We are providing the following information regarding the sizing of the water tap and meter for the
Prospect Plaza Project at W Lake Street and east of Center Avenue Ft. Collins, CO 80526.
The Prospect Plaza project is a Multifamily Student Housing project with a core & shell coffee shop.
The plumbing fixture counts are based on preliminary architectural drawings and unit counts. Note that
the coffee shop will be served by a dedicated domestic water tap and is not included in the calculations
below.
The project has 696 beds, 259 units. We are providing water tap sizing information in accordance with
the AWWA Manual M22 method.
Below is a summary of the plumbing fixtures planned for the entire building excluding the coffee shop.
Prospect Plaza
W Lake Street and Center Ave. Ft. Collins, Colorado
March 12, 2025
Galloway & Company, Inc. Page 2 of 2
Based on figure 4-2 from AWWA Manual M22, 6523 water supply fixtures is roughly equivalent to 102
gpm for an apartment building.
Based on table 6-1 from AWWA Manual M22, a 3” tap and meter is required for this project.
Sincerely,
GALLOWAY
Alicia Thorpe, PE
Principal
AliciaThorpe@GallowayUS.com
03/12/2025
5500 Greenwood Plaza Blvd., Suite 200
Denver, CO 80111
303.770.8884 • GallowayUS.com
March 12, 2025
We are providing the following information regarding the sizing of the water tap and meter for the
Prospect Plaza Project at W Lake Street and east of Center Avenue Ft. Collins, CO 80526.
The Prospect Plaza project is a Multifamily Student Housing project with a core & shell coffee shop.
The plumbing fixture counts are based on preliminary architectural drawings. Note that the coffee shop
will be served by a dedicated domestic water tap.
The coffee shop is anticipated to include (2) flush tank water closets, (2) lavatories, (4) kitchen sink, (1)
Dish Washer, (1) service sink, and (1) 3-comp Sink. We are providing water tap sizing information in
accordance with the Appendix E of the 2021 International Plumbing Code. Approximately 40 wsfu are
dedicated for the coffee shop, using Table E104.1 at over 60psi the project will require a 1” tap with a
1-1/4” distribution line.
Sincerely,
GALLOWAY
Alicia Thorpe, PE
Principal
AliciaThorpe@GallowayUS.com
03/12/2025
Please provide a table similar to
what was provided for the
residential portion of the building.
Please provide a peak demand in GPM.
Please see the table provided on
the following sheet.
Please see the table provided on the
following sheet. The Peak demand is
26.3 GPM.
Coffee Shop Fixture Summary