT CONSTITUTE "APPROVAL" OF PLANS. DESIGN ENGINEER IS RESPONSIBLE FOR ACCURACY AND COMPLETENESS OF DESIGN. GENERAL MANAGER REVIEWED BY: DATE EAST LARIMER COUNTY WATER DISTRICT UTILITY PLAN REVIEW Know what's before you dig. PGS JEP UTILITY PLAN 40 C5.3 - - - - - - - - - - - - - - H: \ H \ H a r t f o r d H o m e s \ C O F o r t C o l l i n s H F H 7 3 - B l o o m C o m m e r c i a l \ 0 C I V \ 3 - C D \ F D P \ H F H 0 7 3 _ C 5 . 0 - U t i l i t y P l a n F D P . d w g - Lu k e K e r n s - 10 / 1 / 2 0 2 5 BL O O M F I L I N G N I N E FI N A L D E V E L O P M E N T P L A N FO R T C O L L I N S , C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 GallowayUS.com NOT F O R CON S T R U C T I O N #Date Issue / Description Init. Project No: Drawn By: Checked By: Date: HFH000073.20 10/01/2025 Sheet of 68 REVIEW DOES NOT CONSTITUTE "APPROVAL" OF PLANS. DESIGN ENGINEER IS RESPONSIBLE FOR ACCURACY AND COMPLETENESS OF DESIGN. GENERAL MANAGER REVIEWED BY: DATE EAST LARIMER COUNTY WATER DISTRICT UTILITY PLAN REVIEW Know what's before you dig. PGS JEP UTILITY PLAN 41 C5.4 - - - - - - - - - - - - - - H: \ H \ H a r t f o r d H o m e s \ C O F o r t C o l l i n s H F H 7 3 - B l o o m C o m m e r c i a l \ 0 C I V \ 3 - C D \ F D P \ H F H 0 7 3 _ C 5 . 0 - U t i l i t y P l a n F D P . d w g - Lu k e K e r n s - 10 / 1 / 2 0 2 5 BL O O M F I L I N G N I N E FI N A L D E V E L O P M E N T P L A N FO R T C O L L I N S , C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 GallowayUS.com NOT F O R CON S T R U C T I O N #Date Issue / Description Init. Project No: Drawn By: Checked By: Date: HFH000073.20 10/01/2025 Sheet of 68 REVIEW DOES NOT CONSTITUTE "APPROVAL" OF PLANS. DESIGN ENGINEER IS RESPONSIBLE FOR ACCURACY AND COMPLETENESS OF DESIGN. GENERAL MANAGER REVIEWED BY: DATE EAST LARIMER COUNTY WATER DISTRICT UTILITY PLAN REVIEW Bloom Commercial Preliminary Drainage Report Detention Project Number:HFH73 | Bloom Commerical Project Location:Fort Collins, Colorado Date: 9/30/2025 Calculations By:H. Feissner Pond Description:POND G1 User Input Cell:Blue Text Design Point:N/A Design Storm:WQCV Required Volume:10803 ft3 4928.21 ft Design Storm:100-year Required Volume:299529 ft3 4935.00 ft Design Storm:N/A Required Volume:0 ft3 N/A ft Contour Elevation Contour Area Depth Incremental Volume Cummulative Volume Incremental Volume Cummulative Volume Cummulative Volume ft ft2 ft ft3 ft3 ft3 ft3 ac-ft 4927.00 0 0 0 0 0 0 0.0 4928.00 17088 1.00 8544 8544 5696 5696 0.1 4929.00 33283 1.00 25185 33729 24740 30436 0.7 4930.00 37173 1.00 35228 68958 35210 65646 1.5 4931.00 40897 1.00 39035 107993 39020 104666 2.4 4932.00 44715 1.00 42806 150799 42792 147458 3.4 4933.00 48638 1.00 46677 197476 46663 194121 4.5 4934.00 52680 1.00 50659 248135 50646 244767 5.6 4935.00 56872 1.00 54776 302910 54762 299529 6.9 Detention Pond Stage-Storage Calculations Required Volume Water Surface Elevation Average End Area Method: Conic Volume Method: 4927 4928 4929 4930 4931 4932 4933 4934 4935 4936 0 50000 100000 150000 200000 250000 300000 350000 Co n t o u r E l e v a t i o n , f t Cummulative Volume, ft3 Stage - Storage | POND G1 Hydraulic Analysis Report Project Data Project Title: HFH073 | Bloom Commercial Designer: Herman Feissner Project Date: Monday, September 29, 2025 Project Units: U.S. Customary Units Notes: Sized to pass 100-yr storm event maximum inflow estimated with SWMM Weir Analysis: POND G1 Spillway Notes: Input Parameters Irregular Weir Coefficient: 2.8000 Irregular Weir Geometry Station (ft) Elevation (ft) 0.00 4936.00 4.00 4935.00 199.00 4935.00 203.00 4936.00 Tailwater (above crest): 0.00 ft Applied Coefficients 0 2.8 1 2.8 2 2.8 Flow: 196.3000 cfs Result Parameters Head: 0.5031 ft Project Number:HFH73 | Bloom Commercial Project Location:Fort Collins, Colorado Date: 9/30/2025 Calculations By:H. Feissner Pond Description:POND H (existing ) User Input Cell:Blue Text Design Point:N/A Design Storm:WQCV Required Volume:2526 ft3 4923.62 ft Design Storm:100-year Required Volume:142128 ft3 4930.04 ft Design Storm:N/A Required Volume:0 ft3 N/A ft Contour Elevation Contour Area Depth Incremental Volume Cummulative Volume Incremental Volume Cummulative Volume Cummulative Volume ft ft2 ft ft3 ft3 ft3 ft3 ac-ft 4923.00 0 0 0 0 0 0 0.0 4923.50 7500 0.50 1875 1875 1250 1250 0.0 4924.00 13790 0.50 5323 7198 5243 6493 0.1 4925.00 16538 1.00 15164 22362 15143 21637 0.5 4926.00 19374 1.00 17956 40318 17937 39574 0.9 4927.00 22335 1.00 20855 61172 20837 60411 1.4 4928.00 25254 1.00 23795 84967 23780 84190 1.9 4929.00 28226 1.00 26740 111707 26726 110917 2.5 4930.00 31335 1.00 29781 141487 29767 140684 3.2 4931.00 34469 1.00 32902 174389 32890 173573 4.0 4932.00 35000 1.00 34735 209124 34734 208307 4.8 Detention Pond Stage-Storage Calculations Required Volume Water Surface Elevation Average End Area Method: Conic Volume Method: 4923 4924 4925 4926 4927 4928 4929 4930 4931 4932 0 50000 100000 150000 200000 250000 Co n t o u r E l e v a t i o n , f t Cummulative Volume, ft3 Stage - Storage | POND H (existing) Project Number:HFH73 | Bloom Commercial Project Location:Fort Collins, Colorado Date: 9/30/2025 Calculations By:H. Feissner Pond Description:POND J User Input Cell:Blue Text Design Point:N/A Design Storm:WQCV Required Volume:1655 ft3 4924.88 ft Design Storm:100-year Required Volume:79564 ft3 4929.36 ft Design Storm:N/A Required Volume:0 ft3 N/A ft Contour Elevation Contour Area Depth Incremental Volume Cummulative Volume Incremental Volume Cummulative Volume Cummulative Volume ft ft2 ft ft3 ft3 ft3 ft3 ac-ft 4924.50 0 0 0 0 0 0 0.0 4925.00 12972 0.50 3243 3243 2162 2162 0.0 4926.00 15030 1.00 14001 17244 13988 16150 0.4 4927.00 17188 1.00 16109 33353 16097 32247 0.7 4928.00 19447 1.00 18318 51671 18306 50553 1.2 4929.00 21806 1.00 20627 72297 20615 71168 1.6 4930.00 24266 1.00 23036 95333 23025 94193 2.2 Detention Pond Stage-Storage Calculations Required Volume Water Surface Elevation Average End Area Method: Conic Volume Method: 4925 4926 4927 4928 4929 4930 0 10000 20000 30000 40000 50000 60000 70000 80000 Co n t o u r E l e v a t i o n , f t Cummulative Volume, ft3 Stage - Storage | POND J Bloom Commercial Preliminary Drainage Report LID and WQCV (i.e., EDB) Calculations Project: Basin ID: Depth Increment = ft Watershed Information Top of Micropool -- 0.00 -- -- -- 25 0.001 Selected SCM Type =EDB 4928 -- 1.00 -- -- -- 17,088 0.392 8,556 0.196 Watershed Area = 6.0 acres 4929 -- 2.00 -- -- -- 33,283 0.764 33,742 0.775 Watershed Length = 650 ft -- -- -- -- Watershed Length to Centroid = 300 ft -- -- -- -- Watershed Slope = 0.020 ft/ft -- -- -- -- Watershed Imperviousness = 100.00% percent -- -- -- -- Percentage Hydrologic Soil Group A = 0.0% percent -- ---- -- Percentage Hydrologic Soil Group B = 100.0% percent ---- -- -- Percentage Hydrologic Soil Groups C/D = 0.0% percent -- -- -- -- Target WQCV Drain Time = 40.0 hours -- -- -- -- Location for 1-hr Rainfall Depths = User Input -- -- ---- -- -- -- -- -- -- -- -- Optional User Overrides -- -- -- -- Water Quality Capture Volume (WQCV) = 0.248 acre-feet acre-feet -- -- -- -- Excess Urban Runoff Volume (EURV) = 0.673 acre-feet acre-feet -- -- -- -- 2-yr Runoff Volume (P1 = 0.83 in.) = 0.375 acre-feet inches -- -- -- -- 5-yr Runoff Volume (P1 = 1.09 in.) = 0.509 acre-feet inches -- -- -- -- 10-yr Runoff Volume (P1 = 1.33 in.) = 0.631 acre-feet inches -- -- -- -- 25-yr Runoff Volume (P1 = 1.69 in.) = 0.813 acre-feet inches -- -- -- -- 50-yr Runoff Volume (P1 = 1.99 in.) = 0.965 acre-feet inches -- -- -- -- 100-yr Runoff Volume (P1 = 2.31 in.) = 1.127 acre-feet inches -- -- -- -- 500-yr Runoff Volume (P1 = 3.14 in.) = 1.547 acre-feet inches -- -- -- -- Approximate 2-yr Detention Volume = 0.379 acre-feet ---- -- -- Approximate 5-yr Detention Volume = 0.513 acre-feet ---- -- -- Approximate 10-yr Detention Volume = 0.650 acre-feet -- -- -- -- Approximate 25-yr Detention Volume = 0.776 acre-feet -- -- -- -- Approximate 50-yr Detention Volume = 0.842 acre-feet -- -- -- -- Approximate 100-yr Detention Volume = 0.895 acre-feet -- -- -- -- -- -- -- -- Define Zones and Basin Geometry -- -- -- -- Zone 1 Volume (WQCV) = 0.248 acre-feet -- -- -- -- Select Zone 2 Storage Volume (Optional) = acre-feet -- -- -- -- Select Zone 3 Storage Volume (Optional) = acre-feet -- -- -- -- Total Detention Basin Volume = 0.248 acre-feet -- -- -- -- Initial Surcharge Volume (ISV) = user ft 3 -- -- -- -- Initial Surcharge Depth (ISD) = user ft -- -- -- -- Total Available Detention Depth (Htotal) = user ft -- -- -- -- Depth of Trickle Channel (HTC) =user ft -- -- -- -- Slope of Trickle Channel (STC) = user ft/ft -- -- -- -- Slopes of Main Basin Sides (Smain) = user H:V -- -- -- -- Basin Length-to-Width Ratio (RL/W ) = user -- -- -- -- -- -- -- -- Initial Surcharge Area (AISV) =user ft 2 -- -- -- -- Surcharge Volume Length (LISV) =user ft -- -- -- -- Surcharge Volume Width (WISV) =user ft -- -- -- -- Depth of Basin Floor (HFLOOR) =user ft -- -- -- -- Length of Basin Floor (LFLOOR) =user ft -- -- -- -- Width of Basin Floor (WFLOOR) =user ft -- -- -- -- Area of Basin Floor (AFLOOR) =user ft 2 -- -- -- -- Volume of Basin Floor (VFLOOR) =user ft 3 -- -- -- -- Depth of Main Basin (HMAIN) =user ft -- -- -- -- Length of Main Basin (LMAIN) =user ft -- -- -- -- Width of Main Basin (WMAIN) =user ft -- -- -- -- Area of Main Basin (AMAIN) =user ft 2 -- -- -- -- Volume of Main Basin (VMAIN) =user ft 3 -- -- -- -- Calculated Total Basin Volume (Vtotal) =user acre-feet -- -- -- -- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- DETENTION BASIN STAGE-STORAGE TABLE BUILDER Optional Override Area (ft 2) Length (ft) Optional Override Stage (ft) Stage (ft) Stage - Storage Description Area (ft 2) Width (ft) HFH073 | Bloom Commercial POND G1 (EDB Sizing Only) MHFD-Detention, Version 4.07 (June 2025) Volume (ft 3) Volume (ac-ft) Area (acre) Total detention volume is less than 100-year volume. After providing required inputs above including 1-hour rainfall depths, click 'Run CUHP' to generate runoff hydrographs using the embedded Colorado Urban Hydrograph Procedure. Example Zone Configuration (Retention Pond) MHFD-Detention_v4.07_G1.xlsm, Basin 9/30/2025, 9:00 PM Project: Basin ID: Estimated Estimated Stage (ft) Volume (ac-ft) Outlet Type Zone 1 (WQCV) 1.13 0.248 Orifice Plate Zone 2 Zone 3 Total (all zones) 0.248 User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration SCM)Calculated Parameters for Underdrain Underdrain Orifice Invert Depth = N/A ft (distance below the filtration media surface) Underdrain Orifice Area = N/A ft2 Underdrain Orifice Diameter = N/A inches Underdrain Orifice Centroid = N/A feet User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation SCM)Calculated Parameters for Plate Centroid of Lowest Orifice = 0.00 ft (relative to basin bottom at Stage = 0 ft) WQ Orifice Area per Row =1.188E-02 ft2 Depth at top of Zone using Orifice Plate = 1.13 ft (relative to basin bottom at Stage = 0 ft) Elliptical Half-Width = N/A feet Orifice Plate: Orifice Vertical Spacing = 4.50 inches Elliptical Slot Centroid = N/A feet Orifice Plate: Orifice Area per Row = 1.71 sq. inches (diameter = 1-7/16 inches) Elliptical Slot Area = N/A ft2 User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest) Row 1 (required) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional) Stage of Orifice Centroid (ft) 0.00 0.38 0.75 Orifice Area (sq. inches) 1.71 1.71 1.71 Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional) Stage of Orifice Centroid (ft) Orifice Area (sq. inches) User Input: Vertical Orifice (Circular or Rectangular)Calculated Parameters for Vertical Orifice Not Selected Not Selected Not Selected Not Selected Invert of Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Area =ft2 Depth at top of Zone using Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Centroid = feet Vertical Orifice Diameter = inches User Input: Overflow Weir (Dropbox with Flat or Sloped Grate and Outlet Pipe OR Rectangular/Trapezoidal Weir and No Outlet Pipe) Calculated Parameters for Overflow Weir grate Not Selected Not Selected Not Selected Not Selected Overflow Weir Front Edge Height, Ho = ft (relative to basin bottom at Stage = 0 ft)Height of Grate Upper Edge, Ht =feet Overflow Weir Front Edge Length = feet Overflow Weir Slope Length = feet Overflow Weir Grate Slope = H:V Grate Open Area / 100-yr Orifice Area = Horiz. Length of Weir Sides = feet Overflow Grate Open Area w/o Debris =ft2 Overflow Grate Type = Overflow Grate Open Area w/ Debris =ft2 Debris Clogging % = % User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice)Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate Not Selected Not Selected Not Selected Not Selected Depth to Invert of Outlet Pipe = ft (distance below basin bottom at Stage = 0 ft)Outlet Orifice Area =ft2 Circular Orifice Diameter = inches Outlet Orifice Centroid = feet Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians User Input: Emergency Spillway (Rectangular or Trapezoidal)Calculated Parameters for Spillway Spillway Invert Stage= ft (relative to basin bottom at Stage = 0 ft) Spillway Design Flow Depth= feet Spillway Crest Length = feet Stage at Top of Freeboard = feet Spillway End Slopes = H:V Basin Area at Top of Freeboard = acres Freeboard above Max Water Surface = feet Basin Volume at Top of Freeboard = acre-ft Max Ponding Depth of Target Storage Volume =1.13 feet Discharge at Top of Freeboard =cfs Routed Hydrograph Results Design Storm Return Period =WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year One-Hour Rainfall Depth (in) =N/A N/A 0.83 1.09 1.33 1.69 1.99 2.31 3.14 CUHP Runoff Volume (acre-ft) =0.248 0.673 0.375 0.509 0.631 0.813 0.965 1.127 1.547 Inflow Hydrograph Volume (acre-ft) =N/A N/A 0.375 0.509 0.631 0.813 0.965 1.127 1.547 CUHP Predevelopment Peak Q (cfs) =N/A N/A 0.1 0.3 1.2 3.9 5.6 7.6 12.2 OPTIONAL Override Predevelopment Peak Q (cfs) =N/A N/A Predevelopment Unit Peak Flow, q (cfs/acre) =N/A N/A 0.02 0.04 0.21 0.66 0.94 1.28 2.05 Peak Inflow Q (cfs) =N/A N/A 7.6 10.1 12.4 16.4 19.5 22.2 30.3 Peak Outflow Q (cfs) =0.1 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 Ratio Peak Outflow to Predevelopment Q =N/A N/A N/A 0.7 0.2 0.1 0.0 0.0 0.0 Structure Controlling Flow =Plate Plate Plate Plate Plate N/A N/A N/A N/A Max Velocity through Grate 1 (fps) =N/A N/A N/A N/A N/A N/A N/A N/A N/A Max Velocity through Grate 2 (fps) =N/A N/A N/A N/A N/A N/A N/A N/A N/A Time to Drain 97% of Inflow Volume (hours) =37 61 46 53 59 67 74 82 102 Time to Drain 99% of Inflow Volume (hours) =40 66 49 58 64 74 82 90 112 Maximum Ponding Depth (ft) =1.13 1.87 1.34 1.57 1.76 2.00 2.00 2.00 2.00 Area at Maximum Ponding Depth (acres) =0.44 0.72 0.51 0.60 0.67 0.76 0.76 0.76 0.76 Maximum Volume Stored (acre-ft) =0.251 0.678 0.346 0.480 0.595 0.775 0.775 0.775 0.775 The user can override the default CUHP hydrographs and runoff volumes by entering new values in the Inflow Hydrographs table (Columns W through AF). DETENTION BASIN OUTLET STRUCTURE DESIGN MHFD-Detention, Version 4.07 (June 2025) HFH073 | Bloom Commercial POND G1 (EDB Sizing Only) Example Zone Configuration (Retention Pond) MHFD-Detention_v4.07_G1.xlsm, Outlet Structure 9/30/2025, 9:01 PM Project: Basin ID: Depth Increment = ft Watershed Information Top of Micropool -- 0.00 -- -- -- 25 0.001 Selected SCM Type =EDB 4923.5 -- 0.50 -- -- -- 7,500 0.172 1,881 0.043 Watershed Area = 2.1 acres 4924 -- 1.50 -- -- -- 13,790 0.317 12,526 0.288 Watershed Length = 650 ft 4925 -- 2.50 -- -- -- 16,538 0.380 27,690 0.636 Watershed Length to Centroid = 300 ft -- -- -- -- Watershed Slope = 0.020 ft/ft -- -- -- -- Watershed Imperviousness = 80.00% percent -- -- -- -- Percentage Hydrologic Soil Group A = 0.0% percent -- ---- -- Percentage Hydrologic Soil Group B = 100.0% percent ---- -- -- Percentage Hydrologic Soil Groups C/D = 0.0% percent -- -- -- -- Target WQCV Drain Time = 40.0 hours -- -- -- -- Location for 1-hr Rainfall Depths = User Input -- -- ---- -- -- -- -- -- -- -- -- Optional User Overrides -- -- -- -- Water Quality Capture Volume (WQCV) = 0.058 acre-feet acre-feet -- -- -- -- Excess Urban Runoff Volume (EURV) = 0.189 acre-feet acre-feet -- -- -- -- 2-yr Runoff Volume (P1 = 0.83 in.) = 0.106 acre-feet inches -- -- -- -- 5-yr Runoff Volume (P1 = 1.09 in.) = 0.146 acre-feet inches -- -- -- -- 10-yr Runoff Volume (P1 = 1.33 in.) = 0.187 acre-feet inches -- -- -- -- 25-yr Runoff Volume (P1 = 1.69 in.) = 0.254 acre-feet inches -- -- -- -- 50-yr Runoff Volume (P1 = 1.99 in.) = 0.308 acre-feet inches -- -- -- -- 100-yr Runoff Volume (P1 = 2.31 in.) = 0.369 acre-feet inches -- -- -- -- 500-yr Runoff Volume (P1 = 3.14 in.) = 0.520 acre-feet inches -- -- -- -- Approximate 2-yr Detention Volume = 0.104 acre-feet ---- -- -- Approximate 5-yr Detention Volume = 0.143 acre-feet ---- -- -- Approximate 10-yr Detention Volume = 0.186 acre-feet -- -- -- -- Approximate 25-yr Detention Volume = 0.222 acre-feet -- -- -- -- Approximate 50-yr Detention Volume = 0.241 acre-feet -- -- -- -- Approximate 100-yr Detention Volume = 0.264 acre-feet -- -- -- -- -- -- -- -- Define Zones and Basin Geometry -- -- -- -- Zone 1 Volume (WQCV) = 0.058 acre-feet -- -- -- -- Select Zone 2 Storage Volume (Optional) = acre-feet -- -- -- -- Select Zone 3 Storage Volume (Optional) = acre-feet -- -- -- -- Total Detention Basin Volume = 0.058 acre-feet -- -- -- -- Initial Surcharge Volume (ISV) = user ft 3 -- -- -- -- Initial Surcharge Depth (ISD) = user ft -- -- -- -- Total Available Detention Depth (Htotal) = user ft -- -- -- -- Depth of Trickle Channel (HTC) =user ft -- -- -- -- Slope of Trickle Channel (STC) = user ft/ft -- -- -- -- Slopes of Main Basin Sides (Smain) = user H:V -- -- -- -- Basin Length-to-Width Ratio (RL/W ) = user -- -- -- -- -- -- -- -- Initial Surcharge Area (AISV) =user ft 2 -- -- -- -- Surcharge Volume Length (LISV) =user ft -- -- -- -- Surcharge Volume Width (WISV) =user ft -- -- -- -- Depth of Basin Floor (HFLOOR) =user ft -- -- -- -- Length of Basin Floor (LFLOOR) =user ft -- -- -- -- Width of Basin Floor (WFLOOR) =user ft -- -- -- -- Area of Basin Floor (AFLOOR) =user ft 2 -- -- -- -- Volume of Basin Floor (VFLOOR) =user ft 3 -- -- -- -- Depth of Main Basin (HMAIN) =user ft -- -- -- -- Length of Main Basin (LMAIN) =user ft -- -- -- -- Width of Main Basin (WMAIN) =user ft -- -- -- -- Area of Main Basin (AMAIN) =user ft 2 -- -- -- -- Volume of Main Basin (VMAIN) =user ft 3 -- -- -- -- Calculated Total Basin Volume (Vtotal) =user acre-feet -- -- -- -- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- Total detention volume is less than 100-year volume. After providing required inputs above including 1-hour rainfall depths, click 'Run CUHP' to generate runoff hydrographs using the embedded Colorado Urban Hydrograph Procedure. Volume (ft 3) Volume (ac-ft) Area (acre) DETENTION BASIN STAGE-STORAGE TABLE BUILDER Optional Override Area (ft 2) Length (ft) Optional Override Stage (ft) Stage (ft) Stage - Storage Description Area (ft 2) Width (ft) HFH073 | Bloom Commercial POND H (EDB Sizing Only) MHFD-Detention, Version 4.07 (June 2025) Example Zone Configuration (Retention Pond) MHFD-Detention_v4.07_H.xlsm, Basin 9/30/2025, 2:46 PM Project: Basin ID: Estimated Estimated Stage (ft) Volume (ac-ft) Outlet Type Zone 1 (WQCV) 0.59 0.058 Orifice Plate Zone 2 Zone 3 Total (all zones) 0.058 User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration SCM)Calculated Parameters for Underdrain Underdrain Orifice Invert Depth = N/A ft (distance below the filtration media surface) Underdrain Orifice Area = N/A ft2 Underdrain Orifice Diameter = N/A inches Underdrain Orifice Centroid = N/A feet User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation SCM)Calculated Parameters for Plate Centroid of Lowest Orifice = 0.00 ft (relative to basin bottom at Stage = 0 ft) WQ Orifice Area per Row =3.889E-03 ft2 Depth at top of Zone using Orifice Plate = 0.59 ft (relative to basin bottom at Stage = 0 ft) Elliptical Half-Width = N/A feet Orifice Plate: Orifice Vertical Spacing = 2.40 inches Elliptical Slot Centroid = N/A feet Orifice Plate: Orifice Area per Row = 0.56 sq. inches (diameter = 13/16 inch) Elliptical Slot Area = N/A ft2 User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest) Row 1 (required) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional) Stage of Orifice Centroid (ft) 0.00 0.20 0.39 Orifice Area (sq. inches) 0.56 0.56 0.56 Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional) Stage of Orifice Centroid (ft) Orifice Area (sq. inches) User Input: Vertical Orifice (Circular or Rectangular)Calculated Parameters for Vertical Orifice Not Selected Not Selected Not Selected Not Selected Invert of Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Area =ft2 Depth at top of Zone using Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Centroid = feet Vertical Orifice Diameter = inches User Input: Overflow Weir (Dropbox with Flat or Sloped Grate and Outlet Pipe OR Rectangular/Trapezoidal Weir and No Outlet Pipe) Calculated Parameters for Overflow Weir grate Not Selected Not Selected Not Selected Not Selected Overflow Weir Front Edge Height, Ho = ft (relative to basin bottom at Stage = 0 ft)Height of Grate Upper Edge, Ht =feet Overflow Weir Front Edge Length = feet Overflow Weir Slope Length = feet Overflow Weir Grate Slope = H:V Grate Open Area / 100-yr Orifice Area = Horiz. Length of Weir Sides = feet Overflow Grate Open Area w/o Debris =ft2 Overflow Grate Type = Overflow Grate Open Area w/ Debris =ft2 Debris Clogging % = % User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice)Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate Not Selected Not Selected Not Selected Not Selected Depth to Invert of Outlet Pipe = ft (distance below basin bottom at Stage = 0 ft)Outlet Orifice Area =ft2 Circular Orifice Diameter = inches Outlet Orifice Centroid = feet Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians User Input: Emergency Spillway (Rectangular or Trapezoidal)Calculated Parameters for Spillway Spillway Invert Stage= ft (relative to basin bottom at Stage = 0 ft) Spillway Design Flow Depth= feet Spillway Crest Length = feet Stage at Top of Freeboard = feet Spillway End Slopes = H:V Basin Area at Top of Freeboard = acres Freeboard above Max Water Surface = feet Basin Volume at Top of Freeboard = acre-ft Max Ponding Depth of Target Storage Volume =0.59 feet Discharge at Top of Freeboard =cfs Routed Hydrograph Results Design Storm Return Period =WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year One-Hour Rainfall Depth (in) =N/A N/A 0.83 1.09 1.33 1.69 1.99 2.31 3.14 CUHP Runoff Volume (acre-ft) =0.058 0.189 0.106 0.146 0.187 0.254 0.308 0.369 0.520 Inflow Hydrograph Volume (acre-ft) =N/A N/A 0.106 0.146 0.187 0.254 0.308 0.369 0.520 CUHP Predevelopment Peak Q (cfs) =N/A N/A 0.0 0.1 0.3 1.0 1.4 1.9 3.1 OPTIONAL Override Predevelopment Peak Q (cfs) =N/A N/A Predevelopment Unit Peak Flow, q (cfs/acre) =N/A N/A 0.02 0.03 0.14 0.46 0.65 0.91 1.46 Peak Inflow Q (cfs) =N/A N/A 1.6 2.2 2.7 3.8 4.7 5.7 7.9 Peak Outflow Q (cfs) =0.0 0.1 0.0 0.0 0.1 0.1 0.1 0.1 0.1 Ratio Peak Outflow to Predevelopment Q =N/A N/A N/A 0.8 0.2 0.1 0.0 0.0 0.0 Structure Controlling Flow =Plate Plate Plate Plate Plate Plate Plate Plate Plate Max Velocity through Grate 1 (fps) =N/A N/A N/A N/A N/A N/A N/A N/A N/A Max Velocity through Grate 2 (fps) =N/A N/A N/A N/A N/A N/A N/A N/A N/A Time to Drain 97% of Inflow Volume (hours) =37 66 50 58 66 77 85 95 116 Time to Drain 99% of Inflow Volume (hours) =40 72 54 64 72 85 94 104 >120 Maximum Ponding Depth (ft) =0.59 1.17 0.79 0.96 1.12 1.36 1.53 1.71 2.15 Area at Maximum Ponding Depth (acres) =0.19 0.27 0.21 0.24 0.26 0.29 0.32 0.33 0.36 Maximum Volume Stored (acre-ft) =0.059 0.191 0.097 0.138 0.175 0.242 0.294 0.355 0.503 DETENTION BASIN OUTLET STRUCTURE DESIGN MHFD-Detention, Version 4.07 (June 2025) HFH073 | Bloom Commercial POND H (EDB Sizing Only) The user can override the default CUHP hydrographs and runoff volumes by entering new values in the Inflow Hydrographs table (Columns W through AF). Example Zone Configuration (Retention Pond) MHFD-Detention_v4.07_H.xlsm, Outlet Structure 9/30/2025, 2:47 PM Project: Basin ID: Depth Increment = ft Watershed Information Top of Micropool -- 0.00 -- -- -- 25 0.001 Selected SCM Type =EDB 4925 -- 0.50 -- -- -- 12,972 0.298 3,249 0.075 Watershed Area = 1.4 acres 4926 -- 1.50 -- -- -- 15,030 0.345 17,250 0.396 Watershed Length = 650 ft -- -- -- -- Watershed Length to Centroid = 300 ft -- -- -- -- Watershed Slope = 0.020 ft/ft -- -- -- -- Watershed Imperviousness = 80.00% percent -- -- -- -- Percentage Hydrologic Soil Group A = 0.0% percent -- ---- -- Percentage Hydrologic Soil Group B = 100.0% percent ---- -- -- Percentage Hydrologic Soil Groups C/D = 0.0% percent -- -- -- -- Target WQCV Drain Time = 40.0 hours -- -- -- -- Location for 1-hr Rainfall Depths = User Input -- -- ---- -- -- -- -- -- -- -- -- Optional User Overrides -- -- -- -- Water Quality Capture Volume (WQCV) = 0.038 acre-feet acre-feet -- -- -- -- Excess Urban Runoff Volume (EURV) = 0.123 acre-feet acre-feet -- -- -- -- 2-yr Runoff Volume (P1 = 0.83 in.) = 0.069 acre-feet inches -- -- -- -- 5-yr Runoff Volume (P1 = 1.09 in.) = 0.096 acre-feet inches -- -- -- -- 10-yr Runoff Volume (P1 = 1.33 in.) = 0.122 acre-feet inches -- -- -- -- 25-yr Runoff Volume (P1 = 1.69 in.) = 0.166 acre-feet inches -- -- -- -- 50-yr Runoff Volume (P1 = 1.99 in.) = 0.201 acre-feet inches -- -- -- -- 100-yr Runoff Volume (P1 = 2.31 in.) = 0.241 acre-feet inches -- -- -- -- 500-yr Runoff Volume (P1 = 3.14 in.) = 0.340 acre-feet inches -- -- -- -- Approximate 2-yr Detention Volume = 0.067 acre-feet ---- -- -- Approximate 5-yr Detention Volume = 0.093 acre-feet ---- -- -- Approximate 10-yr Detention Volume = 0.121 acre-feet -- -- -- -- Approximate 25-yr Detention Volume = 0.144 acre-feet -- -- -- -- Approximate 50-yr Detention Volume = 0.156 acre-feet -- -- -- -- Approximate 100-yr Detention Volume = 0.171 acre-feet -- -- -- -- -- -- -- -- Define Zones and Basin Geometry -- -- -- -- Zone 1 Volume (WQCV) = 0.038 acre-feet -- -- -- -- Select Zone 2 Storage Volume (Optional) = acre-feet -- -- -- -- Select Zone 3 Storage Volume (Optional) = acre-feet -- -- -- -- Total Detention Basin Volume = 0.038 acre-feet -- -- -- -- Initial Surcharge Volume (ISV) = user ft 3 -- -- -- -- Initial Surcharge Depth (ISD) = user ft -- -- -- -- Total Available Detention Depth (Htotal) = user ft -- -- -- -- Depth of Trickle Channel (HTC) =user ft -- -- -- -- Slope of Trickle Channel (STC) = user ft/ft -- -- -- -- Slopes of Main Basin Sides (Smain) = user H:V -- -- -- -- Basin Length-to-Width Ratio (RL/W ) = user -- -- -- -- -- -- -- -- Initial Surcharge Area (AISV) =user ft 2 -- -- -- -- Surcharge Volume Length (LISV) =user ft -- -- -- -- Surcharge Volume Width (WISV) =user ft -- -- -- -- Depth of Basin Floor (HFLOOR) =user ft -- -- -- -- Length of Basin Floor (LFLOOR) =user ft -- -- -- -- Width of Basin Floor (WFLOOR) =user ft -- -- -- -- Area of Basin Floor (AFLOOR) =user ft 2 -- -- -- -- Volume of Basin Floor (VFLOOR) =user ft 3 -- -- -- -- Depth of Main Basin (HMAIN) =user ft -- -- -- -- Length of Main Basin (LMAIN) =user ft -- -- -- -- Width of Main Basin (WMAIN) =user ft -- -- -- -- Area of Main Basin (AMAIN) =user ft 2 -- -- -- -- Volume of Main Basin (VMAIN) =user ft 3 -- -- -- -- Calculated Total Basin Volume (Vtotal) =user acre-feet -- -- -- -- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- -------- Total detention volume is less than 100-year volume. After providing required inputs above including 1-hour rainfall depths, click 'Run CUHP' to generate runoff hydrographs using the embedded Colorado Urban Hydrograph Procedure. Volume (ft 3) Volume (ac-ft) Area (acre) DETENTION BASIN STAGE-STORAGE TABLE BUILDER Optional Override Area (ft 2) Length (ft) Optional Override Stage (ft) Stage (ft) Stage - Storage Description Area (ft 2) Width (ft) HFH073 | Bloom Commercial POND J (EDB Sizing Only) MHFD-Detention, Version 4.07 (June 2025) Example Zone Configuration (Retention Pond) MHFD-Detention_v4.07_J.xlsm, Basin 9/30/2025, 2:21 PM Project: Basin ID: Estimated Estimated Stage (ft) Volume (ac-ft) Outlet Type Zone 1 (WQCV) 0.36 0.038 Orifice Plate Zone 2 Zone 3 Total (all zones) 0.038 User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration SCM)Calculated Parameters for Underdrain Underdrain Orifice Invert Depth = N/A ft (distance below the filtration media surface) Underdrain Orifice Area = N/A ft2 Underdrain Orifice Diameter = N/A inches Underdrain Orifice Centroid = N/A feet User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation SCM)Calculated Parameters for Plate Centroid of Lowest Orifice = 0.00 ft (relative to basin bottom at Stage = 0 ft) WQ Orifice Area per Row =3.194E-03 ft2 Depth at top of Zone using Orifice Plate = 0.36 ft (relative to basin bottom at Stage = 0 ft) Elliptical Half-Width = N/A feet Orifice Plate: Orifice Vertical Spacing = 1.40 inches Elliptical Slot Centroid = N/A feet Orifice Plate: Orifice Area per Row = 0.46 sq. inches (diameter = 3/4 inch) Elliptical Slot Area = N/A ft2 User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest) Row 1 (required) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional) Stage of Orifice Centroid (ft) 0.00 0.12 0.24 Orifice Area (sq. inches) 0.46 0.46 0.46 Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional) Stage of Orifice Centroid (ft) Orifice Area (sq. inches) User Input: Vertical Orifice (Circular or Rectangular)Calculated Parameters for Vertical Orifice Not Selected Not Selected Not Selected Not Selected Invert of Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Area =ft2 Depth at top of Zone using Vertical Orifice = ft (relative to basin bottom at Stage = 0 ft) Vertical Orifice Centroid = feet Vertical Orifice Diameter = inches User Input: Overflow Weir (Dropbox with Flat or Sloped Grate and Outlet Pipe OR Rectangular/Trapezoidal Weir and No Outlet Pipe) Calculated Parameters for Overflow Weir grate Not Selected Not Selected Not Selected Not Selected Overflow Weir Front Edge Height, Ho = ft (relative to basin bottom at Stage = 0 ft)Height of Grate Upper Edge, Ht =feet Overflow Weir Front Edge Length = feet Overflow Weir Slope Length = feet Overflow Weir Grate Slope = H:V Grate Open Area / 100-yr Orifice Area = Horiz. Length of Weir Sides = feet Overflow Grate Open Area w/o Debris =ft2 Overflow Grate Type = Overflow Grate Open Area w/ Debris =ft2 Debris Clogging % = % User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice)Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate Not Selected Not Selected Not Selected Not Selected Depth to Invert of Outlet Pipe = ft (distance below basin bottom at Stage = 0 ft)Outlet Orifice Area =ft2 Circular Orifice Diameter = inches Outlet Orifice Centroid = feet Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians User Input: Emergency Spillway (Rectangular or Trapezoidal)Calculated Parameters for Spillway Spillway Invert Stage= ft (relative to basin bottom at Stage = 0 ft) Spillway Design Flow Depth= feet Spillway Crest Length = feet Stage at Top of Freeboard = feet Spillway End Slopes = H:V Basin Area at Top of Freeboard = acres Freeboard above Max Water Surface = feet Basin Volume at Top of Freeboard = acre-ft Max Ponding Depth of Target Storage Volume =0.36 feet Discharge at Top of Freeboard =cfs Routed Hydrograph Results Design Storm Return Period =WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year One-Hour Rainfall Depth (in) =N/A N/A 0.83 1.09 1.33 1.69 1.99 2.31 3.14 CUHP Runoff Volume (acre-ft) =0.038 0.123 0.069 0.096 0.122 0.166 0.201 0.241 0.340 Inflow Hydrograph Volume (acre-ft) =N/A N/A 0.069 0.096 0.122 0.166 0.201 0.241 0.340 CUHP Predevelopment Peak Q (cfs) =N/A N/A 0.0 0.0 0.2 0.5 0.8 1.1 1.7 OPTIONAL Override Predevelopment Peak Q (cfs) =N/A N/A Predevelopment Unit Peak Flow, q (cfs/acre) =N/A N/A 0.01 0.02 0.11 0.39 0.57 0.79 1.27 Peak Inflow Q (cfs) =N/A N/A 0.9 1.2 1.5 2.2 2.7 3.2 4.6 Peak Outflow Q (cfs) =0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1 Ratio Peak Outflow to Predevelopment Q =N/A N/A N/A 0.9 0.2 0.1 0.1 0.0 0.0 Structure Controlling Flow =Plate Plate Plate Plate Plate Plate Plate Plate Plate Max Velocity through Grate 1 (fps) =N/A N/A N/A N/A N/A N/A N/A N/A N/A Max Velocity through Grate 2 (fps) =N/A N/A N/A N/A N/A N/A N/A N/A N/A Time to Drain 97% of Inflow Volume (hours) =38 67 51 60 68 80 89 98 120 Time to Drain 99% of Inflow Volume (hours) =40 74 55 65 74 88 98 108 >120 Maximum Ponding Depth (ft) =0.36 0.67 0.47 0.55 0.64 0.78 0.89 1.01 1.31 Area at Maximum Ponding Depth (acres) =0.21 0.31 0.27 0.30 0.30 0.31 0.32 0.32 0.34 Maximum Volume Stored (acre-ft) =0.039 0.126 0.063 0.090 0.114 0.157 0.191 0.233 0.328 DETENTION BASIN OUTLET STRUCTURE DESIGN MHFD-Detention, Version 4.07 (June 2025) HFH073 | Bloom Commercial POND J (EDB Sizing Only) The user can override the default CUHP hydrographs and runoff volumes by entering new values in the Inflow Hydrographs table (Columns W through AF). Example Zone Configuration (Retention Pond) MHFD-Detention_v4.07_J.xlsm, Outlet Structure 9/30/2025, 2:22 PM Sheet 1 of 2 Designer: Company: Date: Project: Location: 1. Basin Storage Volume A) Effective Imperviousness of Tributary Area, Ia Ia =80.0 % (100% if all paved and roofed areas upstream of sand filter) B) Tributary Area's Imperviousness Ratio (i = Ia/100)i = 0.800 C) Water Quality Capture Volume (WQCV) Based on 12-hour Drain Time WQCV = 0.26 watershed inches WQCV= 0.8 * (0.91* i3 - 1.19 * i2 + 0.78 * i) D) Contributing Watershed Area (including sand filter area) Area = 288,029 sq ft E) Water Quality Capture Volume (WQCV) Design Volume VWQCV =6,304 cu ft VWQCV = WQCV / 12 * Area F) For Watersheds Outside of the Denver Region, Depth of d6 = in Average Runoff Producing Storm G) For Watersheds Outside of the Denver Region, VWQCV OTHER =cu ft Water Quality Capture Volume (WQCV) Design Volume H) User Input of Water Quality Capture Volume (WQCV) Design Volume VWQCV USER =cu ft (Only if a different WQCV Design Volume is desired) 2. Basin Geometry A) WQCV Depth DWQCV =2.0 ft B) Sand Filter Side Slopes (Horizontal distance per unit vertical, Z = 4.00 ft / ft 4:1 or flatter preferred). Use "0" if sand filter has vertical walls. C) Minimum Filter Area (Flat Surface Area)AMin =2880 sq ft D) Actual Filter Area AActual =3000 sq ft E) Volume Provided VT =8479 cu ft 3. Filter Material 4. Underdrain System A) Are underdrains provided? B) Underdrain system orifice diameter for 12 hour drain time i) Distance From Lowest Elevation of the Storage y =ft Volume to the Center of the Orifice ii) Volume to Drain in 12 Hours Vol12 =cu ft iii) Orifice Diameter, 3/8" Minimum DO = in HFH073 | Bloom Commercial Basin G1 | LID Design Procedure Form: Sand Filter (SF) Herman Feissner Galloway & Company, Inc. July 14, 2025 UD-BMP (Version 3.07, March 2018) Choose One Choose One 18" CDOT Class B or C Filter Material Other (Explain): YES NO HFH073_UD-BMP_v3.07-BasinG1_LID.xlsm, SF 7/14/2025, 9:41 AM Sheet 2 of 2 Designer: Company: Date: Project: Location: 5. Impermeable Geomembrane Liner and Geotextile Separator Fabric A) Is an impermeable liner provided due to proximity of structures or groundwater contamination? 6. Inlet / Outlet Works A) Describe the type of energy dissipation at inlet points and means of conveying flows in excess of the WQCV through the outlet Notes: Design Procedure Form: Sand Filter (SF) Herman Feissner Galloway & Company, Inc. July 14, 2025 HFH073 | Bloom Commercial Basin G1 | LID Choose One YES NO HFH073_UD-BMP_v3.07-BasinG1_LID.xlsm, SF 7/14/2025, 9:41 AM Bloom Commercial Preliminary Drainage Report APPENDIX E SWMM Models Bloom Commercial Preliminary Drainage Report Proposed SWMM Model [TITLE] ;;Project Title/Notes [OPTIONS] ;;Option Value FLOW_UNITS CFS INFILTRATION HORTON FLOW_ROUTING DYNWAVE LINK_OFFSETS DEPTH MIN_SLOPE 0 ALLOW_PONDING NO SKIP_STEADY_STATE NO START_DATE 03/19/2021 START_TIME 00:00:00 REPORT_START_DATE 03/19/2021 REPORT_START_TIME 00:00:00 END_DATE 03/26/2021 END_TIME 00:00:00 SWEEP_START 01/01 SWEEP_END 12/31 DRY_DAYS 0 REPORT_STEP 00:01:00 WET_STEP 00:01:00 DRY_STEP 01:00:00 ROUTING_STEP 0:00:05 RULE_STEP 00:00:00 INERTIAL_DAMPING PARTIAL NORMAL_FLOW_LIMITED BOTH FORCE_MAIN_EQUATION H-W SURCHARGE_METHOD SLOT VARIABLE_STEP 0.75 LENGTHENING_STEP 0 MIN_SURFAREA 12.566 MAX_TRIALS 8 HEAD_TOLERANCE 0.005 SYS_FLOW_TOL 5 LAT_FLOW_TOL 5 MINIMUM_STEP 0.5 THREADS 1 [EVAPORATION] ;;Data Source Parameters ;;-------------- ---------------- CONSTANT 0.0 DRY_ONLY NO [RAINGAGES] ;;Name Format Interval SCF Source ;;-------------- --------- ------ ------ ---------- CoFC_100yr INTENSITY 0:05 1.0 TIMESERIES FC_100yr CoFC_2yr INTENSITY 0:05 1.0 TIMESERIES CoFC_2yr [SUBCATCHMENTS] ;;Name Rain Gage Outlet Area %Imperv Width %Slope CurbLen SnowPack ;;-------------- ---------------- ---------------- -------- -------- -------- -------- -------- ---------------- A CoFC_100yr Pond_A 56 70 960 1.0 0 D CoFC_100yr Pond_D 37.17 48 850 1.0 0 E CoFC_100yr Pond_E 26.61 61 500 1.0 0 C CoFC_100yr Pond_C 22 90 700 1.0 0 G CoFC_100yr Pond_G 19.6 90 500 1.5 0 ;Adjusted area from 18.66 to 12.06-ac (inclusive of detention pond H) H CoFC_100yr Pond_H 12.1 80 810 1.5 0 B CoFC_100yr Pond_B 15.3 70 500 1.0 0 I CoFC_100yr Pond_I 6.4 80 450 1.0 0 S4 CoFC_100yr Pond_G 0.89 78 1300 1 0 ;Adjusted imp. % from 90% to 72.5% (see Bloom Filing 3 PDR, Aspen Engineering) G1 CoFC_100yr Pond_G1 32 72.5 1040 1.5 0 J CoFC_100yr Pond_J 6.9 80 330 1.5 0 [SUBAREAS] ;;Subcatchment N-Imperv N-Perv S-Imperv S-Perv PctZero RouteTo PctRouted ;;-------------- ---------- ---------- ---------- ---------- ---------- ---------- ---------- A 0.016 0.25 0.1 0.3 1 OUTLET D 0.016 0.25 0.1 0.3 1 OUTLET E 0.016 0.25 0.1 0.3 1 OUTLET C 0.016 0.25 0.1 0.3 1 OUTLET G 0.016 0.25 0.1 0.3 1 OUTLET H 0.016 0.25 0.1 0.3 1 OUTLET B 0.016 0.25 0.1 0.3 1 OUTLET I 0.016 0.25 0.1 0.3 1 OUTLET S4 0.016 0.25 0.1 0.3 1 OUTLET G1 0.016 0.25 0.1 0.3 1 OUTLET J 0.016 0.25 0.1 0.3 1 OUTLET [INFILTRATION] ;;Subcatchment Param1 Param2 Param3 Param4 Param5 ;;-------------- ---------- ---------- ---------- ---------- ---------- A 0.51 0.5 6.48 7 0 D 0.51 0.5 6.48 7 0 E 0.51 0.5 6.48 7 0 C 0.51 0.5 6.48 7 0 G 0.51 0.5 6.48 7 0 H 0.51 0.5 6.48 7 0 B 0.51 0.5 6.48 7 0 I 0.51 0.5 6.48 7 0 S4 0.51 0.5 6.48 7 0 G1 0.51 0.5 6.48 7 0 J 0.51 0.5 6.48 7 0 [JUNCTIONS] ;;Name Elevation MaxDepth InitDepth SurDepth Aponded ;;-------------- ---------- ---------- ---------- ---------- ---------- J3 4927 0 0 0 0 J4 4923.0 10 0 0 0 J5 4927 10 0 0 0 J6 4939.0 10 0 0 0 J7 4924.35 10 0 0 0 J8 4938 0 0 0 0 [OUTFALLS] ;;Name Elevation Type Stage Data Gated Route To ;;-------------- ---------- ---------- ---------------- -------- ---------------- Peakview_Storm_Stub 4922.94 FREE NO CooperSlough 4938 FREE NO Lake_Canal 0 FREE NO CooperSloughNorth 4940 FREE NO O1 4926.5 FREE NO O2 4924 FREE NO O3 4922.5 FREE NO [STORAGE] ;;Name Elev. MaxDepth InitDepth Shape Curve Type/Params SurDepth Fevap Psi Ksat IMD ;;-------------- -------- ---------- ----------- ---------- ---------------------------- --------- -------- -------- ------- - Pond_A 4945.5 7 0 TABULAR Pond_A_Vol 0 0 Pond_B 4942.5 8 0 TABULAR Pond_B_Vol 0 0 Pond_C 4938.5 6 0 TABULAR Pond_C_Vol 0 0 Pond_D 4942.5 5 0 TABULAR Pond_D_Vol 0 0 Pond_E 4939.5 7 0 TABULAR Pond_E_Vol 0 0 Pond_G 4928.5 8.0 0 TABULAR Pond_G_Vol 0 0 Pond_H 4923.0 9 0.62 TABULAR Pond_H_Vol 0 0 Pond_I 4922.5 6.5 0 TABULAR Pond_I_Vol 0 0 Pond_G1 4927 8 1.14 TABULAR PondG1 0 0 Pond_J 4924.5 5.5 0.38 TABULAR PondJ 0 0 Pond_G1-WQCV 4927 2 1.14 TABULAR PondG1 0 0 Pond_J-WQCV 4924.5 2 0.38 TABULAR PondJ 0 0 Pond_H-WQCV 4923 2 0.62 FUNCTIONAL 0 0 10000 0 0 [CONDUITS] ;;Name From Node To Node Length Roughness InOffset OutOffset InitFlow MaxFlow ;;-------------- ---------------- ---------------- ---------- ---------- ---------- ---------- ---------- ---------- C3 J3 J4 400 0.016 0 0 0 0 C4 J4 Peakview_Storm_Stub 50 0.016 0 0 0 0 C7 J6 Pond_G 1473 0.016 1 0 0 0 C8 J7 J4 400 0.016 0 0 0 0 C9 J5 J7 1010 0.016 0 0 0 0 C10 J8 CooperSlough 50 .016 0 0 0 0 [ORIFICES] ;;Name From Node To Node Type Offset Qcoeff Gated CloseTime ;;-------------- ---------------- ---------------- ------------ ---------- ---------- -------- ---------- Pond_H_Outlet Pond_H J4 SIDE 0.62 0.65 NO 0 Pond_D_Outlet Pond_D J8 SIDE 0 0.65 NO 0 Pond_E_Outlet Pond_E J6 SIDE 0 0.65 NO 0 Pond_B_Outlet Pond_B J8 SIDE 0 0.65 NO 0 Pond_C_Outlet Pond_C J8 SIDE 0 0.65 NO 0 Pond_A_Outlet Pond_A Pond_B SIDE 0 0.65 NO 0 PondG_Outlet Pond_G J3 SIDE 0 0.65 NO 0 Pond_I_Outlet Pond_I Lake_Canal SIDE 0 0.65 NO 0 PondG1_Outlet Pond_G1 J5 SIDE 1.14 0.65 NO 0 Pond_J_Outlet Pond_J J7 SIDE 0.38 0.65 NO 0 WQCV_G1-Outlet Pond_G1-WQCV O1 SIDE 0 0.65 NO 0 WQCV_J-Outlet Pond_J-WQCV O2 SIDE 0 0.65 NO 0 WQCV_H-Outlet Pond_H-WQCV O3 SIDE 0 0.65 NO 0 [XSECTIONS] ;;Link Shape Geom1 Geom2 Geom3 Geom4 Barrels Culvert ;;-------------- ------------ ---------------- ---------- ---------- ---------- ---------- ---------- C3 CIRCULAR 3 0 0 0 1 C4 CIRCULAR 3 0 0 0 1 C7 CIRCULAR 3 0 0 0 1 C8 CIRCULAR 4 0 0 0 1 C9 CIRCULAR 2 0 0 0 1 C10 CIRCULAR 3 0 0 0 1 Pond_H_Outlet CIRCULAR 0.25 0 0 0 Pond_D_Outlet CIRCULAR 0.575 0 0 0 Pond_E_Outlet CIRCULAR 1 0 0 0 Pond_B_Outlet CIRCULAR .9 0 0 0 Pond_C_Outlet CIRCULAR 1.2 0 0 0 Pond_A_Outlet CIRCULAR 1.1 0 0 0 PondG_Outlet CIRCULAR 1.1 0 0 0 Pond_I_Outlet CIRCULAR 0.12 0 0 0 PondG1_Outlet CIRCULAR 1.0 0 0 0 Pond_J_Outlet CIRCULAR 0.25 0 0 0 WQCV_G1-Outlet CIRCULAR 0.167 0 0 0 WQCV_J-Outlet CIRCULAR 0.1 0 0 0 WQCV_H-Outlet CIRCULAR 0.4 0 0 0 [LOSSES] ;;Link Kentry Kexit Kavg Flap Gate Seepage ;;-------------- ---------- ---------- ---------- ---------- ---------- C7 0.2 1.0 0 NO 0 [CURVES] ;;Name Type X-Value Y-Value ;;-------------- ---------- ---------- ---------- Pond_A_Vol Storage 0 1379 Pond_A_Vol 0.5 7426 Pond_A_Vol 1 20508 Pond_A_Vol 2 61694 Pond_A_Vol 3 87550 Pond_A_Vol 4 98128 Pond_A_Vol 5 107028 Pond_A_Vol 6 116266 Pond_A_Vol 6.8 122049 ; Pond_B_Vol Storage 0 0 Pond_B_Vol 0.5 950 Pond_B_Vol 1 9586 Pond_B_Vol 2 33293 Pond_B_Vol 3 40536 Pond_B_Vol 4 45837 Pond_B_Vol 5 50932 Pond_B_Vol 6 56882 Pond_B_Vol 7 64812 Pond_B_Vol 7.8 70081 ; Pond_D_Vol Storage 0 62296 Pond_D_Vol 0.5 64609 Pond_D_Vol 1.5 69407 Pond_D_Vol 1.6 85153 Pond_D_Vol 2.5 90660 Pond_D_Vol 3.5 97036 Pond_D_Vol 4.5 104986 Pond_D_Vol 5.5 114264 ; Pond_E_Vol Storage 0 24401 Pond_E_Vol 0.5 26000 Pond_E_Vol 1 31564 Pond_E_Vol 2 37246 Pond_E_Vol 3 41386 Pond_E_Vol 4 45783 Pond_E_Vol 5 50483 Pond_E_Vol 6 55591 Pond_E_Vol 7 61098 ; Pond_C_Vol Storage 0 0 Pond_C_Vol 0.5 250 Pond_C_Vol 1 500 Pond_C_Vol 2 17802 Pond_C_Vol 3 33418 Pond_C_Vol 4 42153 Pond_C_Vol 5 52564 Pond_C_Vol 6 69318 Pond_C_Vol 7 44718 Pond_C_Vol 8 51988 ; Pond_F_Vol Storage 0 0 Pond_F_Vol 0.5 11461 Pond_F_Vol 1.5 16311 Pond_F_Vol 2.5 20746 Pond_F_Vol 3.5 25298 Pond_F_Vol 4.5 29960 Pond_F_Vol 5.5 34725 Pond_F_Vol 6.5 39585 Pond_F_Vol 7.5 45239 ; Pond_G_Vol Storage 0 0 Pond_G_Vol 0.5 1225 Pond_G_Vol 1 2781 Pond_G_Vol 2 11995 Pond_G_Vol 3 21178 Pond_G_Vol 4 28923 Pond_G_Vol 5 34193 Pond_G_Vol 6 39657 Pond_G_Vol 7 45391 Pond_G_Vol 8 51481 ; Pond_I_Vol Storage 0 0 Pond_I_Vol 0.5 1204 Pond_I_Vol 1 3620 Pond_I_Vol 2 7729 Pond_I_Vol 3 11716 Pond_I_Vol 4 20445 Pond_I_Vol 5 28364 Pond_I_Vol 6 33098 ; Pond_H_Vol Storage 0 0 Pond_H_Vol 0.5 7500 Pond_H_Vol 1.0 13790 Pond_H_Vol 2.0 16538 Pond_H_Vol 3.0 19374 Pond_H_Vol 4.0 22335 Pond_H_Vol 5.0 25254 Pond_H_Vol 6.0 28226 Pond_H_Vol 7.0 31335 Pond_H_Vol 8.0 34469 Pond_H_Vol 9.0 35000 ; PondG1 Storage 0.00 0 PondG1 1.00 17088 PondG1 2.00 33283 PondG1 3.00 37173 PondG1 4.00 40897 PondG1 5.00 44715 PondG1 6.00 48638 PondG1 7.00 52680 PondG1 8.00 56872 PondG1 8.5 56872 ; PondJ Storage 0.00 0 PondJ 0.50 12972 PondJ 1.50 15030 PondJ 2.50 17188 PondJ 3.50 19447 PondJ 4.50 21806 PondJ 5.50 24266 [TIMESERIES] ;;Name Date Time Value ;;-------------- ---------- ---------- ---------- FC_2year 0:05 0.29 FC_2year 0:10 0.33 FC_2year 0:15 0.38 FC_2year 0:20 0.64 FC_2year 0:25 0.81 FC_2year 0:30 1.57 FC_2year 0:35 2.85 FC_2year 0:40 1.18 FC_2year 0:45 0.71 FC_2year 0:50 0.42 FC_2year 0:55 0.35 FC_2year 1:00 0.30 FC_2year 1:05 0.20 FC_2year 1:10 0.19 FC_2year 1:15 0.18 FC_2year 1:20 0.17 FC_2year 1:25 0.17 FC_2year 1:30 0.16 FC_2year 1:35 0.15 FC_2year 1:40 0.15 FC_2year 1:45 0.14 FC_2year 1:50 0.14 FC_2year 1:55 0.13 FC_2year 2:00 0.13 ; FC_100yr 0:05 1.00 FC_100yr 0:10 1.14 FC_100yr 0:15 1.33 FC_100yr 0:20 2.23 FC_100yr 0:25 2.84 FC_100yr 0:30 5.49 FC_100yr 0:35 9.95 FC_100yr 0:40 4.12 FC_100yr 0:45 2.48 FC_100yr 0:50 1.46 FC_100yr 0:55 1.22 FC_100yr 1:00 1.06 FC_100yr 1:05 1.00 FC_100yr 1:10 0.95 FC_100yr 1:15 0.91 FC_100yr 1:20 0.87 FC_100yr 1:25 0.84 FC_100yr 1:30 0.81 FC_100yr 1:35 0.78 FC_100yr 1:40 0.75 FC_100yr 1:45 0.73 FC_100yr 1:50 0.71 FC_100yr 1:55 0.69 FC_100yr 2:00 0.67 ; CoFC_2yr 5 0.29 CoFC_2yr 10 0.33 CoFC_2yr 15 0.38 CoFC_2yr 20 0.64 CoFC_2yr 25 0.81 CoFC_2yr 30 1.57 CoFC_2yr 35 2.85 CoFC_2yr 40 1.18 CoFC_2yr 45 0.71 CoFC_2yr 50 0.42 CoFC_2yr 55 0.35 CoFC_2yr 60 0.30 CoFC_2yr 65 0.20 CoFC_2yr 70 0.19 CoFC_2yr 75 0.18 CoFC_2yr 80 0.17 CoFC_2yr 85 0.17 CoFC_2yr 90 0.16 CoFC_2yr 95 0.15 CoFC_2yr 100 0.15 CoFC_2yr 105 0.14 CoFC_2yr 110 0.14 CoFC_2yr 115 0.13 CoFC_2yr 120 0.13 [REPORT] ;;Reporting Options SUBCATCHMENTS ALL NODES ALL LINKS ALL [TAGS] [MAP] DIMENSIONS -2215.333 -527.363 12215.333 10321.737 Units None [COORDINATES] ;;Node X-Coord Y-Coord ;;-------------- ------------------ ------------------ J3 5859.249 2302.082 J4 5854.909 179.998 J5 2868.447 1496.773 J6 4583.740 4846.524 J7 4136.412 219.055 J8 7302.748 4759.559 Peakview_Storm_Stub 6623.025 175.659 CooperSlough 7985.672 4758.319 Lake_Canal 3146.974 1052.266 CooperSloughNorth 6191.406 7144.531 O1 -152.510 2071.224 O2 1016.854 2038.741 O3 553.980 2095.586 Pond_A 5842.724 7571.684 Pond_B 6853.908 6129.416 Pond_C 5975.774 5299.180 Pond_D 4230.150 7273.651 Pond_E 4091.778 5437.552 Pond_G 4873.447 2665.433 Pond_H 4874.150 613.962 Pond_I 3133.955 796.227 Pond_G1 2824.809 1899.586 Pond_J 4026.535 681.076 Pond_G1-WQCV -144.390 2639.665 Pond_J-WQCV 1000.612 2623.424 Pond_H-WQCV 553.980 2631.544 [VERTICES] ;;Link X-Coord Y-Coord ;;-------------- ------------------ ------------------ C7 4878.001 4181.710 C9 2891.929 1420.482 C9 3215.336 1109.423 C9 3600.470 834.522 Pond_D_Outlet 5177.925 4758.319 Pond_J_Outlet 4177.638 531.509 ;;Storage Node X-Coord Y-Coord ;;-------------- ------------------ ------------------ Pond_A 5842.724 7571.684 Pond_B 6853.908 6129.416 Pond_C 5975.774 5299.180 Pond_D 4230.150 7273.651 Pond_E 4091.778 5437.552 Pond_G 4873.447 2665.433 Pond_H 4874.150 613.962 Pond_I 3133.955 796.227 Pond_G1 2824.809 1899.586 Pond_J 4026.535 681.076 Pond_G1-WQCV -144.390 2639.665 Pond_J-WQCV 1000.612 2623.424 Pond_H-WQCV 553.980 2631.544 [SYMBOLS] ;;Gage X-Coord Y-Coord ;;-------------- ------------------ ------------------ CoFC_100yr 742.832 4142.164 CoFC_2yr 742.832 4827.493 [BACKDROP] FILE "C:\Users\herman_feissner\Desktop\Screenshot 2025-09-18 171052.png" DIMENSIONS 2321.998 0.000 7678.002 10000.000 EPA STORM WATER MANAGEMENT MODEL - VERSION 5.2 (Build 5.2.4) ------------------------------------------------------------ WARNING 09: time series interval greater than recording interval for Rain Gage CoFC_2yr WARNING 04: minimum elevation drop used for Conduit C10 **************** Analysis Options **************** Flow Units ............... CFS Process Models: Rainfall/Runoff ........ YES RDII ................... NO Snowmelt ............... NO Groundwater ............ NO Flow Routing ........... YES Ponding Allowed ........ NO Water Quality .......... NO Infiltration Method ...... HORTON Flow Routing Method ...... DYNWAVE Surcharge Method ......... SLOT Starting Date ............ 03/19/2021 00:00:00 Ending Date .............. 03/26/2021 00:00:00 Antecedent Dry Days ...... 0.0 Report Time Step ......... 00:01:00 Wet Time Step ............ 00:01:00 Dry Time Step ............ 01:00:00 Routing Time Step ........ 5.00 sec Variable Time Step ....... YES Maximum Trials ........... 8 Number of Threads ........ 1 Head Tolerance ........... 0.005000 ft ************************** Volume Depth Runoff Quantity Continuity acre-feet inches ************************** --------- ------- Total Precipitation ...... 19.157 0.978 Evaporation Loss ......... 0.000 0.000 Infiltration Loss ........ 5.652 0.289 Surface Runoff ........... 12.139 0.620 Final Storage ............ 1.372 0.070 Continuity Error (%) ..... -0.037 ************************** Volume Volume Flow Routing Continuity acre-feet 10^6 gal ************************** --------- --------- Dry Weather Inflow ....... 0.000 0.000 Wet Weather Inflow ....... 12.138 3.955 Groundwater Inflow ....... 0.000 0.000 RDII Inflow .............. 0.000 0.000 External Inflow .......... 0.000 0.000 External Outflow ......... 12.216 3.981 Flooding Loss ............ 0.000 0.000 Evaporation Loss ......... 0.000 0.000 Exfiltration Loss ........ 0.000 0.000 Initial Stored Volume .... 0.804 0.262 Final Stored Volume ...... 0.725 0.236 Continuity Error (%) ..... 0.008 ************************* Highest Continuity Errors ************************* Node J6 (-1.50%) *************************** Time-Step Critical Elements *************************** None ******************************** Highest Flow Instability Indexes ******************************** Link Pond_E_Outlet (33) ********************************* Most Frequent Nonconverging Nodes ********************************* Convergence obtained at all time steps. ************************* Routing Time Step Summary ************************* Minimum Time Step : 3.77 sec Average Time Step : 5.00 sec Maximum Time Step : 5.00 sec % of Time in Steady State : 0.00 Average Iterations per Step : 2.00 % of Steps Not Converging : 0.00 Time Step Frequencies : 5.000 - 3.155 sec : 100.00 % 3.155 - 1.991 sec : 0.00 % 1.991 - 1.256 sec : 0.00 % 1.256 - 0.792 sec : 0.00 % 0.792 - 0.500 sec : 0.00 % *************************** Subcatchment Runoff Summary *************************** ------------------------------------------------------------------------------------------------------------------------------ Total Total Total Total Imperv Perv Total Total Peak Runoff Precip Runon Evap Infil Runoff Runoff Runoff Runoff Runoff Coeff Subcatchment in in in in in in in 10^6 gal CFS ------------------------------------------------------------------------------------------------------------------------------ A 0.98 0.00 0.00 0.29 0.62 0.00 0.62 0.94 13.38 0.629 D 0.98 0.00 0.00 0.51 0.42 0.00 0.42 0.43 10.47 0.432 E 0.98 0.00 0.00 0.38 0.54 0.00 0.54 0.39 6.67 0.548 C 0.98 0.00 0.00 0.10 0.79 0.00 0.79 0.47 9.11 0.809 G 0.98 0.00 0.00 0.10 0.79 0.00 0.79 0.42 8.00 0.809 H 0.98 0.00 0.00 0.20 0.70 0.00 0.70 0.23 10.30 0.720 B 0.98 0.00 0.00 0.29 0.62 0.00 0.62 0.26 6.18 0.629 I 0.98 0.00 0.00 0.20 0.70 0.00 0.70 0.12 4.86 0.720 S4 0.98 0.00 0.00 0.22 0.69 0.00 0.69 0.02 1.98 0.710 G1 0.98 0.00 0.00 0.27 0.64 0.00 0.64 0.55 15.26 0.652 J 0.98 0.00 0.00 0.20 0.70 0.00 0.70 0.13 4.56 0.720 ****************** Node Depth Summary ****************** --------------------------------------------------------------------------------- Average Maximum Maximum Time of Max Reported Depth Depth HGL Occurrence Max Depth Node Type Feet Feet Feet days hr:min Feet --------------------------------------------------------------------------------- J3 JUNCTION 0.09 0.55 4927.55 1 11:23 0.55 J4 JUNCTION 0.22 0.89 4923.89 1 11:33 0.89 J5 JUNCTION 0.13 0.62 4927.62 1 11:52 0.62 J6 JUNCTION 0.93 1.27 4940.27 1 12:16 1.27 J7 JUNCTION 0.10 0.44 4924.79 1 11:56 0.44 J8 JUNCTION 0.27 1.12 4939.12 1 11:22 1.12 Peakview_Storm_Stub OUTFALL 0.13 0.74 4923.68 1 11:33 0.74 CooperSlough OUTFALL 0.15 0.90 4938.90 1 11:22 0.90 Lake_Canal OUTFALL 0.00 0.00 0.00 0 00:00 0.00 CooperSloughNorth OUTFALL 0.00 0.00 4940.00 0 00:00 0.00 O1 OUTFALL 0.00 0.00 4926.50 0 00:00 0.00 O2 OUTFALL 0.00 0.00 4924.00 0 00:00 0.00 O3 OUTFALL 0.00 0.00 4922.50 0 00:00 0.00 Pond_A STORAGE 0.12 1.13 4946.63 1 11:47 1.13 Pond_B STORAGE 0.17 1.47 4943.97 1 12:36 1.47 Pond_C STORAGE 0.07 1.40 4939.90 1 11:16 1.40 Pond_D STORAGE 0.12 0.38 4942.88 1 17:15 0.38 Pond_E STORAGE 0.48 0.81 4940.31 1 12:14 0.81 Pond_G STORAGE 0.11 1.18 4929.68 1 11:23 1.18 Pond_H STORAGE 0.80 1.46 4924.46 1 12:09 1.46 Pond_I STORAGE 0.50 1.85 4924.35 1 17:14 1.85 Pond_G1 STORAGE 1.24 1.81 4928.81 1 11:50 1.81 Pond_J STORAGE 0.48 0.86 4925.36 1 12:12 0.86 Pond_G1-WQCV STORAGE 0.15 1.14 4928.14 0 00:00 1.14 Pond_J-WQCV STORAGE 0.04 0.38 4924.88 0 00:00 0.38 Pond_H-WQCV STORAGE 0.02 0.62 4923.62 0 00:00 0.62 ******************* Node Inflow Summary ******************* ------------------------------------------------------------------------------------------------- Maximum Maximum Lateral Total Flow Lateral Total Time of Max Inflow Inflow Balance Inflow Inflow Occurrence Volume Volume Error Node Type CFS CFS days hr:min 10^6 gal 10^6 gal Percent ------------------------------------------------------------------------------------------------- J3 JUNCTION 0.00 3.95 1 11:23 0 0.727 -0.027 J4 JUNCTION 0.00 5.58 1 11:32 0 1.64 0.009 J5 JUNCTION 0.00 1.59 1 11:50 0 0.553 -0.014 J6 JUNCTION 0.00 0.80 1 12:12 0 0.285 -1.483 J7 JUNCTION 0.00 1.74 1 11:53 0 0.684 0.036 J8 JUNCTION 0.00 8.21 1 11:22 0 2.07 0.004 Peakview_Storm_Stub OUTFALL 0.00 5.58 1 11:33 0 1.64 0.000 CooperSlough OUTFALL 0.00 8.21 1 11:22 0 2.07 0.000 Lake_Canal OUTFALL 0.00 0.08 1 17:14 0 0.122 0.000 CooperSloughNorth OUTFALL 0.00 0.00 0 00:00 0 0 0.000 gal O1 OUTFALL 0.00 0.12 0 00:00 0 0.083 0.000 O2 OUTFALL 0.00 0.02 0 00:00 0 0.014 0.000 O3 OUTFALL 0.00 0.42 0 00:00 0 0.0463 0.000 Pond_A STORAGE 13.38 13.38 1 11:05 0.935 0.935 0.000 Pond_B STORAGE 6.18 7.16 1 11:05 0.256 1.19 0.000 Pond_C STORAGE 9.11 9.11 1 11:05 0.473 0.473 0.003 Pond_D STORAGE 10.47 10.47 1 11:05 0.426 0.426 0.000 Pond_E STORAGE 6.67 6.67 1 11:05 0.387 0.388 1.421 Pond_G STORAGE 9.98 10.00 1 11:05 0.438 0.726 -0.109 Pond_H STORAGE 10.30 10.30 1 11:05 0.231 0.253 0.000 Pond_I STORAGE 4.86 4.86 1 11:05 0.122 0.122 0.000 Pond_G1 STORAGE 15.26 15.26 1 11:05 0.554 0.637 0.000 Pond_J STORAGE 4.56 4.56 1 11:05 0.132 0.146 0.000 Pond_G1-WQCV STORAGE 0.00 0.00 0 00:00 0 0.083 0.001 Pond_J-WQCV STORAGE 0.00 0.00 0 00:00 0 0.014 0.001 Pond_H-WQCV STORAGE 0.00 0.00 0 00:00 0 0.0464 0.004 ********************** Node Surcharge Summary ********************** No nodes were surcharged. ********************* Node Flooding Summary ********************* No nodes were flooded. ********************** Storage Volume Summary ********************** ------------------------------------------------------------------------------------------------ Average Avg Evap Exfil Maximum Max Time of Max Maximum Volume Pcnt Pcnt Pcnt Volume Pcnt Occurrence Outflow Storage Unit 1000 ft³ Full Loss Loss 1000 ft³ Full days hr:min CFS ------------------------------------------------------------------------------------------------ Pond_A 0.453 0.1 0.0 0.0 12.172 2.2 1 11:47 3.77 Pond_B 0.222 0.1 0.0 0.0 9.932 3.0 1 12:36 3.35 Pond_C 0.009 0.0 0.0 0.0 1.843 1.0 1 11:16 5.25 Pond_D 7.832 1.8 0.0 0.0 24.025 5.5 1 17:15 0.39 Pond_E 12.124 4.0 0.0 0.0 21.265 7.0 1 12:14 0.80 Pond_G 0.038 0.0 0.0 0.0 1.979 0.9 1 11:23 3.95 Pond_H 4.948 2.4 0.0 0.0 13.904 6.6 1 12:09 0.22 Pond_I 1.103 1.0 0.0 0.0 6.045 5.7 1 17:14 0.08 Pond_G1 13.125 4.3 0.0 0.0 27.696 9.1 1 11:50 1.59 Pond_J 3.098 3.2 0.0 0.0 8.044 8.4 1 12:12 0.15 Pond_G1-WQCV 1.008 3.0 0.0 0.0 11.095 32.9 0 00:00 0.12 Pond_J-WQCV 0.146 0.6 0.0 0.0 1.873 7.5 0 00:00 0.02 Pond_H-WQCV 0.224 1.1 0.0 0.0 6.200 31.0 0 00:00 0.42 *********************** Outfall Loading Summary *********************** ----------------------------------------------------------- Flow Avg Max Total Freq Flow Flow Volume Outfall Node Pcnt CFS CFS 10^6 gal ----------------------------------------------------------- Peakview_Storm_Stub 93.13 0.39 5.58 1.642 CooperSlough 96.96 0.48 8.21 2.073 Lake_Canal 64.83 0.04 0.08 0.122 CooperSloughNorth 0.00 0.00 0.00 0.000 O1 23.87 0.08 0.12 0.083 O2 21.02 0.01 0.02 0.014 O3 26.51 0.04 0.42 0.046 ----------------------------------------------------------- System 46.62 1.04 13.73 3.981 ******************** Link Flow Summary ******************** ----------------------------------------------------------------------------- Maximum Time of Max Maximum Max/ Max/ |Flow| Occurrence |Veloc| Full Full Link Type CFS days hr:min ft/sec Flow Depth ----------------------------------------------------------------------------- C3 CONDUIT 3.95 1 11:23 3.23 0.07 0.24 C4 CONDUIT 5.58 1 11:33 3.60 0.30 0.27 C7 CONDUIT 0.80 1 12:16 1.43 0.02 0.23 C8 CONDUIT 1.74 1 11:56 1.45 0.03 0.16 C9 CONDUIT 1.59 1 11:53 2.39 0.17 0.26 C10 CONDUIT 8.21 1 11:22 3.93 3.39 0.34 Pond_H_Outlet ORIFICE 0.22 1 12:23 1.00 Pond_D_Outlet ORIFICE 0.39 1 17:15 0.66 Pond_E_Outlet ORIFICE 0.80 1 12:12 0.81 Pond_B_Outlet ORIFICE 3.35 1 12:36 1.00 Pond_C_Outlet ORIFICE 5.25 1 11:14 1.00 Pond_A_Outlet ORIFICE 3.77 1 11:47 1.00 PondG_Outlet ORIFICE 3.95 1 11:23 1.00 Pond_I_Outlet ORIFICE 0.08 1 17:14 1.00 PondG1_Outlet ORIFICE 1.59 1 11:50 0.67 Pond_J_Outlet ORIFICE 0.15 1 12:12 1.00 WQCV_G1-Outlet ORIFICE 0.12 0 00:00 1.00 WQCV_J-Outlet ORIFICE 0.02 0 00:00 1.00 WQCV_H-Outlet ORIFICE 0.42 0 00:00 1.00 *************************** Flow Classification Summary *************************** ------------------------------------------------------------------------------------- Adjusted ---------- Fraction of Time in Flow Class ---------- /Actual Up Down Sub Sup Up Down Norm Inlet Conduit Length Dry Dry Dry Crit Crit Crit Crit Ltd Ctrl ------------------------------------------------------------------------------------- C3 1.00 0.03 0.00 0.00 0.97 0.00 0.00 0.00 0.97 0.00 C4 1.00 0.03 0.00 0.00 0.97 0.00 0.00 0.00 0.00 0.00 C7 1.00 0.03 0.17 0.00 0.80 0.00 0.00 0.00 0.55 0.00 C8 1.00 0.03 0.00 0.00 0.97 0.00 0.00 0.00 0.97 0.00 C9 1.00 0.03 0.00 0.00 0.97 0.00 0.00 0.00 0.00 0.00 C10 1.00 0.03 0.00 0.00 0.97 0.00 0.00 0.00 0.00 0.00 ************************* Conduit Surcharge Summary ************************* ---------------------------------------------------------------------------- Hours Hours --------- Hours Full -------- Above Full Capacity Conduit Both Ends Upstream Dnstream Normal Flow Limited ---------------------------------------------------------------------------- C10 0.01 0.01 0.01 7.17 0.01 Analysis begun on: Tue Sep 30 22:08:17 2025 Analysis ended on: Tue Sep 30 22:08:18 2025 Total elapsed time: 00:00:01 EPA STORM WATER MANAGEMENT MODEL - VERSION 5.2 (Build 5.2.4) ------------------------------------------------------------ WARNING 04: minimum elevation drop used for Conduit C10 **************** Analysis Options **************** Flow Units ............... CFS Process Models: Rainfall/Runoff ........ YES RDII ................... NO Snowmelt ............... NO Groundwater ............ NO Flow Routing ........... YES Ponding Allowed ........ NO Water Quality .......... NO Infiltration Method ...... HORTON Flow Routing Method ...... DYNWAVE Surcharge Method ......... SLOT Starting Date ............ 03/19/2021 00:00:00 Ending Date .............. 03/26/2021 00:00:00 Antecedent Dry Days ...... 0.0 Report Time Step ......... 00:01:00 Wet Time Step ............ 00:01:00 Dry Time Step ............ 01:00:00 Routing Time Step ........ 5.00 sec Variable Time Step ....... YES Maximum Trials ........... 8 Number of Threads ........ 1 Head Tolerance ........... 0.005000 ft ************************** Volume Depth Runoff Quantity Continuity acre-feet inches ************************** --------- ------- Total Precipitation ...... 71.845 3.669 Evaporation Loss ......... 0.000 0.000 Infiltration Loss ........ 11.415 0.583 Surface Runoff ........... 59.076 3.017 Final Storage ............ 1.367 0.070 Continuity Error (%) ..... -0.019 ************************** Volume Volume Flow Routing Continuity acre-feet 10^6 gal ************************** --------- --------- Dry Weather Inflow ....... 0.000 0.000 Wet Weather Inflow ....... 59.057 19.245 Groundwater Inflow ....... 0.000 0.000 RDII Inflow .............. 0.000 0.000 External Inflow .......... 0.000 0.000 External Outflow ......... 58.999 19.226 Flooding Loss ............ 0.038 0.012 Evaporation Loss ......... 0.000 0.000 Exfiltration Loss ........ 0.000 0.000 Initial Stored Volume .... 0.804 0.262 Final Stored Volume ...... 0.826 0.269 Continuity Error (%) ..... -0.004 *************************** Time-Step Critical Elements *************************** Link C10 (12.58%) Link C4 (10.53%) ******************************** Highest Flow Instability Indexes ******************************** Link Pond_E_Outlet (106) Link Pond_C_Outlet (24) Link C10 (22) ********************************* Most Frequent Nonconverging Nodes ********************************* Convergence obtained at all time steps. ************************* Routing Time Step Summary ************************* Minimum Time Step : 2.98 sec Average Time Step : 4.72 sec Maximum Time Step : 5.00 sec % of Time in Steady State : 0.00 Average Iterations per Step : 2.00 % of Steps Not Converging : 0.00 Time Step Frequencies : 5.000 - 3.155 sec : 94.65 % 3.155 - 1.991 sec : 5.35 % 1.991 - 1.256 sec : 0.00 % 1.256 - 0.792 sec : 0.00 % 0.792 - 0.500 sec : 0.00 % *************************** Subcatchment Runoff Summary *************************** ------------------------------------------------------------------------------------------------------------------------------ Total Total Total Total Imperv Perv Total Total Peak Runoff Precip Runon Evap Infil Runoff Runoff Runoff Runoff Runoff Coeff Subcatchment in in in in in in in 10^6 gal CFS ------------------------------------------------------------------------------------------------------------------------------ A 3.67 0.00 0.00 0.62 2.50 0.48 2.98 4.53 233.48 0.812 D 3.67 0.00 0.00 1.14 1.71 0.77 2.48 2.50 144.67 0.676 E 3.67 0.00 0.00 0.84 2.18 0.59 2.77 2.00 108.80 0.755 C 3.67 0.00 0.00 0.15 3.21 0.21 3.43 2.05 138.82 0.934 G 3.67 0.00 0.00 0.15 3.21 0.21 3.43 1.82 122.72 0.934 H 3.67 0.00 0.00 0.30 2.86 0.44 3.29 1.08 96.51 0.898 B 3.67 0.00 0.00 0.54 2.50 0.56 3.06 1.27 85.59 0.834 I 3.67 0.00 0.00 0.30 2.86 0.43 3.29 0.57 49.26 0.897 S4 3.67 0.00 0.00 0.29 2.79 0.52 3.30 0.08 8.81 0.900 G1 3.67 0.00 0.00 0.47 2.59 0.54 3.13 2.72 196.30 0.853 J 3.67 0.00 0.00 0.31 2.86 0.43 3.28 0.62 50.64 0.895 ****************** Node Depth Summary ****************** --------------------------------------------------------------------------------- Average Maximum Maximum Time of Max Reported Depth Depth HGL Occurrence Max Depth Node Type Feet Feet Feet days hr:min Feet --------------------------------------------------------------------------------- J3 JUNCTION 0.12 1.01 4928.01 0 02:23 1.01 J4 JUNCTION 0.38 1.81 4924.81 0 02:21 1.81 J5 JUNCTION 0.21 2.03 4929.03 0 02:11 2.03 J6 JUNCTION 1.10 1.84 4940.84 0 02:25 1.84 J7 JUNCTION 0.18 1.06 4925.41 0 02:18 1.06 J8 JUNCTION 0.45 1.81 4939.81 0 02:20 1.81 Peakview_Storm_Stub OUTFALL 0.28 1.59 4924.53 0 02:21 1.59 CooperSlough OUTFALL 0.31 1.53 4939.53 0 02:20 1.53 Lake_Canal OUTFALL 0.00 0.00 0.00 0 00:00 0.00 CooperSloughNorth OUTFALL 0.00 0.00 4940.00 0 00:00 0.00 O1 OUTFALL 0.00 0.00 4926.50 0 00:00 0.00 O2 OUTFALL 0.00 0.00 4924.00 0 00:00 0.00 O3 OUTFALL 0.00 0.00 4922.50 0 00:00 0.00 Pond_A STORAGE 0.86 6.60 4952.10 0 02:42 6.60 Pond_B STORAGE 1.14 6.04 4948.54 0 07:24 6.04 Pond_C STORAGE 0.40 5.99 4944.49 0 02:07 5.99 Pond_D STORAGE 0.80 3.81 4946.31 0 03:07 3.81 Pond_E STORAGE 0.82 5.26 4944.76 0 02:24 5.26 Pond_G STORAGE 0.63 7.72 4936.22 0 02:22 7.72 Pond_H STORAGE 2.66 7.02 4930.02 0 02:39 7.02 Pond_I STORAGE 4.11 5.58 4928.08 0 03:05 5.58 Pond_G1 STORAGE 1.63 8.00 4935.00 0 02:07 8.00 Pond_J STORAGE 1.39 4.83 4929.33 0 02:36 4.83 Pond_G1-WQCV STORAGE 0.19 1.14 4928.14 0 00:00 1.14 Pond_J-WQCV STORAGE 0.06 0.38 4924.88 0 00:00 0.38 Pond_H-WQCV STORAGE 0.03 0.62 4923.62 0 00:00 0.62 ******************* Node Inflow Summary ******************* ------------------------------------------------------------------------------------------------- Maximum Maximum Lateral Total Flow Lateral Total Time of Max Inflow Inflow Balance Inflow Inflow Occurrence Volume Volume Error Node Type CFS CFS days hr:min 10^6 gal 10^6 gal Percent ------------------------------------------------------------------------------------------------- J3 JUNCTION 0.00 13.27 0 02:22 0 3.81 -0.007 J4 JUNCTION 0.00 24.37 0 02:20 0 8.21 0.001 J5 JUNCTION 0.00 10.02 0 02:07 0 2.7 -0.014 J6 JUNCTION 0.00 8.11 0 02:24 0 1.9 -0.331 J7 JUNCTION 0.00 10.52 0 02:17 0 3.32 0.019 J8 JUNCTION 0.00 22.71 0 02:20 0 10.3 -0.056 Peakview_Storm_Stub OUTFALL 0.00 24.37 0 02:21 0 8.21 0.000 CooperSlough OUTFALL 0.00 22.71 0 02:20 0 10.3 0.000 Lake_Canal OUTFALL 0.00 0.14 0 03:05 0 0.527 0.000 CooperSloughNorth OUTFALL 0.00 0.00 0 00:00 0 0 0.000 gal O1 OUTFALL 0.00 0.12 0 00:00 0 0.083 0.000 O2 OUTFALL 0.00 0.02 0 00:00 0 0.014 0.000 O3 OUTFALL 0.00 0.42 0 00:00 0 0.0463 0.000 Pond_A STORAGE 233.48 233.48 0 00:40 4.53 4.53 0.000 Pond_B STORAGE 85.59 92.50 0 00:40 1.27 5.8 0.000 Pond_C STORAGE 138.82 138.82 0 00:40 2.05 2.05 0.260 Pond_D STORAGE 144.67 144.67 0 00:40 2.5 2.5 0.000 Pond_E STORAGE 108.80 108.80 0 00:40 2 2 0.367 Pond_G STORAGE 131.53 132.99 0 00:40 1.9 3.81 -0.031 Pond_H STORAGE 96.51 96.51 0 00:40 1.08 1.1 0.000 Pond_I STORAGE 49.26 49.26 0 00:40 0.571 0.571 0.000 Pond_G1 STORAGE 196.30 196.30 0 00:40 2.72 2.8 -0.006 Pond_J STORAGE 50.64 50.64 0 00:40 0.615 0.629 0.000 Pond_G1-WQCV STORAGE 0.00 0.00 0 00:00 0 0.083 0.001 Pond_J-WQCV STORAGE 0.00 0.00 0 00:00 0 0.014 0.001 Pond_H-WQCV STORAGE 0.00 0.00 0 00:00 0 0.0464 0.003 ********************** Node Surcharge Summary ********************** No nodes were surcharged. ********************* Node Flooding Summary ********************* Flooding refers to all water that overflows a node, whether it ponds or not. -------------------------------------------------------------------------- Total Maximum Maximum Time of Max Flood Ponded Hours Rate Occurrence Volume Depth Node Flooded CFS days hr:min 10^6 gal Feet -------------------------------------------------------------------------- Pond_G1 0.14 7.48 0 02:07 0.012 0.000 ********************** Storage Volume Summary ********************** ------------------------------------------------------------------------------------------------ Average Avg Evap Exfil Maximum Max Time of Max Maximum Volume Pcnt Pcnt Pcnt Volume Pcnt Occurrence Outflow Storage Unit 1000 ft³ Full Loss Loss 1000 ft³ Full days hr:min CFS ------------------------------------------------------------------------------------------------ Pond_A 51.249 9.3 0.0 0.0 503.288 91.2 0 02:42 9.93 Pond_B 35.301 10.5 0.0 0.0 208.836 62.2 0 07:24 7.84 Pond_C 6.584 3.6 0.0 0.0 180.722 99.8 0 02:07 12.77 Pond_D 59.359 13.7 0.0 0.0 309.429 71.3 0 03:07 2.54 Pond_E 24.183 8.0 0.0 0.0 205.531 67.7 0 02:24 8.11 Pond_G 12.129 5.8 0.0 0.0 195.403 93.1 0 02:22 13.27 Pond_H 41.264 19.7 0.0 0.0 142.128 68.0 0 02:39 0.60 Pond_I 39.833 37.8 0.0 0.0 74.676 70.9 0 03:05 0.14 Pond_G1 29.374 9.7 0.0 0.0 302.910 100.0 0 02:07 10.02 Pond_J 17.951 18.8 0.0 0.0 79.523 83.4 0 02:36 0.51 Pond_G1-WQCV 1.343 4.0 0.0 0.0 11.095 32.9 0 00:00 0.12 Pond_J-WQCV 0.199 0.8 0.0 0.0 1.873 7.5 0 00:00 0.02 Pond_H-WQCV 0.296 1.5 0.0 0.0 6.200 31.0 0 00:00 0.42 *********************** Outfall Loading Summary *********************** ----------------------------------------------------------- Flow Avg Max Total Freq Flow Flow Volume Outfall Node Pcnt CFS CFS 10^6 gal ----------------------------------------------------------- Peakview_Storm_Stub 99.88 2.51 24.37 8.211 CooperSlough 99.92 2.96 22.71 10.343 Lake_Canal 99.91 0.12 0.14 0.527 CooperSloughNorth 0.00 0.00 0.00 0.000 O1 28.06 0.08 0.12 0.083 O2 25.41 0.02 0.02 0.014 O3 30.56 0.05 0.42 0.046 ----------------------------------------------------------- System 54.82 5.73 47.58 19.224 ******************** Link Flow Summary ******************** ----------------------------------------------------------------------------- Maximum Time of Max Maximum Max/ Max/ |Flow| Occurrence |Veloc| Full Full Link Type CFS days hr:min ft/sec Flow Depth ----------------------------------------------------------------------------- C3 CONDUIT 13.27 0 02:23 4.06 0.24 0.47 C4 CONDUIT 24.37 0 02:21 5.89 1.30 0.57 C7 CONDUIT 8.11 0 02:25 1.72 0.17 1.00 C8 CONDUIT 10.52 0 02:18 2.59 0.16 0.36 C9 CONDUIT 10.01 0 02:13 3.85 1.06 0.77 C10 CONDUIT 22.71 0 02:20 5.61 9.37 0.56 Pond_H_Outlet ORIFICE 0.60 0 14:34 1.00 Pond_D_Outlet ORIFICE 2.54 0 03:07 1.00 Pond_E_Outlet ORIFICE 8.11 0 02:24 1.00 Pond_B_Outlet ORIFICE 7.84 0 07:24 1.00 Pond_C_Outlet ORIFICE 12.77 0 02:07 1.00 Pond_A_Outlet ORIFICE 9.93 0 02:09 1.00 PondG_Outlet ORIFICE 13.27 0 02:22 1.00 Pond_I_Outlet ORIFICE 0.14 0 03:05 1.00 PondG1_Outlet ORIFICE 10.02 0 02:07 1.00 Pond_J_Outlet ORIFICE 0.51 0 02:42 1.00 WQCV_G1-Outlet ORIFICE 0.12 0 00:00 1.00 WQCV_J-Outlet ORIFICE 0.02 0 00:00 1.00 WQCV_H-Outlet ORIFICE 0.42 0 00:00 1.00 *************************** Flow Classification Summary *************************** ------------------------------------------------------------------------------------- Adjusted ---------- Fraction of Time in Flow Class ---------- /Actual Up Down Sub Sup Up Down Norm Inlet Conduit Length Dry Dry Dry Crit Crit Crit Crit Ltd Ctrl ------------------------------------------------------------------------------------- C3 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 C4 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 C7 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.12 0.00 C8 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 C9 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.90 0.00 C10 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 ************************* Conduit Surcharge Summary ************************* ---------------------------------------------------------------------------- Hours Hours --------- Hours Full -------- Above Full Capacity Conduit Both Ends Upstream Dnstream Normal Flow Limited ---------------------------------------------------------------------------- C4 0.01 0.01 0.01 7.43 0.01 C7 0.01 0.01 10.88 0.01 0.01 C9 0.01 0.94 0.01 2.57 0.01 C10 0.01 0.01 0.01 32.29 0.01 Analysis begun on: Tue Sep 30 21:53:58 2025 Analysis ended on: Tue Sep 30 21:53:59 2025 Total elapsed time: 00:00:01 Bloom Commercial Preliminary Drainage Report APPENDIX F Drainage Maps G1.3 G1.4 G-OS G1.1 G1.2 G1.15G1.7 G1.16 G1.17 H1 H2 G1.5 G1.12 H5 H6 G1.13 G1.14 G1.11 G1.8 G1.9 acres H1 0.80 1.00 0.61 acres H2 0.81 1.00 0.55 acres H 0.91 1.00 6.16 acres G1.2 0.95 1.00 1.36acres G1.3 0.95 1.00 2.29 acres G1.9 0.46 0.58 2.44 acres G1.10 0.85 1.00 1.00 acres G1.8 0.83 1.00 2.06 acres G1.7 0.63 0.79 0.56 acres G1.12 0.95 1.00 0.61 acres G1.13 0.94 1.00 0.69 acres G1.11 0.87 1.00 0.61 acres G1.4 0.95 1.00 0.23 acres G1.5 0.95 1.00 0.25 acres G1.6 0.95 1.00 0.39 acres G1.16 0.70 0.87 0.12 acres H5 0.62 0.78 0.35 acres G1.1 0.95 1.00 1.56 acres G1.15 0.73 0.91 0.38 acres G1 % IMP. 72.5 32.0 acres G % IMP. 90.0 19.6 DESIGN POINT OVERLAND FLOW DIRECTION (I.E., LANDSCAPING) DIRECT FLOW DIRECTION (I.E., PAVEMENT, CURB AND GUTTER) BASIN ID 2-YR RUNOFF COEFFICIENT BASIN AREA (ACRES) acres A1 0.05 0.35 2.50 A APPROXIMATE DETENTION POND OVERFLOW PATH 100-YR RUNOFF COEFFICIENT BASIN BOUNDARY (i.e., SWMM) A BASIN BOUNDARY (i.e., Rational Method) SWMM BASIN ID SWMM BASIN AREA (ACRES) acres A1 0.05 0.35 2.50 SWMM BASIN IMPERVIOUS (%) RATIONAL METHOD BASIN IDENTIFIER SWMM BASIN IDENTIFIER Know what's before you dig. PGS JEP DRAINAGE PLAN 67 C10.1 - - - - - - - - - - - - - - H: \ H \ H a r t f o r d H o m e s \ C O F o r t C o l l i n s H F H 7 3 - B l o o m C o m m e r c i a l \ 0 C I V \ 3 - C D \ F D P \ H F H 0 7 3 _ C 1 0 . 1 D r a i n a g e P l a n . d w g - He r m a n F e i s s n e r - 10 / 1 / 2 0 2 5 BL O O M F I L I N G N I N E FI N A L D E V E L O P M E N T P L A N FO R T C O L L I N S , C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 GallowayUS.com NOT F O R CON S T R U C T I O N #Date Issue / Description Init. Project No: Drawn By: Checked By: Date: HFH000073.20 10/01/2025 Sheet of 68 J1 J G1.16 G1.17 H3 H8 H5 H6 G1.13 G1.14 acres H7 0.72 0.89 5.31 acres H3 0.85 1.00 0.61 acres J1 0.68 0.85 0.80 acres H8 0.39 0.49 3.09 acres G1.14 0.75 0.94 0.32 acres J 0.82 1.00 6.85 acres0.87 acres G1.17 0.71 0.89 0.12 acres H6 0.63 0.78 0.36 acres H % IMP. 80.0 10.7 acres J % IMP. 80.0 6.9 DESIGN POINT OVERLAND FLOW DIRECTION (I.E., LANDSCAPING) DIRECT FLOW DIRECTION (I.E., PAVEMENT, CURB AND GUTTER) BASIN ID 2-YR RUNOFF COEFFICIENT BASIN AREA (ACRES) acres A1 0.05 0.35 2.50 A APPROXIMATE DETENTION POND OVERFLOW PATH 100-YR RUNOFF COEFFICIENT BASIN BOUNDARY (i.e., SWMM) A BASIN BOUNDARY (i.e., Rational Method) SWMM BASIN ID SWMM BASIN AREA (ACRES) acres A1 0.05 0.35 2.50 SWMM BASIN IMPERVIOUS (%) RATIONAL METHOD BASIN IDENTIFIER SWMM BASIN IDENTIFIER Know what's before you dig. PGS JEP DRAINAGE PLAN 68 C10.2 - - - - - - - - - - - - - - H: \ H \ H a r t f o r d H o m e s \ C O F o r t C o l l i n s H F H 7 3 - B l o o m C o m m e r c i a l \ 0 C I V \ 3 - C D \ F D P \ H F H 0 7 3 _ C 1 0 . 1 D r a i n a g e P l a n . d w g - He r m a n F e i s s n e r - 10 / 1 / 2 0 2 5 BL O O M F I L I N G N I N E FI N A L D E V E L O P M E N T P L A N FO R T C O L L I N S , C O THESE PLANS ARE AN INSTRUMENT OF SERVICE AND ARE THE PROPERTY OF GALLOWAY, AND MAY NOT BE DUPLICATED, DISCLOSED, OR REPRODUCED WITHOUT THE WRITTEN CONSENT OF GALLOWAY. COPYRIGHTS AND INFRINGEMENTS WILL BE ENFORCED AND PROSECUTED. COPYRIGHT 5235 Ronald Reagan Blvd., Suite 200 Johnstown, CO 80534 970.800.3300 GallowayUS.com NOT F O R CON S T R U C T I O N #Date Issue / Description Init. Project No: Drawn By: Checked By: Date: HFH000073.20 10/01/2025 Sheet of 68