Project:Disturbed Acres:0.72
EROSION CONTROL BMPs Units
Estimated
Quantity
Unit
Price
Total
Price
L.F. 800 $2.50 $2,000.00
each 4 $150.00 $600.00
C.Y. 12 $100.00 $1,200.00
each 1 $500.00 $500.00
each 2 $300.00 $600.00
A.C 0.41 $2,000.00 $820.00
Sub-Total: $5,720.00
1.5 x Sub-Total: $8,580.00
Amount of security: $8,580.00
AC 0.72 $2,000.00 $1,440.00
Sub-Total: $1,440.00
1.5 x Sub-Total: $2,160.00
Amount to Re-seed: $2,160.00
Minimum escrow amount: $3,000.00
Erosion Control Escrow:$8,580.00
Erosion and Sediment Control Escrow/Security Calculation
for The City of Fort Collins
BMP Amount
Silt Fence
Inlet Protection
Reseeding Amount
Miniumum Escrow Amount
Heartside Hill - Accessory Building & Child Care Center
Seeding
“The amount of the security must be based on one and one-half times the estimate of the cost to install the approved measures, or one and one-half times
the cost to re-vegetate the disturbed land to dry land grasses based upon unit cost determined by the City's Annual Revegetation and Stabilization Bid,
whichever is greater. In no instance, will the amount of security be less than one thousand five hundred dollars ($1,500) for residential development or
three thousand dollars ($3,000) for commercial development”
Rock Sock
Vehicle Tracking Control Pad
Final Escrow Amount (Maximum between BMP, Reseeding and Minimum Escrow)
Seeding & Mulching
Riprap
5/1/2024 12:04 PM G:\Projects\21-1045-02 HH Community Bldg\03 Design Documents\Cost Estimates\HH-CC Erosion Control Escrow.xls