May 28, 2025
RE: Moor Annexation, ANX250001, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Moor Annexation. If you have questions about any
comments, you may contact the individual commenter or direct your questions through your
Development Review Coordinator, Brandy Bethurem Harras via phone at 970-416-2744 or
via email at bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras bbethuremharras@fcgov.com 970-416-2744
Topic: General
Comment Number: 1
05/22/2025: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email correspondence
with other reviewers and keep me informed of any phone conversations. Thank you!
RESPONSE: Acknowledged
Comment Number: 2
05/22/2025: SUBMITTAL:
As part of your submittal, a response to the comments provided in this letter and
a response to plan markups is required. The final letter is provided to you in
Microsoft Word format. Please use this letter to insert responses to each
comment for your submittal, using a different font color. Please use the markups
to insert responses to each comment on plans. Please do not flatten markup responses.
Provide a detailed response for any comment asking a question or requiring an
action. Any comment requesting a response or requiring action by you with a
response of noted, acknowledged etc. will be considered not addressed. You
will need to provide references to specific project plans, pages, reports, or
2
explanations of why comments have not been addressed [when applicable].
RESPONSE: Acknowledged
Comment Number: 3
05/22/2025: SUBMITTAL:
Correct file naming is required as part of a complete submittal. Please follow
the Electronic Submittal Requirements and File Naming Standards found here:
https://www.fcgov.com/developmentreview/files/electronic-submittal-requiremen
ts-and-file-naming-standards_v1_8-1-19.pdf?1703783275
File names should have the corresponding number, followed by the file type
prefix, project information, and round number.
For example: 1_SITE PLAN_Project Name_FDP_Rd1.
A list of numbers and prefixes for each file can be found at the link above.
RESPONSE: Provided
Comment Number: 4
05/22/2025: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and
remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be
removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove
this feature, type "EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and
newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-AutoCAD.html
RESPONSE: Provided
Comment Number: 5
05/22/2025: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced
notice as possible.
RESPONSE: Acknowledged
Comment Number: 6
05/22/2025: INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the expiration of your project.
RESPONSE: Acknowledged
Comment Number: 7
05/22/2025: INFORMATION:
ANY project that requires four or more rounds of review would be subject to an additional fee of $3,000.00.
RESPONSE: Acknowledged
Comment Number: 8
05/22/2025: NOTICE:
A Development Review sign will be posted on the property. This sign will be
posted through the final decision and appeal process. A request for the removal
3
of signs will be made by your Development Review Coordinator at the
appropriate time.
RESPONSE: Acknowledged
Comment Number: 9
05/22/2025: FOR HEARING:
All "For Hearing" comments need to be addressed and resolved prior to
moving forward with scheduling the Hearing. Staff will need to agree the project
is ready for Hearing approximately 4 to 8 weeks prior to the hearing.
RESPONSE: Acknowledged
Comment Number: 10
05/22/2025:
PRIOR TO INITIATING RESOLUTION:
For the City Clerk's Office, I will need to receive four paper copies of the signed
annexation map at minimum, two weeks prior to the initiating resolution with City Council.
These will be delivered to my attention at the Development Review Center, 281 N College Ave.
RESPONSE: Acknowledged
Comment Number: 11
05/22/2025: EFFECTIVE DATE OF ANNEXATION:
The annexation becomes official on the later of these two dates:
10 days after the annexation ordinance is passed on its second reading (unless
it's an emergency ordinance).
When three certified copies of the annexation ordinance and map are recorded
with the Larimer County Clerk and Recorder.
RESPONSE: Acknowledged
Department: Planning Services
Contact: Arlo Schumann aschumann@fcgov.com 970-221-6599
Topic: General
Comment Number: 1
05/27/2025: INFORMATION:
The City’s Structure Plan provides the framework for the ultimate build out of
Fort Collins, guiding future growth and land uses. For the subject parcel, the
City’s Structure Plan guidance calls for Suburban Neighborhood. Staff finds that
the proposed zoning of Low Density Mixed-Use (LMN) is consistent with the
Structure Plan and will be compatible with existing adjacent land uses.
RESPONSE: Thank you
Department: Historic Preservation
Contact: Jim Bertolini jbertolini@fcgov.com 970-416-4250
Topic: General
Comment Number: 1
05/06/2025: NO HISTORIC REVIEW REQUIRED:
This proposal does not require historic review because there are no designated
historic resources on the site and the nature of the project does not impact any
historic resources that may lie on the development site or within 200 feet of the site.
RESPONSE: Thank you
4
Department: Engineering Development Review
Contact: Tim Dinger tdinger@fcgov.com
Topic: General
Comment Number: 1
05/08/2025: INFORMATION:
Engineering has no comments on the proposed annexation. Further comments
will be provided once the property develops.
Please be aware that the annexation "plat" is not a subdivision plat, and the
subdivision plat will still be required with the development submittal.
RESPONSE: Acknowledged, thank you
Department: Traffic Operation
Contact: Steve Gilchrist sgilchrist@fcgov.com 970-224-6175
Topic: General
Comment Number: 1
05/23/2025: INFORMATION:
The annexation and zoning in and of itself will not require the submittal of a
Transportation Impact Study. TIS waived. However, upon development of these
properties a new evaluation will be conducted to determine if a TIS will be
required based on the anticipated trips that will be generated from said
development. Further information regarding the City of Fort Collins
requirements and content of a transportation impact study can be found in
chapter 4 of the Larimer County Urban Area Street Standards.
RESPONSE: Acknowledged, thank you
Department: Stormwater Engineering
Contact: Andrew Crecca acrecca@fcgov.com
Topic: Erosion Control
Comment Number: 1
05/05/2025: INFORMATION:
Upon Annexation this parcel will be located within the City's MS4 boundaries
and is subject to the erosion control requirements located in the Fort Collins
Stormwater Criteria Manual (FCSCM), Chapter 2, Section 6.0. A copy of those
requirements can be found at www.fcgov.com/erosion
Based upon this project type, Annexation alone does not trigger erosion control
requirements. Please be aware that future submittals or planned work will be
evaluated based upon the submittal requirements of FCSCM and may require
Erosion Control Materials including Plans, Reports, Escrow Calculations and Inspection Fees.
RESPONSE: Acknowledged
Contact: Wes Lamarque wlamarque@fcgov.com 970-416-2418
Topic: General
Comment Number: 2
05/27/2025: INFORMATION:
All comments which were given during the Conceptual Review are applicable at time of development.
5
RESPONSE: Acknowledged
Comment Number: 3
05/27/2025: INFORMATION:
Capital Project Coordination (site specific comment):
In addition to the Lilac Pond project, there also may be a Utilities Small Capital
Improvement Project for the storm drain crossing this site. Please contact Doug
Groves (Stormwater Maintenance Manager, DeGroves@fcgov.com), Alex
Massara (Water Field Operations Engineer, amassara@fcgov.com), and
Stormwater Development Review (WaterUtilitiesEng@fcgov.com) for more information.
RESPONSE: Acknowledged, email sent on 5/28/25
Comment Number: 4
05/27/2025: INFORMATION:
Please be aware that any future development following annexation will be
required to meet all current City Stormwater Criteria.
RESPONSE: Acknowledged
Department: Water-Wastewater Engineering
Contact: Wes Lamarque wlamarque@fcgov.com 970-416-2418
Topic: General
Comment Number: 1
05/27/2025: INFORMATION:
All comments which were given during the Conceptual Review are applicable at time of development.
RESPONSE: Acknowledged
Comment Number: 2
05/27/2025: INFORMATION:
There are no changes to water or wastewater associated with the annexation as
current water and sewer district areas remain the same. Any future
development will be required to meet applicable district Water and Wastewater
Design Criteria, which is also the case currently prior to annexation.
For full details on annexed infrastructure, please reference Larimer County
Urban Area Street Standards Appendix G – Policy and Standard for
Maintenance and Improvement of Annexed Infrastructure (City of Fort Collins only) available at
https://www.larimer.org/engineering/standards-and-guides/urban-area-street-standards.
RESPONSE: Acknowledged
Department: Light And Power
Contact: Rob Irish rirish@fcgov.com 970-224-6167
Topic: General
Comment Number: 1
05/12/2025: INFORMATION:
Light & Power has no comments for the proposed annexation. Further
comments will be provided once a development plan is submitted.
RESPONSE: Thank you
Department: Environmental Planning
Contact: Kristie Raymond kraymond@fcgov.com
Topic: General
6
Comment Number: 1
05/05/2025: INFORMATION:
No comments on the annexation.
RESPONSE: Thank you
Department: Forestry
Contact: Freddie Haberecht fhaberecht@fcgov.com
Topic: General
Comment Number: 1
05/27/2025: INFORMATION:
NO COMMENTS
RESPONSE: Thank you
Department: PFA
Contact: Marcus Glasgow marcus.glasgow@poudre-fire.org 970-416-2869
Topic: General
Comment Number: 1
05/20/2025: INFORMATION:
PFA has no comments on the annexation. Future development will require review.
RESPONSE: Thank you
Department: Building Services
Contact: Russell Hovland rhovland@fcgov.com 970-416-2341
Topic: Building Insp Plan Review
Comment Number: 1
05/27/2025: INFORMATION:
If any new structure are planned as part of this annexation, a building permit is
required, see Building Services web page.
RESPONSE: No structures are proposed with this annexation.
Department: Technical Services
Contact: Jeff County jcounty@fcgov.com 970-221-6588
Topic: Plat
Comment Number: 1
05/27/2025: FOR HEARING:
Please make changes as marked in the Technical Services (TS) markup PDF.
If changes are not made or you disagree with comments, please provide written
response of why corrections were not made. Please provide any responses on
redlined sheets and/or in response letter. If you have any specific questions
about the markups, please contact John Von Nieda at 970-221-6565 or
jvonnieda@fcgov.com
RESPONSE: See updated Annexation Map and responses on PDF.