Response to Comments November 20, 2024
RE: Heritage Christian Academy - ODP, ODP240001, Round Number 1
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Heritage Christian Academy - ODP. If you have questions
about any comments, you may contact the individual commenter or direct your questions
through your Development Review Coordinator, Brandy Bethurem Harras via phone at
970-416-2744 or via email at bbethuremharras@fcgov.com.
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras bbethuremharras@fcgov.com 970-416-2744
Topic: General
Comment Number: 1
10/11/2024: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email correspondence
with other reviewers and keep me informed of any phone conversations. Thank you!
Comment Number: 2
10/11/2024: SUBMITTAL:
As part of your submittal, a response to the comments provided in this letter and
a response to plan markups is required. The final letter is provided to you in
Microsoft Word format. Please use this letter to insert responses to each
comment for your submittal, using a different font color. Please use the markups
to insert responses to each comment on plans. Please do not flatten markup responses.
Provide a detailed response for any comment asking a question or requiring an
action. Any comment requesting a response or requiring action by you with a
response of noted, acknowledged etc. will be considered not addressed. You
will need to provide references to specific project plans, pages, reports, or
Page 2 of 8
explanations of why comments have not been addressed [when applicable].
Comment Number: 3
10/11/2024: SUBMITTAL:
Correct file naming is required as part of a complete submittal. Please follow
the Electronic Submittal Requirements and File Naming Standards found here:
https://www.fcgov.com/developmentreview/files/electronic-submittal-requiremen
ts-and-file-naming-standards_v1_8-1-19.pdf?1703783275
File names should have the corresponding number, followed by the file type
prefix, project information, and round number.
For example: 1_SITE PLAN_Project Name_FDP_Rd1.
A list of numbers and prefixes for each file can be found at the link above.
Comment Number: 4
10/11/2024: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove
this feature, type "EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and
newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-Aut oCAD.html
Comment Number: 5
10/11/2024: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced notice as possible.
Comment Number: 6
10/11/2024: INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the expiration of your project.
Comment Number: 7
10/11/2024: INFORMATION:
ANY project that requires four or more rounds of review would be subject to an additional fee of $3,000.00.
Comment Number: 8
10/11/2024: NOTICE:
A Development Review sign will be posted on the property. This sign will be
posted through the final decision and appeal process. A request for the removal
of signs will be made by your Development Review Coordinator at the appropriate time.
Response: Understood.
Comment Number: 9
10/11/2024: FOR HEARING:
All "For Hearing" comments need to be addressed and resolved prior to
moving forward with scheduling the Hearing. Staff will need to agree the project
is ready for Hearing approximately 4 to 8 weeks prior to the hearing.
Response: All ‘For Hearing’ comments have been addressed and responses included herein.
Page 3 of 8
Comment Number: 10
10/11/2024: FOR HEARING:
This proposed project is processing as a Type 2 Development Plan. The
decision maker for Type 2 is the Planning and Zoning (P&Z) Commission. For
the hearing, we will formally notify surrounding property owners within 800 feet
(excluding public right-of-way and publicly owned open space).
Response: Understood.
Comment Number: 11
10/11/2024: FOR RECORDING:
Could you please update the City signature block on the Overall Development
Plan? Instead of using "this _______ day of ______, 20____," could you opt for
"on this day, _____________" for the date? This alternative format facilitates
smoother date input with digital signatures.
Additionally, kindly ensure there is sufficient space between the signature line
and the title line to accommodate the digital signature.
Response: Cover sheet has been updated with these changes.
Department: Planning Services
Contact: Ryan Mounce rmounce@fcgov.com 970-224-6186
Topic: General
Comment Number: 1
10/11/2024: FOR HEARING:
Please edit the ODP boundary to include only private property and exclude the adjacent
right of way. Adjust the site data table to exclude right-of-way from the size calculations.
Response: ODP boundary and site data table has been revised.
Comment Number: 2
10/11/2024: FOR HEARING:
Please see redlines for additional general ODP notes to include on the cover or site plan sheet.
Response: Additional note has been added as first note.
Comment Number: 3
10/11/2024: INFORMATION:
Will commercial/industrial users continue to occupy the existing building on
Parcel C? Response: Yes, this is leased space that is likely to continue at least until future
development occurs and possibly beyond.
It may make sense to re-label this parcel as 'Primary Uses' for both
existing and proposed use to cover interim users not associated with the school.
Response: Revised to reflect this. Also see comment response below.
Similarly, if any other users or land uses may eventually be entertained across
the site, those parcels could be designated for Primary Uses to create greater
flexibility without the need for future minor/major ODP amendments.
Response: We appreciate this comment. While the intent is for the school to be able to
develop and expand within the ODP area, they also need to preserve flexibility for the
property to be developed within the standards and requirements of the E-Employment zone
district. We have modified the land use table to include both Primary and Secondary Uses
on all parcels with a note indicating that uses will be required to meet these standards.
Page 4 of 8
Comment Number: 4
10/11/2024: INFORMATION:
Timing for ODP approval first requires completion of the annexation process.
Based on current timelines and schedules, the annexation may not be effective
until January 2025 and the ODP could be considered by P&Z in January 2025 at the earliest.
Department: Engineering Development Review
Contact: Sophie Buckingham sbuckingham@fcgov.com
Topic: General
Comment Number: 1
10/15/2024: INFORMATION:
Engineering would like to be involved in any conversations between the
applicant and Traffic Operations about access locations and phasing of
improvements.
Comment Number: 2
10/15/2024: INFORMATION:
Detailed comments about public improvements and access locations will be
provided with each development phase.
Department: Traffic Operation
Contact: Steve Gilchrist sgilchrist@fcgov.com 970-224-6175
Topic: General
Comment Number: 1
10/14/2024: FOR HEARING:
The Transportation Impact Study has been received, and reviewed. We will
continue to coordinate updates to the study agreed upon within an external
meeting between the developer's Traffic Engineer and the City of Fort Collins
Traffic Operations. This included updating Timberline and International data, a
more detailed phasing plan, and bike and pedestrian connectivity. We have
also discussed the addition of any potential secondary uses for the site as the
current school building is shared with another business.
Response: This was further coordinated and discussed in a meeting on 9/11/24
with Steve Gilchrist (Traffic Operations), Kevin Brazelton (United Civil), and Sean
Kellar (Kellar Engineering). Based upon the discussion at this meeting, the TIS
has been updated to include: new traffic counts of Timberline/International;
discussion on ped/bike connectivity at Timberline/International and needs for
connectivity in the future; long term secondary point of ped/bike access for the
neighborhood to the west. Additionally, the TIS has been updated with more
details on future phasing for the site. The updated TIS has been formally
scoped with the City and updated accordingly.
Department: Erosion Control
Contact: Andrew Crecca acrecca@fcgov.com
Topic: Erosion Control
Comment Number: 1
Page 5 of 8
10/11/2024: INFORMATION:
This project is located within the City's MS4 boundaries and is subject to the
erosion control requirements
located in the Fort Collins Stormwater Criteria Manual (FCSCM), Chapter 2,
Section 6.0. A copy of those
requirements can be found at www.fcgov.com/erosion .
Comment Number: 2
10/11/2024: INFORMATION:
This ODP in its preliminary phases does not require Erosion Control
Submittals. Please note as plans develop into specific construction plans
erosion control plans, report and escrow calculation may be required.
Department: Stormwater Engineering
Contact: Dan Mogen dmogen@fcgov.com 970-305-5989
Topic: General
Comment Number: 1
10/14/2024: FOR HEARING:
Please see redlines. I encourage you to reach out with any questions or to
review potential revisions, and I’d be happy to set up a meeting or conference
call to do so.
Response: We have included responses to redlines with the resubmittal.
Department: Water-Wastewater Engineering
Contact: Dan Mogen dmogen@fcgov.com 970-305-5989
Topic: General
Comment Number: 1
10/14/2024: INFORMATION:
Noting this is ELCO Water and Boxelder Sanitation Districts, as indicated in the submittal documents.
Department: Environmental Planning
Contact: Kristie Raymond kraymond@fcgov.com
Topic: General
Comment Number: 1
10/14/2024: FOR HEARING:
According to Section 6.5.2(I)(5) of the Land Use Code, "the overall
development plan shall show the general location and approximate size of all
natural areas, habitats and features within its boundaries and shall indicate the
applicant's proposed rough estimate of the natural area buffer zones as
required pursuant to Section 5.6.1(E)." The presence of natural features on the
project site necessitates a process for the creation of a Natural Habitat Buffer
Zone (NHBZ) to protect that natural feature.
The plans will need to include approximate buffer zones for the following natural features:
1) Lake Canal - 50 foot NHBZ
2) The north stormwater canal was determined to be a wetland feature by the
City of Fort Collins Environmental Planning staff. This will need a 50 foot NHBZ.
Page 6 of 8
Additionally, the detention basin on the south side is noted as a naturalized
detention basin, and the City would like to see the vegetation preserved and
expanded on for this feature.
The stormwater wetlands on the north side of the fence will not require a NHBZ
since this area already has a NHBZ here from a different development.
However, in your planning process please consider the use of native
landscaping species adjacent to the NHBZ to provide an ecologically
appropriate transition.
Response: Thank you for the further conversations and site visit. As we have discussed, we
have indicated the 50’ NHBZ for both Lake Canal and for the north drainage feature. We
anticipate when development plans are submitted in the future, we will request the ability to
mitigate this north feature within the planned development to allow the north parcels to be
utilized. However, the details of any mitigation would occur at the time of these future site-
specific development plans (PDP/FDP) and we have added your note indicated below to the
ODP for this reference.
Comment Number: 2
10/14/2024: FOR HEARING:
Please include the following note on the ODP: "This Overall Development Plan
shows the location and approximate size of all natural areas, habitats, and
features within its boundaries and the proposed estimate of the natural area
buffer zones as required by Land Use Code Section 5.6.1(E). Detailed
mapping of the site's natural areas, habitats, and features will be provided at the
time of individual PDP submittals, and management details of the features and
buffers will be coordinated at that time. General buffer zones shown on this
ODP may be reduced or enlarged by the decision maker during the PDP
process."
Response: Note added.
Comment Number: 3
10/14/2024: FOR HEARING:
Please add the following note on any sheets of the ODP, Master Utility Plan and
Master Drainage Plan that show the Natural Habitat Buffer Zone: "The Natural
Habitat Buffer Zone is intended to be maintained in a native landscape. Please
see Section 5.6 of the Land Use Code for allowable uses within the Natural
Habitat Buffer Zone." This will help preserve the intention behind the buffer
zones and the natural features into the future.
Response: Note added.
Department: Forestry
Contact: Freddie Haberecht fhaberecht@fcgov.com
Topic: General
Comment Number: 1
10/15/2024: INFORMATION:
Please address comments from conceptual review before first round of PDP.
Department: Light And Power
Contact: Luke Unruh lunruh@fcgov.com 970-416-2724
Page 7 of 8
Topic: General
Comment Number: 1
10/14/2024: INFORMATION:
I have no comments pertaining to the ODP. My comments will be site specific during the project review
Department: Park Planning
Contact: Missy Nelson mnelson@fcgov.com
Topic: General
Comment Number: 1
10/15/2024: No comments at this time from Parks or Park Planning and Development. Thank you.
Department: PFA
Contact: Marcus Glasgow marcus.glasgow@poudre-fire.org 970-416-2869
Topic: General
Comment Number: 1
10/10/2024: INFORMATION:
PFA has no comments on the ODP. The future PDP submittal will have further requirements.
Department: Technical Services
Contact: Jeff County jcounty@fcgov.com 970-221-6588
Topic: General
Comment Number: 1
10/15/2024: INFORMATION:
We have no comments, but would like to see any future submittals.
Department: Outside Agencies
Contact: Melissa Buick <melissahbuick@gmail.com>
Topic: General
Comment Number: 1
10/15/2024: INFORMATION:
The Lake Canal ditch borders the properties to the north. The ditch easement
is 50 feet from the centerline of the ditch, is prescriptive in nature, must remain
unobstructed for access and maintenance, and remain free of debris during the construction phases.
Any encroachment or crossing of the ditch or ditch easement will require an
agreement with the Company. We encourage discussions early on in the
process for any modification or crossing of the ditch and or ditch easement and
any questions can be directed to my attention.
Department: Internal Services
Contact: Katy Hand khand@fcgov.com
Topic: Building Insp Plan Review
Comment Number: 1
10/7/2024: BUILDING PERMIT:
New structures shall comply with all applicable building codes, local
Page 8 of 8
amendments and energy codes at the time of permit submittal. Building codes
and structural design criteria can be found here: https://www.fcgov.com/building/codes.
A separate building permit is required for each new detached structure. This
includes flagpoles, fences over 6ft tall and any work that is not explicitly exempt from permit.
NOTICE: the 2025 building codes are planned to be adopted at some point next year (2025)
Response: Understood and will comply at time of future building permit requests.
Comment Number: 2
10/7/2024: BUILDING PERMIT:
At some point, please provide prior permit and certificate of occupancy
documents from the Larimer County Building Department for any existing
buildings being annexed into Fort Collins. (i.e. the current certificate of
occupancy, construction type, fire suppression type, occupant load, etc.). This
ensures that our team has the most current and correct information going
forward as it pertains to future alterations/remodels to the existing building/s.
Response: We are working with the property owner and the Larimer County Building
Department to track down this information.
Comment Number: 3
10/7/2024: BUILDING PERMIT:
It is recommended to consult with an architect early on as it relates to new
buildings. Specifically, regarding the size of the new building/s and placement
on the lot as it relates to building code feasibility topics of allowable area, and fire separation distance.
Response: Understood and will comply at time of future building permit requests.