HomeMy WebLinkAboutTHE MARK - FDP240013 - SUBMITTAL DOCUMENTS - ROUND 2 - Stormwater Management Plan STORMWATER MANAGEMENT PLAN THE MARK FORT COLLINS, COLORADO September 18, 2024 EPSGROUPINC.COM 970.221.4158 FORT COLLINS Home - EPS Group (epsgroupinc.com) Stormwater Management Plan September 18, 2024 Hamilton Reynolds LCD Acquisitions, LLC. 315 Oconee Street Athens, GA 30601 RE: Stormwater Management Plan The Mark To Whom It May Concern: EPS GROUP, Inc. is pleased to submit this Stormwater Management Plan for The Mark Apartments project. This report outlines Best Management Practices (BMPs) to be implemented with the proposed construction in order to minimize potential pollutants in stormwater discharges. We have prepared this report to accompany the Colorado Department of Public Health and Environment General Permit for Stormwater Discharge Associated with Construction Activities (aka, Stormwater Discharge Permit or SDP). The General Permit No. for this SDP is (to be filled-in by permittee) and the Certification No. for this SDP is (to be filled-in by permittee). The Permit Certification is Effective beginning (to be filled-in by permittee), and initial certification expires (to be filled-in by permittee). A copy of the issuance cover letter can be found in the Appendix D of this document (to be provided by permittee). Please note: this Stormwater Management plan (including the Site Maps) is not a static document. It is a dynamic device that should be kept current and logged as construction takes place. As such, this version was prepared to facilitate initial plan approvals and permitting, but does not necessarily reflect the final version, or the transitions throughout the construction process. As the site develops and changes, the Contractor is expected and encouraged to make changes to what is contained herein so that the SWMP works as effectively and efficiently as possible. It shall be the responsibility of the SWMP Administrator and/or the permit holder (or applicant thereof) to ensure the plan is properly maintained and followed. If you should have any questions or comments as you review this report, please feel free to contact us at your convenience. Sincerely, EPS GROUP, INC. Bree Vossdottir, CAD II Project Engineer Home - EPS Group (epsgroupinc.com) Home - EPS Group (epsgroupinc.com) Table 1 – Preliminary Permit and Construction Schedule Home - EPS Group (epsgroupinc.com) 1 | 13 Home - EPS Group (epsgroupinc.com) 2 | 13 • • • • Home - EPS Group (epsgroupinc.com) 3 | 13 • • • • • • • • • • Home - EPS Group (epsgroupinc.com) 4 | 13 Home - EPS Group (epsgroupinc.com) 5 | 13 Home - EPS Group (epsgroupinc.com) 6 | 13 Home - EPS Group (epsgroupinc.com) 7 | 13 Home - EPS Group (epsgroupinc.com) 8 | 13 • • • • Home - EPS Group (epsgroupinc.com) 9 | 13 TASK BEGINNING DATE ENDING DATE "BMP-PHASE OF DEVELOPMENT" Development Construction Permit Issued by City of Fort Collins February 2020 February 2020 I Overlot Grading (Demolition)February 2020 February 2020 I Utility Installation February 2020 March 2020 II Building Construction March 2020 November 2020 III Final Stabilization October 2020 November 2020 IV Home - EPS Group (epsgroupinc.com) 10 | 13 Home - EPS Group (epsgroupinc.com) 11 | 13 Home - EPS Group (epsgroupinc.com) 12 | 13 • • • • • • • • • • • • • Home - EPS Group (epsgroupinc.com) 13 | 13 • • • • • This Stormwater Management Plan (both the text and map) is not a static document. It is a dynamic device intended to be kept current and logged as construction takes place. It shall be the responsibility of the SWMP Administrator and/or the permit holder (or applicant thereof) to ensure the plan is properly maintained and followed. Diligent administration is critical, including processing the Notice to Proceed and noting on the Stormwater Management Plan the dates that various construction activities occur and respective BMPs are installed and/or removed. Home - EPS Group (epsgroupinc.com) 14 | 13 Home - EPS Group (epsgroupinc.com) 15 | 13 1. 2. 3. 4. 5. Home - EPS Group (epsgroupinc.com) EPSGROUPINC.COM | 970.221.4158 SWMP Report: Gregory Cove Subdivision FORT COLLINS | GREELEY | MESA | TUSCON | GOODYEAR | PHEONIX | FORT WORTH APPENDIX APPENDIX A SITE MAPS CF CF CF CF JOHNSON DRIVE SP R I N G C O U R T CF CF CF CF CF CF CF CF D ST ST ST ST ST ST ST FTN D PH PH PH PH PH PH PH D LOT 11 SPRING COURT SUBDIVISION OWNER(S): 2008-2010 SPRING COURT LLC LOT 10 SPRING COURT SUBDIVISION OWNER(S): DWYER FAMILY BUSINESS LLC LOT 9 SPRING COURT SUBDIVISION OWNER(S): DWYER FAMILY BUSINESS LLC ST ST ST ST ST ST ST ST ST ST D /////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / //// ///// // ////////////////// // ///// ///////////////// //// / / / / / / / / / / / / / / / /////////////////////////////////////////////////////////// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / /// /////// / / / / / / / / / / // / / / // / / // / / //////////// /// / // // / / / / / / / / / / / / / / / / / / ///////////////// / / / / / / / / / / / / / / / / ///////////////////////////// / / / / / / / / ///////////////// / //////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////// ////// // /////////// / / / / / / / / / / / / / / / / / / / /////////////////////////////////////////////////////////////// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / // / / / / // / /// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / /////// ///////////////////////////////////////////////////////// D ST ST ST ST ST ST ST FTN D PH PH PH PH PH PH PH D LOT 11 SPRING COURT SUBDIVISION OWNER(S): 2008-2010 SPRING COURT LLC LOT 10 SPRING COURT SUBDIVISION OWNER(S): DWYER FAMILY BUSINESS LLC LOT 9 SPRING COURT SUBDIVISION OWNER(S): DWYER FAMILY BUSINESS LLC ST ST ST ST ST ST ST ST ST ST D /////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / //// ///// // ////////////////// // ///// ///////////////// //// / / / / / / / / / / / / / / / /////////////////////////////////////////////////////////// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / /// /////// / / / / / / / / / / // / / / // / / // / / //////////// /// / // // / / / / / / / / / / / / / / / / / / ///////////////// / / / / / / / / / / / / / / / / ///////////////////////////// / / / / / / / / ///////////////// / //////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////////// ////// // /////////// / / / / / / / / / / / / / / / / / / / /////////////////////////////////////////////////////////////// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / // / / / / // / /// / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / /////// ///////////////////////////////////////////////////////// LOD LOD LOD LOD LOD LOD LOD LOD LOD VANVAN FD FD FD FDFD FD FD FD FD FD FDFD FDFD area reserved for gas meters area reserved for electric meters ar e a r e s e r v e d fo r e l e c t r i c m e t e r s ar e a r e s e r v e d fo r e l e c t r i c m e t e r s ar e a r e s e r v e d fo r e l e c t r i c m e t e r s ar e a r e s e r v e d f o r el e c t r i c m e t e r s ar e a r e s e r v e d f o r el e c t r i c m e t e r s area reserved for electric meters FD C VTC RS RS RS RS RS RS RS RS RS RS RSCF SF SF SF IP W1 W1 W1 W1 W1 W1 W1 W1 W1 W1 W1 W1 RS CWA ECB ECB ECB CF CF IP CF IP W1 RS SF SF W1 IP SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF SF PROTECT NEAREST DOWN STREAM INLETS SF SF SF SF DURING VERTICAL CONSTRUCTION WRAP END OF 18" RCP WITH SILT FENCE AND SECURE IN PLACE SAND FILTER (SAND FILTER MEDIA TO BE INSTALLED AFTER ALL VERTICAL CONSTRUCTION IS COMPLETE) W1 200 JOHNSON DRIVE FORT COLLINS, CO. 80525 SPRING CREEK FEMA FLOODWAY FEMA 100-YR HIGH RISK FLOODPLAIN C4.00 ER O S I O N C O N T R O L P L A N 14 LEGEND: NOTES: PROJECT BOUNDARY EXISTING STORM SEWER ST PROPOSED LOTLINE PROPOSED CURB & GUTTER NORTHNORTH ( IN FEET ) 0 1 INCH = 30 FEET 30 30 60 90 SF IP W2 CF VTC INLET PROTECTION W1 WATTLE SILT FENCE CHAINLINK FENCE WATTLE VEHICLE TRACKING PAD CF ECB EROSION CONTROL BLANKET RS ROCK SOCK W/ MARKER PROPOSED STORM SEWER 1.CONTRACTOR SHALL IMMEDIATELY STABILIZE ALL DISTURBED SLOPES BY CRIMP MULCHING OR SIMILAR METHODS (AS APPLICABLE). 2.TOTAL DISTURBED AREA = 2.63 ACRES 3.SWMP ADMINISTRATOR: Contact ________________________________ Company ________________________________ Address ________________________________ Phone ________________________________ 4.REMOVE SEDIMENT THAT IS TRACKED ONTO THE PUBLIC RIGHT OF WAY DAILY OR MORE FREQUENTLY ASS NEEDED. EXCESS SEDIMENT IN THE ROADWAY INDICATES THAT THE STABILIZED CONSTRUCTION ENTRANCE NEEDS MAINTENANCE. 5.CONTRACTOR TO PROVIDE VEHICLE TRACKING CONTROL FOR CONCRETE WASHOUT AREA IF ACCESS IS OFF PAVEMENT. 6.REMOVE ALL ACCUMULATED SEDIMENT AND DEBRIS FROM THE DANDY SACK, SURFACE AND VICINITY OF THE UNIT AFTER EACH STORM EVENT. IF USING OPTIONAL OIL ABSORBENTS, REMOVE AND REPLACE ABSORBENTS WHEN THEY NEAR SATURATION. 7.REFER TO THE "STORM WATER MANAGEMENT PLAN & EROSION CONTROL REPORT FOR JOHNSON DRIVE APARTMENTS BY EPS GROUP, INC. DATED 09/18/24 FOR ADDITIONAL INFORMATION. 8.PERMANENT VEGETATION SHALL COMPLY WITH THE APPROVED LANDSCAPE PLANS ASSOCIATED WITH THIS PROJECT. TABLE OF CONSTRUCTION SEQUENCE AND BMP APPLICATION Project: THE CLASSIC AT HARMONY PARK CONSTRUCTION PHASE MOBILIZATION DEMOLITION GRADING BEST MANAGEMENT PRACTICES (BMPS) STRUCTURAL "INSTALLATION" Silt Fence Barriers * Flow Barriers (Wattles) * Inlet Filter Bags * Vegetative Temporary Seeding Planting Mulching / Sealant Permanent Seeding Planting Sod Installation Rolled Products : Netting / Blankets / Mats Contour Furrows (Ripping / Disking) Rock Bags * UTILITIES INSTALLATION FLAT WORK INSTALLATION VERTICAL INSTALLATION LANDSCAPE DEMOBILIZATION Vehicle Tracking Pad * * All Temporary BMPs to be Removed once Construction is Complete Any prior inlets that could use protecting Any prior inlets that could use protecting Anytime the site will sit dormant longer than 30 Days Anytime the site will sit dormant longer than 30 Days Anytime the site will sit dormant longer than 30 Days Riprap 1.IT SHOULD BE NOTED THAT ANY EROSION CONTROL PLAN SERVES ONLY AS A GUIDELINE TO THE CONTRACTOR. STAGING AND/OR PHASING OF BEST MANAGEMENT PRACTICES (BMPs) IS EXPECTED. ADDITIONAL AND/OR DIFFERENT BMPs FROM THOSE ORIGINALLY DEPICTED MAY BE NECESSARY DURING CONSTRUCTION DUE TO CHANGING SITE CONDITIONS OR AS REQUIRED BY LOCAL AUTHORITIES. 2.THIS EROSION CONTROL PLAN IS SCHEMATIC IN NATURE. AS SUCH, GRAPHICAL SYMBOLS MAY NOT BE TO SCALE, NOR ARE THEY NECESSARILY SHOWN IN THEIR EXACT LOCATION. 3.THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL PERMITTING (CITY, STATE DISCHARGE PERMIT, ETC.) AND COMPLIANCE WITH GOVERNING AUTHORITIES. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR (OR PERMIT HOLDER) TO ENSURE EROSION CONTROL MEASURES ARE PROPERLY MAINTAINED AND FOLLOWED. 4.CONTRACTOR SHALL IMPLEMENT THE APPROPRIATE EROSION CONTROL MEASURES ACCORDING THE THE CONSTRUCTION SEQUENCING AND LEVEL OF SITE STABILIZATION. 5.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR ALL STORM DRAINS, SWALES, PONDS AND RAIN GARDENS UNTIL SITE IS FULLY STABILIZED. 6.CONTRACTOR SHALL IMPLEMENT APPROPRIATE INLET PROTECTION FOR DOWNSPOUT CONNECTIONS, TO THE STORM DRAIN SYSTEM, UNTIL CONNECTION IS ESTABLISHED WITH DOWNSPOUT. 7.INLET PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN WATTLES FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.) 8.CONTRACTOR IS RESPONSIBLE FOR STABILIZING ALL SLOPES, PARTICULARLY THOSE STEEPER THAN 6:1. CRIMP MULCHING, HYDRO MULCHING, EROSION MATS, TEMPORARY IRRIGATION, AND ADDITIONAL WATTLES OR SILT FENCING MAY BE NECESSARY TO ESTABLISH VEGETATIVE COVER AND STABILIZE THE SLOPE. 9.ADDITIONAL WATTLES, SILT FENCE, OR OTHER MEASURES, MAY BE NECESSARY TO INSURE THAT EACH BUILDING PAD IS STABILIZED THROUGHOUT CONSTRUCTION. AT NO TIME SHALL SEDIMENT BE ALLOWED TO CROSS THE PUBLIC SIDEWALKS. 10.CONTRACTOR SHALL IMPLEMENT APPROPRIATE PERIMETER PROTECTION FOR AREAS DIRECTING DRAINAGE OFFSITE. PERIMETER PROTECTION SHALL BE ADAPTED, AS NECESSARY, TO THE SURROUNDING SURFACE TYPE AND CONDITION (i.e., STAKE-DRIVEN SEDIMENT CONTROL LOGS OR SILT FENCE FOR BARE SOIL, SAND BAGS OR GRAVEL SOCKS FOR PAVEMENT, ETC.) 11.FUELING FACILITIES SHALL BE LOCATED AT LEAST ONE HUNDRED (100) FEET FROM NATURAL BODY OF WATER, WETLAND, NATURAL DRAINAGE WAY OR MANMADE DRAINAGE WAY. THE FUEL TANKS AND FUELING AREA MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW A FUEL SPILL TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. 12.CONSTRUCTION WASTE STORAGE (DUMPSTERS) AND PORTABLE SANITATION UNITS (CONSTRUCTION TOILETS) SHALL BE LOCATED AT LEAST FIFTY (50) FEET FROM ANY STORMWATER INLET, WETLAND, OR DRAINAGE WAY. SAID FACILITIES MUST BE SET IN A CONTAINMENT AREA THAT WILL NOT ALLOW POLLUTANTS TO DIRECTLY FLOW, SEEP, RUN OFF, OR BE WASHED INTO A BODY OF WATER, WETLAND OR DRAINAGE WAY. DUMPSTERS SHALL BE LOCATED ON FLAT, STABLE GROUND, AND CONSTRUCTION TOILETS SHALL BE STAKED DOWN. 13.THE CONTRACTOR AND ALL SUBCONTRACTORS WILL COOPERATE WITH THE CITY'S CONSTRUCTION INSPECTORS BY CEASING OPERATIONS WHEN WINDS ARE OF SUFFICIENT VELOCITY TO CREATE BLOWING DUST WHICH, IN THE INSPECTOR'S OPINION, IS HAZARDOUS TO THE PUBLIC HEALTH AND WELFARE. 14.WHERE SEASONAL CONSTRAINTS (E.G., DURING SUMMER AND WINTER MONTHS) INHIBIT PERMANENT SEEDING OPERATIONS, DISTURBED AREAS WILL BE TREATED WITH MULCH AND MULCH TACKIFIER OR OTHER MATERIALS APPROVED BY EROSION CONTROL STAFF TO PREVENT EROSION. 15.SEE LANDSCAPE PLANS FOR ADDITIONAL INFORMATION ON PLANTING, REVEGETATION, HARDSCAPE AND OTHER PERMANENT SITE STABILIZATION METHODS. 16.ALL ROOF DRAIN SYSTEM INLETS SHAL BE PLUGGED UNTIL CONNECTED TO BUILDINGS. EROSION CONTROL NOTES: CW CONCRETE WASHOUT AREA RR RIPRAP SF Sheet TH E M A R K Th e s e d r a w i n g s a r e in s t r u m e n t s o f s e r v i c e pr o v i d e d b y E P S G r o u p , In c . a n d a r e n o t t o b e u s e d fo r a n y t y p e o f c o n s t r u c t i o n un l e s s s i g n e d a n d s e a l e d by a P r o f e s s i o n a l E n g i n e e r in t h e e m p l o y o f E P S Gr o u p , I n c . NO T F O R C O N S T R U C T I O N RE V I E W S E T of 23 FO R T C O L L I N S | G R E E L E Y | M E S A | G O O D Y E A R | T U C S O N | N O R T H P H O E N I X | F O R T W O R T H no r t h e r n e n g i n e e r i n g . c o m 97 0 . 2 2 1 . 4 1 5 8 CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE, OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what'sbelow. before you dig.Call R Home - EPS Group (epsgroupinc.com) EPSGROUPINC.COM | 970.221.4158 SWMP Report: Gregory Cove Subdivision FORT COLLINS | GREELEY | MESA | TUSCON | GOODYEAR | PHEONIX | FORT WORTH APPENDIX APPENDIX B EROSION CONTROL DETAILS C4.01 ER O S I O N C O N T R O L D E T A I L S 15 CHAIN LINK FENCE006 CF 003 CURB INLET PROTECTION 007 WATTLE INSTALLATION FLOW 3'-4' ADJACENT ROLLS SHALL TIGHTLY ABUT W1 NOTES: INSTALLATION: WHEN INSTALLING RUNNING LENGTHS OF WATTLES, BUTT THE SECOND WATTLE TIGHTLY AGAINST THE FIRST, DO NOT OVERLAP THE ENDS. STAKE THE WATTLES AT EACH END AND FOUR FOOT ON CENTER. FOR EXAMPLE: A 25 FOOT WATTLE USES 6 STAKES A 20 FOOT WATTLE USES 5 STAKES A 12 FOOT WATTLE USES 4 STAKES STAKES SHOULD BE DRIVEN THROUGH THE MIDDLE OF THE WATTLE. LEAVING 2 - 3 INCHES OF THE STAKE PROTRUDING ABOVE THE WATTLE. A HEAVY SEDIMENT LOAD WILL TEND TO PICK THE WATTLE UP AND COULD PULL IT OFF THE STAKES IF THEY ARE DRIVEN DOWN TOO LOW. IT MAY BE NECESSARY TO MAKE A HOLE IN THE WATTLE WITH A PICK END OF YOUR MADDOX IN ORDER TO GET THE STAKE THROUGH THE STRAW. WHEN STRAW WATTLES ARE USED FOR FLAT GROUND APPLICATIONS, DRIVE THE STAKES STRAIGHT DOWN; WHEN INSTALLING WATTLES ON SLOPES, DRIVE THE STAKES PERPENDICULAR TO THE SLOPE. DRIVE THE FIRST END STAKE OF THE SECOND WATTLE AT AN ANGLE TOWARD THE FIRST WATTLE IN ORDER TO HELP ABUT THEM TIGHTLY TOGETHER. IF YOU HAVE DIFFICULTY DRIVING THE STAKE INTO EXTREMELY HARD OR ROCKY SLOPES, A PILOT BAR MAY BE NEEDED TO BEGIN THE STAKE HOLE. 1"x 1" WOOD STAKES 18"-24" BAILING WIRE OR NYLON ROPE WATTLE "A"WATTLE "B" 1'2' TYP. 1'1' W2 NOTES: INSTALLATION: STAKES SHOULD BE DRIVEN ACROSS FROM EACH OTHER AND ON EACH SIDE OF THE WATTLE. LEAVING 4"-6" OF STAKE PROTRUDING ABOVE THE WATTLE. BAILING WIRE OR NYLON ROPE SHOULD BE TIED TO THE STAKES ACROSS THE WATTLE. STAKES SHOULD THEN BE DRIVEN UNTIL THE BAILING WIRE OR NYLON ROPE IS SUFFICIENTLY SNUG TO THE WATTLE. WHEN INSTALLING RUNNING LENGTHS OF WATTLES, TO PREVENT SHIFTING, BUTT THE SECOND WATTLE TIGHTLY AGAINST THE FIRST. DO NOT OVERLAP THE ENDS. STAKES SHOULD BE DRIVEN 1 FT. FROM END, ACROSS FROM AND ON EACH SIDE OF WATTLE LEAVING 4"-6" OF STAKE PROTRUDING ABOVE THE WATTLE. BAILING WIRE OR NYLON ROPE SHOULD BE TIED TO STAKES IN AN HOUR GLASS FORMATION (FRONT TO BACK OF WATTLE "A", ACROSS TO FRONT OF WATTLE "B", ACROSS TO BACK AND BACK TO FRONT OF WATTLE "A"). STAKES SHOULD THEN BE DRIVEN IN UNTIL BAILING WIRE OR NYLON ROPE IS SUFFICIENTLY SNUG TO THE WATTLE. W1 & W2 INSTALLATION NOTES: 1. THE LOCATION AND LENGTH OF WATTLE IS DEPENDENT ON THE CONDITIONS OF EACH SITE. 2. WATTLES SHALL BE INSTALLED PRIOR TO ANY LAND-DISTURBING ACTIVITIES. 3. WATTLES SHALL CONSIST OF STRAW, COMPOST, EXCELSIOR, OR COCONUT FIBER. 4. NOT FOR USE IN CONCENTRATED FLOW AREAS. 5. THE WATTLES SHALL BE TRENCHED INTO THE GROUND A MINIMUM OF TWO (2) INCHES. 6. WATTLES SHALL BE INSTALLED PER MANUFACTURERS SPECIFICATIONS. 7. ON SLOPES, WATTLES SHOULD BE INSTALLED ON CONTOUR WITH A SLIGHT DOWNWARD ANGLE AT THE END OF THE ROW IN ORDER TO PREVENT PONDING AT THE MID SECTION. 8. RUNNING LENGTHS OF WATTLES SHOULD BE ABUTTED FIRMLY TO ENSURE NO LEAKAGE AT THE ABUTMENTS. 9. SPACING - DOWNSLOPE: VERTICAL SPACING FOR SLOPE INSTALLATIONS SHOULD BE DETERMINED BY SITE CONDITIONS. SLOPE GRADIENT AND SOIL TYPE ARE THE MAIN FACTORS. A GOOD RULE OF THUMB IS: 1:1 SLOPES = 10 FEET APART 2:1 SLOPES = 20 FEET APART 3:1 SLOPES = 30 FEET APART 4:1 SLOPES = 40 FEET APART, ETC. HOWEVER, ADJUSTMENTS MAY HAVE TO BE MADE FOR THE SOIL TYPE: FOR SOFT, LOAMY SOILS - ADJUST THE ROWS CLOSER TOGETHER; FOR HARD, ROCKY SOILS - ADJUST THE ROWS FURTHER APART. A SECONDARY WATTLE PLACED BEHIND THE ABUTMENT OF TWO WATTLES IS ENCOURAGED ON STEEP SLOPES OR WHERE JOINTS HAVE FAILED IN THE PAST. 10. STAKING: THE CITY RECOMMENDS USING WOOD STAKES TO SECURE THE WATTLES. 1/2" TO 5/8" REBAR IS ALSO ACCEPTABLE. BE SURE TO USE A STAKE THAT IS LONG ENOUGH TO PROTRUDE SEVERAL INCHES ABOVE THE WATTLE: 18" IS A GOOD LENGTH FOR HARD, ROCKY SOIL. FOR SOFT LOAMY SOIL USE A 24" STAKE. 4"-6" ABOVE WATTLE AFTER BAILING WIRE OR NYLON ROPE IS ATTACHED. STAKES NEED TO BE TAMPED UNTIL WIRE/ROPE IS SNUG WITH WATTLE. 1"x 1" WOOD STAKES 18"-24" ENDS OF ADJACENT WATTLES SHALL BE TIGHTLY ABUTTED TO PREVENT SEDIMENT BYPASS W2 NOTE: ONLY WATTLES MADE WITH COCONUT FIBERS SHALL BE USED WHEN INSTALLATION COMES IN CONTACT WITH A WATER BODY. 002 SILT FENCE SF SF ROCK SOCK SECTION ROCK SOCK PLAN ROCK SOCK JOINTING GRADATION TABLE SIEVE SIZE MASS PERCENT PASSING SQUARE MESH SIEVES NO. 4 2"100 1-1/2"90-100 1"20-55 3/4"0-15 3/8"0-5 MATCHES SPECIFICATIONS FOR NO. 4 COARSE AGGREGATE FOR CONCRETE PER AASHTO M43. ALL ROCK SHALL BE FRACTURED FACE, ALL SIDES RS VTC 004 VEHICLE CONTROL TRACKING PAD 001 CONCRETE WASHOUT AREA ROCK SOCK DETAIL005 CW IP RP GROUTED RIPRAP008 AT PIPE OUTLET AREAS OF STREAMS AND DRAINAGE CHANNELS - DETAIL A IN DIVERSION DITCH OR SMALL DITCH DRAINAGE WAY - DETAIL B OUTSIDE OF STREAMS AND DRAINAGE CHANNELS - DETAIL C ANCHOR DETAILS PERIMETER ANCHOR TRENCH JOINT ANCHOR TRENCH INTERMEDIATE ANCHOR TRENCH OVERLAPPING JOINT WOOD STAKE DETAIL MINIMUM THICKNESS 1" USE 2x4 MATERIAL FOR STAKES JOINT ANCHOR TRENCH, TYP. PERIMETER ANCHOR TRENCH, TYP. TOP OF CHANNEL BANK TYPE OF BLANKET AS INDICATED IN PLAN VIEW, IN ALL DISTURBED AREAS OF STREAMS AND DRAINAGE CHANNELS TO DEPTH "D" ABOVE CHANNEL INVERT. BLANKET SHALL GENERALLY BE ORIENTED PARALLEL TO FLOW DIRECTION. STAKING PATTERN SHALL MATCH BLANKET TYPE. UNDISTURBED SOIL TYPE OF BLANKET, INDICATED IN PLAN VIEW PER MANUFACTURER SPEC. OR TYPE 2 OR 3 STAKING (MATCH SPECIFIED BLANKET TYPE) SEE THE STAKING PATTERNS DETAIL ON NEXT SHEET PERIMETER ANCHOR TRENCH, TYP. JOINT ANCHOR TRENCH, TYP. COMPACTED SUBGRADE 1 >3 THE BLANKET SHALL BE EXTENDED TO THE TOP OF CHANNEL "D " 6 " TO P S O I L "M" OVERLAPPING JOINT, SEE DETAIL ON THIS SHEET STAGGER OVERLAPS PERIMETER ANCHOR TRENCH SEE DETAIL ON THIS SHEET PER MANUFACTURER SPEC. OR TYPE 1 STAKING SEE THE STAKING PATTERN DETAIL ON NEXT SHEET BLANKET SHALL BE 100% STRAW MIN. DIVERSION DITCH TYPICALLY AT TOP OF SLOPE 6 " TO P S O I L 6" MIN. (TYP.) 3" MIN. (TYP.) SINGLE EDGE EROSION CONTROL BLANKET (TYP.) COMPACTED BACKFILL (TYP.) STAKE (TYP.) TWO EDGES OF TWO ADJACENT ROLLS LOOP FROM MIDDLE OF ROLL FLOW 6" 3" MIN. 1 2 " MI N . STAKING PATTERNS SHALL BE IN ACCORDANCE WITH MANUFACTURER'S SPECIFICATION. IF NO MANUFACTURER'S SPECIFICATION IS AVAILABLE USE THE ACCEPTABLE STAKING PATTERN (AS SHOWN ABOVE) PERIMETER ANCHOR TRENCH OR JOINT ANCHOR TRENCH, TYP. STRAW-COCONUT COCONUT OR EXCELSIOR STRAW ROLL WIDTH "W" (TYP.) 6' 3'1/2 "W" 1/2 "W" 1/2 "W" 1/2 "W" 1/2 "W" 4' 3' 2' EROSION CONTROL BLANKET TYPE TYPE STRAW* STRAW-COCONUT EXCELSIOR COCONUT CONTENT - 30% MIN. - STRAW CONTENT 100% - NETTING MIN. DOUBLE/NATURAL 100% - - EXCELSIOR CONTENT COCONUT --100% * FOR OUTSIDE OF STREAMS AND DRAINAGE CHANNELS DOUBLE/NATURAL DOUBLE/NATURAL DOUBLE/NATURAL MAX.70% EROSION CONTROL BLANKET009 Storm Line/Culvert Label Pipe Diameter (in) No. of Barrels Riprap Type Spec Length of Riprap (ft) Spec Width of Riprap (ft) 2*d50, Depth of Riprap (ft) Storm A 18 1 Type M 10.00 30.60 2.0 REFER TO SHEET ##### FOR EXACT SIZING DIMENSIONS Sheet TH E M A R K Th e s e d r a w i n g s a r e in s t r u m e n t s o f s e r v i c e pr o v i d e d b y E P S G r o u p , In c . a n d a r e n o t t o b e u s e d fo r a n y t y p e o f c o n s t r u c t i o n un l e s s s i g n e d a n d s e a l e d by a P r o f e s s i o n a l E n g i n e e r in t h e e m p l o y o f E P S Gr o u p , I n c . NO T F O R C O N S T R U C T I O N RE V I E W S E T of 23 FO R T C O L L I N S | G R E E L E Y | M E S A | G O O D Y E A R | T U C S O N | N O R T H P H O E N I X | F O R T W O R T H no r t h e r n e n g i n e e r i n g . c o m 97 0 . 2 2 1 . 4 1 5 8 CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE, OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what'sbelow. before you dig.Call R C4.02 ER O S I O N C O N T R O L N O T E S 16 Sheet TH E M A R K Th e s e d r a w i n g s a r e in s t r u m e n t s o f s e r v i c e pr o v i d e d b y E P S G r o u p , In c . a n d a r e n o t t o b e u s e d fo r a n y t y p e o f c o n s t r u c t i o n un l e s s s i g n e d a n d s e a l e d by a P r o f e s s i o n a l E n g i n e e r in t h e e m p l o y o f E P S Gr o u p , I n c . NO T F O R C O N S T R U C T I O N RE V I E W S E T of 23 FO R T C O L L I N S | G R E E L E Y | M E S A | G O O D Y E A R | T U C S O N | N O R T H P H O E N I X | F O R T W O R T H no r t h e r n e n g i n e e r i n g . c o m 97 0 . 2 2 1 . 4 1 5 8 CALL 2 BUSINESS DAYS IN ADVANCE BEFORE YOU DIG, GRADE, OR EXCAVATE FOR THE MARKING OF UNDERGROUND MEMBER UTILITIES. CALL UTILITY NOTIFICATION CENTER OF COLORADO Know what'sbelow. before you dig.Call R CONSTRUCTION NOTES A. Erosion Control Notes 1.The Property Owner, Owner’s Representative, Developer, Design Engineer, General Contractor, Sub-contractors, or similar title for the developing entity (here after referred to as the Developer) has provided these Erosion Control Materials in accordance with Erosion Control Criteria set forth in the Manual as an attempt to identify erosion, sediment, and other potential pollutant sources associated with these Construction Activities and preventing those pollutants from leaving the project site as an illicit discharge. Full City requirements and are outlined and clarified in the Manual under Chapter 4: Construction Control Measures and should be used to identify and define what is needed on a project. 2.The Developer shall make themselves thoroughly familiar with the provisions and the content of the specifications laid out in the Manual, the Development Agreement, the Erosion Control Materials compiled for this project, and the following notes as all these materials are applicable to this project. 3.The Developer shall implement and maintain Control Measures for all potential pollutants from the start of land disturbing activities until final stabilization of the construction site. 4.The City Erosion Control Inspector shall be notified at least twenty-four (24) hours prior to the desired start of any construction activities on this site to allow adequate time for on-site confirmation (initial inspection which can take up to two business days after receiving the request) that the site is in fact protected from sediment and pollutants discharges off site. Please contact erosion@fcgov.com early to schedule those Initial Erosion Control Inspections well in advance so that demolition, clearing, grubbing, tree removal, and scraping may begin without delay. Failure to receive an on-site confirmation before construction activities commence is an automatic “Notice of Violation” and can result in further enforcement actions. 5.The Developer shall proactively provide all appropriate Control Measures to prevent damage to adjacent downstream and leeward properties. This includes but is not limited to: trees, shrubs, lawns, walks, pavements, roadways, structures, creeks, wetlands, streams, rivers, and utilities that are not designed for removal, relocation, or replacement in the course of construction. 6.At all times the Developer shall be responsible to ensure adequate Control Measures are designed, selected, installed, maintain, repaired, replaced, and ultimately removed in order to prevent and control erosion suspension, sediment transportation, and pollutant discharge as a result of construction activities associated with this project. 7.All applicable Control Measures based upon the sequencing and/or phasing of the project shall be installed prior to those construction activities commencing. 8.As dynamic conditions (due to the nature, timing, sequence, and phasing of construction) in the field may warrant Control Measures in addition, or different, to what is shown on these plans, the Developer shall at all times be responsible to implement the Control Measures that are most effective with the current state and progress of construction. The Developer shall implement whatever measures are determined necessary, and/or as directed by the City Erosion Control Inspector. The Developer shall insure that all Erosion Control Plans (Maps) or SWMP documents are updated to reflect the current site conditions, with updates being initialed and dated. These site inspections and site condition updates shall be made available upon request by the City. 9.All listings, provisions, materials, procedures, activities, site work and the like articulated in this or other written site-specific documents (Including but not limited to the erosion control reports, development agreements, landscape, and drainage materials) shall meet or exceed the most restrictive language for City, County, State, and Federal regulations with regards to erosion, sediment, pollutant, and other pollution source Control Measures. The Developer shall be responsible to comply with all of these aforementioned laws and regulations. 10.The Developer shall ensure that all appropriate permits (CDPS General Permit Stormwater Discharges Associated with Construction Activity, Dewatering, Clean Water Act, Army Corps of Engineers’ 404 Wetlands Mitigation Permit, etc.) have been attained prior to the relevant activity has begun. These permits or copies shall be made available upon request by the City. 11.The Developer shall furnish all conveniences and assistances to aid the Erosion Control Inspectors of materials, workmanship, records, and self-inspections, etc. of the Control Measures involved in the construction activities. 12.The Developer shall request clarification of all apparent site construction issues that may arise due to inconsistencies in construction plans for the site or site conditions around the selected Control Measures by contacting the Erosion Control Inspector. The Erosion Control Inspector will not be responsible for any explanations, interpretations, or supplementary data provided by others. 13.All Control Measures shall be installed in accordance with the Manual. 14.The City reserves the right to require additional Control Measures as site conditions warrant, to the extent authorized by relevant legal authority. 15.As with any construction standards, occasions may arise where the minimum erosion control standards are either inappropriate or cannot be justified. In these cases, a variance to these standards may be applied for pursuant to the terms, conditions, and procedures of the Manual. 16.Inspection. The contractor shall inspect site pollutant sources and implement Control Measures at a minimum of once every two weeks during construction and within 24 hours following a precipitation event. Documentation of each inspection shall be recorded and retained by the contractor. 17.All temporary Control Measures shall be cleaned, repaired, or reconstructed as necessary in order to assure continual performance of their intended function. All retained sediments, particularly those on paved roadway surfaces, shall be removed and disposed of in a manner and location so as not to cause their release into any drainage way. 18.Any Control Measure may be substituted for another standard Control Measure so long as that Control Measure is equal to, or of greater protection than the original Control Measure that was to be used in that location. (ex. silt fence, for wattles, or for compact berms) Wattle alone on commercial construction sites have shown to be an ineffective substitute for silt fence or compact berms unless it is accompanied by a construction fence to prevent vehicle traffic. 19.Any implementation or replacement of existing Control Measures for a non-standard control, or alternative Control Measure, shall require the review and acceptance by the City erosion control staff before the measure will be allowed to be used on this project. These Control Measures’ details shall be submitted, reviewed and accepted to be in accordance with the Erosion Control Criteria based upon the functionality and effectiveness in accordance with sound engineering and hydrological practices. Land disturbance, Stockpiles, and Storage of Soils 20.There shall be no earth-disturbing activity outside the limits designated on the accepted plans. Off road staging areas or stockpiles must be preapproved by the City. Disturbances beyond these limits will be restored to original condition. 21.Pre-disturbance vegetation shall be identified, protected, and retained wherever possible. Removal or disturbance of existing vegetation shall be limited to the area required for immediate construction operations, and for the shortest practical period of time. This should include sequencing and phasing construction activities in a way so that the soil is not exposed for long periods of time by schedule or limit grading to small areas. This should also include when practical advancing the schedule on stabilization activities such that landscaping takes place shortly if not immediately after grading has occurred. Vegetation efforts shall start as soon as possible to return the site to a stabilized condition. Sensitive areas should avoid clearing and grading activities as much possible. 22.All exposed soils or disturbed areas are considered a potential pollutant and shall have Control Measures implemented on the site to prevent materials from leaving the site. 23.All soils exposed during land disturbing activity (stripping, grading, utility installations, stockpiling, filling, etc.) shall be kept in a roughened condition at all times by equipment tracking, scarifying or disking the surface on a contour with a 2 to 4 inch minimum variation in soil surface until mulch, vegetation, and/or other permanent erosion control is installed. 24.No soil stockpile shall exceed ten (10) feet in height. All soil stockpiles shall be protected from sediment transport through the use of surface roughening, watering, and down gradient perimeter controls. All soil stockpiles shall be protected from sediment transport by wind in accordance with Municipal Code §12-150. All stockpiles shall be flattened to meet grade or removed from site as soon as practical, and no later than the completion of construction activities or abandonment of the project. All off-site stockpile storage locations in City limitsshall have a stockpile permit from the City Engineering Department prior to using the area to store material. If frequent access from hardscape to the stockpile is needed a structural tracking Control Measure shall be implemented. 25.All required Control Measures shall be installed prior to any land disturbing activity (stockpiling, stripping, grading, etc.). All of the required erosion Control Measures must be installed at the appropriate time in the construction sequence as indicated in the approved project schedule, construction plans, and erosion control report. 26.All inlets, curb-cuts, culverts, and other storm sewer infrastructure which could be potentially impacted by construction activities shall be protected with Control Measures. Material accumulated from this Control Measure shall be promptly removed and in cases where the protection has failed, the pipes shall be thoroughly cleaned out. 27.All streams, stream corridors, buffers, woodlands, wetlands, or other sensitive areas shall be protected from impact by any construction activity through the use of Control Measures. 28.All exposed dirt shall have perimeter control. Any perimeter controls that drain off or has the ability to be tracked onto the nearby hardscape shall have some form of effective sediment control as the, or as part of the, perimeter control. 29.All exposed slopes should be protected. All exposed steep slopes (Steeper than 3:1 H:V) shall be protected from erosion and sediment transport through use of Control Measures. 30.No soils shall remain exposed by land disturbing activity for more than thirty (30) days after activity has ceased before required temporary seeding or permanent erosion control (e.g. seed/mulch, landscaping, etc.) is installed. This is not just limited to projects that are abandoned; this includes any project that is temporarily halted and no immediate activity is to resume within the next thirty (30) days, unless otherwise approved by the City Erosion Control Inspector. During a season when seeding does not produce vegetative cover, another temporary erosion control shall be implemented with or until temporary seeding or permanent erosion control can be performed. 31.All individual lots shall have effective sediment controls located on the street side and any down gradient side. Typically most lots drain to the front yet on those cases where houses are along a pond or drainage swale have the lot drain in a different direction than the street, those individual lots will need protection on that down gradient side to prevent sediment from leaving the lot. See the Individual Lot Details for further clarification. Vehicle Tracking 32.At all points where vehicles exit or leave the exposed dirt area on to a hardscape or semi hardscape (concrete, asphalt, road base, etc.) shall have installed at least one structural tracking Control Measure to prevent vehicle tracking. All areas not protected by an adequate perimeter control shall be considered a point where vehicles exit the site. Access points should be limited to as few entrances as possible (All perimeter areas shall be protected from tracking activities). 33.In all areas that the structural tracking Control Measures fail to prevent vehicle tracking, collection and proper disposal of that material is required. All inlets located near access points and affected by tracking activities shall be prevented from the introduction of sediment into the drainage system. 34.34) City Municipal Code §20-62, among other things, prohibits the tracking, dropping, or depositing of soils or any other material onto city streets by or from any source. City Municipal Code, §26-498, among other things, prohibits the discharge of pollutants on public or private property if there is a significant potential for migration of such pollutant. Therefore, all tracked or deposited materials (intentional or inadvertent) are not permitted to remain on the street or gutter and shall be removed and legally disposed of by the Developer in a timely and immediate manner. Dirt ramps installed in the curb-lines are not exempt to these sections of code and shall not be permitted in the street right of way (public or private). 35.If repeated deposit of material occurs on a site, additional structural tracking controls may be required of the Developer by the City Erosion Control Inspector. Loading and Unloading Operations 36.The Developer shall apply Control Measure to limit traffic (site worker or public) impacts and proactively locate material delivered to the site in close proximity to the work area or immediately incorporated in the construction to limit operational impacts to disturbed areas, vehicle tracking, and sediment deposition that could impact water quality. Outdoor Storage or Construction Site Materials, Building Materials, Fertilizers, and Chemicals 37.Any materials of a non-polluting nature (steel, rock, brick, lumber, etc.) shall be inspected for any residue coming off the material during routine inspection and will generally be located where practical at least fifty (50) feet from any permanent or interim drainage ways. 38.38) Any high environmental impact pollutant materials that have a high likelihood to result in discharge when in contact with stormwater (lubricants, fuels, paints, solvents, detergents, fertilizers, chemical sprays, bags of cement mix, etc.) should not be kept on site where practical. When not practical, they should be stored inside (vehicle, trailer, connex, building, etc.) and out of contact with stormwater or stormwater runoff. Where not available, they shall be stored outside in a raised (high spots or on pallets), covered (plastic or tarped), and sealed (leak proof container) in secondary containment location. The secondary containment or other Control Measure shall be adequately sized, located, where practical, at least fifty (50) feet from any permanent or interim stormwater structures or drainage ways and shall be monitored as part of the routine inspections. Vehicle and equipment maintenance and fueling 39.Parking, refueling, and maintenance of vehicles and equipment should be limited in one area of the site to minimize possible spills and fuel storage areas. This area shall be located, where practical, at least fifty (50) feet from any permanent or interim stormwater structures or drainage ways and shall be monitored as part of the routine inspections. All areas shall keep spill kits and supplies close. Significant Dust or Particulate generating Process 40.The property must be actively preventing the emission of fugitive dust at all times during construction and vegetation activities. All land disturbing activities that result in fugitive dust shall be in accordance with Municipal Code §12-150 to reduce the impacts to adjacent properties and community health. All required practices shall be implemented and additional ones shall be followed. These practices include watering the sites and discontinuing construction activities until the wind subsides as determined by any City Inspectors. Concrete truck / equipment washing, including the concrete truck chute and associated fixtures and equipment 41.All concrete and equipment washing shall use structural Control Measures appropriate to the volume of wash and frequency of use. These Control Measures shall be located, where practical, at least fifty (50) feet from any permanent or interim stormwater structures or drainage ways and shall be monitored as part of the routine inspections. These areas shall be clearly identified and protected from any wash from leaving the Control Measure. If frequent access from hardscape to the Control Measure is to occur, a structural tracking Control Measure shall be implemented. These Control Measures shall be frequently cleaned out. 42.The Developer is responsible for ensuring washing activity is taking place at the appropriate Control Measure and site workers are not washing or dumping wash water on to the dirt or other uncontrolled locations. Dedicated Asphalt and concrete batch plants 43.Dedicated asphalt and concrete batch plants are not acceptable on construction sites within the City of Fort Collins without an expressed written request and plan to reduce pollutants associated with that type of activity and approval by the City of Fort Collins specifically the Erosion Control Inspector. The Developer shall inform the erosion control inspection staff of any dedicated asphalt, or concrete batch plants that is to be used on site. Concrete Saw Cutting Materials 44.Saw cutting material shall be in accordance with Municipal Code §12-150 for air emissions and all water applications to the saw cutting shall prevent material from leaving the immediate site and collected. These cutting locations, once dried, shall be swept and scraped of all material and shall have proper and legal disposal. Waste Materials Storage and Sanitary Facilities 45.Trash, debris, material salvage, and/or recycling areas shall be, where practical, at least fifty (50) feet from any permanent or interim stormwater structures or drainage ways and shall be monitored as part of the routine inspections. These facilities should be located out of the wind and covered as able. Where not able to cover, locating said areas on the side of other structures to reduce exposure to winds, and follow maximum loading guidelines as marked on the container. The Developer is required to practice good housekeeping to keep the construction site free of litter, construction debris, and leaking containers. 46.Sanitary facilities shall be prevented from tipping through the use of anchoring to the ground or lashing to a stabilized structure. These facilities shall also be located as far as practical from an inlet, curb cut, drainage swale or other drainage conveyances to prevent material transport from leaving the local area. This consists of the facility being located, where practical, at least fifty (50) feet from any permanent or interim drainage ways. Other Site Operations and Potential Spill Areas 47.Spills: For those minor spills that; are less than the State’s reportable quantity for spills, stay within the permitted area, and in no way threaten any stormwater conveyance, notify the City of Fort Collins Utilities by email at erosion@fcgov.com or phone (970) 817-4770. For any significant, major, or hazardous spills, notify the City of Fort Collins Utilities by phone only after Emergency Response (911) has been notified and is on route, County Health Department (LCDHE) has been notified through Larimer County Sheriff Dispatch (970) 416-1985, and the State Spill Hotline Incident Reporting have been contacted 1-877-518-5608. Written documentation shall be provided to the City within 5 days of the event. All spills shall be cleaned up immediately. 48.Selection of “plastic welded” erosion control blankets shall not be used in areas that wildlife, such as snakes, are likely to be located as these have proven to cause entrapment issues. Final stabilization and project completion 49.Any stormwater facilities used as a temporary Control Measure will be restored and storm sewer lines will be cleaned upon completion of the project and before turning the maintenance over to the Owner, Homeowners Association (HOA), or other party responsible for long term maintenance of those facility. 50.50) All final stabilization specifications shall be done in accordance with the Manual, Chapter 4: Construction Control Measures. 51.All disturbed areas designed to be vegetated shall be amended, seeded & mulched, or landscaped as specified in the landscape plans within 14 working days of final grading. 52.Soil in all vegetated (landscaped or seeded) areas, including parkways and medians shall comply with all requirements set forth in Sections 12-130 through 12-132 of the City Municipal Code, as well as Section 3.8.21 for the City Land Use Code. 53.All seeding shall refer to landscaping plans for species mixture and application rates and depths requirements. 54.All seed shall be drilled where practical to a depth based upon the seed type. Broadcast seeding shall be applied at double the rate as prescribed for drill seeding and shall be lightly hand raked after application. Hydroseeding may be substituted for drill seeding on slopes steeper than 3(H):1(V) or on other areas not practical to drill seed and crimp and mulch. All hydroseeding must be conducted as two separate processes of seeding and tackification. 55.All seeded areas must be mulched within twenty-four (24) after planting. All mulch shall be mechanically crimped and or adequately applied tackifier. The use of crimped mulch or tackifier may require multiple re-applications if not properly installed or have weathered or degraded before vegetation has been established. Areas of embankments having slopes greater than or equal to 3H:1V shall be stabilized with an erosion mat or approved equal to ensure seed will be able to germinate on the steep slopes. During a season when seeding does not produce vegetative cover, another temporary erosion control shall be implemented along with, or until, temporary seeding or permanent erosion control can be performed. 56.The Developer shall warranty and maintain all vegetative measures for two growing seasons after installation or until seventy percent (70%) vegetative cover has been established, whichever is longer and meets all the Criteria outlined in the Fort Collins Stormwater Criteria Manual Chapter 4: Construction Control Measures. 57.The Developer shall maintain, monitor, repair, and replace any and all applicable Control Measures until final stabilization has been obtained. All Control Measures must remain until such time as all upstream contributing pollutant sources have been vegetated or removed from the site. When any Control Measure is removed, the Developer shall be responsible for the cleanup and removal of all sediment and debris from that Control Measure. At the point at which the site has been deemed stabilized and verified by City Erosion Control Inspector, all temporary Control Measures can then be fully removed. All measures shall be removed within 30 days after final stabilization is achieved. 58.The responsible party shall maintain and keep current all payments or related forms of security for the Erosion Control Escrow until 1) stabilization has been reached and 2) all Control Measures and/or BMPs have sediment materials collected and the Control Measure removed from the site. At that time the site will be considered completed and any remaining Erosion Control Escrow shall be returned to the appropriate parties. 59.For additional information see separate Stormwater Management Plan / Erosion Control Report for THE MARK. B.Street Improvement Notes 1.All street construction is subject to the General Notes on the cover sheet of these plans as well as the Street Improvements Notes listed here. 2.A paving section design, signed and stamped by a Colorado licensed Engineer, must be submitted to the City of Fort Collins Engineer for approval, prior to any street construction activity, (full depth asphalt sections are not permitted at a depth greater than 8 inches of asphalt). The job mix shall be submitted for approval prior to placement of any asphalt. 3.Where proposed paving adjoins existing asphalt, the existing asphalt shall be saw cut, a minimum distance of 12 inches from the existing edge, to create a clean construction joint. The Developer shall be required to remove existing pavement to a distance where a clean construction joint can be made. Wheel cuts shall not be allowed unless approved by the City of Fort Collins Engineer in Fort Collins. 4.Street subgrades shall be scarified the top 12 inches and re-compacted prior to subbase installation. No base material shall be laid until the subgrade has been inspected and approved by the City of Fort Collins Engineer. 5.Valve boxes and manholes are to be brought up to grade at the time of pavement placement or overlay. Valve box adjusting rings are not allowed. 6.When an existing asphalt street must be cut, the street must be restored to a condition equal to or better than its original condition. The existing street condition shall be documented by the Inspector before any cuts are made. Cutting and patching shall be done in conformance with Chapter 25, Reconstruction and Repair. The finished patch shall blend smoothly into the existing surface. The determination of need for a complete overlay shall be made by the City of Fort Collins Engineer. All overlay work shall be coordinated with adjacent landowners such that future projects do not cut the new asphalt overlay work. 7.All traffic control devices shall be in conformance with these plans or as otherwise specified in M.U.T.C.D. (including Colorado supplement) and as per the Right-of-Way Work Permit traffic control plan. 8.The Developer is required to perform a gutter water flow test in the presence of the City of Fort Collins Inspector and prior to installation of asphalt. Gutters that hold more than 1/4 inch deep or 5 feet longitudinally, of water, shall be completely removed and reconstructed to drain properly. 9.Prior to placement of H.B.P. or concrete within the street and after moisture/density tests have been taken on the subgrade material (when a full depth section is proposed) or on the subgrade and base material (when a composite section is proposed), a mechanical "proof roll" will be required. The entire subgrade and/or base material shall be rolled with a heavily loaded vehicle having a total GVW of not less than 50,000 lbs. and a single axle weight of at least 18,000 lbs. with pneumatic tires inflated to not less that 90 p.s.i.g. "Proof roll" vehicles shall not travel at speeds greater than 3 m.p.h. Any portion of the subgrade or base material which exhibits excessive pumping or deformation, as determined by the City of Fort Collins Engineer, shall be reworked, replaced or otherwise modified to form a smooth, non-yielding surface. The City of Fort Collins Engineer shall be notified at least 24 hours prior to the "proof roll." All "proof rolls" shall be preformed in the presence of an Inspector. C.Traffic Signing and Pavement Marking Construction Notes 1.All signage and marking is subject to the General Notes on the cover sheet of these plans, as well as the Traffic Signing and Marking Construction Notes listed here. 2.All symbols, including arrows, ONLYS, crosswalks, stop bars, etc. shall be pre-formed thermo-plastic. 3.All signage shall be per the City of Fort Collins Standards and these plans or as otherwise specified in MUTCD. 4.All lane lines for asphalt pavement shall receive two coats of latex paint with glass beads. 5.All lane lines for concrete pavement should be epoxy paint. 6.Prior to permanent installation of traffic striping and symbols, the Developer shall place temporary tabs or tape depicting alignment and placement of the same. Their placement shall be approved by the City of Fort Collins Traffic Engineer prior to permanent installation of striping and symbols. 7.Pre-formed thermo-plastic applications shall be as specified in these Plans and/or these Standards. 8.Epoxy applications shall be applied as specified in CDOT Standard Specifications for Road and Bridge Construction. 9.All surfaces shall be thoroughly cleaned prior to installation of striping or markings. 10.All sign posts shall utilize break-away assemblies and fasteners per the Standards. 11.A field inspection of location and installation of all signs shall be performed by the City of Fort Collins Traffic Engineer. All discrepancies identified during the field inspection must be corrected before the 2-year warranty period will begin. 12.The Developer installing signs shall be responsible for locating and protecting all underground utilities. 13.Special care shall be taken in sign location to ensure an unobstructed view of each sign. 14.Signage and striping has been determined by information available at the time of review. Prior to initiation of the warranty period,the City of Fort Collins Traffic Engineer reserves the right to require additional signage and/or striping if the City of Fort Collins Traffic Engineer determines that an unforeseen condition warrants such signage according to the MUTCD or the CDOT M and S Standards. All signage and striping shall fall under the requirements of the 2-year warranty period for new construction (except fair wear on traffic markings). 15.Sleeves for sign posts shall be required for use in islands/medians. Refer to Chapter 14, Traffic Control Devices, for additional detail 16.Contractor is responsible for removing all anchors, posts, signs and/or delineators in Construction area. Contractor may keep the signs, or call the City Traffic Division to have them removed. 17.No “Reset” anchors, posts, signs, and/or delineators will be accepted. 18.All anchors, posts, signs, and/or delineators shall be new and be consistent with the LCUASS criteria. D.Storm Drainage Notes 1.The City of Fort Collins shall not be responsible for the maintenance of storm drainage facilities located on private property. Maintenance of onsite drainage facilities shall be the responsibility of the property owner(s). 2.All recommendations of the Final Drainage Report for Johnson Drive Apartments dated 07/31/24 by Northern Engineering shall be followed and implemented. 3.Prior to final inspection and acceptance by the City of Fort Collins, certification of the drainage facilities, by a registered engineer, must by submitted to and approved by the Stormwater Utility Department. Certification shall be submitted to the Stormwater Utility Department at least two weeks prior to the release of a certificate of occupancy for single family units. For commercial properties, certification shall by submitted to the Stormwater Utility Department at least two weeks prior to the release of any building permits in excess of those allowed prior to certification per the Development Agreement. 4.See City of Fort Collins Stormwater Criteria Manual – Appendix F Construction Control Measures Standard Notes and Standard Erosion Control Notes. E.Utility Notes 1.All waterline and sanitary sewer construction shall conform to the City of Fort Collins Utility standards and specifications current to date of construction. 2.The minimum cover over water lines is 4.5 feet and the maximum cover is 5.5 feet unless otherwise noted in the plans and approved by the water utility. 3.Water mains shall be poly-wrapped D.I.P, or PVC with tracer wire. 4.HDPE pipe may be used for 1-1/2 and 2 inch water services. The pipe shall meet the standards of AWWA 901, NSF Standard 61 and ASTM. The HDPE pipe shall be SDR 9 having a pressure rating of 200 psi. Stiffeners shall be used at all fittings and connections. Tracer wire shall be installed with the HDPE service, and shall extend up the curb stop. The curb stop shall be covered with a metal valve box and "water" lid per City Water Detail 11A. 5. Home - EPS Group (epsgroupinc.com) EPSGROUPINC.COM | 970.221.4158 SWMP Report: Gregory Cove Subdivision FORT COLLINS | GREELEY | MESA | TUSCON | GOODYEAR | PHEONIX | FORT WORTH APPENDIX APPENDIX C LANDSCAPE PLAN Home - EPS Group (epsgroupinc.com) EPSGROUPINC.COM | 970.221.4158 SWMP Report: Gregory Cove Subdivision FORT COLLINS | GREELEY | MESA | TUSCON | GOODYEAR | PHEONIX | FORT WORTH APPENDIX APPENDIX D PERMITS / APPLICATIONS For Agency Use Only Permit Number Assigned COR03- Date Received /_ /_ Month Day Year COLORADO DISCHARGE PERMIT SYSTEM (CDPS) ST ORM WAT ER DISCHARGE ASSOCIATED WITH CONSTRUCTION ACTIVITIES APPLICATION PHOTO COPIES, FAXED COPIES, PDF COPIES OR EM AILS WILL NOT BE ACCEPTED. Please print or type. Original signatures are required. All item s m ust be com pleted accurately and in their entirety for the application to be deem ed com plete. Incom plete applications will not be processed until all inform ation is received which will ultim ately delay the issuance of a perm it. If m ore space is required to answer any question, please attach additional sheets to the application form . Applications m ust be subm itted by m ail or hand delivered to: Colorado Department of Public Health and Environment Water Quality Control Division 4300 Cherry Creek Drive South WQCD-P-B2 Denver, Colorado 80246-1530 Any additional inform ation that you would lik e the Division to consider in developing the perm it should be provided with the application. Exam ples include effluent data and/or m odeling and planned pollutant rem oval strategies. PERM IT INFORM ATION Reason for Application: NEW CERT RENEW CERT EXISTING CERT # Applicant is: Property Owner Contractor/Operator A. CONTACT INFORMATION - NOT ALL CONTACT TYPES MAY APPLY * indicates required *PERMITTEE (If more than one please add additional pages) *ORGANIZATION FORMAL NAME: 1) *PERMITTEE the person authorized to sign and certify the permit application. This person receives all permit correspondences and is legally responsible for compliance with the permit. Responsible Position (Title): Currently Held By (Person): Telephone No:_ email address Organization: Mailing Address: City:_ State: Zip: This form must be signed by the Permittee (listed in item 1) to be considered complete. Per Regulation 61 In all cases, it shall be signed as follows: a) In the case of corporations, by a responsible corporate officer. For the purposes of this section, the responsible corporate officer is responsible for the overall operation of the facility from which the discharge described in the application originates. b) In the case of a partnership, by a general partner. c) In the case of a sole proprietorship, by the proprietor. d) In the case of a municipal, state, or other public facility, by either a principal executive officer or ranking elected offic ial page 1 of 5 revised April 2011 2) DMR COGNIZANT OFFICIAL (i.e. authorized agent) the person or position authorized to sign and certify reports required by the Division including Discharge Monitoring Reports *DMR’s, Annual Reports, Compliance Schedule submittals, and other information requested by the Division. The Division will transmit pre-printed reports (ie. DMR’s) to this person. If more than one, please add additional pages. Same As 1) Permittee Responsible Position (Title): Currently Held By (Person): Telephone No:_ email address Organization: Mailing Address: City:_ State: Zip: Per Regulation 61 : All reports required by permits, and other information requested by the Division shall be signed by the permittee or by a duly authorized representative of that person. A person is a duly authorized representative only if: (i) The authorization is made in writing by the permittee (ii) The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters for the company. (A duly authorized representative may thus be either a named individual or any individual occupying a named position); and (iii) The written authorization is submitted to the Division 3) *SITE CONTACT local contact for questions relating to the facility & discharge authorized by this permit for the facility. Same As 1) Permittee Responsible Position (Title): Currently Held By (Person): Telephone No:_ email address Organization: Mailing Address: City:_ State: Zip: 4) * BILLING CONTACT if different than the permittee Responsible Position (Title): Currently Held By (Person): Telephone No:_ email address Organization: Mailing Address: City:_ State: Zip: Page 2 of 5 revised April 2011 5) OTHER CONTACT TYPES (check below) Add pages if necessary: ResponsiblePosition (Title): Currently Held By (Person): Telephone No:_ email address Organization: Mailing Address: City:_ State: Zip: o Pretreatment Coordinator o Environmental Contact o Biosolids Responsible Party o Property Owner Inspection Facility Contact Consultant Compliance Contact Stormwater MS4 Responsible Person Stormwater Authorized Representative Other B. Permitted Project/Facility Information Project/Facility Name Street Address or cross streets (e.g., “S. of Park St. between 5th Ave. and 10th Ave.”, or “W. side of C.R. 21, 3.25 miles N. of Hwy 10”; A street name without an address, intersection, mile marker, or other identifying information describing the location of the project is not adequate. For linear projects, the route of the project should be described as best as possible with the location more accurately indicated by a map.) City, Zip Code County Facility Latitude/Longitude— (approxim ate center of site to nearest 15 seconds using one of following f orm ats 001A Latitude . Longitude . (e.g., 39.703°, 104.933°’) degrees (to 3 decimal places) degrees (to 3 decimal places) or 001A Latitude º ’ " Longitude º ’ " (e.g., 39°46'11"N, 104°53'11"W ) degrees minutes seconds degrees minutes seconds For the approximate center point of the property, to the nearest 15 seconds. The latitude and longitude must be provided as either degrees, minutes, and seconds, or in decimal degrees with three decimal places. This information may be obtained from a variety of sources, including: o Surveyors or engineers for the project should have, or be able to calculate, this information. o EPA maintains a web-based siting tool as part of their Toxic Release Inventory program that uses interactive maps and aerial photography to help users get latitude and longitude. The siting tool can be accessed at www.epa.gov/tri/report/siting_tool/index.htm o U.S. Geological Survey topographical map(s), available at area map stores. o Using a Global Positioning System (GPS) unit to obtain a direct reading. Note: the latitude/longitude required above is not the directional degrees, minutes, and seconds provided on a site legal description to define property boundaries. C. MAP (Attachment) If no map is submitted, the permit will not be issued. Map: Attach a map that indicates the site location and that CLEARLY shows the boundaries of the area that will be disturbed. Maps must be no larger than 11x17 inches. D. LEGAL DESCRIPTION Legal description: If subdivided, provide the legal description below, or indicate that it is not applicable (do not supply Township/Range/Section or metes and bounds description of site) Subdivision(s): Lot(s): Block(s): OR Not applicable (site has not been subdivided) page 3 of 5 revised April 2011 E. AREA OF CONSTRUCTION SIT E Total area of project site (acres): Area of project site to undergo disturbance (acres): Note: aside from clearing, grading and excavation activities, disturbed areas also include areas receiving overburden (e.g., stockpiles), demolition areas, and areas with heavy equipment/vehicle traffic and storage that disturb existing vegetative cover Total disturbed area of Larger Common Plan of Development or Sale, if applicable: (i.e., total, including all phases, filings, lots, and infrastructure not covered by this application) Provide both the total area of the construction site, and the area that will undergo disturbance, in acres. Note: aside from clearing, grading and excavation activities, disturbed areas also include areas receiving overburden (e.g., stockpiles), demolition areas, and areas with heavy equipment/vehicle traffic and storage that disturb existing vegetative cover (see construction activity description under the APPLICABILITY section on page 1). If the project is part of a larger common plan of development or sale (see the definition under the APPLICABILITY section on page 1), the disturbed area of the total plan must also be included. F. NATURE OF CONST RUCTION ACTIVIT Y Check the appropriate box(s) or provide a brief description that indicates the general nature of the construction activities. (The full description of activities must be included in the Stormwater Management Plan.) Single Family Residential Development Multi-Family Residential Development Commercial Development Oil and Gas Production and/or Exploration (including pad sites and associated infrastructure) Highway/Road Development (not including roadways associated with commercial or residential development) Other – Description: G. ANTICIPAT ED CONSTRUCT ION SCHEDULE Construction Start Date: ___________________________ Final Stabilization Date: _____________________________ Construction Start Date - This is the day you expect to begin ground disturbing activities, including grubbing, stockpiling, excavating, demolition, and grading activities. Final Stabilization Date - in terms of permit coverage, this is when the site is finally stabilized. This means that all ground surface disturbing activities at the site have been completed, and all disturbed areas have been either built on, paved, or a uniform vegetative cover has been established with an individual plant density of at least 70 percent of pre-disturbance levels. Permit coverage must be maintained until the site is finally stabilized. Even if you are only doing one part of the project, the estimated final stabilization date must be for the overall project. If permit coverage is still required once your part is completed, the permit certification may be transferred or reassigned to a new responsible entity(s). H. RECEIVING WAT ERS (If discharge is to a ditch or storm sewer, include the name of the ultimate receiving waters) Immediate Receiving Water(s): Ultimate Receiving Water(s): Identify the receiving water of the stormwater from your site. Receiving waters are any waters of the State of Colorado. This includes all water courses, even if they are usually dry. If stormwater from the construction site enters a ditch or storm sewer system, identify that system and indicate the ultimate receiving water for the ditch or storm sewer. Note: a stormwater discharge permit does not allow a discharge into a ditch or storm sewer system without the approval of the owner/operator of that system. page 4 of 5 revised April 2011 I. REQUIRED SIGNAT URES (Both parts i. and ii. must be signed) Signature of Applicant: The applicant must be either the owner and/or operator of the constr uction site. Refer to Part B of the instructions for additional information. The application must be signed by the applicant to be considered complete. In all cases, it shall be signed as follows: (Regulation 61.4 (1ei) a) In the case of corporations, by the responsible corporate officer is responsible for the overall operation of the facility from which the discharge described in the form originates b) In the case of a partnership, by a general partner. c) In the case of a sole proprietorship, by the proprietor. d) In the case of a municipal, state, or other public facility, by either a principal executive officer, ranking elected officia l, (a principal executive officer has responsibility for the overall operation of the facility from which the discharge originates). STOP!: A Stormwater Management Plan must be completed prior to signing the following certifications! i. ST ORM WAT ER M ANAGEMENT PLAN CERTIFICATION “I certify under penalty of law that a complete Stormwater Management Plan, has been prepared for my activity. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the Stormwater Management Plan is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for falsely certifying the completion of said SWMP, including the possibility of fine and imprisonment for knowing violations.” XX Signature of Legally Responsible Person or Authorized Agent (submission must include original signature) Date Signed Name (printed) Title ii. SIGNAT URE OF PERMIT LEGAL CONT ACT "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is to t he best of my knowledge and belief, true, accurate and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." “I understand that submittal of this application is for coverage under the State of Colorado General Permit for Stormwater Discharges Associated with Construction Activity for the entirety of the construction site/project described and applied for, until such time as the application is amended or the certification is transferred, inactivated, or expired.” XX Signature of Legally Responsible Person (submission must include original signature) Date Signed Name (printed Title DO NOT INCLUDE A COPY OF THE STORMWATER MANAGEMENT PLAN DO NOT INCLUDE PAYMENT – AN INVOICE WILL BE SENT AFTER THE CERTIFICATION IS ISSUED. page 5 of 5 revised April 2011 COLORADO DISCHARGE PERMIT SYSTEM (CDPS) For Agency Use Only Permit Number Assigned COG07-______________ Date Received ____/____/____ Month Day Year CONSTRUCTION DEWATERING INDUSTRIAL WASTEWATER DISCHARGE APPLICATION PHOTO COPIES, FAXED COPIES, PDF COPIES OR EMAILS WILL NOT BE ACCEPTED. Please print or type. Original signatures are required. All items must be completed accurately and in their entirety for the application to be deemed complete. Incomplete applications will not be processed until all information is received which will ultimately delay the issuance of a permit. If more space is required to answer any question, please attach additional sheets to the application form. Applications must be submitted by mail or hand delivered to: Colorado Department of Public Health and Environment Water Quality Control Division 4300 Cherry Creek Drive South WQCD-P-B2 Denver, Colorado 80246-1530 Any additional information that you would like the Division to consider in developing the permit should be provided with the application. Examples include effluent data and/or modeling and planned pollutant removal strategies. PERMIT INFORMATION Reason for Application: NEW CERT RENEW CERT EXISTING CERT #____________________ Applicant is: Property Owner Contractor/Operator A. Contact Information Permittee (If more than one please add additional pages) Organization Formal Name: ___________________________________________________________ 1. Permittee the person authorized to sign and certify the permit application. This person receives all permit correspondences and is legally responsible for compliance with the permit. Responsible Position (Title): ______________________________________________________________ Currently Held By (Person): _______________________________________________________________ Telephone No:__________________________________________________________________________ email address__________________________________________________________________________ Organization: ___________________________________________________________________________ Mailing Address: ________________________________________________________________________ City:_______________________________ State: ______________________ Zip: ____________________ This form must be signed by the Permittee to be considered complete. Per Regulation 61: In all cases the permit application shall be signed as follows: a) In the case of corporations, by a responsible corporate officer. For the purposes of this section, the responsible corporate officer is responsible for the overall operation of the facility from which the discharge described in the application originates. b) In the case of a partnership, by a general partner. c) In the case of a sole proprietorship, by the proprietor. d) In the case of a municipal, state, or other public facility, by either a principal executive officer or ranking elected official Page 1 of 6 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com 2. DMR Cognizant Official (i.e. authorized agent)—the person or position authorized to sign and certify reports required by permits including Discharge Monitoring Reports [DMR’s], Annual Reports, Compliance Schedule submittals, and other information requested by the Division. The Division will send pre-printed reports (e.g. DMR’s) to this person. If more than one, please add additional pages. Same as 1) Permittee Responsible Position (Title): _______________________________________________________ Currently Held By (Person): ________________________________________________________ Telephone No:___________________________________________________________________ Email address____________________________________________________________________ Organization: ____________________________________________________________________ Mailing Address: _________________________________________________________________ City:______________________________ State: ______________ Zip: ______________________ Per Regulation 61: All reports required by permits, and other information requested by the Division shall be signed by the permittee or by a duly authorized representative of that person. A person is a duly authorized representative only if: (i) The authorization is made in writing by the permittee; (ii) The authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity such as the position of plant manager, operator of a well or a well field, superintendent, position of equivalent responsibility, or an individual or position having overall responsibility for environmental matters for the company. (A duly authorized representative may thus be either a named individual or any individual occupying a named position); and (iii) The written authorization is submitted to the Division. 3. Site/Local Contact—contact for questions regarding the facility & discharges authorized by this permit Same as Permittee—Item 1 Responsible Position (Title): ________________________________________________________ Currently Held By (Person): _________________________________________________________ Telephone No:____________________________________________________________________ Email address_____________________________________________________________________ Organization: _____________________________________________________________________ Mailing Address: __________________________________________________________________ City:______________________________ State: ______________ Zip: _______________________ 4. Operator in Responsible Charge Same as Permittee—Item 1 Responsible Position (Title): __________________________________________________________ Currently Held By (Person): ___________________________________________________________ Telephone No:______________________________________________________________________ Email address______________________________________________________________________ Organization: _______________________________________________________________________ Mailing Address: ____________________________________________________________________ City:_______________________________ State: ______________ Zip: ________________________ Certification Type____________________Certification Number________________________________ Page 2 of 6 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com 5. Billing Contact (if different than the permittee) Responsible Position (Title): _____________________________________________________________ Currently Held By (Person): ______________________________________________________________ Telephone No:_________________________________________________________________________ Email address_________________________________________________________________________ Organization: __________________________________________________________________________ Mailing Address: _______________________________________________________________________ City:______________________________ State: ______________ Zip: ____________________________ 6. Other Contact Types (check below) Add pages if necessary: Responsible Position (Title): ______________________________________________________________ Currently Held By (Person): _______________________________________________________________ Telephone No:__________________________________________________________________________ Email address__________________________________________________________________________ Organization: ___________________________________________________________________________ Mailing Address: ________________________________________________________________________ City:______________________________________ State: ______________ Zip: _____________________ Pretreatment Coordinator Environmental Contact Biosolids Responsible Party Property Owner Inspection Facility Contact Consultant Compliance Contact Stormwater MS4 Responsible Person Stormwater Authorized Representative Other ____________________ B. Permitted Project/Facility Information 1. Project/Facility Name ____________________________________________________________________________ Street Address or cross streets_____________________________________________________________________ City, State and Zip Code _____________________________________________County _____________________ Type of Facility Ownership City Government Corporation Private Municipal or Water District State Government Mixed Ownership _________________________________ 2. Facility Latitude/Longitude—List the latitude and longitude of the excavation(s) resulting in the discharge(s). If the exact excavation location(s) are not known, list the latitude and longitude of the center point of the construction project. If using the center point, be sure to specify that it is the center point of construction activity. 001A Latitude __________ . _________ Longitude ___________ . _____________ (e.g., 39.703°, 104.933°’) degrees (to 3 decimal places) degrees (to 3 decimal places) or 001A Latitude _____ º _____’ _____" Longitude _____ º _____’ _____" (e.g., 39°46'11"N, 104°53'11"W ) degrees minutes seconds degrees minutes seconds Horizontal Collection Method: GPS Unspecified Interpolation Map – Map Scale Number__________ Reference Point: Project/Facility Entrance Project/Facility Center/Centroid Horizontal Accuracy Measure (WQCD Requires use of NAD83 Datum for all references)___________________ (add additional pages if necessary) Page 3 of 6 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com B. Permitted Project/Facility Information Continued… 3. Facility Activity and Anticipated Schedule Dewatering will begin (date) _______________ Estimate how long dewatering will last: Years____________Months_______________Days_________________ Describe Activity e.g., highway bridge and tunnel construction, storm drain expansion, etc. and a description of activities being performed, including construction schedule and months of operation. Specify source(s) of wastewater to be discharged (i.e.well, foundation excavation, trenching, etc). 4. Will the discharge go to a ditch or storm sewer? YES NO If YES, in the appropriate table below include the name of the ultimate receiving waters where the ditch or storm sewer discharges. If YES, applicant must contact the owner of the ditch or storm sewer system (prior to discharging) to verify local ordinances and to determine whether or not additional requirements are going to be imposed by the owner. 5. What type of discharge will this be? Defined Discharge Undefined Discharge A Defined Discharge is a discharge where the dewatering discharge locations and number of outfalls are known at the time of permit application. If discharge is Defined – enter information in table C for Defined Discharges An Undefined Discharge is a discharge where the exact dewatering discharge locations are unknown at the time of permit application. The permit applicant must request the maximum number of potential outfalls (dis charges) for the permitted facility. If discharge is Undefined – enter information in table D for Undefined Discharges Note: For undefined discharges, the site specific sampling and monitoring parameters will be selected based on the potential pollutant sources found within the entire permitted project area and will be applied to all outfall(s). The most stringent of the surface water limitations for each identified site specific parameter will be applied to each permitted outfall. C. Information for Defined Discharge Location(s): 1. In the following table, include the following information for the discharge: Include the number of discharge points (outfalls); Include the name of the receiving stream for each Outfall Number. If the discharge is to groundwater fill out discharge information located next to G001A, G002A, etc.—Please review the Division’s Low Risk Discharge Guidance for Discharges of Uncontaminated Groundwater to Land to determine if discharges to groundwater can be allowed under the Guidance in lieu of obtaining a Construction Dewatering Permit.; Include the approximate location of the discharge (e.g. ―discharge will occur between 5th Avenue and 20th Avenue‖, or ―the discharge will enter the storm sewer located at the corn er of Speer Blvd and 8th Ave., which eventually flows to Cherry Creek‖ ; Include the maximum anticipated flow rate of the discharge; this can be based on pump capacity or other applicable measure. Add more pages if necessary Page 4 of 6 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com D. Information for Undefined Discharge Location(s): 1. In the following table include the following information for the discharge: Include the maximum number of potential outfalls (discharges) for the permitted facility/project; Include the maximum anticipated flow rate of the discharge; this can be based on pump capacity or other applicable measure ; Include the name of all potential receiving streams for the entire project. I f the discharge is to groundwater fill out discharge information located next to G001A, G002A, etc.—Please review the Division’s Low Risk Discharge Guidance for Discharges of Uncontaminated Groundwater to Land to determine if discharges to groundwater can be allowed under the Guidance in lieu of obtaining a Construction Dewatering Permit. Note: For undefined discharges, the site specific sampling and monitoring parameters will be selected based on the potential pollutant sources found within the entire permitted project area and will be applied to all outfall(s). The most stringent of the surface water limitations for each identified site specific parameter will be applied to each permitted outfall. Add more pages if necessary Sampling and Reporting Requirements for Defined and Undefined Discharges: Sampling must occur at every end-of- pipe dewatering location (after going through your choice of BMP, if necessary). The permittee will be issued Discharge Monitoring Report (DMR) forms for all requested outfall numbers. The permittee will be required to submit the DMR forms for each requested outfall number monthly. For the outfall numbers(s) where no discharge occurred for a given month, the permittee shall mark ―No Discharge‖ on the DMR forms. The sampling results must be maintained by the permittee. E. A Location Map for Defined and Undefined Discharges—designating the location of the project/facility, the location of the discharge point(s)/outfalls—applicable only to defined discharges, and the receiving water(s) listed in Items C & D. A north arrow shall be shown. This map must be on paper that can be folded to 8 ½ x 11 inches. F. A Legible Sketch of the Site 1. For Defined Discharges—A legible site sketch shall be submitted and must include: the location of the end of pipe dewatering discharges at the site (e.g. where the flow will be discharged from the pump or BMP), the BMP(s) that will be used to treat the discharge(s), and the sampling location(s). Refer to the instructions for additional guidance specific to sites with multiple potential dewatering locations. This map must be on paper that can be folded to 8 ½ x 11 inches. OR 2. For Undefined Discharges—A legible site sketch shall be submitted and must include: the limits of the construction site boundary to include street names (if applicable) or landmarks; description of the BMPs to be implemented; and location of all potential receiving waters. This map must be on paper that can be folded to 8 ½ x 11 inches. G. Potential Groundwater Contamination 1. Is this operation located within one mile of a landfill, abandoned landfill or any mine or mill tailings? YES NO 2. Has the dewatering discharge been analyzed for any parameters (pH, Oil and Grease, Metals, Organics, etc.)? YES NO If YES, please attach a copy of the sampling results. Page 5 of 6 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com Note to the applicant: Upon review of the application, the Division may request characterization of the water to be discharged or analysis of certain parameters once the application has been reviewed. If the Division requests a representative analysis of the water to be discharged, the application processing time may be lengthened. 3. Has the dewatering area been checked for possible groundwater contamination, such as plumes from leaking underground storage tanks, mine tailings,etc –or- has a Phase I or Phase II been conducted on the site? YES NO If YES, show location of the landfill, tailings, or possible groundwater contamination on the location map or general sketch map. (Explain the location, extent of contamination, and possible effect on the groundwater pumping from this facility). Or include a copy of the phase I or Phase II report. If the reports are not available, submit a summary of the results of the report. If any sampling results are available, please attach a copy of all data. Note: Contact Water Quality Control Division for the proper water chemistry parameters to report. H. Additional Information 1. Does the applicant have a Stormwater Permit for Construction Activities? YES NO PENDING If Yes, Stormwater Construction Permit Number _________________________________ WATER RIGHTS The State Engineers Office (SEO) has indicated that any discharge that does not return water directly to surface waters (i.e.land application, rapid infiltration basins, etc.) has the potential for material injury to a water right. As a result, the SEO needs to determine that material injury to a water right will not occur from such activities. To make this judgment, the SEO requests that a copy of all documentation demonstrating that the requirements of Colorado water law have been met, be submitted to their office for review. The submittal should be made as soon as possible to the following address: Colorado Division of Water Resources 1313 Sherman Street, Room 818 Denver, Colorado 80203 Should there be any questions on the issue of water rights, the SEO can be contacted at (303) 866-3581. It is important to understand that any CDPS permit issued by the Division does not constitute a water right. The issuance of a CDPS permit does not negate the need to also have the necessary water rights in place. Additionally, if the activity has an existing CDPS permit, there is no guarantee that the proper water rights are in place. I. Required Certification Signature [Reg 61.4(1)(h)] "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or p ersons who manage the system, or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief, true, accurate and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations." ―I understand that submittal of this application is for coverage under the State of Colorado General Permit for Discharges Associated with Construction Dewatering for the entirety of the construction site/project described and applied for, until such time as the application is amended or the certification is transferred, inactivated, or expired .‖ Signature (Legally Responsible Party)_________________________________________Date ________________ Name (printed) _____________________________________________Title______________________________ Page 6 of 6 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com Construction Dewatering Application Instructions Item A- Contact Information Permit Applicant: Provide the company, corporation, or organization name 1. Permittee—Identify the title and name of the individual who is the legally responsible for the permit. The requirement of who can be listed as the legally responsible party is included in the permit application. Include all requested information such as the legal party‘s phone number, email address and mailing address. The individual identified here must sign the permit application—Part I. 2. DMR Cognizant Official—Identify the title and individual‘s name 3. Site Contact—Identify the title and name of individual who is familiar with the day to day operations of the site. This person will have first-hand information regarding the construction site, discharges occurring on site, and implementation of BMPs. 4. Operator in Responsible Charge— Identify the title and individual‘s name if there is an Operator in Charge (Not required) 5. Billing Contact— Identify the title and individual‘s name 6. Other Contacts – Identify the title and individual‘s name for any of the listed descriptions (Not required) Item B – Permitted Project/Facility Information 1. Name of the project/facility and location; include the name of the project/facility and include a description of the locatio n of the project/facility. The location may be a physical address or if the exact address is not available you may use an approximate address such as: the nearest intersection or boundary streets including directional identifiers (e.g., ―South of 14th Avenue between Sherman St. and Logan St.‖, or ―West side of C.R. 21, 3.25 miles North of Hwy 10‖) or other identifying information. A street name without an address, intersection, mile marker or other identifying information is not adequate. 2. Latitude/Longitude: For each excavation resulting in a discharge/outfall provide the Latitude/Longitude of the excavation. If the exact location of the disturbance resulting in discharge is not known, provide the lat/long of the center point of the construction activity. If identifying the center point of construction activity, make sure to write in ―center point‘ next to lat/long. The lat/long may be provided as decimal degrees or degrees, minutes, seconds format. This information can be obtained from a variety of sources, including:  Various Websites: http://terraserver.microsoft.com, http://geocoder.us/, or www.epa.gov/tri/reports/siting_tool/index.htm  U.S Geological Survey topographical map, available at area map stores  Surveyors or engineers for the construction project should have, or be able to calculate this information using a Global Positioning System (GPS) unit Specify whether the Latitude/Longitude information was collected either by using a GPS unit or through Map interpolation. 3. Facility Activity and Schedule: Include the anticipated start date of construction dewatering and provide the length of time dewatering is anticipated to last. Provide a description of the general nature of the construction activities th at are requiring the dewatering. Also describe if the dewatering discharge is from an open excavation, such as a trench or foundation, or from groundwater lowering wells. Examples of activity descriptions may include: ‗open trench excavation for installation of 4,000 linear feet of new water lines‘, or ‗a series of shallow groundwater wells will be installed around the perimeter of the construction site in order to lower the water table for construction of a new 5,000 square foot music shop—all wells will be piped to one manifold resulting in one discharge location as indicated on our site sketch. 4. Discharges to ditches and storm sewers: Indicate by checking yes or no whether or not the immediate effluent will be discharged to a ditch or storm sewer. If yes is marked, the applicant must contact the owner of the ditch or storm sewer system prior to discharge to verify if the owner will allow a discharge to their system. The owner of the ditch/storm sewer system may impose additional requirements. Storm drainage systems are typically owned by the city or county they are located within, and therefore contacting the local city/county is the appropriate place to start. If yes is marked, in Table C or Table D be sure to include the location of the system and the ultimate receiving waters. 5. Defined or Undefined Discharge: Identify whether the applicant is applying for a Defined or Undefined discharge. A Defined Discharge is a discharge where the dewatering discharge locations are known at the time of permit application. If discharge is Defined – enter discharge information in Table C Page 1 of 3—Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com An Undefined Discharge is a discharge where the exact dewatering discharge locations are unknown at the time of permit application. The permit applicant must request the maximum number of potential outfalls (discharges) for the permitted facility/project. If discharge is Undefined – enter discharge information in Table D. The applicant must identify all potential receiving streams for the entire project. If the applicant is requesting undefined discharges, the site specific sampling and monitoring parameters will be selected based on the potential pollutant sources found within the entire permitted project area and will be applied to all outfall(s). The most stringent of the surface water limitations for each identified site specific parameter will be applied to each permitted outfall. For example, if the undefined project includes installation of 8 miles of linear pipeline and leaking underground storage tanks are expected to present in one section of the project, sampling and monitoring for Benzene, Toluene, Ethyl benzene, and Xylenes will be required for all requested outfall(s). Item C- Information for Defined Discharge Location(s). 1. If Defined Discharge was marked in Section B.5 fill out Table C. Table C requires the following information:  Number of discharge(s) (outfalls)—Identify the number of outfalls requested in Table C, this includes discharges to surface water and groundwater. If there are more than two requested discharges to surface water, attach a separate piece of paper including all requested information.  Name of the receiving water(s)—If the discharge is to a ditch, identify the ditch and the ultimate receiving water(s). Receiving waters are any waters of the state of Colorado, even if the natural drainage is usually dry. If discharge is to groundwater, then fill out the appropriate information within Table C next to G001A, G001A. If there are more than two discharges to groundwater, attach a sepa rate piece of paper including all requested information. If the applicant is requesting a discharge to groundwater, please review the Division‘s Low Risk Discharge Guidance for Discharges of Uncontaminated Groundwater to Land . http://www.cdphe.state.co.us/wq/PermitsUnit/policyguidancefactsheets/policyandguidance/lowriskgwdischargeto land.pdf Discharges performed in accordance with the Guidance for Discharges of Uncontaminated Groundwater to Land do not require a separate construction dewatering permit.  Narrative description of the approximate location of the discharge—Include a narrative description of the discharge path. For example, ―the dewatering discharge will enter the storm sewer located at 6th Avenue and Sheridan which flows to Bear Creek‖ or ―the dewatering will discharge to a field located at 66th and Farmers Road with potential to runoff to Sanders Creek‖. If there is more than one known discharge, include this descriptive information for all known discharges.  Maximum anticipated flow rate of the discharge (in gallons per minute)—Do not leave this section blank. Include the maximum flow rate. You may estimate the flow contribution based on pump capacity if data is not available.  Latitude/Longitude of each discharge location—Include the latitude/longitude of each discharge location. See the instructions B.2 for information on how to obtain latitude/longitude information. Item D- Information for Undefined Discharge Location(s). 1. If Undefined Discharge was marked in Section B.5 fill out Table D. Table D requires the flowing information:  Maximum number of potential outfalls (discharges) for the permitted facility—The applicant must identify the maximum number of discharge locations (outfalls) for the entire construction project. If more than 5 outfalls are requested, attach a separate piece of paper. DMRs will be sent to the permittee for each requested ou tfall.  Maximum anticipated flow rate of the discharge (in gallons per minute)—Do not leave this section blank. The flow rate may be estimated based on pump capacity if data is not available.  Name(s) of the all potential receiving stream(s)—Identify all potential receiving streams for the entire project. If the discharge is to groundwater then fill out the information in Table D next to G001A, G002A, etc. Page 2 of 3 Revised April 2011 Industrial Wastewater Discharge Permit – Construction Dewatering www.coloradowaterpermits.com Item E – Location Map—A location map is required to be submitted with all applications for both defined and undefined discharges. The location map must include the location of the project/facility, the approximate location of each defined discharge points, and the identified receiving water(s) listed in Items C or D. The map must have a minimum scale of 1:24000 (the scale of a USGS 7.5 minute map). A legible submittal is required on paper that can be folded to8 ½ by 11 inches. Item F- Detailed Sketch of the Site—If a defined discharge is requested please submit a detailed site sketch which includes the information requested in F.1. If an undefined discharge is requested please submit a detailed site sketch which includes the information requested in F.2. 1. Detailed Sketch of the Site for Defined Discharges—Must included a detailed sketch of the site showing the location of end of pipe dewatering discharge(s) at the site —to include the flow line of each requested dewatering discharge. The location and identification of the structural Best Management Practices (BMPs) used to treat the effluent prior to discharge. The map shall also include the sampling locations for each requested outfall. A legible submittal is required on paper that can be folded to 8 ½ by 11 inches. 2. Detailed Sketch of the Site for Undefined Discharges—This map must include the boundary of the construction site where all potential dewatering could occur. The boundaries should include a northern boundary, an eastern boundary, a southern boundary and a western boundary. The map must highlight or call out street names that border the project boundary. If streets are not available, landmarks or mile-markers must be identified. The map must highlight all potential receiving streams. The map must also include the identification of the structural BM Ps used to treat the effluent prior to discharge. A legible submittal is required on paper that can be folded to 8 ½ by 11 inches. Item G—Potential Groundwater Contamination 1. Dewatering on/near Landfills, Mines, or Mill Tailings: If the dewatering project is located within one mile of a landfill, abandoned landfill, mine or mill tailings check yes. In addition, provide as much detail as possible regarding the extent of contamination and attach all sampling data. Indicate the location of the landfill, m ine, etc. on the Location and Detail Maps.  Contamination plume information can be obtained from the following source: http://www.cdphe.state.co.us/hm/HMSiteCover.htm 2. Sampling Data: If any sampling data is available that is representative of the prop osed discharge mark yes. Attach a copy of all sampling results to the application. If the data was collected for another agency or private company include a brief description as to why the data was collected. 3. Additional Sources of Contamination: Mark yes if the proposed construction site resulting in a dewatering discharge has been evaluated for any additional sources of contamination. Additional sources include underground storage tanks, dry cleaners, voluntary clean-up sites, etc. Also mark yes, if a Phase I or Phase II has been conducted on the property or adjacent properties. Attach a copy of all records (phase I, phase II, sampling efforts) that could help characterized the water to be discharged.  Contamination plume information can be obtained from the following source: http://www.cdphe.state.co.us/hm/HMSiteCover.htm Item H—Additional Information 1. Stormwater Permit for Construction Activities: If the applicant holds a stormwater permit for construction related activities (parcels > 1 acre) include the stormwater permit number. If you have applied, or intend to apply but have not yet obtained coverage and your certification number, indicate ―Pending‖ for this item. Item I—Signature Requirements—The permit applicant listed in Part A.1 must sign the permit application. Signatures must meet the requirements established in Regulation 61.4(1)(h). Page 3 of 3—Revised April 2011 Home - EPS Group (epsgroupinc.com) EPSGROUPINC.COM | 970.221.4158 SWMP Report: Gregory Cove Subdivision FORT COLLINS | GREELEY | MESA | TUSCON | GOODYEAR | PHEONIX | FORT WORTH APPENDIX APPENDIX E INSPECTION LOGS Page 1 of 6 CDOT Form #1176 2/21 COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name:(2) Project Contractor:(3) SWMP Administrator (Qualified Stormwater Manager) /Erosion Control Inspector: (4) CDOT Project Engineer/CDOT Designee:(5) Other Attendee(s) (Name and Title): (6) CDOT Project Number:(7) Project Code (Sub Account #):(8) CDPS-SCP Certification#: (12)REASON FOR INSPECTION / EXCLUSION ❑Routine Inspection: (A routine erosion control inspection shall be conducted at a minimum, once every 7 Calendar Days)❑Runoff Event: (Post-storm event inspections must be conducted within 24 hours after the end of any precipitation or snowmelt event that causes surface erosion. If no construction activities will occur following a storm event, post-storm event inspections shall be conducted prior to re-commencing construction activities, but no later than 72 hours following the storm event. The occurrence of any such delayed inspection must be documented in the inspection record.) Routine inspections still must be conducted every 7 calendar days. Storm Start Date: Approximate End Time of Storm (hrs): ❑Third Party Request: Winter Conditions Inspections Exclusion: Inspections are not required at sites where construction activities are temporarily halted, snow cover exists over the entire site for an extended period, and melting conditions posing a risk of surface erosion do not exist. This exception is applicable only during the period where melting conditions do not exist, and applies to the routine 7-day inspections, as well as the post- storm-event inspections. If visual inspection of the site verifies that all of these conditions are satisfied, document the conditions in section 17 (General Notes) and proceed to section 18 (Inspection Certification). Documentation must include: dates when snow cover existed, date when construction activities ceased, and date when melting conditions began.❑ (13)SWMP MANAGEMENT Yes No N/A (g) Reason for N/A (a) Is the SWMP located on site? (b) Are changes to the SWMP documents noted and approved? (c) Are the inspection reports retained in the SWMP? (d) Are corrective actions from the last inspection completed? (e) Is the Spill Response Plan updated in the SWMP? (f) Is a list of potential pollutants updated in the SWMP? (14)CURRENT CONSTRUCTION ACTIVITIES (a)Describe current phase of construction activities (b)Estimate of disturbed area at the time of the inspection, use guidance found in 208.04 (e): (c) Has the SWMP Phased Control Measure Implementation Matrix been updated? ❑ Yes ❑No Page 2 of 5 CDOT Form #1176 2/21 (15)CONSTRUCTION SITE ASSESSMENT & CORRECTIVE ACTIONS **Off-site Pollutant Discharges are a Violation of the Permit and Reason for Immediate Project Suspension** The Construction Site Boundary/Limits of Construction (LOC), all disturbed areas, designated haul roads, material and/or waste storage areas that are exposed to precipitation, discharge locations, and locations where vehicles exit the site shall be inspected for evidence of, or the potential for, pollutants leaving the LOC, entering the stormwater drainage system, or discharging to State waters. If there is evidence of sediment or other pollutants discharging from the site, see section 16 (Construction Site Assessment). All erosion and sediment control practices identified in the SWMP shall be evaluated to ensure that they are maintained and operating correctly. Identify the condition of the control measure, using more than one letter if necessary: (I) Inadequate control measure; (M) Maintenance is needed; (A) Additional control measure is needed; (R) Remove control measure. Keep copies of this blank page for additional room if needed. Continuous maintenance is required on all control measures. As per CDPS-SCP: “Control measures that are not operating effectively, have proven to be inadequate, or have failed must be addressed as soon as possible, immediately in most cases.” Location Control Measure Completed & Initials Page 3 of 6 CDOT Form #1176 2/21 (16)CONSTRUCTION SITE ASSESSMENT **Off-site Pollutant Discharges are a Violation of the Permit and Reason for Immediate Project Suspension** (a) Is there evidence of discharge of sediment or other pollutants from the site?❑Yes ❑ No *If yes, explain the discharge, the location and the associated corrective actions in section 15 (Construction Site Assessment & Corrective Actions) or section 18 (General Notes). (b) Has sediment or other pollutants discharging from the site reached State waters? ❑ Yes ❑ No *If yes, see subsection 208.03(c) and Part I.L.6 of the permit for reporting requirements. (17)GENERAL NOTES (18)INSPECTION CERTIFICATION By signing this form, I certify that I attended the inspection in accordance with specification 208.03. Contractor’s SWMP Administrator (Qualified Stormwater Manager) Print Name: Signature Required: Date: Contractor’s Erosion Control Inspector (If Needed): Print Name: Signature (if needed) Date: (19)COMPLIANCE CERTIFICATION I verify that, to the best of my knowledge and belief, that if any corrective action items were identified during the inspection, those corrective actions are complete, and the site is currently in compliance with the permit (Part I.A.3.f.i). Contractor’s SWMP Administrator/ECI Print Name: Signature Required: Date Contractor’s Superintendent/Approved Designee Print Name: Signature Required: Date: CDOT Project Engineer/CDOT Designee Print Name: Signature Required: Date: Page 4 of 6 CDOT Form #1176 2/21 Stormwater Management Field Inspection Report Instructions State waters are defined to be any and all surface and subsurface waters which are contained in or flow through the state, including, streams, rivers, lakes, drainage ditches, storm drains, ground water, and wetlands, but not including waters in sewage systems, waters in treatment works of disposal systems, waters in potable water distribution systems, and all water withdrawn for use until use and treatment have been completed. (Per subsection 107.25 and 25-8-103 (19) CRS) (3)SWMP Administrator (Qualified Stormwater Manager) and Erosion Control Inspector: Indicate the name(s) of the individual responsible for implementing, maintaining and revising the SWMP. An Erosion Control Inspector(s) may be the SWMP Administrator in projects with not more than 40 acres of disturbance (see 208.03(c)). (4)CDOT Project Engineer/CDOT Designee: Indicate the name of the CDOT representative performing the inspection with the SWMP Administrator/Erosion Control Inspector(s). This person should be the Project Engineer or an authorized representative. (9) CDPS-SCP Certification #: Indicate the Colorado Discharge Permit System (CDPS) Stormwater Construction Permit (SCP) (for Stormwater Discharges Associated with Construction Activities) certification number, issued by CDPHE, for the project which the report is being completed. Certification number can be found on the first page of the SCP. (12)Reason(s) for Inspection / Exclusion: Indicate the purpose for the inspection or exclusion. These inspections are required to comply with the CDOT Specifications and the CDPS-SCP. ❑Routine Inspections. These inspections are required at least every 7 calendar days during active construction. Suspended projects require the 7 calendar day inspection unless snow cover exists over the entire site for an extended period of time, and melting conditions do not exist (see, Winter Conditions Inspections Exclusions). ❑ Runoff Event Inspection for Active Sites. See page 1 for definition. ❑Third Party Request. Indicate the name of the third party requesting the inspection and, if known, the reason the request was made. ❑Winter Conditions Inspections Exclusions. See page 1 for definition. An inspection does not need to be completed, but use this form to document the conditions that meet the Exclusion. ❑ Other. Specify any other reason(s) that resulted in the inspection. (13)SWMP Management: Review the SWMP records and documents and use a ✔ to answer the question. To comply with CDOT Standard Specifications and the CDPS-SCP, all of the items identified must be adhered to. If No is checked, indicate the necessary corrective action in section 15 (Construction Site Assessment & Corrective Actions). Specification 208.03(d). a)A copy of the SWMP must be retained on site, unless another location (specified by the permit) is approved by the Division. b)Indicate all changes that have been made to any portion of the SWMP documents during construction. Changes shall be dated and signed at the time of occurrence. Amendments may include items listed in subsection 208.03(d). c)The SWMP Administrator shall keep a record of inspections. Inspection reports must identify any incidents of noncompliance with the terms and conditions of the CDOT specifications or the CDPS-SCP. Inspection records must be retained for three years from expiration or inactivation of permit coverage. d)Are corrective actions from the last inspection completed? Is a description of the corrective action(s), the date(s) of the corrective action(s), and the measure(s) taken to prevent future violations (including changes to the SWMP, as necessary) documented? e)Subsection 208.06(c) requires that a Spill Response Plan be developed and implemented to establish operating procedures and that the necessary employee training be provided to minimize accidental releases of pollutants that can contaminate stormwater runoff. Records of spills, leaks or overflows that result in the discharge of pollutants must be documented and maintained. Information that should be recorded for all occurrences include the time and date, weather conditions, reasons for spill, etc. Some spills may need to be reported to the Water Quality Control Division immediately. f)(f) Subsection 107.25(b)6 requires the Erosion Control Supervisor to identify and describe all potential pollutant sources, including materials and activities, and evaluate them for the potential to contribute pollutants to stormwater discharge. g)(g) If N/A is checked for any of the items (a) through (f), indicate why in the space provided, if additional space is needed indicate in section 17 (General Notes). Page 5 of 6 CDOT Form #1176 2/21 Stormwater Management Field Inspection Report Instructions (continued) (14) Current Construction Activities: a)Provide a short description of the current construction activities/phase at the project site; include summary of grading activities, installation of utilities, paving, excavation, landscaping, etc. (1)Estimate of disturbed area at the time of the inspection, use guidance found in 208.04 (e). Estimate the acres of disturbed area at the time of the inspection. Include clearing, grading, excavation activities, areas receiving overburden (e.g. stockpiles), demolition areas and areas with heavy equipment/vehicle traffic, installation of new or improved haul roads and access roads, staging areas, borrow areas and storage that will disturb existing vegetative cover, (Areas that have been: hard armored or paved should not be counted for total disturbance). b)Has the Phased control measure Implementation Matrix on the SWMP been updated? As part of the inspection the Phased control measure Implementation matrix for both the structural and non-structural control measures found at the beginning of the SWMP sheets must be reviewed to ensure that “In use on site” box is checked for control measures currently in use at the time of the inspection. (15) Construction Site Assessment & Corrective Actions: Inspect the construction site and indicate where control measure feature(s) identified in section 13 (SWMP Management), require corrective action. Erosion and sediment control practices identified in the SWMP shall be evaluated to ensure that they are operating correctly. •Condition. Identify the condition of the control measure, using more than one letter (identified in section 15) if necessary. •Location. Site location (e.g., project station number, mile marker, intersection quadrant, etc.). •Control measure. Indicate the type of control measure at this location that requires corrective action (e.g., silt fence, erosion logs, soil retention blankets, etc.). •Date Completed & Initials. Date and initial when the corrective action was completed and the preventative measure statement finished. •Description of Corrective Action and Preventative Measure Taken. Provide the proposed corrective action needed to bring the area or control measure into compliance. Once corrective actions are completed, state the measures taken to prevent future violations and ensure that the control measures are operating correctly, including the required changes made to the •SWMP. Inadequate control measure: Is any control measure that is not designed or implemented in accordance with the requirements of the permit and/or any control measure that is not implemented to operate in accordance with its design, this includes control measures that have not been implemented for pollution sources. If it is infeasible to install or repair the control measure immediately after discovering the deficiency the reason must be documented and a schedule included to return the control measure to effective operating condition as soon as possible. Control measures requiring routine maintenance: Any control measure that is still operating in accordance with its design and the requirements of the permit, but requires maintenance to prevent a breach of the control measure. These items are not subject to the corrective action requirements as specified in Part I.b.1.c of the permit. Additional: Any control measure inadequate for its application or an area with insufficient control measure(s). If it is infeasible to install revised or additional control measure(s) immediately after discovering the deficiency the reason must be documented and a schedule included to return the control measure to effective operating condition as soon as possible. Remove: Control measure no longer necessary (16) Construction Site Assessment: Was there any off site discharge of sediment at this site since the last inspection? a)Is there evidence of discharge of sediment or other pollutants from the site? Off-site pollutant discharges are a violation of the permit. (The construction site perimeter, all disturbed areas, material and/or waste storage areas that are exposed to precipitation, discharge locations, and locations where vehicles access the site shall be inspected for evidence of, or the potential for, pollutants leaving the construction site boundaries, entering the stormwater drainage system). b)Are pollutants discharging to State water? c)Has sediment or other pollutants discharging from the site reached State waters? Off-site pollutant discharges are a violation of the permit. If off site discharge has occurred, explain the discharge and the corrective actions in section 15 (Construction Site Assessment & Corrective Actions) or section 17 (General Notes). Page 6 of 6 CDOT Form #1176 2/21 (17)General Notes: Indicate any additional notes that add detail to the inspection; this may include positive practices noted on the project. (18)Inspection Certification: In accordance with 208.03, required personnel shall sign to verify that they were in attendance. (19)Compliance Certification: After all corrections have been made, this signature must be completed in accordance with Part I.A.3.f of the CDPS-SCP. Home - EPS Group (epsgroupinc.com) Home - EPS Group (epsgroupinc.com) Home - EPS Group (epsgroupinc.com)