HomeMy WebLinkAboutMASON STREET INFRASTRUCTURE PROJECT - FDP230016 - SUBMITTAL DOCUMENTS - ROUND 6 - Responses (2)
1
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6689
970.224.6134 - fax
fcgov.com/developmentreview
March 29, 2024
RE: Mason Street Infrastructure Project, FDP230016, Round Number 5
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of Mason Street Infrastructure Project. If you have questions
about any comments, you may contact the individual commenter or direct your questions
through your Development Review Coordinator, Brandy Bethurem Harras via phone at
970-4162744 or via email at bbethuremharras@fcgov.com-.
Ripley Design
Applicant
Northern Engineering
Fox Tuttle
Cedar Creek
Comment Summary:
Department: Development Review Coordinator
Contact: Brandy Bethurem Harras bbethuremharras@fcgov.com 970-416-2744
Topic: General
Comment Number: 1
06/02/2023: INFORMATION:
I will be your primary point of contact throughout the development review and
permitting process. If you have any questions, need additional meetings with the
project reviewers, or need assistance throughout the process, please let me
know and I can assist you and your team. Please include me in all email
correspondence with other reviewers and keep me informed of any phone
conversations. Thank you!
Ripley Response: Understood, thank you.
Comment Number: 2
2
06/02/2023: SUBMITTAL:
As part of your resubmittal, you will respond to the comments provided in this
letter. This letter is provided to you in Microsoft Word format. Please use this
document to insert responses to each comment for your submittal, using a
different font color.
When replying to the comment letter please be detailed in your responses, as
all comments should be thoroughly addressed. Comments requiring action
should NOT have a response such as noted or acknowledged. You will need to
provide references to specific project plans, pages, reports, or explanations of
why comments have not been addressed [when applicable].
Ripley Response: Understood, thank you.
Comment Number: 3
06/02/2023: SUBMITTAL:
Correct file naming is required as part of a complete submittal. Please follow
the Electronic Submittal Requirements and File Naming Standards found here:
https://www.fcgov.com/developmentreview/files/electronic -submittal-requiremen
ts-and-file-naming-standards_v1_8-1-19.pdf?1680306305.
File names should have the corresponding number, followed by the file type
prefix, project information, and round number. For example: 1_SITE
PLAN_MasonStreet_FDP_Rd1. A list of numbers and prefixes for each file can
be found at the link above.
Ripley Response: Understood, thank you.
Comment Number: 4
03/20/2024: *AutoCad SHX Text on Plat.
06/02/2023: SUBMITTAL:
All plans should be saved as optimized/flattened PDFs to reduce file size and
remove layers.
Per the Electronic Submittal Requirements AutoCAD SHX attributes need to be
removed from the PDF’s.
AutoCAD turns drawing text into comments that appear in the PDF plan set,
and these must be removed prior to submittal as they can cause issues with the
PDF file.
The default setting is "1" ("on") in AutoCAD. To change the setting and remove
this feature, type "EPDFSHX" (version 2016.1) or “PDFSHX (version 2017 and
newer) in the command line and enter "0".
Read this article at Autodesk.com for more on this topic:
https://knowledge.autodesk.com/support/autocad/troubleshooting/caas/sfdcarti
cles/sfdcarticles/Drawing-text-appears-as-Comments-in-a-PDF-created-by-Aut
OCAD.html
Ripley Response: Understood, thank you.
Comment Number: 5
06/02/2023: SUBMITTAL:
Resubmittals are accepted any day of the week, with Wednesday at noon being
the cut-off for routing the same week. When you are preparing to resubmit your
plans, please notify me with an expected submittal date with as much advanced
notice as possible.
Ripley Response: Understood, thank you.
Comment Number: 6
06/02/2023: INFORMATION:
Please resubmit within 180 days, approximately 6 months, to avoid the
3
expiration of your project.
Ripley Response: Understood, thank you.
Comment Number: 8
06/02/2023: FOR HEARING:
All "For Hearing" comments need to be addressed and resolved prior to
moving forward with scheduling the Hearing. Staff will need to agree the project
is ready for Hearing approximately 4 to 8 weeks prior to the hearing.
Ripley Response: Understood, thank you.
Comment Number: 9
03/20/2024: FOR RECORDING – PLAT & SITE PLAN - UPDATED:
You can remove the “, 20___.” from the date line also. The digital signature date
will provide the month, day, and year.
If you could also make the date update to the site plan.
The line for the City Clerk signature has not been removed from the plat. Again,
this is not necessary as The City Clerk does not sign the plat.
Additionally, kindly ensure there is sufficient space between the signature line
and the title line to accommodate the digital signature. If you need an example,
please let me know.
02/20/2024: FOR RECORDING - PLAT:
Could you please update the City signature blocks on the plat? Instead of using
"this _______ day of ______A.D., 20____," could you opt for "on this day,
_____________" for the date? This alternative format facilitates smoother date
input with digital signatures.
Additionally, kindly ensure there is sufficient space between the signature line
and the title line to accommodate the digital signature.
If you need an example please let me know.
The City Clerk does not sign the plat, you can remove their dedicated signature line.
Thank you.
Northern Response: Plat signature has been revised.
Ripley Response: Site plan signature block has been revised.
Department: Engineering Development Review
Contact: Sophie Buckingham sbuckingham@fcgov.com
Topic: General
Comment Number: 18
03/25/2024: FOR HEARING REVISED-:
Per offline coordination with the applicant team, the interim and future grading
along the east side of Mason Street will be included in the final utility plan. The
future design will need to show that the grading will not impact the trees' critical
root zones. The design engineer is already working on updated grading sheets
and cross-sections to include in the final utility plan. We have discussed several
design options, including sloping the east sidewalk away from the street,
increasing the east side of the street cross -slope to 3 or 4 percent,
implementing a multi-use path instead of separate bike and pedestrian facilities
on the east side, and the possibility of a boardwalk instead of a traditional
concrete sidewalk on the east side. An additional pre-Hearing round of review
is strongly recommended, to prevent multiple rounds after the Hearing.
Northern Response: Road cross section and future grading has been coordinated , reviewed, and approved by city staff. A 2-ft
shoulder from the curb and gutter will be proposed along the east side of Mason Street.
4
Comment Number: 19
03/25/2024: FOR FINAL APPROVAL & RECORDING:
Per offline coordination with the applicant team, cross -sections for Mason
Street will be included in a post-Hearing round of review. The design engineer
has already created the cross-sections to include in the final utility plan. I will
need to review the design in detail in a postHearing- round of review.
Northern Response: Road cross section and future grading has been coordinated , reviewed, and approved by city staff. A 2-ft
shoulder from the curb and gutter is currently proposed along the east side of Mason Street. The cross-sections are included in this
latest submittal. Thanks for the help resolving this issue between rounds!
Comment Number: 20
03/26/2024: INFORMATION:
The City's right-of-way contractor has obtained signed License to Enter
Agreements from the three properties where the City will be acquiring
right-of-way and easements. I will work with the other City departments to
determine whether documentation of the acquisition process should be included
in the Hearing packet.
Northern Response: Thank you.
Department: Traffic Operation
Contact: Steve Gilchrist sgilchrist@fcgov.com 970-224-6175
Topic: General
Comment Number: 5
03/24/2024: FOR HEARING:
I apologize for missing this minor striping change previously. Please carry the
double yellow centerline, and bike lane striping through the south driveway
access. We don't break striping for driveways. See note on page 24, 25 of the
Utility Plans.
Northern Response: Striping has been extended across driveway and sheets have been revised.
Department: Stormwater Engineering
Contact: Matt Simpson masimpson@fcgov.com (970) 416-2754
Topic: General
Comment Number: 25
03/25/2024: FOR APPROVALS:
Staff is continuing to work on this item.
02/20/2024: FOR FINAL APPROVAL & RECORDING:
We will continue to work on this internally and report back with any direction for
the developer. Likely solutions, to document and memorialize the transfer and
deferral of NHBZ mitigation to the future Hickory Pond, include DA items and an
Inter-Department Agreement approved by Directors.
01/09/2024: FOR HEARING - UNRESOLVED:
Hickory Pond – NHBZ Transfer (Follow up from Stormwater Comment 3f)
- Previous Comment: The “transfer” of NHBZ requirements to the City pond
parcel will need further coordination and discussion regarding the identification,
documentation, and monumentation of these requirements for the ultimate
implementation of the future pond.
- Updated Comment: The transfer of NHBZ mitigation requirements to the
City’s Hickory Pond will need further discussion.
Northern Response: Acknowledged thank you for your continued assistance.
5
Comment Number: 34
03/25/2024: FOR FINAL APPROVAL - FOLLOW UP:
For approval you will need to provide a plan for groundwater monitoring before
and during the construction. Preferably updated groundwater monitoring will be
in progress before project approvals.
02/20/2024: INFORMATION:
Follow up on Groundwater – When do you expect to be able to reestablish the
groundwater monitoring wells and resume the measuring and reporting? This
needs to be completed as part of the project design. We will allow for this to
continue into construction, however want to get reporting during the high
groundwater months (July – Sept) of this year (2024). Our allowance for this to
continue into construction will be included in the DA.
Northern Response: A groundwater investigation report has been included with this submittal and the report details the installed
monitoring well and measured values. Per the report, measurements will be obtained monthly and coordinated with city staff.
Comment Number: 35
03/25/2024: FOR FINAL APPROVAL - UNRESOLVED:
02/20/2024: FOR HEARING:
The post-construction groundwater monitoring well detail needs to be upgraded
to a standard well type. The Geotech should provide input on recommended
depth. Please see redlines on the detail sheet of the Utility Plans for more comments
Northern Response: A typical well detail has been added to sheet D7. A groundwater investigation report has been included with
this submittal and the report details the installed monitoring well. Reference to the monitoring well has been included in the
construction plans.
Comment Number: 36
03/25/2024: FOR FINAL APPROVAL & RECORDING:
02/20/2024: FOR FINAL APPROVAL & RECORDING:
The offsite storm easement will need to be executed and recorded before
project approvals. Further discussion should be had on the timing of these and
approval processes.
Northern Response: Acknowledged.
Comment Number: 39
03/25/2024: INFORMATION:
02/20/2024: INFORMATION:
A CDOT permit will likely be necessary for the storm drain work in the College Ave ROW.
Northern Response: Understood. We will let JHL (the contractor) know they will need to acquire that.
Comment Number: 42
03/25/2024: FOR FINAL APPROVAL:
This item is in my court. I will send the approved variance form to you as soon
as I have. Please add a place-holder to the drainage report.
02/23/2024: FOR FINAL APPROVAL & RECORDING:
Regarding the stormwater pond overflow spillway and significant variance from
criteria, we will internally write and approve a stormwater department variance.
This document will need to be included with the final drainage report.
Northern Response: Understood. We will leave placeholder in drainage report. Appendix F
Comment Number: 43
03/25/2024: FOR HEARING:
On the south end of Lot 1, will these irrigation lines be above ground or below?
If below, relocate irrigation line(s) away from water transmission main. 10 -ft min
horizontal separation.
MPi Designs Response: IRRIGATION LINEWORK FOR ZONE T3 WILL REMAIN - HOWEVER, NOTES WILL BE ADDED TO
STATE THAT THIS ZONE SHALL BE INSTALLED ABOVE GRADE TO AVOID WATER MAIN IN THE AREA.
6
Comment Number: 44
03/25/2024: FOR HEARING:
See Redlines on UT Plans and PIP.
Northern Response: Responses have been added to the redlines.
Ripley Response: Responses have been added to the redlines.
Comment Number: 45
03/25/2024: FOR HEARING:
In the drainage report, the two conceptual exhibits for N Mason future storm
drain were removed from the Round 5 drainage report. These need to be
added back to the report.
Northern Response: The ultimate exhibits have been added back in to the drainage report.
Department: Water-Wastewater Engineering
Contact: Matt Simpson
Topic: General
Comment Number: 4
03/25/2024: FOR APPROVAL:
02/20/2024: FOR APPROVAL – UPDATED:
The offsite sewer and water easements or ROW need to be executed and
recorded before project approvals. Further discussion should be had on the
timing of these and approval processes.
01/09/2024: FOR APPROVAL – UPDATED:
The linework for the offsite easements will need to be coordinated with the
City’s ROW acquisition team and consultant.
10/31/2023: FOR APPROVAL – UPDATED:
Thank you for providing easement documents for the sewer and storm
easements. See redlines on these exhibits as well as the UT plans for
comments.
06/19/2023: FOR APPROVAL:
The City will consider aiding in procuring the necessary offsite easements for
the proposed sanitary sewer running parallel to the 36-inch water main. The City
will need further internal discussion to determine the next steps.
Northern Response: Acknowledged.
Comment Number: 21
03/25/2024: FOR FINAL APPROVAL:
02/20/2024: FOR HEARING:
We will need to continue working on the developer repay outside of formal
review. Please update the repay tabulation and exhibit based on the recent
discussion and send back to me. I will send you directly more information
about how the repay process will work.
Northern Response: We will continue to coordinate with you.
Comment Number: 26
03/25/2024: INFORMATION:
02/20/2024: INFORMATION:
The water fees for the Lot 2 irrigation service will be based on the larger
outdoor water use table between this project and the FCRM project.
Ripley Response: Acknowledged.
Comment Number: 28
03/25/2024: FOR HEARING:
See Redlines on UT Plans and PIP.
7
Northern Response: Responses have been added to the redlines.
Ripley Response: Responses have been added to the redlines.
Department: Light And Power
Contact: Tyler Siegmund tsiegmund@fcgov.com 970-416-2772
Topic: General
Comment Number: 4
02/20/2024: FOR HEARING:
Please see minor markups for revised switch cabinet location on the southwest
side of Mason St. to avoid storm drain conflict
01/09/2024: FOR FINAL:
Please see markups for minor revisions.
Northern Response: The switch cabinet and electric crossing have been adjusted per the redlines. Thank you for coordinating this
between rounds of review with us!
Department: Environmental Planning
Contact: Kristie Raymond kraymond@fcgov.com
Topic: General
Comment Number: 9
01/06/2024: FOR RECORDING:
Language regarding the protection and enhancement of the Natural Habitat
Buffer Zone will be included in the Development Agreement for this project.
Prior to the FDP approval please provide an cost estimate of the landscaping
costs for the Natural Habitat Buffer Zone, including materials, labor, monitoring
for a minimum of three years, weed mitigation and irrigation.
We then use the approved estimate to collect security at 125% of the total
amount for final approval.
Ripley Response: An estimate will be provided prior to recording.
Comment Number: 10
10/30/2023: FOR DCP:
The agreed upon NHBZ security will need to be collected prior to DCP issuance.
Ripley Response: Acknowledged.
Comment Number: 24
03/26/2024: FOR HEARING:
Please change the following note on L01.03 of the Site and Landscape plan,
"NOTE: NEW LANDSCAPE IN THE NHBZ WILL BE ESCROWED AND
INSTALLED AT THE TIME OF FUTURE PROPOSAL TO LOT 2." to
"NOTE: The Developer shall ensure that all landscaping and restoration
activities within the Natural Habitat Buffer Zone (NHBZ) are properly installed
and maintained until the performance criteria outlined by the Development
Agreement is met. If City of Fort Collins Utilities is ready to construct the
ultimate Hickory Pond before the developer has met the NHBZ performance
criteria, the obligation to maintain the NHBZ transfers to Utilities and City of Fort
8
Collins Environmental Planning will release security to the Developer and
transfer NHBZ performance criteria to Utilities. When Fort Collins Utilities
begins construction on the final condition of the Hickory Detention Pond, Utilities
will accept the NHBZ maintenance at the time that a development application is
submitted to the Planning Department for the final construction of the Hickory
Detention Pond."
Ripley Response: Note has been updated.
Comment Number: 27
03/26/2024: FOR FINAL APPROVAL:
Please swap the willow and cottonwood noted on the Site and Landscape plan
to be compatible with the adjustment to grading and moisture needs.
Ripley Response: Tree locations have been switched.
Comment Number: 28
03/26/2024: FOR HEARING:
Please indicate how the trees within the natural feature of Tract A will be
protected with the construction of the sidewalk.
Northern Response: The grading has been adjusted and a 2 -ft shoulder from curb and gutter is currently proposed along the east
side of Mason Street to provide as much space to the existing trees as possible. Additional tree protection notes are also on the
Existing Conditions sheet.
Comment Number: 29
03/26/2024: FOR FINAL APPROVAL:
Please address the comments noted in the Restoration Plan Summary on the
Site and Landscape Plan. In addition to these comments, please add the
following details as well:
1) Add a comment about communicating (email and report) the results after
each monitoring visit to City of Fort Collins Environmental Planning, the
developer, and the contractor.
2) Please make note of when Fort Collins Environmental Planning should be
contacted prior to further work. This should occur prior to the commencement of
grading showing proof of equipment cleaning. Also, prior to seeding an
Environmental Planning inspector needs to confirm proper seed bed
preparation and seed mix details are appropriate.
Additionally, make sure all these changes are made to the full Restoration Plan
as well.
Cedar Creek Response: These updates have been made to the full restoration plan and Restoration Plan Summary on the Site and
Landscape Plan, where applicable.
Comment Number: 30
03/26/2024: FOR FINAL APPROVAL:
Additional comments to address within the Full Restoration Plan:
- Monitoring and restoration efforts should continue until the performance criteria
is met (could be longer than 3 years).
- Please mention success criteria using line point intercept.
- Please include the reference area explanation sheet provided by City of Fort
Collins, Environmental Planning. It is titled, Natural Habitat Buffer Zone
Reference Area Primer, and can be found at:
https://www.fcgov.com/developmentreview/environmental -planning-resources
9
Cedar Creek Response: These updates have been made to the full restoration plan and Restoration Plan Summary on the Site and
Landscape Plan, where applicable.
Department: Forestry
Contact: Christine Holtz choltz@fcgov.com
Topic: General
Comment Number: 14
03/26/2024: FOR APROVAL:
Please switch the location of a couple of proposed trees - a willow and plains
cottonwood - so the willow is closer to the future drainage channel. See Forestry
redlines on L1.03.
Ripley Response: Tree locations have been switched.
Comment Number: 15
03/27/2024: FOR INFORMATION
How will the trees along Tract A be protected with the proposed addition of the
sidewalk. Please think thoughtfully about the critical root zones of the trees (1
foot for every inch of diameter) and keep excavation or grading as far from the
critical root zone as possible.
Northern Response: The grading has been adjusted and a 2 -ft shoulder from curb and gutter is currently proposed along the east
side of Mason Street to provide as much space to the existing trees as possible. Additional tree protection notes are also on the
Existing Conditions sheet.
Department: Technical Services
Contact: Jeff County jcounty@fcgov.com 970-221-6588
Topic: Plat
Comment Number: 1
03/26/2024: FOR HEARING:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the markups, please contact
John Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
01/09/2024: FOR HEARING:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the markups, please contact
John Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
10/31/2023: FOR HEARING:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the markups, please contact
10
John Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
06/20/2023: FOR HEARING:
Please make changes as marked. If changes are not made or you disagree
with comments, please provide written response of why corrections were not
made. Please provide any responses on redlined sheets and/or in response
letter. If you have any specific questions about the redlines, please contact John
Von Nieda at 970-221-6565 or jvonnieda@fcgov.com
Northern Response: Responses have been added to redlines.