HomeMy WebLinkAboutProject Narratives - 03/12/2025Project Information and Design Narrative
Liberty Common Junior High School – Phase 2
March 12, 2025
The project consists of the change of use, change of occupancy and interior tenant finish renovations to
change the existing building located at 1901 Sharp Point Drive from an office building into a school,
Liberty Common Junior High School. The project also includes the construction of an addition
connecting this building to 1825 Sharp Point Drive. Site work as part of this project includes diversion of
storm water flows away from the addition, creation of new stormwater detention and water quality
features, re-routing public access and emergency access around the building, and relocating utilities
around the building footprint.
The interior program spaces will include construction of classrooms, administrative space, a cafeteria, a
regulation-sized gymnasium and various support spaces to accommodate 330 junior high school
students.
This is the second SPAR submittal for Liberty Common Junior High School. Phase 1 included the change
of use and tenant finish work in 1825 Sharp Point Drive. Construction is underway on Phase 1 with an
anticipated finish and owner move in this summer, ahead of school opening for the 2025/2026 school
year.
Earlier this year, City Council approved the vacation of the public ROW in Riverbend Court. Part of this
project will include re-dedicating public access, emergency access, drainage and utility easements as
necessary for the new site layout.
Our team is grateful for the support of City staff who have all been very collaborative in developing the
site design and project solutions shown in this submittal. We look forward to continued collaboration in
the development of this project.